SlideShare a Scribd company logo
DEPARTMENT OF CIVIL ENGINEERING
1
PRESENTATION ON PRESTRESSED CONCRETE
DESIGN OF CONTINUOUS MEMBERS IN PRESTRESSED
PRESENTED BY
LOGESH. S
M.E STRUCTURAL
19TPCV011
2
DESIGN OF CONTINUOUS MEMBERS IN
PRESTRESSED
3
• A continuous beam is having more than one span is carried
by several supports.
• It is mainly used in bridge construction.
• Simple beam cannot be used for large spans, as it requires
more strength and stiffness.
• But continuous PSC beam not only provides adequate
strength and stiffness, but also provides sufficient ductility.
Continuous Beam
4
• An important distinction between them is that the
prestressing force does not produce any secondary moments in
simple beams, considerable secondary moments are produced
in continuous PSC beams.
• Also, the behavior of continuous PSC beams nearer to
ultimate load is different from the behavior of a corresponding
simple beam.
Continuous Beam
5
Merits
• Ultimate loads carrying capacity is higher than the statically
determinate structures due to the effect of redistribution of
moments.
• An increase in stability of framed structures. This is feasible
due to the distribution of moments.
• The deflections in continuous beams are relatively small when
compared to simply supported beams. This is due to the fact
that the continuity of members makes the rotation less at the
places of supports. Thus, the deflections are less.
6
• The maximum bending moment that occurs in a continuous
beam is less than that for same spans, if the beams are cut into
simply supported beams.
• In continuous beam, the bending moments are evenly
distributed throughout the span and results in reduction in size
of members. Thus, lighter weight structures made.
• An effective usage of curved cables is possible to resist the
supports and span moments.
• A reduction in cost and construction time is possible due to the
use of number of anchorages.
Merits
7
• Frictional loss in continuous tendons
• Shortening of long continuous beams under prestress
• Secondary stresses
• Location of both maximum moment and shear force over
supports
• Reversal of moments
• Moment packs
• Continuity for precast elements
• Difficulty in designing.
Demerits
8
The profile of the CGS for a post-tensioned beam is shown in the sketch.
Plot the pressure line due to a prestressing force Pe = 1112 kN.
Solution
1) Plot M1 diagram
The values of M1 are calculated from M1 = Pee.
e (m) M1 (kN m)
0.06 – 66.72
0.24 – 266.88
– 0.12 133.44
0.27 – 300.24
.06 C
G
C
0.08 rad
A 9 m D 6 m B 7.5 m
0.176 rad
7.5 m C
.27.12.24
9
0.24
0.06
0.270.12
-66.72
-266.88 -300.24
133.44
M1 diagram (kN m)
Profile of the CGS
Plot V diagram
For AD,
V= dM1/dx
= (-266.9 - (-66.7))/9
= -22.2 kN
For DB,
V= dM1/dx
= (133.4 - (-266.9))/6
= 66.7 kN
A D B C
10
For BC, to find dM1/dx, an approximate parabolic equation for the M1 diagram can
be used.
M1 = - 4Peex (L - x )/L2
V= dM1/dx
= - 4Pee(L - 2x )/L2
=- 4Pee/L
=- 4 ×(133.4 + 300.2)
15
= -115.6 kN
At B,
V =
L
M1
Pee x
11
The exact value of V at B is
V = - 107.0 kN
The difference of V between C and B is given from the change in slope of the M1 diagram.
V|C - V|B = 0.176 × 1112
= 195.7 kN
Therefore, value of V at C is given as follows.
V|C = 195.7 – 107.0
= 89.0 kN
66.72
266.88 300.24
133.44
V diagram (kN)
66.7
89.0
-107.0-
22.2
M1 Diagram (kN m)
12
3) Plot equivalent load (weq) diagram. Include moment 66.7 kN-m at A.
Point load at D
W|D = 66.7- (- 22.2 )
= 88.9 kN
Since B is a reaction point, the downward load at B need not be considered. Distributed load
within B and C
w BC = 89.0 - (-107.0)
15
= 13.0 kN/m
–
22.2
66.7 89.0
Equivalent load diagram
66.7 kN m 13.0
kN/m
88.9
kN
– 107.0 Kn
V diagran
13
0.5 0.5
88.9x9×6^2 88.9×9^2 ×6 13.0×15^2
15^2 15^2 12
=128 = -192 = 244 –244
–194.7 244
–97 122
–38.5 –38.5
–66.7 –327.5 327.5 0
66.7
DF
88.9
FEM
Bal
CO
Bal
Total
13.0
In the previous table,
Bal = Balanced
CO = Carry Over moment
DF = Distribution Factor
FEM = Fixed End Moment
4) Plot the M2 diagram.
Calculate moment at supports by moment distribution
14
M2 (kN m) ec (m)
– 66.7 0.06
327.0 0.294
0.0 0.184
Calculate values of ec at support.
The values of ec are calculated from ec= M2/Pe.
M2 diagram (kN m)
Profile of CGS
Pressure line
0.06
0.136
0.294
0.184
327.0
-66.7
66.7
knm
0
88.9 kn 13kn/
m
15

