SlideShare a Scribd company logo
1 of 8
Download to read offline
Make out most of your timing tests
Abstract
The timing tests are made to determine the time required for circuit-breakers or components to
operate on open, close, close-open and reclosing operations. However, everybody is aware that on
circuit-breakers, those are the typically used test sequences. But what do they really mean? How do
they refer to the standards?
Introduction
A circuit-breaker is a mechanical switching device, capable of making, carrying, and breaking currents
under normal circuit conditions, also making and carrying for a specified time, and breaking currents
under specified abnormal circuit conditions such as those of short-circuit. Therefore this constitutes
an important and critical component in the electric power system. During commissioning and
maintenance of circuit-breakers, one of the most common offline test methods have been the timing
tests, among others; a brief explanation of these tests is: measure the mechanical operation time
when the circuit-breaker is performing a mechanical sequence under no-load condition. So, this paper
presents the explanation of the standards for each test sequence and then, the application and how
to interpret the results of the timing tests.
Timing tests and Standards
The standards IEC 62271-100 and ANSI C37.100-1992 both contain explanations of sequences and
operations defined for circuit-breakers. In fact, the sequences defined are close (C), open (O), close-
open (CO) and open-close (O-C); and then the rated operating sequences or duty cycles.
Firstly, timing tests are done in the factory during the routine tests, then typically during the
commissioning tests. In addition to timing tests, during the routine tests is also measured time spread
between units of one pole and between poles, recharging time of the operating mechanism device,
consumption of the tripping and closing devices and possible recording of the current of the releases,
duration of opening and closing command impulses, ohmic resistance of the main circuit and time-
travel chart, among others. The assessment of these tests, during the commissioning or maintenance
is done comparing the results obtained with the results obtained in the routine tests.
Opening time
The opening time is measured during an operation by which the device is brought from the closed
position to the open position. The letter O signifies this operation. According to the standards
mentioned above, the opening time is the interval of time between the instant of energizing the
opening release, the circuit-breaker being in the closed position, and the instant when the arcing
contacts have separated in all the poles. If the circuit-breaker has more than one interrupting unit per
pole, the instant when the arcing contacts have separated in all poles is determined as the instant of
contact separation in the first unit of the last pole. Figure No. 1 illustrates the opening operation
according to IEC 62271-100.
Figure No. 1 Opening operation
However, on site, while the commissioning, maintenance and during no-load operation, when the
opening timing test is performed, just is possible to measure the opening time, such as seen in the
Figure No. 1a. The arcing and break times are not possible to measure because there is no way to
measure the arc duration and extinction when the circuit breaker is performing a no-load operation.
Figure No. 1a Opening timing test
Closing time
The closing time is measured during an operation by which the device is brought from the open
position to the closed position. The letter C signifies this operation. The closing time is the interval of
time between energizing the closing circuit, the circuit-breaker being in the open position, and the
instant when the contacts touch in all poles. This closing time includes the operating time of any
auxiliary equipment necessary to close the circuit-breaker and forming an integral part of the circuit-
breaker. The Figure No. 2 illustrates the closing operation according to IEC 62271-100.
Figure No. 2 Closing operation
So, for the same reasons that the arcing time cannot be measured as was explained in the opening
operation, also the pre-arcing time cannot be measured. While commissioning, maintenance and
during no-load operation when the closing test is performed, just is possible to measure the closing
time. Just as shown in figure 2a.
Figure No. 2a Closing timing test
Simultaneity or synchronization
When timing tests are performed, is essential to analyze the synchronization time between poles and
interrupting units per pole, as long as there more than one interrupting unit per pole. In fact, according
to IEC 62271-100 and ANSI C37.04-1999, when no special requirement with respect to simultaneous
operation of poles is stated, the maximum difference during opening shall not exceed 1/6 of a cycle
of rate frequency and during the closing shall not exceed 1/4 of a cycle of rate frequency as well.
