SlideShare a Scribd company logo
- Mr. Hole G.R.
Lecturer-Civil Department,
JSP,HADAPSAR
 The works which are constructed at the head of the canal
in order to divert the river water toward the canal, so as
to ensure a regulated continuous supply mostly silt free
water with certain minimum head into the canal, are
known as diversion headworks.
 Storage Headwork :
A storage Headwork is structure( Dam) which is constructed
across river to store water during excess inflow and used to
supply during less inflow and high Demand.
 Diversion Headwork:
It is structure which constructed across river (Weir) to raise the
water level in river so that it can diverted in to canal system.
The Following are the objective of Diversion Head works
 To Raise the water level at the head of canal.
 To form a storage by construction of dykes on both
side of banks of the river so that water is available
throughout the year.
 To control the entry of silt into the canal and to
control the deposition of silt at the head of canal.
 To control the fluctuation of water level in the river
during different seasons.
The following points should be considered to select a
site for this diversion headworks.
 The river should be straight and narrow at the site
 The elevation of site should be higher than the area to
be irrigated for gravity flow.
 River banks at site should be well defined and stable.
 Valuable land upstream of the barrier like weir or
barrage should not be submerged.
 Material of construction should be locally available.
 Roads or railway communication to the site is essential
to carry the material of construction.
 Site should be close to the cropland to minimize loss of
water due to seepage and evaporation of canal.
 The site should provide a good foundation for
construction of weir or barrage.
The components of diversion headworks are:
 Weir or barrage
 Canal head regulator
 Divide Wall
 Fish Ladder
 Scouring Sluices Under sluices
 Silt excluder
 Silt ejector.
 Marginal embankment or dikes
 Guide bank
 Silt pocket or trap.
1.Weir
It is a solid obstruction placed across the river. Its main
function is to raise the water level so that water can be
diverted by canal to crop field due to difference of head.
Barrage is practically a low weir with an adjustable
gate over this low weir. Heading up of water is
affected by gate.
1.Vertical Drop Weir(Masonry Weir)
 A crest gate may be provided to store more water
during flood period.
 At the upstream and downstream ends of impervious
floor cut off piles are provided.
 Launching apron are provided both at upstream and
downstream ends of floor to safeguard against
scouring action.
 A graded filter is provided immediately at the
downstream end of impervious floor to relieve the
uplift pressure.
 This type of weir is suitable for any type of
foundation.
 This type is suitable for soft sandy foundation.
 It is used where difference in weir crest and
downstream river bed is not more than 3 m.
 Hydraulic jump is formed when water passes over the
sloping glacis.
 Suitable for soft soil foundation.
 In rock fill type weir, there are no of core wall on D/S of main
weir wall and space between weir wall is filled with rock
fragments that’s why it is called as Rock fill Weir.
 Requires large quantity of rock fragments so it is economical
when rock are available easily in surrounding region.
 Suitable for fine sand foundation.
 Structure at the head of canal taking off from a reservoir may
consist of number of spans separated by piers and operated by
gates.
 Regulators are normally aligned at 90° to the weir.
 These are used for diversion of flow.
 Silt reduces carriage capacity of flow.
 Provides platform for bridges for communication facility.
 To maintain constant supply in off tacking canal during
low Discharge Period.
 To cut off the Discharge of parent canal during
maintenance on D/S side.
 The Divide Wall is a long wall constructed at right angle to
the weir or barrage, it may be constructed with stone masonry
or cement concrete.
 On the upstream side, the wall is extended just to cover the
canal regulator and on the down stream side, it is extended up
to the launching apron.
 The functions of the divide wall are as follows,
1. To form a still water pocket in front of the canal head so that
the suspended silt can be settled down which then later can be
cleared through the scouring sluices from time to time.
2. It controls the eddy current or cross current in front of the canal
head.
3. It provides a straight approach in front of the canal head.
4. It resists the overturning effect on the weir or barrage caused by
the pressure of the impounding water.
 The Scouring sluices are the openings provided at the
base of the weir or barrage at lower level.
 It is provided at same side on which off tacking canal
is located.
 The crest of under sluices is kept lower than crest of
weir due to which water is attracted towards sluice
which helps to easy diversion of water in to canal.
 The Fish Ladder is passage provided adjacent to divide
wall for the movement of fishes from U/S to D/S and
vice-versa.
 In general, the tendency of fish is to move from
upstream to downstream in winters and from
downstream to upstream in monsoons. This movement
is essential for their survival.
 In the fish ladder, the baffle walls are constructed in
the zigzag manner so that the velocities of flow within
the ladder does not exceed 3 m/s
 Silt excluder is the structure
provided in still pocket to pass silt
content water in D/S .
 This is helps to allow clear water
entry in canal.
 Water contains silt is having high
density so it is always near to bed
level.
 The tunnel nearest to the head
regulator is longest, and the
successive tunnels decrease in
length, the tunnel nearest to the
divide wall is shortest.
 The tunnels are covered by R.C.C.
Slab.
 The top level of the slab is kept
below the sill level of the head
regulator.
 So, the completely clear water is
allowed to flow in the canal
through the head regulator.
 Silt ejectors, also called silt
extractors, are those devices
which extract the silt from the
canal water after the silted
water has traveled a certain
distance in the off-take canal.
 These works are, therefore,
constructed on the bed of the
canal, and little distance
downstream from the head
regulator.
 It consist of tunnels parallel to
flow of canal and turns in to 90
to eject silt.
 The length provided may be
different.
THANK YOU

