SlideShare a Scribd company logo
10/22/2013
Movement to the full
Digital Substation
CIGRE
Ravindranauth Ramlachan
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 2
• Safety issues – equipment isolation, touch and step potentials, EMC
• Copper – raw material cost has increased 400% in 10 years
• Material cost – cubicle wiring and test costs, labour cost per wire end
termination
• Schematic design - verification cost, excessive on-site work content
• Civil work costs – trays, troughing, cable access/egress…
• Maintainability cost
Why Digital - Wiring, wiring, wiring…….
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 3
What is a Digital Substation?
Digital substations are those which have embedded processing
intelligence in order to implement part of their operational duties,
and as such typically exceed the capability of their analogue
predecessors. The intelligence adds:
• Ease of use
• Asset management
• Modularity
• Vendor interoperability
• Real time awareness
Realized by digitizing the data related to the primary process at
the point where it is measured
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 4
The Digital Substation – Architect Levels
CIT & NCIT
CTs and VTs
Station Control
Protection and
Control
Primary
Equipment
Process
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 5
Key Drivers
Improved Safety
-Eliminate open circuit CTs
Asset Optimisation
-Intelligent monitoring of equipment
Reduced Maintenance Cost
-Condition-based maintenance
Optimisation of New Investments
Increased Reliability and Availability
extensive self-diagnosis capability, redundancy
Why install a digital substation?
“Not only does it optimise overall lifecycle costs, it is easier
to use. Asset managers now have a vital tool that, with less
wiring and fewer commissioning tests, accommodates
preventive maintenance and can extend transformer and
switchgear lifetime. Digital substations are modular, so they
can be tailored to system needs and open to third-party
devices. It is easy to retrofit protection and control schemes
with minimal outage constraints. Ultimately, operators
manage a smarter grid, with better, more complete real-time
situational awareness, making the system more available and
secure.”
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 6
Key Drivers
Standardisation and Interoperability
-Multi Vendor
Ease of Refurbishment
-Refurbish with minimum primary outage
Improved communication capability
-Data available to all levels
Environmental Responsibility
-Wiring is reduced by typically 80%.
Why install a digital substation?
“Not only does it optimise overall lifecycle costs, it is easier
to use. Asset managers now have a vital tool that, with less
wiring and fewer commissioning tests, accommodates
preventive maintenance and can extend transformer and
switchgear lifetime. Digital substations are modular, so they
can be tailored to system needs and open to third-party
devices. It is easy to retrofit protection and control schemes
with minimal outage constraints. Ultimately, operators
manage a smarter grid, with better, more complete real-time
situational awareness, making the system more available and
secure.”
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 7
Technology Enablers and Standards
• Ethernet (typically 100Mbit/s, moving towards 1Gb)
• IEC 61850
−IEC 61850-8-1 and GOOSE Service
−IEC 61850-9-2LE for Sample Values
• IEC 62439-3
−PRP for redundant star architecture
−HSR for redundant ring architecture
• IEEE C37.118 – phasor measurement
• Precision time synchronising (µs)
−GPS (1pps)
−IEEE 1588
• Non Conventional CTs (NCIT) & Merging Units (MU)
• Cyber security
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 8
What does IEC 61850 solve?
Control Centre HMI, Station
controller
Gateway
Relay
X1
Bay
Controller
Conventional
Switchgear
Conventional
CT / VT's
Relay
X2
Relay
X1
Bay
Controller
Conventional
Switchgear
Relay
X2
Conventional
CT / VT's
Vendor specific protocols like LON, MVB, SPA,
Profibus, FIP, DNP3.0, Modbus etc
Hardwired with parallel Cu wires
Serial communications
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 9
What does IEC 61850 solve?
Control Centre
Router
Relay
X1
Bay
Controller
Intelligent
Switchgear
Non
conventional
CT/VT
Relay
X2
Relay
X1
Bay
Controller
Intelligent
Switchgear
Relay
X2
Non
conventional
CT/VT
HMI, Station
controller
Ethernet communications
Ethernet communications
Station Bus
