SlideShare a Scribd company logo
OG 321 DRILLING 1
LECTURE SIX
DRILLING COST AND DRILLING RATE
DRILLING COST ANALYSIS
Drilling cost predictions are made so that sound economic
decision can be made
The drilling engineer recommends
• drilling procedures that will safely drilled and complete the
well at the minimum cost possible
• routine rig operations such as
Drilling fluid treatment
Pump operation
Bit selection
Any problem encountered in drilling operation
3
The Drilling Cost Equation
Cf = drilling cost, $/ft
Cb= cost of bit, $/bit
Cr = fixed operating cost of rig, $/hr
tb = total rotating time, hrs
tc = total non-rotating time, hrs
tt = total trip time (round trip), hrs
D

ft
D
t
t
t
C
C
C
t
c
b
r
b
f
$
)
(





= footage drilled
with bit, ft/bit
Also known as cost per foot equation
4
Example
A recommended bit program is being prepared for a
new well using bit performance records from nearby
wells.
Drilling performance records for three bits are shown
for a thick limestone formation at 9,000 ft.
Determine which bit gives the lowest drilling cost if the
operating cost of the rig is $400/hr, the trip time is 7
hours, and connection time is 1 minute per connection.
5
Assume that each of the bits was operated at near
the minimum cost per foot attainable for that bit.
Mean
Bit Rotating Connection Penetration
Cost Time Time Rate
Bit ($) (hours) (hours) (ft/hr)
A 800 14.8 0.1 13.8
B 4,900 57.7 0.4 12.6
C 4,500 95.8 0.5 10.2
Example cont’d
Which bit would you select?
6
Solution:
The cost per foot drilled for each bit type can
be computed using drilling cost equation for
Bit A, the cost per foot is
/ft.
81
.
46
$
)
8
.
14
(
8
.
13
)
7
1
.
0
8
.
14
(
400
800





f
C
ft
D
t
t
t
C
C
C
t
c
b
r
b
f
$
)
(





7
Solution:
Similarly, for Bit B,
/ft.
56
.
42
$
)
7
.
57
(
6
.
12
)
7
4
.
0
7
.
57
(
400
900
,
4





f
C
ft
D
t
t
t
C
C
C
t
c
b
r
b
f
$
)
(





8
Solution, cont’d
Finally, for Bit C,
/ft.
89
.
46
$
)
8
.
95
(
2
.
10
)
7
5
.
0
8
.
95
(
400
500
,
4





f
C
ft
D
t
t
t
C
C
C
t
c
b
r
b
f
$
)
(





9
Solution, cont’d
Bit A: $46.81 /ft
Bit B: $42.56 /ft
Bit C: $46.89 /ft
The lowest drilling cost was obtained using Bit
B.
Regardless of highest bit cost …it has
intermediate bit life and ROP...
10
Drilling Costs
• Tend to increase exponentially with depth.
Thus, when curve-fitting drilling cost data, it is
often convenient to assume a relationship
between total well cost, C, and depth, D, given
by
C = aebD
• Constants a and b depend primarily on the
well location.
11
Drilling Costs, cont’d
Shown on the next page is a least-squares
curve fit of the south Louisiana completed well
data given in Table 1.7 (ADE book)
Depth range of 7,500 ft to 21,000 ft.
For these data,
a = 1 X 105 dollars
b = 2 X 10-4 ft -1.
C = aebD
12
Fig. 1-65. Least-square curve fit of 1978 completed well costs for wells below
7,500 ft in the south Louisiana area.
13
Penetration Rate
When major variations are not present in the
subsurface lithology, the penetration rate
usually decreases exponentially with depth.
Under these conditions, the penetration rate
can be related to depth, D, by
where K and a2 are constants.
D
a
Ke
dt
dD 2
303
.
2


14
Drilling Time
The drilling time, td , required to drill to a given
depth can be obtained by separating variables
and integrating. Separating variables gives
dD
e
dt
K D
a
303
.
2
D
0
t
0
2
d