Figure No. 3a Synchronization time closing operation Figure No. 3b Synchronization time opening operation
If one pole consists of more than one interrupter unit connected in series, the maximum difference
between the instants of contact separation within these series connected interrupter units shall not
exceed 1/8 of a cycle of rated frequency, and between the instants of contacts touching within these
series connected interrupter units shall not exceed a 1/6 of a cycle of rated frequency. Sometimes,
the simultaneity of poles also is called time spread between poles or between units of one pole. In the
figure 3c are showed the synchronization times.
Figure No. 3c Synchronization times
Close-open time
The close-open time is measured during an operation by which the device is brought from the open
position to the closed position followed immediately by an open operation without purposely delayed
action. The letters CO signify this operation. The close-open time is the interval of time between the
instant when the contacts touch in the first pole during a closing operation and the instant when the
arcing contacts have separated in all poles during the subsequent opening operation. The Figure No.
4 illustrates the closing operation described by the standard IEC 62271-100.
Figure No. 4 Close-open operation
This sequence also is known with the name of short-circuit time or trip-free operation. With this
sequence also is possible to perform the simulation of fault-making operation, or in other words, a
tripping operation after the circuit-breaker has been closed under a fault condition.
Since that only one closing operation of the circuit-breaker mechanism shall result from each close
command, even though the circuit-breaker trips while the close command is still applied and
maintained. This requirement ensures that the circuit-breaker will not pump if it trips during a closing
operation. It means that, with this sequence, is also possible to test the anti-pumping function. In the
figure 4a is showed the close-open timing test.
Figure No. 4a Close-open timing test
Open-close time
This sequence is known with the name of reclosing cycle or auto-reclosing operation. The open-close
time is measured during an operation by which the device is brought from the closed position to the
open position, followed immediately by a close operation. The letters O-C signify this operation. The
open-close time during auto-reclosing is the interval of time between the instant when the arcing
contacts have separated in all poles and the instant when the contacts touch in the first pole during a
reclosing cycle. Also, the reclosing time is defined as the interval of time between the beginning of the
opening time and the instant when the contacts touch in all poles during a reclosing cycle. The Figure
No. 5 illustrates the open-close operation described by the standard IEC 62271-100.
Figure No. 5 Open-close operation
With this sequence, a closing operation after the circuit breaker has tripped to clear a fault is
simulated. In the figure 5a is showed the open-close timing test.
Figure No. 5a Open-close operation
The rated operating duty cycle, as is referred in ANSI, is known as the rated operated sequence by IEC.
Normally there is some confusion between the standard duty cycle and reclosing duty cycle, the
standard duty cycle is the basis of circuit breaker design, application and design testing. The standard
duty cycle establishes a uniform basis for the performance of the circuit breakers. Also, it establishes
a uniform basis for the short-circuit design tests conducted in the power laboratory. And by the other
hand, the reclosing duty cycle is just used in a particular application, for example an auto-reclosing in
a radial transmission line. For rated operating duty cycle ANSI specifies the standard operating duty
as a sequence consisting of the following operations; O – 15 sec – CO – 3min – CO, that is an opening
operation followed, after a 15 second delay, by a close-open operation and finally after a 3 minute
delay by another close-open operation. For circuit breakers intended for rapid reclosing duty the
sequence is O – 0.3sec – CO – 3min – CO.
IEC offers two alternatives, one is O – 3min – CO – 3min – CO and the second alternative is the same
duty cycle prescribed by ANSI. However, for circuit breaker that are rated for rapid reclosing duties
the time between the opening and close is reduced to 0.3 seconds. In fact, ANSI establishes that the
minimum reclosing time of a circuit breaker is 0.3 seconds. This is the shortest permissible time in
which the circuit breaker is required to close.
Figure No. 5b illustrates the rapid reclosing duty sequence O – 0.3s – CO.
Figure No. 5 rapid reclosing duty sequence
References
[1] Garzon, Ruben: High Voltage Circuit Breakers Design and Applications. 2nd Ed. 2007; New York,
Marcel Dekker
[2] ANSI C37.04-1999 Standard
[3] ANSI C37.100-1992 (R 2001) Standard
[4] IEC 62271-1 :2007 Standard
[5] IEC 62271-100 :2007 Standard