Process Bus
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 10
The Digital Substation
CIT & NCIT
CTs and VTs
Enablers
-Ethernet
-Redundancy
-61850
-Station Bus
-Process Bus
-Precision Timing
-NCIT/MU
-Cyber Security
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 11
NCIT Advantages
• Cost Savings (particularly at voltages above 200kV)
− Compact and lightweight primary current and voltage transformers
− Space-efficient, easily transportable
• Digital Standard IEC 61850-9.2 - Interoperability
− Interoperability between conventional CT/VTs, other vendors supporting IEC
61850-9.2, and test equipment
− Ease of integration in the Total Digital Substation.
• Safety - Reliability - Availability
− No explosion risk
− No wired cross-site CT connection
• Measurement Improvement
− No saturation, no ferroresonance, accurate transient response
− High bandwidth: Wide dynamic range for Protection short circuits, whilst
retaining accuracy for low-current Measurement
• Exploitation Ease
− Ethernet distribution of sampled analogue values to multiple devices
− Ease of extension or modification without affecting physical wiring
− Measurement class accuracy and Protection dynamic range
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 12
Digital Substation Challenges
• Redundancy
• Extends to communication network
• Same considerations as with “traditional” substation
• Testing
• How to isolate and test
• Precision Timing
• Common time source needed
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 13
Architecture Redundancy Considerations
• There are numerous ways to increase the reliability and availability of
a digital substation through redundancy
− Redundant sensors
− Redundant IEDs
− Redundant networks
Station Bus (Redundant PRP)
Main
GOOSE A
GOOSE
B
Prot
B Backup
MUs A/B Main
MUs A/B
CB Control /
RTU
GOOSE & MMS
Prot
A
Main
GOOSE & MMS
Process Bus (Duplicated A/B)
Process Bus (Redundant PRP)
Switch (Process / Station bus
boundary)
SV
SV
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 14
SV considerations – isolation and testing
• Set IED into ‘Simulation’ mode
• IED processes SV frames with Test/Simulation indication
set
−Does not operate IED trip outputs
IED
Sim=TRUE
MU1
Simulator
MU1
(process) X
SV Sim=FALSE
SV Sim=TRUE
Prot
Functions
Trip
values Output
X
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 15
Merging Unit considerations – SV delays
• Different delay in samples from different MUs
−could be from different vendors
IEC 61850
Merging Unit 1
Ethernet
Switch
IA1, IB 1, IC 1
IEC 61850
Merging Unit 2
IEC 61850
Merging Unit 3
IY1
IA3, IB 3, IC3
IY 2
IA5, IB 5, IC5
IY 3
VA , VB , VC
Protection
IED
-
9
-
2
L
E
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 16
Merging Unit considerations – SV delays
• Need each MU to be accurately synchronized
−1 PPS, IEEE 1588 PTP
• IED processes global/local synchronization indication for SV received
−Adapts protection functions – e.g. inhibits current differential
−Alarms on loss of synchronization
• IED should align SV according to maximum time delay between subscribed Merging
Units
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 17
Presentation title - 01/01/2010 - P 17
Pilot Project – ENDESA, Spain
ENDESA substation:
SE Llobregat
145kV
Pilot Projects
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 18
Pilot Project – ENERGIENET, Denmark
ENERGINET: Denmark – Full digital solution
6 Underground 420 kV Cables differential monitoring
OHL
420kV
3000A
RF 1.2
Diff 1
Cable 1 - 420kV
1500A - RF 2
> 20km
NXMU ’s
In : 3 currents
Out : 2x 61850 9 -2LE
Diff 2
Redundancy
Cable 2 - 420kV
1500A - RF 2
> 20km
9 - 2LE 9 - 2LE
9 - 2LE
9 - 2LE
MICOM
P594
1PPS
MICOM
P594
1PPS
AIS scope:
• 72 COSI CT420
• 24 COSI NXMU
SAS scope:
• 24 P546
• 12 P594
x6
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 19
The Digital Substation: Conclusion
• The Digital Substation requires:
− A common, coherent solution integrated using modern communication
architectures
− An optimized solution for customers, with reduced costs of ownership and higher
performance
• This is supported by the application of IEC 61850 within the substation :
− Digitization of data at source
− Implementation of “real-time” communications
− Integration of all control, measurement, protection and monitoring functions
− Test features
www.alstom.com
With Alstom, preserve the environment.
Is printing this presentation really necessary?