Integrating and solving for td yields
)
1
(
303
.
2
1 2
303
.
2
2

 D
a
d e
K
a
t
15
Drilling Time cont’d
Plotting depth vs. drilling time from past drilling
operations:
• Allows more accurate prediction of time and cost for
drilling a new well
• Is used in evaluating new drilling procedures
(designed to reduce drilling time to a given depth).
16
EXAMPLE - Cost per ft
t R D Total Cost Cf
hr fph ft $ $/ft
5 90 475 36,950 77.80
10 80 900 47,800 53.10
20 60 1,600 69,200 43.30
25 50 1,875 79,750 42.50
30 40 2,100 90,200 43.00
35 30 2,275 100,550 44.20
40 20 2,400 110,800 46.20
These cost data are plotted below.
17
Cost per ft for one entire bit run
Minimum Cost
80
70
60
50
40
18
Economic Procedure in previous Table
 Can pull bit after about 25 hr. ($42.50/ft)
- the precise pulling time is not critical
Note that the cost in dollars per foot
was $43.00 after 30 hr.
 Primarily applicable to tooth-type bits
where wear rate is predictable.
19
Economic Procedure in above Table
 Also used with tungsten carbide insert
bits when inserts are broken or
pulled out of the matrix.
 Unfortunately, wear rate with insert
bits is unpredictable.
 Economically, the insert bit should be
pulled when the cost in $/ft begins to
increase.
20
Economic Procedure in Table
– Bits pulled for economic reasons make it
hard to obtain wear information.
– Operator might pull bit after 120 hr of use
but part of bit might get left in hole.
Recovery is very difficult. Avoid!
– 75% of rock bits are pulled green or
before the bit is worn out.
21
An increase in
TORQUE may
indicate that a bit
should be pulled.
Experience often
dictates when to
pull bit (footage or
hours).
22
Factors that affect Penetration Rate
 Type of Drill bit
 Bit weight
 Rotary speed
 Bottom-hole cleaning
 Mud properties
 Rock hardness
 Formation pore pressure
Variables:
Fixed Factors:
23
Bit Selection is based on
 Past bit records
 Geologic predictions of lithology
 Drilling costs in $/bit...
 Drilling cost in $/ft
24
Bit Weight and Rotary Speed
• Increasing bit weight and rotary speed
boosts drilling rate
• These increases accelerate bit wear
• Field tests show that drilling rate
increases more or less in direct
proportion to bit weight
25
Consider 10” hole
(don’t overdo!!)
Bit Weight x 1,000 lb/in
40,000 lbf
26
Rotary Speed, RPM
Don’t overdo!
Casing wear,
bit life ...
27
EFFECT OF BACK PRESSURE
Keep P_bit = const.= 550 psi
28
Hydrostatic Pressure, 1,000’s of psi
EFFECT OF BACK PRESSURE
0 - 5,000 psi
29
Drilling Time, days
Drilled with gas
Drilled with mud
EFFECT OF DRILLING FLUID
mud vs. gas
30
Rotating Time, hours
EFFECT OF DRILLING FLUID
water vs. air
31
Old style water course bits
32
EFFECT OF SOLIDS IN THE MUD

More Related Content

What's hot

Formation evaluation
Formation evaluationFormation evaluation
Formation evaluation
Shah Naseer
 
Immiscible Fluid Displacement.pptx
Immiscible Fluid Displacement.pptxImmiscible Fluid Displacement.pptx
Immiscible Fluid Displacement.pptx
54PeAravindswamy
 
PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4
PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4
PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4
PetroSync
 
Well logging
Well loggingWell logging
Well logging
saikiranrohith
 
OIL RECOVERY TECHNIQUES
OIL RECOVERY TECHNIQUESOIL RECOVERY TECHNIQUES
OIL RECOVERY TECHNIQUES
Gerikaran Patel
 
rig types and its components
rig types and its componentsrig types and its components
rig types and its components
University of Azad Jammu & Kashmir
 
Directional Drilling 2020-2021.pdf
Directional Drilling 2020-2021.pdfDirectional Drilling 2020-2021.pdf
Directional Drilling 2020-2021.pdf
ssuserd324d9
 
