SlideShare a Scribd company logo
1 of 3
Sustained three phase short circuit test
Table of Content:
1 Objective...........................................................................................................
2 Scope................................................................................................................
3 Referenced Documents....................................................................................
4 Definitions and Abbreviations...........................................................................
5 Sustained three-phase short-circuit test and overcurrent test.........................
5.1 Preparation.......................................................................................
5.2 Conduction of test.............................................................................
5.3 Appendix for site testing...................................................................
6 Proceeding in case of deviations.....................................................................
7 Copyright.........................................................................................................
1 Objective
The sustained three-phase short-circuit test is performed to establish the relationship
between the armature short-circuited winding current and the excitation current (short-
circuit saturation characteristic). It is also used to verify the capability of the machine to
withstand occasional excess current without damages. From the data of the short-circuit
test (as well as the open-circuit saturation test) the following machine characteristics and
quantities are determined: − Three-phase short-circuit saturation characteristic − Direct-
axis synchronous reactance Xd − Short-circuit ratio Kc − Potier reactance Xp Note:
Continuous operation of the generator in 3-phase short-circuit condition is performed for:
− SC-heat run of turbo generators in the works − Determination of load loss of (vertical)
HYDRO generators by calorimetric method (see P GEN QC3 6102DEFS) − Drying of
wet windings (see P GEN QC3 6111DEFS)
2 Scope
All types of synchronous machines during final tests in workshop or at site.
3 Referenced Documents
IEC 34-4, 26*), 27 (resp. EN 60034-4, 26, 27)
IEC 34-1, 8.2 (resp. EN 60034-1, 8.2).
IEC 34-3, 14 (resp. EN 60034-3, 14)
IEEE 115, 4.2.8, 4.3.15
Efficiency Determination on Hydro generators by Calorimetric Method
Insulation Resistance Testing
4 Definitions and Abbreviations
None
5 Sustained three-phase short-circuit test and overcurrent test
Page 1 of 3
5.1 Preparation
- Set the generator in three-phase armature winding short-circuit condition - Install the
precision instruments for the armature and field current measurement - Unlock trip order
from protection relays
5.2 Conduction of test
− Operate the unit at rated speed with the manual control of the excitation system
Note: When a prime mover is not available, this test can (acc. IEC, *) also be conducted
during retardation
− Supply small field current, then check, whether instruments, excitation system and
generator are in the proper condition
− After that, gradually change field current and measure the armature and field currents
− Check the armature current balance in the three phases at approximately rated
current.]
− Maximum armature current is limited to 120 % of the rated armature current, with
exception of the short-time overcurrent test, which is only performed on special request
by the customer with current magnitude and duration as defined in the contract.
Note: The overcurrent test can only be conducted when a prime mover is available.
5.3 Appendix for site testing
− When a work shop test was performed and this test is repeated at site, or generally for
all turbogenerators during commissioning tests, it is sufficient to check correspondence
with the original measured characteristic by measuring one (or a few) point(s), including
approximately rated current. For comparison data see the original test report of the
tested machine, or the type test report for this type of machine and exciter respectively.
− Excitation of the generator is from its own exciter (brushless) or excitation system
(static) as appropriate.
− When the short circuit, contrary to international standards (IEC, IEEE), can only be
made on the HV side of the step-up transformer, measure also the voltage between the
generator terminals.
The generator is loaded with the short –circuit stray impedance of the transformer. To
induce the voltage that appears at the generator terminals, additional excitation current
is required. The relationship between the generator voltage and the excitation current is
(with sufficient accuracy) represented by the zero p.f. curve U=f(If), which is obtained by
sliding (the vector from the top of) the Potier (short-circuit) triangle along the open-circuit
saturation characteristic. The excitation current for shorted generator terminals is thus
simply obtained by drawing a parallel to the air gap line through the measured point of U
and If and extrapolating back to zero voltage.
This procedure is to be repeated for different armature currents. The linear dimensions
of the Potier triangle vary proportionate to the armature current. The relationship
between the armature current and the excitation current for short-circuit at the HV side of
the transformer I = f(If) is a straight line, which is flatter than the generator synchronous
impedance line. However, when also separate load losses are to be determined either
by retardation or calorimetric method, the short circuit must be realized as near as
possible to the generator main terminals, but in any case before the machine
transformer.
Page 2 of 3
6 Proceeding in case of deviations
Any nominal value, minimum value, maximum value, tolerance etc given in an instruction
is intended to serve for quality control purposes only. In the case of deviations, a
nonconformity report has to be written according to PNG Power Standard
17 Copyright
2This Document is properly of PNG Power internal use only and must neither be copied.
Neither is it to be handed over nor in other way communicated to a third party.
Infringement will lead to prosecution.
Page 3 of 3