More Related Content

What's hot

smart grid
smart grid smart grid
smart grid
Molla Morshad
 
“MODELING AND ANALYSIS OF DC-DC CONVERTER FOR RENEWABLE ENERGY SYSTEM” Final...
“MODELING AND ANALYSIS OF DC-DC CONVERTER  FOR RENEWABLE ENERGY SYSTEM” Final...“MODELING AND ANALYSIS OF DC-DC CONVERTER  FOR RENEWABLE ENERGY SYSTEM” Final...
“MODELING AND ANALYSIS OF DC-DC CONVERTER FOR RENEWABLE ENERGY SYSTEM” Final...
8381801685
 
Minimizing losses in power distribution system
Minimizing losses in power distribution systemMinimizing losses in power distribution system
Minimizing losses in power distribution system
harshal567
 
Technical seminar
Technical seminarTechnical seminar
Technical seminar
Mihir Acharya
 
UNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMUNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEM
erramansaini1947
 
Protection and control of Microgrid
Protection and control of MicrogridProtection and control of Microgrid
Protection and control of Microgrid
Amarjeet S Pandey
 
SMART GRID TECHNOLOGY
SMART GRID TECHNOLOGYSMART GRID TECHNOLOGY
SMART GRID TECHNOLOGY
asegekar18
 
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMSLOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
Editor IJMTER
 
Solar Power Based Micro Grid Systems.pptx
Solar Power Based Micro Grid Systems.pptxSolar Power Based Micro Grid Systems.pptx
Solar Power Based Micro Grid Systems.pptx
Niuru Ranaweera
 
Flywheel Energy Storage System
Flywheel Energy Storage SystemFlywheel Energy Storage System
Flywheel Energy Storage System
Seminar Links
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
Ang Sovann
 
Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relay
CS V
 
Smart grid ppt
Smart grid pptSmart grid ppt
Smart grid ppt
Ravish Pandey
 
Faults on Power System
Faults on Power SystemFaults on Power System
Faults on Power System
Vinod Srivastava
 
Smart power grid
Smart power gridSmart power grid
Smart power gridk shiva
 
Automated Meter Reading System
Automated Meter Reading SystemAutomated Meter Reading System
Automated Meter Reading System
Umang Dhuri
 
Earthing Syatem
Earthing SyatemEarthing Syatem
Earthing SyatemNoman Khan
 
Decentralized Generation In Microgrids
Decentralized Generation In MicrogridsDecentralized Generation In Microgrids
Decentralized Generation In Microgrids
Juan C. Vasquez
 

What's hot (20)

smart grid
smart grid smart grid
smart grid
 
Smart grid
Smart gridSmart grid
Smart grid
 
“MODELING AND ANALYSIS OF DC-DC CONVERTER FOR RENEWABLE ENERGY SYSTEM” Final...
“MODELING AND ANALYSIS OF DC-DC CONVERTER  FOR RENEWABLE ENERGY SYSTEM” Final...“MODELING AND ANALYSIS OF DC-DC CONVERTER  FOR RENEWABLE ENERGY SYSTEM” Final...
“MODELING AND ANALYSIS OF DC-DC CONVERTER FOR RENEWABLE ENERGY SYSTEM” Final...
 
ppt on Smart Grid
ppt on Smart Gridppt on Smart Grid
ppt on Smart Grid
 
Minimizing losses in power distribution system
Minimizing losses in power distribution systemMinimizing losses in power distribution system
Minimizing losses in power distribution system
 
Technical seminar
Technical seminarTechnical seminar
Technical seminar
 
UNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMUNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEM
 
Protection and control of Microgrid
Protection and control of MicrogridProtection and control of Microgrid
Protection and control of Microgrid
 
SMART GRID TECHNOLOGY
SMART GRID TECHNOLOGYSMART GRID TECHNOLOGY
SMART GRID TECHNOLOGY
 
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMSLOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
 
Solar Power Based Micro Grid Systems.pptx
Solar Power Based Micro Grid Systems.pptxSolar Power Based Micro Grid Systems.pptx
Solar Power Based Micro Grid Systems.pptx
 
Flywheel Energy Storage System
Flywheel Energy Storage SystemFlywheel Energy Storage System
Flywheel Energy Storage System
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
 
Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relay
 
Smart grid ppt
Smart grid pptSmart grid ppt
Smart grid ppt
 
Faults on Power System
Faults on Power SystemFaults on Power System
Faults on Power System
 
Smart power grid
Smart power gridSmart power grid
Smart power grid
 
Automated Meter Reading System
Automated Meter Reading SystemAutomated Meter Reading System
Automated Meter Reading System
 