More Related Content

What's hot

Lec.5 strength design method rectangular sections 1
Lec.5   strength design method rectangular sections  1Lec.5   strength design method rectangular sections  1
Lec.5 strength design method rectangular sections 1
Muthanna Abbu
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and Design
Umer Farooq
 
Concrete cloth
Concrete clothConcrete cloth
Concrete cloth
aryan922
 
A UHPC (ultra high performance concrete) presentation projects.
A UHPC (ultra high performance concrete) presentation projects.A UHPC (ultra high performance concrete) presentation projects.
A UHPC (ultra high performance concrete) presentation projects.
Nolan Mayrhofer
 
Masonry structures -_chapter_9_and_10
Masonry structures -_chapter_9_and_10Masonry structures -_chapter_9_and_10
Masonry structures -_chapter_9_and_10
Jagajyoti Panda
 
Structural dynamics good notes
Structural dynamics good notesStructural dynamics good notes
Structural dynamics good notes
santosh161832
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints
Hanzlahakhlaq
 
Bonding old and new concrete
Bonding old and new concreteBonding old and new concrete
Bonding old and new concrete
Sajjad Ahmad
 
SELF COMPACTING CONCRETE MIX DESIGN [IS 10262-2019].pptx
SELF COMPACTING CONCRETE MIX DESIGN [IS 10262-2019].pptxSELF COMPACTING CONCRETE MIX DESIGN [IS 10262-2019].pptx
SELF COMPACTING CONCRETE MIX DESIGN [IS 10262-2019].pptx
Shivaprasad Rajoor
 
Principles and design concepts of reinforced soil walls
Principles and design concepts of reinforced soil wallsPrinciples and design concepts of reinforced soil walls
Principles and design concepts of reinforced soil walls
Prakash Ravindran
 
Design steps of foot bridge , stringer and cross girder
Design steps of foot bridge , stringer and cross girderDesign steps of foot bridge , stringer and cross girder
Design steps of foot bridge , stringer and cross girder
Gaurav Ghai
 
Lecture 6 7 Rm Shear Walls
Lecture 6 7 Rm Shear WallsLecture 6 7 Rm Shear Walls
Lecture 6 7 Rm Shear Walls
Teja Ande
 
Cracks in concrete and its remedial measures
Cracks in concrete and its remedial measures Cracks in concrete and its remedial measures
Cracks in concrete and its remedial measures
kamariya keyur
 
hot and cold weather concreting
hot and cold weather concretinghot and cold weather concreting
hot and cold weather concreting
Construction Tech. and Mgmt., VNIT Nagpur
 
Bs8110 design notes
Bs8110 design notesBs8110 design notes
Bs8110 design notes
Lawrence Omai
 
Unit IV composite beams and continuous beams
Unit IV composite beams and continuous beamsUnit IV composite beams and continuous beams
Unit IV composite beams and continuous beams
Selvakumar Palanisamy
 