Well Workover
Well Workover Well Workover
Well Workover
Christian Akhilome
 
Life Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsLife Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas Wells
Mohamed Elnagar
 
Basic drilling engineering
Basic drilling engineeringBasic drilling engineering
Basic drilling engineering
Saad Raja
 
Estmation of oil & gas proven probable posiible
Estmation of oil & gas proven probable posiibleEstmation of oil & gas proven probable posiible
Estmation of oil & gas proven probable posiible
Narendra Kumar Dewangan
 
Type of rig
Type of rigType of rig
Type of rig
Shailesh Gadkari
 
Well Test Analysis in Horizontal Wells
Well Test Analysis in Horizontal WellsWell Test Analysis in Horizontal Wells
Well Test Analysis in Horizontal Wells
Sohil Shah
 
Petroleum economics
Petroleum economicsPetroleum economics
Petroleum economics
Sadegh Yazdani
 
Source rock
Source rockSource rock
Source rock
Sohail Nawab
 
formation evaluation
formation evaluationformation evaluation
formation evaluation
Abel Carrasquilla
 
Petroleum well completion overview
Petroleum well completion overviewPetroleum well completion overview
Petroleum well completion overview
Andi Anriansyah
 
Blow out preventer (bop)
Blow out preventer (bop)Blow out preventer (bop)
Blow out preventer (bop)
danperth
 
Introduction to Mudlogging
Introduction to MudloggingIntroduction to Mudlogging
Programming in Petroleum Engineering Graduation Project 2020
Programming in Petroleum Engineering Graduation Project 2020Programming in Petroleum Engineering Graduation Project 2020
Programming in Petroleum Engineering Graduation Project 2020
Mahmoud Morsy
 

What's hot (20)

Formation evaluation
Formation evaluationFormation evaluation
Formation evaluation
 
Immiscible Fluid Displacement.pptx
Immiscible Fluid Displacement.pptxImmiscible Fluid Displacement.pptx
Immiscible Fluid Displacement.pptx
 
PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4
PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4
PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4
 
Well logging
Well loggingWell logging
Well logging
 
OIL RECOVERY TECHNIQUES
OIL RECOVERY TECHNIQUESOIL RECOVERY TECHNIQUES
OIL RECOVERY TECHNIQUES
 
rig types and its components
rig types and its componentsrig types and its components
rig types and its components
 
Directional Drilling 2020-2021.pdf
Directional Drilling 2020-2021.pdfDirectional Drilling 2020-2021.pdf
Directional Drilling 2020-2021.pdf
 
Well Workover
Well Workover Well Workover
Well Workover
 
Life Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsLife Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas Wells
 
Basic drilling engineering
Basic drilling engineeringBasic drilling engineering
Basic drilling engineering
 
Estmation of oil & gas proven probable posiible
Estmation of oil & gas proven probable posiibleEstmation of oil & gas proven probable posiible
Estmation of oil & gas proven probable posiible
 
Type of rig
Type of rigType of rig
Type of rig
 
Well Test Analysis in Horizontal Wells
Well Test Analysis in Horizontal WellsWell Test Analysis in Horizontal Wells
Well Test Analysis in Horizontal Wells
 
Petroleum economics
Petroleum economicsPetroleum economics
Petroleum economics
 
Source rock
Source rockSource rock
Source rock
 
formation evaluation
formation evaluationformation evaluation
formation evaluation
 
Petroleum well completion overview
Petroleum well completion overviewPetroleum well completion overview
Petroleum well completion overview
 
Blow out preventer (bop)
Blow out preventer (bop)Blow out preventer (bop)
Blow out preventer (bop)
 
Introduction to Mudlogging
Introduction to MudloggingIntroduction to Mudlogging
Introduction to Mudlogging
 
Programming in Petroleum Engineering Graduation Project 2020
Programming in Petroleum Engineering Graduation Project 2020Programming in Petroleum Engineering Graduation Project 2020
Programming in Petroleum Engineering Graduation Project 2020
 