Earthing Syatem
Earthing SyatemEarthing Syatem
Earthing Syatem
 
Decentralized Generation In Microgrids
Decentralized Generation In MicrogridsDecentralized Generation In Microgrids
Decentralized Generation In Microgrids
 

Similar to Digital-Substation-ALSTOM.pdf

Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...
Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...
Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...
MobileMonday Switzerland
 
Building Next Generation Transport Networks
Building Next Generation Transport NetworksBuilding Next Generation Transport Networks
Building Next Generation Transport Networks
Infinera
 
Elevator pitches from Digital Railways competition consortia building day
Elevator pitches from Digital Railways competition consortia building dayElevator pitches from Digital Railways competition consortia building day
Elevator pitches from Digital Railways competition consortia building day
KTN
 
Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...
Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...
Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...
ADVA
 
Stork Presentation on Migration (Willem Hazenberg)
Stork Presentation on Migration (Willem Hazenberg)Stork Presentation on Migration (Willem Hazenberg)
Stork Presentation on Migration (Willem Hazenberg)
ARC Advisory Group
 
Smart Grid Deployment Experience and Utility Case Studies
Smart Grid Deployment Experience and Utility Case StudiesSmart Grid Deployment Experience and Utility Case Studies
Smart Grid Deployment Experience and Utility Case Studies
Tata Power Delhi Distribution Limited
 
teltonika-networks-use-case-catalog-v1.2.pdf
teltonika-networks-use-case-catalog-v1.2.pdfteltonika-networks-use-case-catalog-v1.2.pdf
teltonika-networks-use-case-catalog-v1.2.pdf
itsamihaland
 
Protection, Automation and Monitoring: SIPROTEC 5 v7.9/v8.0
Protection, Automation and Monitoring:  SIPROTEC 5 v7.9/v8.0Protection, Automation and Monitoring:  SIPROTEC 5 v7.9/v8.0
Protection, Automation and Monitoring: SIPROTEC 5 v7.9/v8.0
Ryan O'Mara
 
Strainlabs - Wireless sensor technology for a predictable future
Strainlabs - Wireless sensor technology for a predictable futureStrainlabs - Wireless sensor technology for a predictable future
Strainlabs - Wireless sensor technology for a predictable future
Gösta Rydin
 
Estimating the cost of a CCS System - Jean-François Léandri, Alstom
Estimating the cost of a CCS System - Jean-François Léandri, AlstomEstimating the cost of a CCS System - Jean-François Léandri, Alstom
Estimating the cost of a CCS System - Jean-François Léandri, Alstom
Global CCS Institute
 
BRKIOT-2108.pdf
BRKIOT-2108.pdfBRKIOT-2108.pdf
BRKIOT-2108.pdf
JokaTek
 
Splunk for Monitoring and Diagnostics Breakout Session
Splunk for Monitoring and Diagnostics Breakout SessionSplunk for Monitoring and Diagnostics Breakout Session
Splunk for Monitoring and Diagnostics Breakout Session
Splunk
 
Fluke Connect Condition Based Maintenance
Fluke Connect Condition Based MaintenanceFluke Connect Condition Based Maintenance
Fluke Connect Condition Based MaintenanceFrederic Baudart, CMRP
 
5G SA security: a comprehensive overview of threats, vulnerabilities and rem...
 5G SA security: a comprehensive overview of threats, vulnerabilities and rem... 5G SA security: a comprehensive overview of threats, vulnerabilities and rem...
5G SA security: a comprehensive overview of threats, vulnerabilities and rem...
PositiveTechnologies
 
MohdRiyazKhan_Resume
MohdRiyazKhan_ResumeMohdRiyazKhan_Resume
MohdRiyazKhan_ResumeRIYAZ Khan
 
IRJET- Secure and Efficient Transmission Mechanism for Emergency Data in ...
IRJET-  	  Secure and Efficient Transmission Mechanism for Emergency Data in ...IRJET-  	  Secure and Efficient Transmission Mechanism for Emergency Data in ...
IRJET- Secure and Efficient Transmission Mechanism for Emergency Data in ...
IRJET Journal
 
Asset Utilization Metrics Propel a Revival in Safety Solutions
Asset Utilization Metrics Propel a Revival in Safety SolutionsAsset Utilization Metrics Propel a Revival in Safety Solutions
Asset Utilization Metrics Propel a Revival in Safety Solutions
ARC Advisory Group
 
Ge specialized Protection Numerical Relays
Ge specialized Protection Numerical RelaysGe specialized Protection Numerical Relays
Ge specialized Protection Numerical Relays
Digital and Smart Grid Enterprises
 
Ge network stability and control relay
Ge network stability and control relayGe network stability and control relay
Ge network stability and control relay
Digital and Smart Grid Enterprises
 

Similar to Digital-Substation-ALSTOM.pdf (20)

Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...
Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...
Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...
 