More Related Content

What's hot

Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis pptkarikalan123
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsPower System Operation
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformerssiddharam kantoli
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protectionashwin fcc
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEJamil Abdullah
 
Protection of power transformer
Protection of power transformerProtection of power transformer
Protection of power transformerRitesh Verma
 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adamShaik Abdullah Adam
 
Power quality-disturbances and monitoring Seminar
Power quality-disturbances and monitoring  SeminarPower quality-disturbances and monitoring  Seminar
Power quality-disturbances and monitoring SeminarSurabhi Vasudev
 
Calculation of short circuit currents
Calculation of short circuit currents Calculation of short circuit currents
Calculation of short circuit currents Maria Romina Angustia
 
Protection of transformer
Protection of transformerProtection of transformer
Protection of transformerSumeet Ratnawat
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guideSlides Hub
 
Motor Control Centre
Motor Control CentreMotor Control Centre
Motor Control Centresalehkhan
 
ETAP - csd - Control System Diagram
ETAP - csd - Control System DiagramETAP - csd - Control System Diagram
ETAP - csd - Control System DiagramHimmelstern
 
Calculo de Corriente de cortocircuito
Calculo de Corriente de cortocircuitoCalculo de Corriente de cortocircuito
Calculo de Corriente de cortocircuitoJesús Castrillón
 
Instrument Transformer (ALIV - BANGLADESH)
Instrument Transformer (ALIV - BANGLADESH)Instrument Transformer (ALIV - BANGLADESH)
Instrument Transformer (ALIV - BANGLADESH)Md Abu Jauad Khan Aliv
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relaysPremanandDesai
 

What's hot (20)

Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protection
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGE
 
Electric Motors
Electric MotorsElectric Motors
Electric Motors
 
Protection of power transformer
Protection of power transformerProtection of power transformer
Protection of power transformer
 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adam
 
Power quality-disturbances and monitoring Seminar
Power quality-disturbances and monitoring  SeminarPower quality-disturbances and monitoring  Seminar
Power quality-disturbances and monitoring Seminar
 
distance relay
distance relaydistance relay
distance relay
 
Out of step
Out of stepOut of step
Out of step
 
Calculation of short circuit currents
Calculation of short circuit currents Calculation of short circuit currents
Calculation of short circuit currents
 
Protection of transformer
Protection of transformerProtection of transformer
Protection of transformer
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guide
 
Motor Control Centre
Motor Control CentreMotor Control Centre
Motor Control Centre
 
ETAP - csd - Control System Diagram
ETAP - csd - Control System DiagramETAP - csd - Control System Diagram
ETAP - csd - Control System Diagram
 
Calculo de Corriente de cortocircuito
Calculo de Corriente de cortocircuitoCalculo de Corriente de cortocircuito
Calculo de Corriente de cortocircuito
 
Instrument Transformer (ALIV - BANGLADESH)
Instrument Transformer (ALIV - BANGLADESH)Instrument Transformer (ALIV - BANGLADESH)
Instrument Transformer (ALIV - BANGLADESH)
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relays
 
Overcurrent protection
Overcurrent protectionOvercurrent protection
Overcurrent protection
 

Similar to Sustained three phase short-circuit test and overcurrent test

Open circuit saturation test
Open circuit saturation testOpen circuit saturation test
Open circuit saturation testDonald Stephen
 
Sudden three phase short-circuit test
Sudden three phase short-circuit testSudden three phase short-circuit test
Sudden three phase short-circuit testDonald Stephen
 
Determination of the transient open circuit time constant
Determination of the transient open circuit time constantDetermination of the transient open circuit time constant
Determination of the transient open circuit time constantDonald Stephen
 
Line to-line sustained short-circuit test
Line to-line sustained short-circuit testLine to-line sustained short-circuit test
Line to-line sustained short-circuit testDonald Stephen
 
Basics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud DetectionBasics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud DetectionAbhisek Swain
 
06 -synchronous_machine_parameter_measurement
06  -synchronous_machine_parameter_measurement06  -synchronous_machine_parameter_measurement
06 -synchronous_machine_parameter_measurementEllixies Fair
 
Comparison of coupling capacitors and the inverter filter in partial discharg...
Comparison of coupling capacitors and the inverter filter in partial discharg...Comparison of coupling capacitors and the inverter filter in partial discharg...
Comparison of coupling capacitors and the inverter filter in partial discharg...IOSR Journals
 