More Related Content

What's hot

Determination of a Three - Phase Induction Machine Parameters
Determination of a Three  - Phase Induction Machine ParametersDetermination of a Three  - Phase Induction Machine Parameters
Determination of a Three - Phase Induction Machine ParametersAli Altahir
 
Transformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisTransformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisHamedPasha1
 
Catalog for high voltage test equipment
Catalog for high voltage test equipmentCatalog for high voltage test equipment
Catalog for high voltage test equipmentkatherine feng
 
Operation and maintenance of transformer
Operation and maintenance of transformerOperation and maintenance of transformer
Operation and maintenance of transformerKapil Singh
 
Close Loop V/F Control of Voltage Source Inverter using Sinusoidal PWM, Third...
Close Loop V/F Control of Voltage Source Inverter using Sinusoidal PWM, Third...Close Loop V/F Control of Voltage Source Inverter using Sinusoidal PWM, Third...
Close Loop V/F Control of Voltage Source Inverter using Sinusoidal PWM, Third...IAES-IJPEDS
 
Final instrumentation lab manual
Final instrumentation lab manualFinal instrumentation lab manual
Final instrumentation lab manualkishorereddy_btech
 
Dynamic behaviour of hydraulic pressure relief valve
Dynamic behaviour of hydraulic pressure relief valveDynamic behaviour of hydraulic pressure relief valve
Dynamic behaviour of hydraulic pressure relief valveIAEME Publication
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
Simulation of build-up test in multi-layered reservoirs
Simulation of build-up test in multi-layered reservoirsSimulation of build-up test in multi-layered reservoirs
Simulation of build-up test in multi-layered reservoirsMohammed Yousif
 
Catastrophic failure of system equipment during switching of 115kV shunt reac...
Catastrophic failure of system equipment during switching of 115kV shunt reac...Catastrophic failure of system equipment during switching of 115kV shunt reac...
Catastrophic failure of system equipment during switching of 115kV shunt reac...rannaluru
 
Modeling piping connection to pressure vessels
Modeling piping connection to pressure vesselsModeling piping connection to pressure vessels
Modeling piping connection to pressure vesselsAvinash Sawant
 
Transformer Oil Testing services
Transformer Oil Testing servicesTransformer Oil Testing services
Transformer Oil Testing servicesPower Electronical
 
Types of load cell and principle
Types of load cell and principle Types of load cell and principle
Types of load cell and principle Mostafa Ragab
 
Pull through failure performance of light gauge steel roof battens
Pull through failure performance of light gauge steel roof battensPull through failure performance of light gauge steel roof battens
Pull through failure performance of light gauge steel roof battensSudarshan (Sid) Bhandari
 

What's hot (20)

Determination of a Three - Phase Induction Machine Parameters
Determination of a Three  - Phase Induction Machine ParametersDetermination of a Three  - Phase Induction Machine Parameters
Determination of a Three - Phase Induction Machine Parameters
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
 
Vta 315
 Vta 315 Vta 315
Vta 315
 
Transformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisTransformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response Analysis
 
Unit 1-2-a
Unit 1-2-aUnit 1-2-a
Unit 1-2-a
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Recontact
RecontactRecontact
Recontact
 
Catalog for high voltage test equipment
Catalog for high voltage test equipmentCatalog for high voltage test equipment
Catalog for high voltage test equipment
 
Operation and maintenance of transformer
Operation and maintenance of transformerOperation and maintenance of transformer
Operation and maintenance of transformer
 
Close Loop V/F Control of Voltage Source Inverter using Sinusoidal PWM, Third...
Close Loop V/F Control of Voltage Source Inverter using Sinusoidal PWM, Third...Close Loop V/F Control of Voltage Source Inverter using Sinusoidal PWM, Third...
Close Loop V/F Control of Voltage Source Inverter using Sinusoidal PWM, Third...
 
Final instrumentation lab manual
Final instrumentation lab manualFinal instrumentation lab manual
Final instrumentation lab manual
 
Dynamic behaviour of hydraulic pressure relief valve
Dynamic behaviour of hydraulic pressure relief valveDynamic behaviour of hydraulic pressure relief valve
Dynamic behaviour of hydraulic pressure relief valve
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
Simulation of build-up test in multi-layered reservoirs
Simulation of build-up test in multi-layered reservoirsSimulation of build-up test in multi-layered reservoirs
Simulation of build-up test in multi-layered reservoirs
 
Block 30 SP 13
Block 30   SP 13Block 30   SP 13
Block 30 SP 13
 
Catastrophic failure of system equipment during switching of 115kV shunt reac...
Catastrophic failure of system equipment during switching of 115kV shunt reac...Catastrophic failure of system equipment during switching of 115kV shunt reac...
Catastrophic failure of system equipment during switching of 115kV shunt reac...
 
