SlideShare a Scribd company logo
1 of 45
Trepezoidal Sarda type fall
Straight glacis fall
3/20/2014 1
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
u/s wing walls :
D/s wing walls :
D/s *bed pitching :
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
2
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
3
Radius = 5 to 6 times H
= 5 x 0.83 to 6 x 0.83
= 4.15 to 4.98 m
Say R = 4.50 m
Provide u/s wing walls having
segmental portion with radius 4.5 m
and subtending an angle of 60Β°, at the
centre and starting from the u/s edge
of the crest wall.
3/20/2014 4
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
3/20/2014 5
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
Length of d/s wing wall with
vertical face
= 6 H β€’ HL
= 6-7 0.83 x 1.5
= 6.70 m
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
6
3/20/2014 7
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
Length of warped wing with a splay
of 1 in 3 = height * splay = 2.5 * 3
= 7.5 m
Total length of d/s wing wall = 6.70
+ 7.5 = 14.2 m.
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
8
Length of d/s bed pitching
= 9 + 2Hl
= 9 + 2 x 1.5
= 12 m
Provide horizontal pitching up to
the end of masonry wing walls for a
length of 6.3 m and then sloping at 1
in 10 for length of 6 m.
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
9
Wingwall
103.77
12 M
PITCHING
3/18/2014 10
PREPARED BY V.H.KHOKHANI
ASSISTANT PROFESSOR, DIET
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
11
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
12
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
13
FLUMED
FALL
UNFLUMED
FALL
METER
FALL
NONMETER
FALL
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
14
1. Crest design
2. Cistern design
3. Impervious floor
4. u/s wing walls
5. d/s wing walls
6. d/s side protection
7. Roughening devices
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
15
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
16
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
17
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
18
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
19
Length of crest = width of bed (for
unflumed fall)
L = 35.0 m
For non-meter fall, narrow crest is
provided.
Discharge Q is given by :
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
20
H = 0.85 m
R.L. of crest = u/s FSL – H
= 203.5 – 0.85
= 202.65 M
height of crest above u/s bed,
= R.L.of crest – U/S bed level
= 202.65 - 201.5 = 1.15
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
21
Crest width for non meter fall
= (2/3) H
= (2/3) 0.85
= 0.57
The d/s glacis is provided in a slope of
2 : 1
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
22
Compare it with d/s bed level
because as we know cistern is
always below d/s bed level.
Ef2 can be obtained from blench
curve from available q and Hl
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
23
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
24
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
25
d/s bed level
u/s bed level
cistern level
0.25 ef2
d/s TEL = d/s FSL + Ha =202 + 0.02
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
26
d/s bed RL is 200 m which is lower
than obtained cistern level.
So provide minimum depth of
cistern = 0.25 Ef2 = 0.25 (1.40) =
0.35 m.
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
27
Length of cistern = 5 ef2 to 6 ef2
= 5(1.40) to 6 (1.40)
= 7.0 to 8.4 m
Provide length of cistern 8 .0 m
The cistern is joined to the d/s bed of
the channel with a slope of 5 : 1.
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
28
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
29
d/s bed level
u/s bed level
cistern level
0. 35 m
8.0 m
5 in 1
Assuming 0.6 m additional cutoff
depth.
u/s cutoff depth = D1/3 + 0.6
D/S cutoff depth = D2/2 + 0.6
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
30
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
31
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
32
d/s bed level
u/s bed level
cistern level
0. 35 m
8.0 m
5 in 1
0.2 m
Deflector
wall
1.6 m
1.40 m
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
33
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
34
Provide total horizontal length of
impervious flow = 20.60 m
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
35
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
36
d/s bed level = 200
u/s bed level
= 201.5
cistern level =
199.65
8.0 m
1.6 m
1.40 m
crest level =
202.65
0.5 IN 1
L = b
Lu = total length – d/s glacis – u/s glacis – crest width
Provide total horizontal length of
impervious flow = 20.60 m
crest width = 0.55 m
horizontal length of u/s glacis =
(202.65 - 201.5) x 0.5 = 0.58 m
horizontal length of d/s glacis =
(202.65 - 199.65) x 2 = 6.0 m
length of cistern = 8 m
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
37
(a) u/s cutoff wall
d{ = 1.30 m
b = 20.60 m
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
38
Assume a thickness of 0.4 m at the
end of u/s floor
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
39
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
40
(b) d/s cutoff
d2 = 1.60 m
b = 20.6 m
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
41
Assume thickness of 0.5 m at the
end of d/s floor.
Neglecting effect of mutual
interference.
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
42
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
43
ib) At 3 m from the toe of glacis :
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
44
(2) D/s wing walls :
Provide d/s wing walls upto the end of the
d/s floor and then join them to the return
walls.
Top level of wing wall = 202 + 0.5 = 202.5
m.
d/s Bed Protection :
No bed protection is required as a deflector
has been provided,
d/s Side Protection :
Length of side protection = 3D2 = 3 x 2= 6
m
Provide 20 cm thick brick side pitching
over 10 cm ballast for a length of
6 m at a slope of 1 : 1 beyond the d/s
impervious floor.
3/20/2014
PREPARED BY VIDHI H. KHOKHANI
ASST. PROF. DIET
45