Similar to Drill.pptx

ZBC in commodities.ppt
ZBC in commodities.pptZBC in commodities.ppt
ZBC in commodities.ppt
SoulmananIndia
 
Prefeseability study of petroleum field
Prefeseability study of petroleum fieldPrefeseability study of petroleum field
Prefeseability study of petroleum field
Safwen Sakhraoui
 
PNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxPNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docx
stilliegeorgiana
 
01 kern's method.
01 kern's method.01 kern's method.
01 kern's method.
Naveen Kushwaha
 
Cylindrical liner
Cylindrical linerCylindrical liner
Cylindrical liner
Hridoy Saha
 
Wells & Pumps Project Report
Wells & Pumps Project ReportWells & Pumps Project Report
Wells & Pumps Project Report
Mohammed Alsharekh
 
5 economics
5   economics5   economics
5 economics
amrhaggag
 
Skimming Vision System Project (4) 6th Feb 2015
Skimming Vision System Project (4) 6th Feb 2015Skimming Vision System Project (4) 6th Feb 2015
Skimming Vision System Project (4) 6th Feb 2015
John Dunne
 
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTFIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
MUHAMMAD NOMAN KHAN
 
Diesel Production: Equipments Design
Diesel Production: Equipments DesignDiesel Production: Equipments Design
Diesel Production: Equipments Design
Pratik Patel
 
2016.12.14 DryFining Coal Gen presentation FINAL
2016.12.14 DryFining Coal Gen presentation FINAL2016.12.14 DryFining Coal Gen presentation FINAL
2016.12.14 DryFining Coal Gen presentation FINAL
Sandra Broekema
 
Rectangular tank example_latest
Rectangular tank example_latestRectangular tank example_latest
Rectangular tank example_latest
Vedachalam Mani
 
Field Development Project of E11 drilling dept.ppt
Field Development Project of E11 drilling dept.pptField Development Project of E11 drilling dept.ppt
Field Development Project of E11 drilling dept.ppt
MUHAMMAD NOMAN KHAN
 
Design of Oxidation Pond
Design of Oxidation PondDesign of Oxidation Pond
Design of Oxidation Pond
Nelson Kandel
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimation
jose2424
 
Basic E&Mcalculations for a coal mining project
Basic E&Mcalculations for a coal mining projectBasic E&Mcalculations for a coal mining project
Basic E&Mcalculations for a coal mining project
Singareni Collieries Company Limited
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
kiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
kiransuresh7
 
Working Safely while saving time & cost
Working Safely while saving time & costWorking Safely while saving time & cost
Working Safely while saving time & cost
MECandPMV
 
thermal project # 2
thermal project # 2thermal project # 2
thermal project # 2
James Li
 

Similar to Drill.pptx (20)

ZBC in commodities.ppt
ZBC in commodities.pptZBC in commodities.ppt
ZBC in commodities.ppt
 
Prefeseability study of petroleum field
Prefeseability study of petroleum fieldPrefeseability study of petroleum field
Prefeseability study of petroleum field
 
PNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxPNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docx
 
01 kern's method.
01 kern's method.01 kern's method.
01 kern's method.
 
Cylindrical liner
Cylindrical linerCylindrical liner
Cylindrical liner
 
Wells & Pumps Project Report
Wells & Pumps Project ReportWells & Pumps Project Report
Wells & Pumps Project Report
 
5 economics
5   economics5   economics
5 economics
 
Skimming Vision System Project (4) 6th Feb 2015
Skimming Vision System Project (4) 6th Feb 2015Skimming Vision System Project (4) 6th Feb 2015
Skimming Vision System Project (4) 6th Feb 2015
 
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTFIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
 
Diesel Production: Equipments Design
Diesel Production: Equipments DesignDiesel Production: Equipments Design
Diesel Production: Equipments Design
 
2016.12.14 DryFining Coal Gen presentation FINAL
2016.12.14 DryFining Coal Gen presentation FINAL2016.12.14 DryFining Coal Gen presentation FINAL
2016.12.14 DryFining Coal Gen presentation FINAL
 