EWTEC_Presentation_v2
EWTEC_Presentation_v2EWTEC_Presentation_v2
EWTEC_Presentation_v2
 
Building Next Generation Transport Networks
Building Next Generation Transport NetworksBuilding Next Generation Transport Networks
Building Next Generation Transport Networks
 
Elevator pitches from Digital Railways competition consortia building day
Elevator pitches from Digital Railways competition consortia building dayElevator pitches from Digital Railways competition consortia building day
Elevator pitches from Digital Railways competition consortia building day
 
Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...
Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...
Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...
 
Stork Presentation on Migration (Willem Hazenberg)
Stork Presentation on Migration (Willem Hazenberg)Stork Presentation on Migration (Willem Hazenberg)
Stork Presentation on Migration (Willem Hazenberg)
 
Smart Grid Deployment Experience and Utility Case Studies
Smart Grid Deployment Experience and Utility Case StudiesSmart Grid Deployment Experience and Utility Case Studies
Smart Grid Deployment Experience and Utility Case Studies
 
teltonika-networks-use-case-catalog-v1.2.pdf
teltonika-networks-use-case-catalog-v1.2.pdfteltonika-networks-use-case-catalog-v1.2.pdf
teltonika-networks-use-case-catalog-v1.2.pdf
 
Protection, Automation and Monitoring: SIPROTEC 5 v7.9/v8.0
Protection, Automation and Monitoring:  SIPROTEC 5 v7.9/v8.0Protection, Automation and Monitoring:  SIPROTEC 5 v7.9/v8.0
Protection, Automation and Monitoring: SIPROTEC 5 v7.9/v8.0
 
Strainlabs - Wireless sensor technology for a predictable future
Strainlabs - Wireless sensor technology for a predictable futureStrainlabs - Wireless sensor technology for a predictable future
Strainlabs - Wireless sensor technology for a predictable future
 
Estimating the cost of a CCS System - Jean-François Léandri, Alstom
Estimating the cost of a CCS System - Jean-François Léandri, AlstomEstimating the cost of a CCS System - Jean-François Léandri, Alstom
Estimating the cost of a CCS System - Jean-François Léandri, Alstom
 
BRKIOT-2108.pdf
BRKIOT-2108.pdfBRKIOT-2108.pdf
BRKIOT-2108.pdf
 
Splunk for Monitoring and Diagnostics Breakout Session
Splunk for Monitoring and Diagnostics Breakout SessionSplunk for Monitoring and Diagnostics Breakout Session
Splunk for Monitoring and Diagnostics Breakout Session
 
Fluke Connect Condition Based Maintenance
Fluke Connect Condition Based MaintenanceFluke Connect Condition Based Maintenance
Fluke Connect Condition Based Maintenance
 
5G SA security: a comprehensive overview of threats, vulnerabilities and rem...
 5G SA security: a comprehensive overview of threats, vulnerabilities and rem... 5G SA security: a comprehensive overview of threats, vulnerabilities and rem...
5G SA security: a comprehensive overview of threats, vulnerabilities and rem...
 
MohdRiyazKhan_Resume
MohdRiyazKhan_ResumeMohdRiyazKhan_Resume
MohdRiyazKhan_Resume
 
IRJET- Secure and Efficient Transmission Mechanism for Emergency Data in ...
IRJET-  	  Secure and Efficient Transmission Mechanism for Emergency Data in ...IRJET-  	  Secure and Efficient Transmission Mechanism for Emergency Data in ...
IRJET- Secure and Efficient Transmission Mechanism for Emergency Data in ...
 