More Related Content

What's hot

Concrete dam lecture 2
Concrete dam lecture 2Concrete dam lecture 2
Concrete dam lecture 2Vidhi Khokhani
Β 
Design of columns uniaxial load as per IS 456-2000
Design of columns  uniaxial load as per IS 456-2000Design of columns  uniaxial load as per IS 456-2000
Design of columns uniaxial load as per IS 456-2000PraveenKumar Shanmugam
Β 
L- beams or flanged beams
L- beams or flanged beamsL- beams or flanged beams
L- beams or flanged beamshoneysid
Β 
Lab reports transportation engineering i
Lab reports transportation engineering iLab reports transportation engineering i
Lab reports transportation engineering iSushrut Gautam
Β 
Deep excavations
Deep excavationsDeep excavations
Deep excavationsBhargava Ram
Β 
Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Saqib Imran
Β 
presentation : cross drainage work
presentation : cross drainage workpresentation : cross drainage work
presentation : cross drainage workEddy Ankit Gangani
Β 
Bridge loading
Bridge loadingBridge loading
Bridge loadingkapilpant12
Β 
Dymanics of open channel flow
Dymanics of open channel flowDymanics of open channel flow
Dymanics of open channel flowMohsin Siddique
Β 
Drop structure lecture 1
Drop structure lecture 1Drop structure lecture 1
Drop structure lecture 1Vidhi Khokhani
Β 
Unit 3 spillway
Unit 3 spillwayUnit 3 spillway
Unit 3 spillwayMood Naik
Β 
APPLICATION OF SPECIFIC ENERGY IN FLUID MECHANICS
APPLICATION OF SPECIFIC ENERGY IN FLUID MECHANICSAPPLICATION OF SPECIFIC ENERGY IN FLUID MECHANICS
APPLICATION OF SPECIFIC ENERGY IN FLUID MECHANICSKaran Patel
Β 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and typesRajkumar G
Β 
economic channel section
economic channel sectioneconomic channel section
economic channel sectionVaibhav Pathak
Β 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxsubhashini214160
Β 
design of weirs
design of weirsdesign of weirs
design of weirsSANJEEV Wazir
Β 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam Yash Patel
Β 

What's hot (20)

Concrete dam lecture 2
Concrete dam lecture 2Concrete dam lecture 2
Concrete dam lecture 2
Β 
Design of columns uniaxial load as per IS 456-2000
Design of columns  uniaxial load as per IS 456-2000Design of columns  uniaxial load as per IS 456-2000
Design of columns uniaxial load as per IS 456-2000
Β 
L- beams or flanged beams
L- beams or flanged beamsL- beams or flanged beams
L- beams or flanged beams
Β 
Lab reports transportation engineering i
Lab reports transportation engineering iLab reports transportation engineering i
Lab reports transportation engineering i
Β 
Deep excavations
Deep excavationsDeep excavations
Deep excavations
Β 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
Β 
Minor Project Report On Construction of Pipe Culvert
Minor Project Report  On Construction of  Pipe CulvertMinor Project Report  On Construction of  Pipe Culvert
Minor Project Report On Construction of Pipe Culvert
Β 
Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413
Β 
presentation : cross drainage work
presentation : cross drainage workpresentation : cross drainage work
presentation : cross drainage work
Β 
Bridge loading
Bridge loadingBridge loading
Bridge loading
Β 
Dymanics of open channel flow
Dymanics of open channel flowDymanics of open channel flow
Dymanics of open channel flow
Β 
Drop structure lecture 1
Drop structure lecture 1Drop structure lecture 1
Drop structure lecture 1
Β 
Unit 3 spillway
Unit 3 spillwayUnit 3 spillway
Unit 3 spillway
Β 
APPLICATION OF SPECIFIC ENERGY IN FLUID MECHANICS
APPLICATION OF SPECIFIC ENERGY IN FLUID MECHANICSAPPLICATION OF SPECIFIC ENERGY IN FLUID MECHANICS
APPLICATION OF SPECIFIC ENERGY IN FLUID MECHANICS
Β 
Canal design
Canal designCanal design
Canal design
Β 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
Β 
economic channel section
economic channel sectioneconomic channel section
economic channel section
Β 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
Β 
design of weirs
design of weirsdesign of weirs
design of weirs
Β 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam
Β 