Rectangular tank example_latest
Rectangular tank example_latestRectangular tank example_latest
Rectangular tank example_latest
 
Field Development Project of E11 drilling dept.ppt
Field Development Project of E11 drilling dept.pptField Development Project of E11 drilling dept.ppt
Field Development Project of E11 drilling dept.ppt
 
Design of Oxidation Pond
Design of Oxidation PondDesign of Oxidation Pond
Design of Oxidation Pond
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimation
 
Basic E&Mcalculations for a coal mining project
Basic E&Mcalculations for a coal mining projectBasic E&Mcalculations for a coal mining project
Basic E&Mcalculations for a coal mining project
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Working Safely while saving time & cost
Working Safely while saving time & costWorking Safely while saving time & cost
Working Safely while saving time & cost
 
thermal project # 2
thermal project # 2thermal project # 2
thermal project # 2
 

Recently uploaded

CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
Aditya Rajan Patra
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 

Recently uploaded (20)

CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 

Drill.pptx

  • 1. OG 321 DRILLING 1 LECTURE SIX DRILLING COST AND DRILLING RATE
  • 2. DRILLING COST ANALYSIS Drilling cost predictions are made so that sound economic decision can be made The drilling engineer recommends • drilling procedures that will safely drilled and complete the well at the minimum cost possible • routine rig operations such as Drilling fluid treatment Pump operation Bit selection Any problem encountered in drilling operation
  • 3. 3 The Drilling Cost Equation Cf = drilling cost, $/ft Cb= cost of bit, $/bit Cr = fixed operating cost of rig, $/hr tb = total rotating time, hrs tc = total non-rotating time, hrs tt = total trip time (round trip), hrs D  ft D t t t C C C t c b r b f $ ) (      = footage drilled with bit, ft/bit Also known as cost per foot equation
  • 4. 4 Example A recommended bit program is being prepared for a new well using bit performance records from nearby wells. Drilling performance records for three bits are shown for a thick limestone formation at 9,000 ft. Determine which bit gives the lowest drilling cost if the operating cost of the rig is $400/hr, the trip time is 7 hours, and connection time is 1 minute per connection.
  • 5. 5 Assume that each of the bits was operated at near the minimum cost per foot attainable for that bit. Mean Bit Rotating Connection Penetration Cost Time Time Rate Bit ($) (hours) (hours) (ft/hr) A 800 14.8 0.1 13.8 B 4,900 57.7 0.4 12.6 C 4,500 95.8 0.5 10.2 Example cont’d Which bit would you select?
  • 6. 6 Solution: The cost per foot drilled for each bit type can be computed using drilling cost equation for Bit A, the cost per foot is /ft. 81 . 46 $ ) 8 . 14 ( 8 . 13 ) 7 1 . 0 8 . 14 ( 400 800      f C ft D t t t C C C t c b r b f $ ) (     
  • 7. 7 Solution: Similarly, for Bit B, /ft. 56 . 42 $ ) 7 . 57 ( 6 . 12 ) 7 4 . 0 7 . 57 ( 400 900 , 4      f C ft D t t t C C C t c b r b f $ ) (     
  • 8. 8 Solution, cont’d Finally, for Bit C, /ft. 89 . 46 $ ) 8 . 95 ( 2 . 10 ) 7 5 . 0 8 . 95 ( 400 500 , 4      f C ft D t t t C C C t c b r b f $ ) (     
  • 9. 9 Solution, cont’d Bit A: $46.81 /ft Bit B: $42.56 /ft Bit C: $46.89 /ft The lowest drilling cost was obtained using Bit B. Regardless of highest bit cost …it has intermediate bit life and ROP...
  • 10. 10 Drilling Costs • Tend to increase exponentially with depth. Thus, when curve-fitting drilling cost data, it is often convenient to assume a relationship between total well cost, C, and depth, D, given by C = aebD • Constants a and b depend primarily on the well location.