Asset Utilization Metrics Propel a Revival in Safety Solutions
Asset Utilization Metrics Propel a Revival in Safety SolutionsAsset Utilization Metrics Propel a Revival in Safety Solutions
Asset Utilization Metrics Propel a Revival in Safety Solutions
 
Ge specialized Protection Numerical Relays
Ge specialized Protection Numerical RelaysGe specialized Protection Numerical Relays
Ge specialized Protection Numerical Relays
 
Ge network stability and control relay
Ge network stability and control relayGe network stability and control relay
Ge network stability and control relay
 

Recently uploaded

一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
The Role of Electrical and Electronics Engineers in IOT Technology.pdf
The Role of Electrical and Electronics Engineers in IOT Technology.pdfThe Role of Electrical and Electronics Engineers in IOT Technology.pdf
The Role of Electrical and Electronics Engineers in IOT Technology.pdf
Nettur Technical Training Foundation
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 

Recently uploaded (20)

一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
The Role of Electrical and Electronics Engineers in IOT Technology.pdf
The Role of Electrical and Electronics Engineers in IOT Technology.pdfThe Role of Electrical and Electronics Engineers in IOT Technology.pdf
The Role of Electrical and Electronics Engineers in IOT Technology.pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 

Digital-Substation-ALSTOM.pdf

  • 1. 10/22/2013 Movement to the full Digital Substation CIGRE Ravindranauth Ramlachan
  • 2. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 2 • Safety issues – equipment isolation, touch and step potentials, EMC • Copper – raw material cost has increased 400% in 10 years • Material cost – cubicle wiring and test costs, labour cost per wire end termination • Schematic design - verification cost, excessive on-site work content • Civil work costs – trays, troughing, cable access/egress… • Maintainability cost Why Digital - Wiring, wiring, wiring…….
  • 3. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 3 What is a Digital Substation? Digital substations are those which have embedded processing intelligence in order to implement part of their operational duties, and as such typically exceed the capability of their analogue predecessors. The intelligence adds: • Ease of use • Asset management • Modularity • Vendor interoperability • Real time awareness Realized by digitizing the data related to the primary process at the point where it is measured
  • 4. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 4 The Digital Substation – Architect Levels CIT & NCIT CTs and VTs Station Control Protection and Control Primary Equipment Process
  • 5. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 5 Key Drivers Improved Safety -Eliminate open circuit CTs Asset Optimisation -Intelligent monitoring of equipment Reduced Maintenance Cost -Condition-based maintenance Optimisation of New Investments Increased Reliability and Availability extensive self-diagnosis capability, redundancy Why install a digital substation? “Not only does it optimise overall lifecycle costs, it is easier to use. Asset managers now have a vital tool that, with less wiring and fewer commissioning tests, accommodates preventive maintenance and can extend transformer and switchgear lifetime. Digital substations are modular, so they can be tailored to system needs and open to third-party devices. It is easy to retrofit protection and control schemes with minimal outage constraints. Ultimately, operators manage a smarter grid, with better, more complete real-time situational awareness, making the system more available and secure.”
  • 6. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 6 Key Drivers Standardisation and Interoperability -Multi Vendor Ease of Refurbishment -Refurbish with minimum primary outage Improved communication capability -Data available to all levels Environmental Responsibility -Wiring is reduced by typically 80%. Why install a digital substation? “Not only does it optimise overall lifecycle costs, it is easier to use. Asset managers now have a vital tool that, with less wiring and fewer commissioning tests, accommodates preventive maintenance and can extend transformer and switchgear lifetime. Digital substations are modular, so they can be tailored to system needs and open to third-party devices. It is easy to retrofit protection and control schemes with minimal outage constraints. Ultimately, operators manage a smarter grid, with better, more complete real-time situational awareness, making the system more available and secure.”
  • 7. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 7 Technology Enablers and Standards • Ethernet (typically 100Mbit/s, moving towards 1Gb) • IEC 61850 −IEC 61850-8-1 and GOOSE Service −IEC 61850-9-2LE for Sample Values • IEC 62439-3 −PRP for redundant star architecture −HSR for redundant ring architecture • IEEE C37.118 – phasor measurement • Precision time synchronising (µs) −GPS (1pps) −IEEE 1588 • Non Conventional CTs (NCIT) & Merging Units (MU) • Cyber security