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONSANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
Girish Singh
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing MethodMd Tanvir Alam
 
Lecture 8 raft foundation
Lecture 8 raft foundationLecture 8 raft foundation
Lecture 8 raft foundation
Dr.Abdulmannan Orabi
 

What's hot (20)

Lec.5 strength design method rectangular sections 1
Lec.5   strength design method rectangular sections  1Lec.5   strength design method rectangular sections  1
Lec.5 strength design method rectangular sections 1
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and Design
 
Concrete cloth
Concrete clothConcrete cloth
Concrete cloth
 
A UHPC (ultra high performance concrete) presentation projects.
A UHPC (ultra high performance concrete) presentation projects.A UHPC (ultra high performance concrete) presentation projects.
A UHPC (ultra high performance concrete) presentation projects.
 
Masonry structures -_chapter_9_and_10
Masonry structures -_chapter_9_and_10Masonry structures -_chapter_9_and_10
Masonry structures -_chapter_9_and_10
 
Structural dynamics good notes
Structural dynamics good notesStructural dynamics good notes
Structural dynamics good notes
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints
 
Bonding old and new concrete
Bonding old and new concreteBonding old and new concrete
Bonding old and new concrete
 
SELF COMPACTING CONCRETE MIX DESIGN [IS 10262-2019].pptx
SELF COMPACTING CONCRETE MIX DESIGN [IS 10262-2019].pptxSELF COMPACTING CONCRETE MIX DESIGN [IS 10262-2019].pptx
SELF COMPACTING CONCRETE MIX DESIGN [IS 10262-2019].pptx
 
Principles and design concepts of reinforced soil walls
Principles and design concepts of reinforced soil wallsPrinciples and design concepts of reinforced soil walls
Principles and design concepts of reinforced soil walls
 
Design steps of foot bridge , stringer and cross girder
Design steps of foot bridge , stringer and cross girderDesign steps of foot bridge , stringer and cross girder
Design steps of foot bridge , stringer and cross girder
 
Lecture 6 7 Rm Shear Walls
Lecture 6 7 Rm Shear WallsLecture 6 7 Rm Shear Walls
Lecture 6 7 Rm Shear Walls
 
Cracks in concrete and its remedial measures
Cracks in concrete and its remedial measures Cracks in concrete and its remedial measures
Cracks in concrete and its remedial measures
 
hot and cold weather concreting
hot and cold weather concretinghot and cold weather concreting
hot and cold weather concreting
 
Bs8110 design notes
Bs8110 design notesBs8110 design notes
Bs8110 design notes
 
Concrete Materials.ppt
Concrete Materials.pptConcrete Materials.ppt
Concrete Materials.ppt
 
Unit IV composite beams and continuous beams
Unit IV composite beams and continuous beamsUnit IV composite beams and continuous beams
Unit IV composite beams and continuous beams
 
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONSANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing Method
 
Lecture 8 raft foundation
Lecture 8 raft foundationLecture 8 raft foundation
Lecture 8 raft foundation
 

Similar to DESIGN OF CONTINUOUS MEMBERS IN PRESTRESSED

Design Of Continuous Beams 30_8.pptx
Design Of Continuous Beams 30_8.pptxDesign Of Continuous Beams 30_8.pptx
Design Of Continuous Beams 30_8.pptx
Krish Bhavsar
 
140204-5-PTI EDC-130-Continuous Members-41.pdf
140204-5-PTI EDC-130-Continuous Members-41.pdf140204-5-PTI EDC-130-Continuous Members-41.pdf
140204-5-PTI EDC-130-Continuous Members-41.pdf
ephrem53
 
Prestressed concrete continuous beam
Prestressed concrete continuous beamPrestressed concrete continuous beam
Prestressed concrete continuous beam
PraveenKumar Shanmugam
 
Connections
Connections Connections
Connections
kamariya keyur
 
Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C Beam
Ar. Aakansha
 
Rectangular tank
Rectangular tankRectangular tank
Rectangular tank
JayswalShashank1
 