More Related Content

What's hot

Diversion headwork
Diversion headwork Diversion headwork
Diversion headwork
Bibhabasu Mohanty
 
CANAL IRRIGATION
CANAL IRRIGATIONCANAL IRRIGATION
CANAL IRRIGATION
kannan1407
 
Spillways
SpillwaysSpillways
Canal regulation works. m4pptx
Canal regulation works. m4pptxCanal regulation works. m4pptx
Canal regulation works. m4pptx
Bibhabasu Mohanty
 
Canal
CanalCanal
DIVERSION HEAD WORK
DIVERSION HEAD WORKDIVERSION HEAD WORK
DIVERSION HEAD WORK
SANJEEV Wazir
 
River engineering
River engineeringRiver engineering
River engineering
Sandra4Smiley
 
Diversion head work
Diversion head workDiversion head work
Diversion head work
Divya Vishnoi
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
Rajkumar G
 
weir & barrage
weir & barrageweir & barrage
weir & barrage
Raj Daxini
 
Silt excluders
Silt excludersSilt excluders
Silt excluders
Raees Shah
 
River training method
River training methodRiver training method
River training method
Muhammad Bilal
 
River training works lecture
River training works lectureRiver training works lecture
River training works lecture
sarhad university peshawer
 
Storage and distribution reservoirs
Storage and distribution reservoirsStorage and distribution reservoirs
Storage and distribution reservoirs
farooq husain
 
Dams and spillways
Dams and spillwaysDams and spillways
River and it's training work
River and it's training workRiver and it's training work
River and it's training work
SHUBHAM SINGH
 
Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation Works
SANJEEV Wazir
 
Canal of design
Canal of designCanal of design
Canal of design
PREMKUMAR
 
Canal lining
Canal liningCanal lining
Canal lining
MANJUNATH BORAKANAVAR
 

What's hot (20)

Diversion headwork
Diversion headwork Diversion headwork
Diversion headwork
 
CANAL IRRIGATION
CANAL IRRIGATIONCANAL IRRIGATION
CANAL IRRIGATION
 
Spillways
SpillwaysSpillways
Spillways
 
Canal regulation works. m4pptx
Canal regulation works. m4pptxCanal regulation works. m4pptx
Canal regulation works. m4pptx
 
Canal
CanalCanal
Canal
 
DIVERSION HEAD WORK
DIVERSION HEAD WORKDIVERSION HEAD WORK
DIVERSION HEAD WORK
 
River engineering
River engineeringRiver engineering
River engineering
 
Diversion head work
Diversion head workDiversion head work
Diversion head work
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
 
weir & barrage
weir & barrageweir & barrage
weir & barrage
 
Silt excluders
Silt excludersSilt excluders
Silt excluders
 
River training method
River training methodRiver training method
River training method
 
River training works lecture
River training works lectureRiver training works lecture
River training works lecture
 
Storage and distribution reservoirs
Storage and distribution reservoirsStorage and distribution reservoirs
Storage and distribution reservoirs
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
River and it's training work
River and it's training workRiver and it's training work
River and it's training work
 
Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation Works
 
Canal of design
Canal of designCanal of design
Canal of design
 
Canal lining
Canal liningCanal lining
Canal lining
 
Irrigation
IrrigationIrrigation
Irrigation
 

Similar to Diversion Headwork in Canal

Wreii unitv-170917082636
Wreii unitv-170917082636Wreii unitv-170917082636
Wreii unitv-170917082636
saibabu48
 
DIVERSION HEAD WORKS
DIVERSION HEAD WORKSDIVERSION HEAD WORKS
DIVERSION HEAD WORKS
Mood Naik
 
Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413
Saqib Imran
 
Presenation on Diversion Headworks irrigation.pptx
Presenation on Diversion Headworks irrigation.pptxPresenation on Diversion Headworks irrigation.pptx
Presenation on Diversion Headworks irrigation.pptx
qureshixahoor
 
Diversionheadworkm3 120625052707-phpapp02
Diversionheadworkm3 120625052707-phpapp02Diversionheadworkm3 120625052707-phpapp02
Diversionheadworkm3 120625052707-phpapp02
saibabu48
 
UNIT 5 Distribution Works.pptx
UNIT 5 Distribution Works.pptxUNIT 5 Distribution Works.pptx
UNIT 5 Distribution Works.pptx
Divs97
 
Diversion head work
Diversion head workDiversion head work
Diversion head work
dhruvalsu
 
Krishna
KrishnaKrishna
Krishna
krishna sai
 
Ce 413 hydraulic structures 8th
Ce 413 hydraulic structures 8thCe 413 hydraulic structures 8th
Ce 413 hydraulic structures 8th
EngrHayatHussain
 
chapter-3.pptx: CHANNEL HEADWORKS AND CANALS
chapter-3.pptx: CHANNEL HEADWORKS AND CANALSchapter-3.pptx: CHANNEL HEADWORKS AND CANALS
chapter-3.pptx: CHANNEL HEADWORKS AND CANALS
mulugeta48
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
Jimit Shah
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
Dipesh Raiyani
 
Barrage Gate Operation Rules and Silt Control Devices Report
Barrage Gate Operation Rules and Silt Control Devices Report Barrage Gate Operation Rules and Silt Control Devices Report
Barrage Gate Operation Rules and Silt Control Devices Report
vikas rahangdale
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
saibabu48
 
Diversion of headwork
Diversion of headwork Diversion of headwork
Diversion of headwork
Jay Khoradiya
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
brijlata sharma
 
Canal headworks
Canal headworksCanal headworks
Canal headworks
Atul Hajong
 
Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01
saibabu48
 
intakes and transportation of water
intakes and transportation of waterintakes and transportation of water
intakes and transportation of water
atul azad
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
GAURAV. H .TANDON
 

Similar to Diversion Headwork in Canal (20)

Wreii unitv-170917082636
Wreii unitv-170917082636Wreii unitv-170917082636
Wreii unitv-170917082636
 
DIVERSION HEAD WORKS
DIVERSION HEAD WORKSDIVERSION HEAD WORKS
DIVERSION HEAD WORKS
 
Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413
 
Presenation on Diversion Headworks irrigation.pptx
Presenation on Diversion Headworks irrigation.pptxPresenation on Diversion Headworks irrigation.pptx
Presenation on Diversion Headworks irrigation.pptx
 
Diversionheadworkm3 120625052707-phpapp02
Diversionheadworkm3 120625052707-phpapp02Diversionheadworkm3 120625052707-phpapp02
Diversionheadworkm3 120625052707-phpapp02
 
UNIT 5 Distribution Works.pptx
UNIT 5 Distribution Works.pptxUNIT 5 Distribution Works.pptx
UNIT 5 Distribution Works.pptx
 
Diversion head work
Diversion head workDiversion head work
Diversion head work
 
Krishna
KrishnaKrishna
Krishna
 
Ce 413 hydraulic structures 8th
Ce 413 hydraulic structures 8thCe 413 hydraulic structures 8th
Ce 413 hydraulic structures 8th
 
chapter-3.pptx: CHANNEL HEADWORKS AND CANALS
chapter-3.pptx: CHANNEL HEADWORKS AND CANALSchapter-3.pptx: CHANNEL HEADWORKS AND CANALS
chapter-3.pptx: CHANNEL HEADWORKS AND CANALS
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Barrage Gate Operation Rules and Silt Control Devices Report
Barrage Gate Operation Rules and Silt Control Devices Report Barrage Gate Operation Rules and Silt Control Devices Report
Barrage Gate Operation Rules and Silt Control Devices Report
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
 