D032030035038
D032030035038D032030035038
D032030035038theijes
 
symmetrical_fault_analysis.pdf
symmetrical_fault_analysis.pdfsymmetrical_fault_analysis.pdf
symmetrical_fault_analysis.pdfShanmukhSaiR
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)ingcortez
 
Enhancing Power Quality in Transmission System Using Fc-Tcr
Enhancing Power Quality in Transmission System Using Fc-TcrEnhancing Power Quality in Transmission System Using Fc-Tcr
Enhancing Power Quality in Transmission System Using Fc-TcrIJMER
 
Transient Stability Enhancement of a Multi-Machine System using Particle Swar...
Transient Stability Enhancement of a Multi-Machine System using Particle Swar...Transient Stability Enhancement of a Multi-Machine System using Particle Swar...
Transient Stability Enhancement of a Multi-Machine System using Particle Swar...IJERA Editor
 
Three Phase Digitally Controlled Power Factor Improvement System
Three Phase Digitally Controlled Power Factor Improvement SystemThree Phase Digitally Controlled Power Factor Improvement System
Three Phase Digitally Controlled Power Factor Improvement SystemIOSR Journals
 
Power system stability improvement under three
Power system stability improvement under threePower system stability improvement under three
Power system stability improvement under threeeSAT Publishing House
 
Speed control of Three phase Induction motor using AC voltage regulator
Speed control of Three phase Induction motor using AC voltage regulatorSpeed control of Three phase Induction motor using AC voltage regulator
Speed control of Three phase Induction motor using AC voltage regulatorShivagee Raj
 
Practical Implementation for Stator Faults Protection and Diagnosisin 3-Ph IM...
Practical Implementation for Stator Faults Protection and Diagnosisin 3-Ph IM...Practical Implementation for Stator Faults Protection and Diagnosisin 3-Ph IM...
Practical Implementation for Stator Faults Protection and Diagnosisin 3-Ph IM...theijes
 
Thesis- Cont sys for wind turbines (Sept 2015 revision)
Thesis- Cont sys for wind turbines (Sept 2015 revision)Thesis- Cont sys for wind turbines (Sept 2015 revision)
Thesis- Cont sys for wind turbines (Sept 2015 revision)Larry Branscomb
 
A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...
A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...
A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...Thorne & Derrick International
 

Similar to Sustained three phase short-circuit test and overcurrent test (20)

Open circuit saturation test
Open circuit saturation testOpen circuit saturation test
Open circuit saturation test
 
Sudden three phase short-circuit test
Sudden three phase short-circuit testSudden three phase short-circuit test
Sudden three phase short-circuit test
 
Determination of the transient open circuit time constant
Determination of the transient open circuit time constantDetermination of the transient open circuit time constant
Determination of the transient open circuit time constant
 
Line to-line sustained short-circuit test
Line to-line sustained short-circuit testLine to-line sustained short-circuit test
Line to-line sustained short-circuit test
 
Basics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud DetectionBasics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud Detection
 
06 -synchronous_machine_parameter_measurement
06  -synchronous_machine_parameter_measurement06  -synchronous_machine_parameter_measurement
06 -synchronous_machine_parameter_measurement
 
Comparison of coupling capacitors and the inverter filter in partial discharg...
Comparison of coupling capacitors and the inverter filter in partial discharg...Comparison of coupling capacitors and the inverter filter in partial discharg...
Comparison of coupling capacitors and the inverter filter in partial discharg...
 
D032030035038
D032030035038D032030035038
D032030035038
 
symmetrical_fault_analysis.pdf
symmetrical_fault_analysis.pdfsymmetrical_fault_analysis.pdf
symmetrical_fault_analysis.pdf
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)
 
Enhancing Power Quality in Transmission System Using Fc-Tcr
Enhancing Power Quality in Transmission System Using Fc-TcrEnhancing Power Quality in Transmission System Using Fc-Tcr
Enhancing Power Quality in Transmission System Using Fc-Tcr
 
Transient Stability Enhancement of a Multi-Machine System using Particle Swar...
Transient Stability Enhancement of a Multi-Machine System using Particle Swar...Transient Stability Enhancement of a Multi-Machine System using Particle Swar...
Transient Stability Enhancement of a Multi-Machine System using Particle Swar...
 