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdfDeflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
vijayvijay327286
 
Analysis of two reinforced concrete multistored building
Analysis of two reinforced concrete multistored building Analysis of two reinforced concrete multistored building
Analysis of two reinforced concrete multistored building
RakeshKuli
 
rectangular and section analysis in bending and shear
rectangular and section analysis in bending and shearrectangular and section analysis in bending and shear
rectangular and section analysis in bending and shearqueripan
 
Columns lecture#1
Columns lecture#1Columns lecture#1
Columns lecture#1Irfan Malik
 
Column
ColumnColumn
Eurocode 2 design of composite concrete
Eurocode 2 design of composite concreteEurocode 2 design of composite concrete
Eurocode 2 design of composite concrete
Jo Gijbels
 
Special moment frames aci 318 - اطارات مقاومة للعزوم
Special moment frames aci   318 - اطارات مقاومة للعزوم Special moment frames aci   318 - اطارات مقاومة للعزوم
Special moment frames aci 318 - اطارات مقاومة للعزوم
Dr.Youssef Hammida
 
unit-3.ppt
unit-3.pptunit-3.ppt
unit-3.ppt
sabishanu
 
DESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERING
DESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERINGDESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERING
DESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERING
LiyaWilson4
 
Building project rc column
Building project rc columnBuilding project rc column
Building project rc column
sathananthankartheep
 
Design ppt
Design pptDesign ppt
Design ppttishu001
 
Chapter 6 column
Chapter 6   columnChapter 6   column
Chapter 6 column
Simon Foo
 

Similar to DESIGN OF CONTINUOUS MEMBERS IN PRESTRESSED (20)

Design Of Continuous Beams 30_8.pptx
Design Of Continuous Beams 30_8.pptxDesign Of Continuous Beams 30_8.pptx
Design Of Continuous Beams 30_8.pptx
 
140204-5-PTI EDC-130-Continuous Members-41.pdf
140204-5-PTI EDC-130-Continuous Members-41.pdf140204-5-PTI EDC-130-Continuous Members-41.pdf
140204-5-PTI EDC-130-Continuous Members-41.pdf
 
Prestressed concrete continuous beam
Prestressed concrete continuous beamPrestressed concrete continuous beam
Prestressed concrete continuous beam
 
Connections
Connections Connections
Connections
 
Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C Beam
 
Rectangular tank
Rectangular tankRectangular tank
Rectangular tank
 
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdfDeflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
 
Analysis of two reinforced concrete multistored building
Analysis of two reinforced concrete multistored building Analysis of two reinforced concrete multistored building
Analysis of two reinforced concrete multistored building
 
rectangular and section analysis in bending and shear
rectangular and section analysis in bending and shearrectangular and section analysis in bending and shear
rectangular and section analysis in bending and shear
 
Losses in prestress
Losses in prestressLosses in prestress
Losses in prestress
 
Columns lecture#1
Columns lecture#1Columns lecture#1
Columns lecture#1
 
Column
ColumnColumn
Column
 
Eurocode 2 design of composite concrete
Eurocode 2 design of composite concreteEurocode 2 design of composite concrete
Eurocode 2 design of composite concrete
 
Special moment frames aci 318 - اطارات مقاومة للعزوم
Special moment frames aci   318 - اطارات مقاومة للعزوم Special moment frames aci   318 - اطارات مقاومة للعزوم
Special moment frames aci 318 - اطارات مقاومة للعزوم
 
unit-3.ppt
unit-3.pptunit-3.ppt
unit-3.ppt
 
DESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERING
DESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERINGDESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERING
DESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERING
 
Building project rc column
Building project rc columnBuilding project rc column
Building project rc column
 
Column design1
Column design1Column design1
Column design1
 
Design ppt
Design pptDesign ppt
Design ppt
 
Chapter 6 column
Chapter 6   columnChapter 6   column
Chapter 6 column
 

Recently uploaded

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 

Recently uploaded (20)