Viewers also liked

Drop structure lecture 3
Drop structure lecture 3Drop structure lecture 3
Drop structure lecture 3Vidhi Khokhani
Β 
Embankment lecture 4
Embankment lecture 4Embankment lecture 4
Embankment lecture 4Vidhi Khokhani
Β 
Dam outlet works lecture 2
Dam outlet works lecture 2Dam outlet works lecture 2
Dam outlet works lecture 2Vidhi Khokhani
Β 
Embankment lecture 7
Embankment lecture 7Embankment lecture 7
Embankment lecture 7Vidhi Khokhani
Β 
Irrigation Engineering
Irrigation EngineeringIrrigation Engineering
Irrigation EngineeringVidhi Khokhani
Β 
Embankment lecture 3
Embankment lecture 3Embankment lecture 3
Embankment lecture 3Vidhi Khokhani
Β 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1Vidhi Khokhani
Β 
Irrigation water management
Irrigation water management Irrigation water management
Irrigation water management Vidhi Khokhani
Β 
project on sharda
project on shardaproject on sharda
project on shardaKTOO
Β 
Internship certificate
Internship certificateInternship certificate
Internship certificateSarmad Shakeel
Β 
Earth+and+rock+fill+dams
Earth+and+rock+fill+damsEarth+and+rock+fill+dams
Earth+and+rock+fill+damsMohd Danish
Β 
Drop structure lecture 2
Drop structure lecture 2Drop structure lecture 2
Drop structure lecture 2Vidhi Khokhani
Β 
Concrete dam lecture 11
Concrete dam lecture 11Concrete dam lecture 11
Concrete dam lecture 11Vidhi Khokhani
Β 
Embankment lecture 12
Embankment lecture 12Embankment lecture 12
Embankment lecture 12Vidhi Khokhani
Β 
Introduction chapter `1
Introduction chapter `1Introduction chapter `1
Introduction chapter `1Vidhi Khokhani
Β 
Dam outlet works lecture 1
Dam outlet works lecture 1Dam outlet works lecture 1
Dam outlet works lecture 1Vidhi Khokhani
Β 
Final Project Report
Final Project ReportFinal Project Report
Final Project ReportSarmad Shakeel
Β 
Dam outlet works lecture 3
Dam outlet works lecture 3Dam outlet works lecture 3
Dam outlet works lecture 3Vidhi Khokhani
Β 
Irrigation water management
Irrigation water managementIrrigation water management
Irrigation water managementVidhi Khokhani
Β 

Viewers also liked (20)

Canal Fall
Canal FallCanal Fall
Canal Fall
Β 
Drop structure lecture 3
Drop structure lecture 3Drop structure lecture 3
Drop structure lecture 3
Β 
Embankment lecture 4
Embankment lecture 4Embankment lecture 4
Embankment lecture 4
Β 
Dam outlet works lecture 2
Dam outlet works lecture 2Dam outlet works lecture 2
Dam outlet works lecture 2
Β 
Embankment lecture 7
Embankment lecture 7Embankment lecture 7
Embankment lecture 7
Β 
Irrigation Engineering
Irrigation EngineeringIrrigation Engineering
Irrigation Engineering
Β 
Embankment lecture 3
Embankment lecture 3Embankment lecture 3
Embankment lecture 3
Β 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1
Β 
Irrigation water management
Irrigation water management Irrigation water management
Irrigation water management
Β 
project on sharda
project on shardaproject on sharda
project on sharda
Β 
Internship certificate
Internship certificateInternship certificate
Internship certificate
Β 
Earth+and+rock+fill+dams
Earth+and+rock+fill+damsEarth+and+rock+fill+dams
Earth+and+rock+fill+dams
Β 
Drop structure lecture 2
Drop structure lecture 2Drop structure lecture 2
Drop structure lecture 2
Β 
Concrete dam lecture 11
Concrete dam lecture 11Concrete dam lecture 11
Concrete dam lecture 11
Β 
Embankment lecture 12
Embankment lecture 12Embankment lecture 12
Embankment lecture 12
Β 
Introduction chapter `1
Introduction chapter `1Introduction chapter `1
Introduction chapter `1
Β 
Dam outlet works lecture 1
Dam outlet works lecture 1Dam outlet works lecture 1
Dam outlet works lecture 1
Β 
Final Project Report
Final Project ReportFinal Project Report
Final Project Report
Β 
Dam outlet works lecture 3
Dam outlet works lecture 3Dam outlet works lecture 3
Dam outlet works lecture 3
Β 
Irrigation water management
Irrigation water managementIrrigation water management
Irrigation water management
Β 