Diversion of headwork
Diversion of headwork Diversion of headwork
Diversion of headwork
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Canal headworks
Canal headworksCanal headworks
Canal headworks
 
Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01
 
intakes and transportation of water
intakes and transportation of waterintakes and transportation of water
intakes and transportation of water
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 

More from holegajendra

PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxPRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
holegajendra
 
4. traffic engineering
4. traffic engineering4. traffic engineering
4. traffic engineering
holegajendra
 
Introduction to Hydrology
Introduction to HydrologyIntroduction to Hydrology
Introduction to Hydrology
holegajendra
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highway
holegajendra
 
Introduction to irrigation engineering 19 07 1 (1)
Introduction to irrigation engineering 19 07 1 (1)Introduction to irrigation engineering 19 07 1 (1)
Introduction to irrigation engineering 19 07 1 (1)
holegajendra
 
1.introduction to highway engineering
1.introduction to highway engineering1.introduction to highway engineering
1.introduction to highway engineering
holegajendra
 
Application of GIS and RS in Watershed Management
Application of GIS and RS in Watershed ManagementApplication of GIS and RS in Watershed Management
Application of GIS and RS in Watershed Management
holegajendra
 
Dam engineering
Dam engineeringDam engineering
Dam engineering
holegajendra
 
Spillway and gates
Spillway and gatesSpillway and gates
Spillway and gates
holegajendra
 
Maintenence of road
Maintenence of roadMaintenence of road
Maintenence of road
holegajendra
 
Hill roads and Drainage
Hill roads and DrainageHill roads and Drainage
Hill roads and Drainage
holegajendra
 
Cross Drainage Work
Cross Drainage Work Cross Drainage Work
Cross Drainage Work
holegajendra
 

More from holegajendra (12)

PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxPRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
 
4. traffic engineering
4. traffic engineering4. traffic engineering
4. traffic engineering
 
Introduction to Hydrology
Introduction to HydrologyIntroduction to Hydrology
Introduction to Hydrology
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highway
 
Introduction to irrigation engineering 19 07 1 (1)
Introduction to irrigation engineering 19 07 1 (1)Introduction to irrigation engineering 19 07 1 (1)
Introduction to irrigation engineering 19 07 1 (1)
 
1.introduction to highway engineering
1.introduction to highway engineering1.introduction to highway engineering
1.introduction to highway engineering
 
Application of GIS and RS in Watershed Management
Application of GIS and RS in Watershed ManagementApplication of GIS and RS in Watershed Management
Application of GIS and RS in Watershed Management
 
Dam engineering
Dam engineeringDam engineering
Dam engineering
 
Spillway and gates
Spillway and gatesSpillway and gates
Spillway and gates
 
Maintenence of road
Maintenence of roadMaintenence of road
Maintenence of road
 
Hill roads and Drainage
Hill roads and DrainageHill roads and Drainage
Hill roads and Drainage
 
Cross Drainage Work
Cross Drainage Work Cross Drainage Work
Cross Drainage Work
 

Recently uploaded

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 

Recently uploaded (20)