Modeling piping connection to pressure vessels
Modeling piping connection to pressure vesselsModeling piping connection to pressure vessels
Modeling piping connection to pressure vessels
 
Transformer Oil Testing services
Transformer Oil Testing servicesTransformer Oil Testing services
Transformer Oil Testing services
 
Types of load cell and principle
Types of load cell and principle Types of load cell and principle
Types of load cell and principle
 
Pull through failure performance of light gauge steel roof battens
Pull through failure performance of light gauge steel roof battensPull through failure performance of light gauge steel roof battens
Pull through failure performance of light gauge steel roof battens
 

Similar to Curvas cibano 500

Dynamic Analysis and Testing of on-load tap changer
Dynamic Analysis and Testing of on-load tap changerDynamic Analysis and Testing of on-load tap changer
Dynamic Analysis and Testing of on-load tap changerLeonardo Nicolini
 
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...paperpublications3
 
Electrical disturbances from conduction and coupling.pptx
Electrical disturbances from conduction and coupling.pptxElectrical disturbances from conduction and coupling.pptx
Electrical disturbances from conduction and coupling.pptxPritishPachhapure1
 
Transient Stability Assessment of the Nigerian 330kV Network.
Transient Stability Assessment of the Nigerian 330kV Network.Transient Stability Assessment of the Nigerian 330kV Network.
Transient Stability Assessment of the Nigerian 330kV Network.CSCJournals
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSatish Pydimarla
 
Devlopement of the dynamic resistance measurement (drm) method for condition ...
Devlopement of the dynamic resistance measurement (drm) method for condition ...Devlopement of the dynamic resistance measurement (drm) method for condition ...
Devlopement of the dynamic resistance measurement (drm) method for condition ...eSAT Publishing House
 
Implementation and control of integral cycle controller for resistance spot w...
Implementation and control of integral cycle controller for resistance spot w...Implementation and control of integral cycle controller for resistance spot w...
Implementation and control of integral cycle controller for resistance spot w...eSAT Journals
 
Circuit Breaker and its types
Circuit Breaker and its typesCircuit Breaker and its types
Circuit Breaker and its typesRakesh Gothwal
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakersKabilesh K
 
cricuit breaker report
cricuit breaker reportcricuit breaker report
cricuit breaker reportAnkit Vij
 
Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)Rohini Haridas
 
DESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATOR
DESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATORDESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATOR
DESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATORVLSICS Design
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalNihal Shiroya
 
Simplifying Plant Safety Instrumentation
Simplifying Plant Safety InstrumentationSimplifying Plant Safety Instrumentation
Simplifying Plant Safety InstrumentationMiller Energy, Inc.
 
DESIGN AND IMPLEMENTATION OF AREA AND POWER OPTIMISED NOVEL SCANFLOP
DESIGN AND IMPLEMENTATION OF AREA AND POWER OPTIMISED NOVEL SCANFLOPDESIGN AND IMPLEMENTATION OF AREA AND POWER OPTIMISED NOVEL SCANFLOP
DESIGN AND IMPLEMENTATION OF AREA AND POWER OPTIMISED NOVEL SCANFLOPVLSICS Design
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushingNovia Putri
 

Similar to Curvas cibano 500 (20)

Dynamic Analysis and Testing of on-load tap changer
Dynamic Analysis and Testing of on-load tap changerDynamic Analysis and Testing of on-load tap changer
Dynamic Analysis and Testing of on-load tap changer
 
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
 
Electrical disturbances from conduction and coupling.pptx
Electrical disturbances from conduction and coupling.pptxElectrical disturbances from conduction and coupling.pptx
Electrical disturbances from conduction and coupling.pptx
 
Transient Stability Assessment of the Nigerian 330kV Network.
Transient Stability Assessment of the Nigerian 330kV Network.Transient Stability Assessment of the Nigerian 330kV Network.
Transient Stability Assessment of the Nigerian 330kV Network.
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptx
 
Devlopement of the dynamic resistance measurement (drm) method for condition ...
Devlopement of the dynamic resistance measurement (drm) method for condition ...Devlopement of the dynamic resistance measurement (drm) method for condition ...
Devlopement of the dynamic resistance measurement (drm) method for condition ...
 
Implementation and control of integral cycle controller for resistance spot w...
Implementation and control of integral cycle controller for resistance spot w...Implementation and control of integral cycle controller for resistance spot w...
Implementation and control of integral cycle controller for resistance spot w...
 
Circuit Breaker and its types
Circuit Breaker and its typesCircuit Breaker and its types
Circuit Breaker and its types
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
 
cricuit breaker report
cricuit breaker reportcricuit breaker report
cricuit breaker report
 
Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)
 
DESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATOR
DESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATORDESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATOR
DESIGN AND PERFORMANCE ANALYSIS OF NINE STAGES CMOS BASED RING OSCILLATOR
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
 
Vcb ppt.
Vcb ppt.Vcb ppt.
Vcb ppt.
 