More from Vidhi Khokhani

2. w index and 5 index
2. w index and 5 index2. w index and 5 index
2. w index and 5 indexVidhi Khokhani
Β 
Concrete dam lecture 4
Concrete dam lecture 4Concrete dam lecture 4
Concrete dam lecture 4Vidhi Khokhani
Β 
Concrete dam lecture 1
Concrete dam lecture 1Concrete dam lecture 1
Concrete dam lecture 1Vidhi Khokhani
Β 
check basin , furrow and border strip method
check basin , furrow and border strip methodcheck basin , furrow and border strip method
check basin , furrow and border strip methodVidhi Khokhani
Β 
Lecture 1-aerial photogrammetry
Lecture 1-aerial photogrammetryLecture 1-aerial photogrammetry
Lecture 1-aerial photogrammetryVidhi Khokhani
Β 
Embankment lecture 2
Embankment lecture 2Embankment lecture 2
Embankment lecture 2Vidhi Khokhani
Β 
irrigation water management
irrigation water managementirrigation water management
irrigation water managementVidhi Khokhani
Β 
Design of Hydraulic Structure
Design of Hydraulic StructureDesign of Hydraulic Structure
Design of Hydraulic StructureVidhi Khokhani
Β 
Chapter 2 part 1 sprinkler
Chapter 2 part 1 sprinklerChapter 2 part 1 sprinkler
Chapter 2 part 1 sprinklerVidhi Khokhani
Β 

More from Vidhi Khokhani (10)

2. w index and 5 index
2. w index and 5 index2. w index and 5 index
2. w index and 5 index
Β 
ogee design
ogee designogee design
ogee design
Β 
Concrete dam lecture 4
Concrete dam lecture 4Concrete dam lecture 4
Concrete dam lecture 4
Β 
Concrete dam lecture 1
Concrete dam lecture 1Concrete dam lecture 1
Concrete dam lecture 1
Β 
check basin , furrow and border strip method
check basin , furrow and border strip methodcheck basin , furrow and border strip method
check basin , furrow and border strip method
Β 
Lecture 1-aerial photogrammetry
Lecture 1-aerial photogrammetryLecture 1-aerial photogrammetry
Lecture 1-aerial photogrammetry
Β 
Embankment lecture 2
Embankment lecture 2Embankment lecture 2
Embankment lecture 2
Β 
irrigation water management
irrigation water managementirrigation water management
irrigation water management
Β 
Design of Hydraulic Structure
Design of Hydraulic StructureDesign of Hydraulic Structure
Design of Hydraulic Structure
Β 
Chapter 2 part 1 sprinkler
Chapter 2 part 1 sprinklerChapter 2 part 1 sprinkler
Chapter 2 part 1 sprinkler
Β 

Recently uploaded

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
Β 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
Β 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
Β 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
Β 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
Β 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
Β 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
Β 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
Β 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
Β 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
Β 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
Β 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
Β 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
Β 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
Β 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
Β 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
Β 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
Β 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
Β 
Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”
Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”
Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”soniya singh
Β 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
Β 

Recently uploaded (20)

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
Β 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
Β 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
Β 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
Β 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
Β 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
Β 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Β 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
Β 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
Β 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
Β 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
Β 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
Β 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Β 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
Β 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Β 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
Β 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
Β 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
Β 
Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”
Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”
Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”
Β 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
Β 