  • 11. 11 Drilling Costs, cont’d Shown on the next page is a least-squares curve fit of the south Louisiana completed well data given in Table 1.7 (ADE book) Depth range of 7,500 ft to 21,000 ft. For these data, a = 1 X 105 dollars b = 2 X 10-4 ft -1. C = aebD
  • 12. 12 Fig. 1-65. Least-square curve fit of 1978 completed well costs for wells below 7,500 ft in the south Louisiana area.
  • 13. 13 Penetration Rate When major variations are not present in the subsurface lithology, the penetration rate usually decreases exponentially with depth. Under these conditions, the penetration rate can be related to depth, D, by where K and a2 are constants. D a Ke dt dD 2 303 . 2  
  • 14. 14 Drilling Time The drilling time, td , required to drill to a given depth can be obtained by separating variables and integrating. Separating variables gives dD e dt K D a 303 . 2 D 0 t 0 2 d    Integrating and solving for td yields ) 1 ( 303 . 2 1 2 303 . 2 2   D a d e K a t
  • 15. 15 Drilling Time cont’d Plotting depth vs. drilling time from past drilling operations: • Allows more accurate prediction of time and cost for drilling a new well • Is used in evaluating new drilling procedures (designed to reduce drilling time to a given depth).
  • 16. 16 EXAMPLE - Cost per ft t R D Total Cost Cf hr fph ft $ $/ft 5 90 475 36,950 77.80 10 80 900 47,800 53.10 20 60 1,600 69,200 43.30 25 50 1,875 79,750 42.50 30 40 2,100 90,200 43.00 35 30 2,275 100,550 44.20 40 20 2,400 110,800 46.20 These cost data are plotted below.
  • 17. 17 Cost per ft for one entire bit run Minimum Cost 80 70 60 50 40
  • 18. 18 Economic Procedure in previous Table  Can pull bit after about 25 hr. ($42.50/ft) - the precise pulling time is not critical Note that the cost in dollars per foot was $43.00 after 30 hr.  Primarily applicable to tooth-type bits where wear rate is predictable.
  • 19. 19 Economic Procedure in above Table  Also used with tungsten carbide insert bits when inserts are broken or pulled out of the matrix.  Unfortunately, wear rate with insert bits is unpredictable.  Economically, the insert bit should be pulled when the cost in $/ft begins to increase.
  • 20. 20 Economic Procedure in Table – Bits pulled for economic reasons make it hard to obtain wear information. – Operator might pull bit after 120 hr of use but part of bit might get left in hole. Recovery is very difficult. Avoid! – 75% of rock bits are pulled green or before the bit is worn out.
  • 21. 21 An increase in TORQUE may indicate that a bit should be pulled. Experience often dictates when to pull bit (footage or hours).
  • 22. 22 Factors that affect Penetration Rate  Type of Drill bit  Bit weight  Rotary speed  Bottom-hole cleaning  Mud properties  Rock hardness  Formation pore pressure Variables: Fixed Factors:
  • 23. 23 Bit Selection is based on  Past bit records  Geologic predictions of lithology  Drilling costs in $/bit...  Drilling cost in $/ft
  • 24. 24 Bit Weight and Rotary Speed • Increasing bit weight and rotary speed boosts drilling rate • These increases accelerate bit wear • Field tests show that drilling rate increases more or less in direct proportion to bit weight
  • 25. 25 Consider 10” hole (don’t overdo!!) Bit Weight x 1,000 lb/in 40,000 lbf
  • 26. 26 Rotary Speed, RPM Don’t overdo! Casing wear, bit life ...
  • 27. 27 EFFECT OF BACK PRESSURE Keep P_bit = const.= 550 psi
  • 28. 28 Hydrostatic Pressure, 1,000’s of psi EFFECT OF BACK PRESSURE 0 - 5,000 psi
  • 29. 29 Drilling Time, days Drilled with gas Drilled with mud EFFECT OF DRILLING FLUID mud vs. gas
  • 30. 30 Rotating Time, hours EFFECT OF DRILLING FLUID water vs. air
  • 31. 31 Old style water course bits
  • 32. 32 EFFECT OF SOLIDS IN THE MUD