Simplifying Plant Safety Instrumentation
Simplifying Plant Safety InstrumentationSimplifying Plant Safety Instrumentation
Simplifying Plant Safety Instrumentation
 
Testing of cb
Testing of cbTesting of cb
Testing of cb
 
DESIGN AND IMPLEMENTATION OF AREA AND POWER OPTIMISED NOVEL SCANFLOP
DESIGN AND IMPLEMENTATION OF AREA AND POWER OPTIMISED NOVEL SCANFLOPDESIGN AND IMPLEMENTATION OF AREA AND POWER OPTIMISED NOVEL SCANFLOP
DESIGN AND IMPLEMENTATION OF AREA AND POWER OPTIMISED NOVEL SCANFLOP
 
Transient Recovery Voltage Part-1
Transient Recovery Voltage Part-1Transient Recovery Voltage Part-1
Transient Recovery Voltage Part-1
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 

Curvas cibano 500

  • 1. Make out most of your timing tests Abstract The timing tests are made to determine the time required for circuit-breakers or components to operate on open, close, close-open and reclosing operations. However, everybody is aware that on circuit-breakers, those are the typically used test sequences. But what do they really mean? How do they refer to the standards? Introduction A circuit-breaker is a mechanical switching device, capable of making, carrying, and breaking currents under normal circuit conditions, also making and carrying for a specified time, and breaking currents under specified abnormal circuit conditions such as those of short-circuit. Therefore this constitutes an important and critical component in the electric power system. During commissioning and maintenance of circuit-breakers, one of the most common offline test methods have been the timing tests, among others; a brief explanation of these tests is: measure the mechanical operation time when the circuit-breaker is performing a mechanical sequence under no-load condition. So, this paper presents the explanation of the standards for each test sequence and then, the application and how to interpret the results of the timing tests. Timing tests and Standards The standards IEC 62271-100 and ANSI C37.100-1992 both contain explanations of sequences and operations defined for circuit-breakers. In fact, the sequences defined are close (C), open (O), close- open (CO) and open-close (O-C); and then the rated operating sequences or duty cycles. Firstly, timing tests are done in the factory during the routine tests, then typically during the commissioning tests. In addition to timing tests, during the routine tests is also measured time spread between units of one pole and between poles, recharging time of the operating mechanism device, consumption of the tripping and closing devices and possible recording of the current of the releases, duration of opening and closing command impulses, ohmic resistance of the main circuit and time- travel chart, among others. The assessment of these tests, during the commissioning or maintenance is done comparing the results obtained with the results obtained in the routine tests. Opening time The opening time is measured during an operation by which the device is brought from the closed position to the open position. The letter O signifies this operation. According to the standards mentioned above, the opening time is the interval of time between the instant of energizing the opening release, the circuit-breaker being in the closed position, and the instant when the arcing contacts have separated in all the poles. If the circuit-breaker has more than one interrupting unit per pole, the instant when the arcing contacts have separated in all poles is determined as the instant of contact separation in the first unit of the last pole. Figure No. 1 illustrates the opening operation according to IEC 62271-100.
  • 2. Figure No. 1 Opening operation However, on site, while the commissioning, maintenance and during no-load operation, when the opening timing test is performed, just is possible to measure the opening time, such as seen in the Figure No. 1a. The arcing and break times are not possible to measure because there is no way to measure the arc duration and extinction when the circuit breaker is performing a no-load operation. Figure No. 1a Opening timing test
  • 3. Closing time The closing time is measured during an operation by which the device is brought from the open position to the closed position. The letter C signifies this operation. The closing time is the interval of time between energizing the closing circuit, the circuit-breaker being in the open position, and the instant when the contacts touch in all poles. This closing time includes the operating time of any auxiliary equipment necessary to close the circuit-breaker and forming an integral part of the circuit- breaker. The Figure No. 2 illustrates the closing operation according to IEC 62271-100. Figure No. 2 Closing operation So, for the same reasons that the arcing time cannot be measured as was explained in the opening operation, also the pre-arcing time cannot be measured. While commissioning, maintenance and during no-load operation when the closing test is performed, just is possible to measure the closing time. Just as shown in figure 2a.