  • 8. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 8 What does IEC 61850 solve? Control Centre HMI, Station controller Gateway Relay X1 Bay Controller Conventional Switchgear Conventional CT / VT's Relay X2 Relay X1 Bay Controller Conventional Switchgear Relay X2 Conventional CT / VT's Vendor specific protocols like LON, MVB, SPA, Profibus, FIP, DNP3.0, Modbus etc Hardwired with parallel Cu wires Serial communications
  • 9. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 9 What does IEC 61850 solve? Control Centre Router Relay X1 Bay Controller Intelligent Switchgear Non conventional CT/VT Relay X2 Relay X1 Bay Controller Intelligent Switchgear Relay X2 Non conventional CT/VT HMI, Station controller Ethernet communications Ethernet communications Station Bus Process Bus
  • 10. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 10 The Digital Substation CIT & NCIT CTs and VTs Enablers -Ethernet -Redundancy -61850 -Station Bus -Process Bus -Precision Timing -NCIT/MU -Cyber Security
  • 11. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 11 NCIT Advantages • Cost Savings (particularly at voltages above 200kV) − Compact and lightweight primary current and voltage transformers − Space-efficient, easily transportable • Digital Standard IEC 61850-9.2 - Interoperability − Interoperability between conventional CT/VTs, other vendors supporting IEC 61850-9.2, and test equipment − Ease of integration in the Total Digital Substation. • Safety - Reliability - Availability − No explosion risk − No wired cross-site CT connection • Measurement Improvement − No saturation, no ferroresonance, accurate transient response − High bandwidth: Wide dynamic range for Protection short circuits, whilst retaining accuracy for low-current Measurement • Exploitation Ease − Ethernet distribution of sampled analogue values to multiple devices − Ease of extension or modification without affecting physical wiring − Measurement class accuracy and Protection dynamic range
  • 12. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 12 Digital Substation Challenges • Redundancy • Extends to communication network • Same considerations as with “traditional” substation • Testing • How to isolate and test • Precision Timing • Common time source needed
  • 13. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 13 Architecture Redundancy Considerations • There are numerous ways to increase the reliability and availability of a digital substation through redundancy − Redundant sensors − Redundant IEDs − Redundant networks Station Bus (Redundant PRP) Main GOOSE A GOOSE B Prot B Backup MUs A/B Main MUs A/B CB Control / RTU GOOSE & MMS Prot A Main GOOSE & MMS Process Bus (Duplicated A/B) Process Bus (Redundant PRP) Switch (Process / Station bus boundary) SV SV
  • 14. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 14 SV considerations – isolation and testing • Set IED into ‘Simulation’ mode • IED processes SV frames with Test/Simulation indication set −Does not operate IED trip outputs IED Sim=TRUE MU1 Simulator MU1 (process) X SV Sim=FALSE SV Sim=TRUE Prot Functions Trip values Output X
  • 15. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 15 Merging Unit considerations – SV delays • Different delay in samples from different MUs −could be from different vendors IEC 61850 Merging Unit 1 Ethernet Switch IA1, IB 1, IC 1 IEC 61850 Merging Unit 2 IEC 61850 Merging Unit 3 IY1 IA3, IB 3, IC3 IY 2 IA5, IB 5, IC5 IY 3 VA , VB , VC Protection IED - 9 - 2 L E
  • 16. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 16 Merging Unit considerations – SV delays • Need each MU to be accurately synchronized −1 PPS, IEEE 1588 PTP • IED processes global/local synchronization indication for SV received −Adapts protection functions – e.g. inhibits current differential −Alarms on loss of synchronization • IED should align SV according to maximum time delay between subscribed Merging Units
  • 17. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 17 Presentation title - 01/01/2010 - P 17 Pilot Project – ENDESA, Spain ENDESA substation: SE Llobregat 145kV Pilot Projects
  • 18. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 18 Pilot Project – ENERGIENET, Denmark ENERGINET: Denmark – Full digital solution 6 Underground 420 kV Cables differential monitoring OHL 420kV 3000A RF 1.2 Diff 1 Cable 1 - 420kV 1500A - RF 2 > 20km NXMU ’s In : 3 currents Out : 2x 61850 9 -2LE Diff 2 Redundancy Cable 2 - 420kV 1500A - RF 2 > 20km 9 - 2LE 9 - 2LE 9 - 2LE 9 - 2LE MICOM P594 1PPS MICOM P594 1PPS AIS scope: • 72 COSI CT420 • 24 COSI NXMU SAS scope: • 24 P546 • 12 P594 x6
  • 19. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 19 The Digital Substation: Conclusion • The Digital Substation requires: − A common, coherent solution integrated using modern communication architectures − An optimized solution for customers, with reduced costs of ownership and higher performance • This is supported by the application of IEC 61850 within the substation : − Digitization of data at source − Implementation of “real-time” communications − Integration of all control, measurement, protection and monitoring functions − Test features
  • 20. www.alstom.com With Alstom, preserve the environment. Is printing this presentation really necessary?