Drop structure lecture 4

  • 1. Trepezoidal Sarda type fall Straight glacis fall 3/20/2014 1 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET
  • 2. u/s wing walls : D/s wing walls : D/s *bed pitching : 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 2
  • 3. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 3
  • 4. Radius = 5 to 6 times H = 5 x 0.83 to 6 x 0.83 = 4.15 to 4.98 m Say R = 4.50 m Provide u/s wing walls having segmental portion with radius 4.5 m and subtending an angle of 60Β°, at the centre and starting from the u/s edge of the crest wall. 3/20/2014 4 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET
  • 5. 3/20/2014 5 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET
  • 6. Length of d/s wing wall with vertical face = 6 H β€’ HL = 6-7 0.83 x 1.5 = 6.70 m 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 6
  • 7. 3/20/2014 7 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET
  • 8. Length of warped wing with a splay of 1 in 3 = height * splay = 2.5 * 3 = 7.5 m Total length of d/s wing wall = 6.70 + 7.5 = 14.2 m. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 8
  • 9. Length of d/s bed pitching = 9 + 2Hl = 9 + 2 x 1.5 = 12 m Provide horizontal pitching up to the end of masonry wing walls for a length of 6.3 m and then sloping at 1 in 10 for length of 6 m. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 9
  • 10. Wingwall 103.77 12 M PITCHING 3/18/2014 10 PREPARED BY V.H.KHOKHANI ASSISTANT PROFESSOR, DIET
  • 11. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 11
  • 12. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 12
  • 13. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 13
  • 15. 1. Crest design 2. Cistern design 3. Impervious floor 4. u/s wing walls 5. d/s wing walls 6. d/s side protection 7. Roughening devices 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 15
  • 16. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 16
  • 17. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 17
  • 18. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 18
  • 19. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 19
  • 20. Length of crest = width of bed (for unflumed fall) L = 35.0 m For non-meter fall, narrow crest is provided. Discharge Q is given by : 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 20
  • 21. H = 0.85 m R.L. of crest = u/s FSL – H = 203.5 – 0.85 = 202.65 M height of crest above u/s bed, = R.L.of crest – U/S bed level = 202.65 - 201.5 = 1.15 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 21
  • 22. Crest width for non meter fall = (2/3) H = (2/3) 0.85 = 0.57 The d/s glacis is provided in a slope of 2 : 1 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 22
  • 23. Compare it with d/s bed level because as we know cistern is always below d/s bed level. Ef2 can be obtained from blench curve from available q and Hl 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 23
  • 24. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 24
  • 25. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 25 d/s bed level u/s bed level cistern level 0.25 ef2
  • 26. d/s TEL = d/s FSL + Ha =202 + 0.02 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 26
  • 27. d/s bed RL is 200 m which is lower than obtained cistern level. So provide minimum depth of cistern = 0.25 Ef2 = 0.25 (1.40) = 0.35 m. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 27
  • 28. Length of cistern = 5 ef2 to 6 ef2 = 5(1.40) to 6 (1.40) = 7.0 to 8.4 m Provide length of cistern 8 .0 m The cistern is joined to the d/s bed of the channel with a slope of 5 : 1. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 28
  • 29. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 29 d/s bed level u/s bed level cistern level 0. 35 m 8.0 m 5 in 1
  • 30. Assuming 0.6 m additional cutoff depth. u/s cutoff depth = D1/3 + 0.6 D/S cutoff depth = D2/2 + 0.6 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 30
  • 31. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 31
  • 32. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 32 d/s bed level u/s bed level cistern level 0. 35 m 8.0 m 5 in 1 0.2 m Deflector wall 1.6 m 1.40 m
  • 33. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 33
  • 34. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 34
  • 35. Provide total horizontal length of impervious flow = 20.60 m 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 35
  • 36. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 36 d/s bed level = 200 u/s bed level = 201.5 cistern level = 199.65 8.0 m 1.6 m 1.40 m crest level = 202.65 0.5 IN 1 L = b Lu = total length – d/s glacis – u/s glacis – crest width
  • 37. Provide total horizontal length of impervious flow = 20.60 m crest width = 0.55 m horizontal length of u/s glacis = (202.65 - 201.5) x 0.5 = 0.58 m horizontal length of d/s glacis = (202.65 - 199.65) x 2 = 6.0 m length of cistern = 8 m 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 37
  • 38. (a) u/s cutoff wall d{ = 1.30 m b = 20.60 m 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 38
  • 39. Assume a thickness of 0.4 m at the end of u/s floor 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 39
  • 40. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 40
  • 41. (b) d/s cutoff d2 = 1.60 m b = 20.6 m 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 41
  • 42. Assume thickness of 0.5 m at the end of d/s floor. Neglecting effect of mutual interference. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 42
  • 43. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 43
  • 44. ib) At 3 m from the toe of glacis : 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 44
  • 45. (2) D/s wing walls : Provide d/s wing walls upto the end of the d/s floor and then join them to the return walls. Top level of wing wall = 202 + 0.5 = 202.5 m. d/s Bed Protection : No bed protection is required as a deflector has been provided, d/s Side Protection : Length of side protection = 3D2 = 3 x 2= 6 m Provide 20 cm thick brick side pitching over 10 cm ballast for a length of 6 m at a slope of 1 : 1 beyond the d/s impervious floor. 3/20/2014 PREPARED BY VIDHI H. KHOKHANI ASST. PROF. DIET 45