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 

Diversion Headwork in Canal

  • 1. - Mr. Hole G.R. Lecturer-Civil Department, JSP,HADAPSAR
  • 2.  The works which are constructed at the head of the canal in order to divert the river water toward the canal, so as to ensure a regulated continuous supply mostly silt free water with certain minimum head into the canal, are known as diversion headworks.
  • 3.  Storage Headwork : A storage Headwork is structure( Dam) which is constructed across river to store water during excess inflow and used to supply during less inflow and high Demand.  Diversion Headwork: It is structure which constructed across river (Weir) to raise the water level in river so that it can diverted in to canal system.
  • 4. The Following are the objective of Diversion Head works  To Raise the water level at the head of canal.  To form a storage by construction of dykes on both side of banks of the river so that water is available throughout the year.  To control the entry of silt into the canal and to control the deposition of silt at the head of canal.  To control the fluctuation of water level in the river during different seasons.
  • 5. The following points should be considered to select a site for this diversion headworks.  The river should be straight and narrow at the site  The elevation of site should be higher than the area to be irrigated for gravity flow.  River banks at site should be well defined and stable.  Valuable land upstream of the barrier like weir or barrage should not be submerged.
  • 6.  Material of construction should be locally available.  Roads or railway communication to the site is essential to carry the material of construction.  Site should be close to the cropland to minimize loss of water due to seepage and evaporation of canal.  The site should provide a good foundation for construction of weir or barrage.
  • 7.
  • 8. The components of diversion headworks are:  Weir or barrage  Canal head regulator  Divide Wall  Fish Ladder  Scouring Sluices Under sluices  Silt excluder  Silt ejector.  Marginal embankment or dikes  Guide bank  Silt pocket or trap.
  • 9. 1.Weir It is a solid obstruction placed across the river. Its main function is to raise the water level so that water can be diverted by canal to crop field due to difference of head.
  • 10.
  • 11. Barrage is practically a low weir with an adjustable gate over this low weir. Heading up of water is affected by gate.
  • 12.
  • 13.
  • 14. 1.Vertical Drop Weir(Masonry Weir)  A crest gate may be provided to store more water during flood period.  At the upstream and downstream ends of impervious floor cut off piles are provided.  Launching apron are provided both at upstream and downstream ends of floor to safeguard against scouring action.  A graded filter is provided immediately at the downstream end of impervious floor to relieve the uplift pressure.  This type of weir is suitable for any type of foundation.
  • 15.
  • 16.  This type is suitable for soft sandy foundation.  It is used where difference in weir crest and downstream river bed is not more than 3 m.  Hydraulic jump is formed when water passes over the sloping glacis.  Suitable for soft soil foundation.
  • 17.  In rock fill type weir, there are no of core wall on D/S of main weir wall and space between weir wall is filled with rock fragments that’s why it is called as Rock fill Weir.  Requires large quantity of rock fragments so it is economical when rock are available easily in surrounding region.  Suitable for fine sand foundation.
  • 18.  Structure at the head of canal taking off from a reservoir may consist of number of spans separated by piers and operated by gates.  Regulators are normally aligned at 90° to the weir.  These are used for diversion of flow.  Silt reduces carriage capacity of flow.
  • 19.  Provides platform for bridges for communication facility.  To maintain constant supply in off tacking canal during low Discharge Period.  To cut off the Discharge of parent canal during maintenance on D/S side.
  • 20.  The Divide Wall is a long wall constructed at right angle to the weir or barrage, it may be constructed with stone masonry or cement concrete.  On the upstream side, the wall is extended just to cover the canal regulator and on the down stream side, it is extended up to the launching apron.  The functions of the divide wall are as follows, 1. To form a still water pocket in front of the canal head so that the suspended silt can be settled down which then later can be cleared through the scouring sluices from time to time. 2. It controls the eddy current or cross current in front of the canal head. 3. It provides a straight approach in front of the canal head. 4. It resists the overturning effect on the weir or barrage caused by the pressure of the impounding water.
  • 21.  The Scouring sluices are the openings provided at the base of the weir or barrage at lower level.  It is provided at same side on which off tacking canal is located.  The crest of under sluices is kept lower than crest of weir due to which water is attracted towards sluice which helps to easy diversion of water in to canal.
  • 22.  The Fish Ladder is passage provided adjacent to divide wall for the movement of fishes from U/S to D/S and vice-versa.  In general, the tendency of fish is to move from upstream to downstream in winters and from downstream to upstream in monsoons. This movement is essential for their survival.  In the fish ladder, the baffle walls are constructed in the zigzag manner so that the velocities of flow within the ladder does not exceed 3 m/s
  • 23.
  • 24.  Silt excluder is the structure provided in still pocket to pass silt content water in D/S .  This is helps to allow clear water entry in canal.  Water contains silt is having high density so it is always near to bed level.  The tunnel nearest to the head regulator is longest, and the successive tunnels decrease in length, the tunnel nearest to the divide wall is shortest.  The tunnels are covered by R.C.C. Slab.  The top level of the slab is kept below the sill level of the head regulator.  So, the completely clear water is allowed to flow in the canal through the head regulator.
  • 25.  Silt ejectors, also called silt extractors, are those devices which extract the silt from the canal water after the silted water has traveled a certain distance in the off-take canal.  These works are, therefore, constructed on the bed of the canal, and little distance downstream from the head regulator.  It consist of tunnels parallel to flow of canal and turns in to 90 to eject silt.  The length provided may be different.