P and i report
P and i reportP and i report
P and i report
 
Senior Design Project
Senior Design ProjectSenior Design Project
Senior Design Project
 
Three Phase Digitally Controlled Power Factor Improvement System
Three Phase Digitally Controlled Power Factor Improvement SystemThree Phase Digitally Controlled Power Factor Improvement System
Three Phase Digitally Controlled Power Factor Improvement System
 
Power system stability improvement under three
Power system stability improvement under threePower system stability improvement under three
Power system stability improvement under three
 
Speed control of Three phase Induction motor using AC voltage regulator
Speed control of Three phase Induction motor using AC voltage regulatorSpeed control of Three phase Induction motor using AC voltage regulator
Speed control of Three phase Induction motor using AC voltage regulator
 
Practical Implementation for Stator Faults Protection and Diagnosisin 3-Ph IM...
Practical Implementation for Stator Faults Protection and Diagnosisin 3-Ph IM...Practical Implementation for Stator Faults Protection and Diagnosisin 3-Ph IM...
Practical Implementation for Stator Faults Protection and Diagnosisin 3-Ph IM...
 
Thesis- Cont sys for wind turbines (Sept 2015 revision)
Thesis- Cont sys for wind turbines (Sept 2015 revision)Thesis- Cont sys for wind turbines (Sept 2015 revision)
Thesis- Cont sys for wind turbines (Sept 2015 revision)
 
A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...
A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...
A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...
 

More from Donald Stephen

Tangent delta test report form
Tangent delta test report formTangent delta test report form
Tangent delta test report formDonald Stephen
 
Stator insulation test setup
Stator insulation test setupStator insulation test setup
Stator insulation test setupDonald Stephen
 
Stator core induction test
Stator core induction testStator core induction test
Stator core induction testDonald Stephen
 
Stator core compr test
Stator core compr testStator core compr test
Stator core compr testDonald Stephen
 
Rotor insul test setup
Rotor insul test setupRotor insul test setup
Rotor insul test setupDonald Stephen
 
Measurement of winding resistances
Measurement of winding resistancesMeasurement of winding resistances
Measurement of winding resistancesDonald Stephen
 
Measurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsMeasurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsDonald Stephen
 
Measurement of partial discharges
Measurement of partial dischargesMeasurement of partial discharges
Measurement of partial dischargesDonald Stephen
 
Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta testDonald Stephen
 
Insulation resistance testing
Insulation resistance testingInsulation resistance testing
Insulation resistance testingDonald Stephen
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance testDonald Stephen
 
Impedance measurement of field windings
Impedance measurement of field windingsImpedance measurement of field windings
Impedance measurement of field windingsDonald Stephen
 
Efficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodEfficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodDonald Stephen
 
Determination of inertia by load rejection
Determination of inertia by load rejectionDetermination of inertia by load rejection
Determination of inertia by load rejectionDonald Stephen
 

More from Donald Stephen (20)

Tangent delta test report form
Tangent delta test report formTangent delta test report form
Tangent delta test report form
 
Stator insulation test setup
Stator insulation test setupStator insulation test setup
Stator insulation test setup
 
Stator core induction test
Stator core induction testStator core induction test
Stator core induction test
 
Stator core compr test
Stator core compr testStator core compr test
Stator core compr test
 
Rotor insul test setup
Rotor insul test setupRotor insul test setup
Rotor insul test setup
 
Noise measurement
Noise measurementNoise measurement
Noise measurement
 
Measurement of winding resistances
Measurement of winding resistancesMeasurement of winding resistances
Measurement of winding resistances
 
Measurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsMeasurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearings
 
Measurement of partial discharges
Measurement of partial dischargesMeasurement of partial discharges
Measurement of partial discharges
 
Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta test
 
Load test
Load testLoad test
Load test
 
Insulation resistance testing
Insulation resistance testingInsulation resistance testing
Insulation resistance testing
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance test
 
Impedance measurement of field windings
Impedance measurement of field windingsImpedance measurement of field windings
Impedance measurement of field windings
 
High potential test
High potential testHigh potential test
High potential test
 
Efficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodEfficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric method
 
Determination of inertia by load rejection
Determination of inertia by load rejectionDetermination of inertia by load rejection
Determination of inertia by load rejection
 
Crack monitor
Crack monitorCrack monitor
Crack monitor
 
Core deffect detector
Core deffect detectorCore deffect detector
Core deffect detector
 
Check pole connector
Check pole connectorCheck pole connector
Check pole connector
 

Recently uploaded

ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 

Recently uploaded (20)

ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 

Sustained three phase short-circuit test and overcurrent test

  • 1. Sustained three phase short circuit test Table of Content: 1 Objective........................................................................................................... 2 Scope................................................................................................................ 3 Referenced Documents.................................................................................... 4 Definitions and Abbreviations........................................................................... 5 Sustained three-phase short-circuit test and overcurrent test......................... 5.1 Preparation....................................................................................... 5.2 Conduction of test............................................................................. 5.3 Appendix for site testing................................................................... 6 Proceeding in case of deviations..................................................................... 7 Copyright......................................................................................................... 1 Objective The sustained three-phase short-circuit test is performed to establish the relationship between the armature short-circuited winding current and the excitation current (short- circuit saturation characteristic). It is also used to verify the capability of the machine to withstand occasional excess current without damages. From the data of the short-circuit test (as well as the open-circuit saturation test) the following machine characteristics and quantities are determined: − Three-phase short-circuit saturation characteristic − Direct- axis synchronous reactance Xd − Short-circuit ratio Kc − Potier reactance Xp Note: Continuous operation of the generator in 3-phase short-circuit condition is performed for: − SC-heat run of turbo generators in the works − Determination of load loss of (vertical) HYDRO generators by calorimetric method (see P GEN QC3 6102DEFS) − Drying of wet windings (see P GEN QC3 6111DEFS) 2 Scope All types of synchronous machines during final tests in workshop or at site. 3 Referenced Documents IEC 34-4, 26*), 27 (resp. EN 60034-4, 26, 27) IEC 34-1, 8.2 (resp. EN 60034-1, 8.2). IEC 34-3, 14 (resp. EN 60034-3, 14) IEEE 115, 4.2.8, 4.3.15 Efficiency Determination on Hydro generators by Calorimetric Method Insulation Resistance Testing 4 Definitions and Abbreviations None 5 Sustained three-phase short-circuit test and overcurrent test Page 1 of 3
  • 2. 5.1 Preparation - Set the generator in three-phase armature winding short-circuit condition - Install the precision instruments for the armature and field current measurement - Unlock trip order from protection relays 5.2 Conduction of test − Operate the unit at rated speed with the manual control of the excitation system Note: When a prime mover is not available, this test can (acc. IEC, *) also be conducted during retardation − Supply small field current, then check, whether instruments, excitation system and generator are in the proper condition − After that, gradually change field current and measure the armature and field currents − Check the armature current balance in the three phases at approximately rated current.] − Maximum armature current is limited to 120 % of the rated armature current, with exception of the short-time overcurrent test, which is only performed on special request by the customer with current magnitude and duration as defined in the contract. Note: The overcurrent test can only be conducted when a prime mover is available. 5.3 Appendix for site testing − When a work shop test was performed and this test is repeated at site, or generally for all turbogenerators during commissioning tests, it is sufficient to check correspondence with the original measured characteristic by measuring one (or a few) point(s), including approximately rated current. For comparison data see the original test report of the tested machine, or the type test report for this type of machine and exciter respectively. − Excitation of the generator is from its own exciter (brushless) or excitation system (static) as appropriate. − When the short circuit, contrary to international standards (IEC, IEEE), can only be made on the HV side of the step-up transformer, measure also the voltage between the generator terminals. The generator is loaded with the short –circuit stray impedance of the transformer. To induce the voltage that appears at the generator terminals, additional excitation current is required. The relationship between the generator voltage and the excitation current is (with sufficient accuracy) represented by the zero p.f. curve U=f(If), which is obtained by sliding (the vector from the top of) the Potier (short-circuit) triangle along the open-circuit saturation characteristic. The excitation current for shorted generator terminals is thus simply obtained by drawing a parallel to the air gap line through the measured point of U and If and extrapolating back to zero voltage. This procedure is to be repeated for different armature currents. The linear dimensions of the Potier triangle vary proportionate to the armature current. The relationship between the armature current and the excitation current for short-circuit at the HV side of the transformer I = f(If) is a straight line, which is flatter than the generator synchronous impedance line. However, when also separate load losses are to be determined either by retardation or calorimetric method, the short circuit must be realized as near as possible to the generator main terminals, but in any case before the machine transformer. Page 2 of 3
  • 3. 6 Proceeding in case of deviations Any nominal value, minimum value, maximum value, tolerance etc given in an instruction is intended to serve for quality control purposes only. In the case of deviations, a nonconformity report has to be written according to PNG Power Standard 17 Copyright 2This Document is properly of PNG Power internal use only and must neither be copied. Neither is it to be handed over nor in other way communicated to a third party. Infringement will lead to prosecution. Page 3 of 3