  • 4. Figure No. 2a Closing timing test Simultaneity or synchronization When timing tests are performed, is essential to analyze the synchronization time between poles and interrupting units per pole, as long as there more than one interrupting unit per pole. In fact, according to IEC 62271-100 and ANSI C37.04-1999, when no special requirement with respect to simultaneous operation of poles is stated, the maximum difference during opening shall not exceed 1/6 of a cycle of rate frequency and during the closing shall not exceed 1/4 of a cycle of rate frequency as well. Figure No. 3a Synchronization time closing operation Figure No. 3b Synchronization time opening operation If one pole consists of more than one interrupter unit connected in series, the maximum difference between the instants of contact separation within these series connected interrupter units shall not exceed 1/8 of a cycle of rated frequency, and between the instants of contacts touching within these series connected interrupter units shall not exceed a 1/6 of a cycle of rated frequency. Sometimes, the simultaneity of poles also is called time spread between poles or between units of one pole. In the figure 3c are showed the synchronization times.
  • 5. Figure No. 3c Synchronization times Close-open time The close-open time is measured during an operation by which the device is brought from the open position to the closed position followed immediately by an open operation without purposely delayed action. The letters CO signify this operation. The close-open time is the interval of time between the instant when the contacts touch in the first pole during a closing operation and the instant when the arcing contacts have separated in all poles during the subsequent opening operation. The Figure No. 4 illustrates the closing operation described by the standard IEC 62271-100. Figure No. 4 Close-open operation This sequence also is known with the name of short-circuit time or trip-free operation. With this sequence also is possible to perform the simulation of fault-making operation, or in other words, a tripping operation after the circuit-breaker has been closed under a fault condition. Since that only one closing operation of the circuit-breaker mechanism shall result from each close command, even though the circuit-breaker trips while the close command is still applied and
  • 6. maintained. This requirement ensures that the circuit-breaker will not pump if it trips during a closing operation. It means that, with this sequence, is also possible to test the anti-pumping function. In the figure 4a is showed the close-open timing test. Figure No. 4a Close-open timing test Open-close time This sequence is known with the name of reclosing cycle or auto-reclosing operation. The open-close time is measured during an operation by which the device is brought from the closed position to the open position, followed immediately by a close operation. The letters O-C signify this operation. The open-close time during auto-reclosing is the interval of time between the instant when the arcing contacts have separated in all poles and the instant when the contacts touch in the first pole during a reclosing cycle. Also, the reclosing time is defined as the interval of time between the beginning of the opening time and the instant when the contacts touch in all poles during a reclosing cycle. The Figure No. 5 illustrates the open-close operation described by the standard IEC 62271-100. Figure No. 5 Open-close operation
  • 7. With this sequence, a closing operation after the circuit breaker has tripped to clear a fault is simulated. In the figure 5a is showed the open-close timing test. Figure No. 5a Open-close operation The rated operating duty cycle, as is referred in ANSI, is known as the rated operated sequence by IEC. Normally there is some confusion between the standard duty cycle and reclosing duty cycle, the standard duty cycle is the basis of circuit breaker design, application and design testing. The standard duty cycle establishes a uniform basis for the performance of the circuit breakers. Also, it establishes a uniform basis for the short-circuit design tests conducted in the power laboratory. And by the other hand, the reclosing duty cycle is just used in a particular application, for example an auto-reclosing in a radial transmission line. For rated operating duty cycle ANSI specifies the standard operating duty as a sequence consisting of the following operations; O – 15 sec – CO – 3min – CO, that is an opening operation followed, after a 15 second delay, by a close-open operation and finally after a 3 minute delay by another close-open operation. For circuit breakers intended for rapid reclosing duty the sequence is O – 0.3sec – CO – 3min – CO. IEC offers two alternatives, one is O – 3min – CO – 3min – CO and the second alternative is the same duty cycle prescribed by ANSI. However, for circuit breaker that are rated for rapid reclosing duties the time between the opening and close is reduced to 0.3 seconds. In fact, ANSI establishes that the minimum reclosing time of a circuit breaker is 0.3 seconds. This is the shortest permissible time in which the circuit breaker is required to close. Figure No. 5b illustrates the rapid reclosing duty sequence O – 0.3s – CO. Figure No. 5 rapid reclosing duty sequence
  • 8. References [1] Garzon, Ruben: High Voltage Circuit Breakers Design and Applications. 2nd Ed. 2007; New York, Marcel Dekker [2] ANSI C37.04-1999 Standard [3] ANSI C37.100-1992 (R 2001) Standard [4] IEC 62271-1 :2007 Standard [5] IEC 62271-100 :2007 Standard