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 

DESIGN OF CONTINUOUS MEMBERS IN PRESTRESSED

  • 1. DEPARTMENT OF CIVIL ENGINEERING 1 PRESENTATION ON PRESTRESSED CONCRETE DESIGN OF CONTINUOUS MEMBERS IN PRESTRESSED PRESENTED BY LOGESH. S M.E STRUCTURAL 19TPCV011
  • 2. 2 DESIGN OF CONTINUOUS MEMBERS IN PRESTRESSED
  • 3. 3 • A continuous beam is having more than one span is carried by several supports. • It is mainly used in bridge construction. • Simple beam cannot be used for large spans, as it requires more strength and stiffness. • But continuous PSC beam not only provides adequate strength and stiffness, but also provides sufficient ductility. Continuous Beam
  • 4. 4 • An important distinction between them is that the prestressing force does not produce any secondary moments in simple beams, considerable secondary moments are produced in continuous PSC beams. • Also, the behavior of continuous PSC beams nearer to ultimate load is different from the behavior of a corresponding simple beam. Continuous Beam
  • 5. 5 Merits • Ultimate loads carrying capacity is higher than the statically determinate structures due to the effect of redistribution of moments. • An increase in stability of framed structures. This is feasible due to the distribution of moments. • The deflections in continuous beams are relatively small when compared to simply supported beams. This is due to the fact that the continuity of members makes the rotation less at the places of supports. Thus, the deflections are less.
  • 6. 6 • The maximum bending moment that occurs in a continuous beam is less than that for same spans, if the beams are cut into simply supported beams. • In continuous beam, the bending moments are evenly distributed throughout the span and results in reduction in size of members. Thus, lighter weight structures made. • An effective usage of curved cables is possible to resist the supports and span moments. • A reduction in cost and construction time is possible due to the use of number of anchorages. Merits
  • 7. 7 • Frictional loss in continuous tendons • Shortening of long continuous beams under prestress • Secondary stresses • Location of both maximum moment and shear force over supports • Reversal of moments • Moment packs • Continuity for precast elements • Difficulty in designing. Demerits
  • 8. 8 The profile of the CGS for a post-tensioned beam is shown in the sketch. Plot the pressure line due to a prestressing force Pe = 1112 kN. Solution 1) Plot M1 diagram The values of M1 are calculated from M1 = Pee. e (m) M1 (kN m) 0.06 – 66.72 0.24 – 266.88 – 0.12 133.44 0.27 – 300.24 .06 C G C 0.08 rad A 9 m D 6 m B 7.5 m 0.176 rad 7.5 m C .27.12.24
  • 9. 9 0.24 0.06 0.270.12 -66.72 -266.88 -300.24 133.44 M1 diagram (kN m) Profile of the CGS Plot V diagram For AD, V= dM1/dx = (-266.9 - (-66.7))/9 = -22.2 kN For DB, V= dM1/dx = (133.4 - (-266.9))/6 = 66.7 kN A D B C
  • 10. 10 For BC, to find dM1/dx, an approximate parabolic equation for the M1 diagram can be used. M1 = - 4Peex (L - x )/L2 V= dM1/dx = - 4Pee(L - 2x )/L2 =- 4Pee/L =- 4 ×(133.4 + 300.2) 15 = -115.6 kN At B, V = L M1 Pee x
  • 11. 11 The exact value of V at B is V = - 107.0 kN The difference of V between C and B is given from the change in slope of the M1 diagram. V|C - V|B = 0.176 × 1112 = 195.7 kN Therefore, value of V at C is given as follows. V|C = 195.7 – 107.0 = 89.0 kN 66.72 266.88 300.24 133.44 V diagram (kN) 66.7 89.0 -107.0- 22.2 M1 Diagram (kN m)
  • 12. 12 3) Plot equivalent load (weq) diagram. Include moment 66.7 kN-m at A. Point load at D W|D = 66.7- (- 22.2 ) = 88.9 kN Since B is a reaction point, the downward load at B need not be considered. Distributed load within B and C w BC = 89.0 - (-107.0) 15 = 13.0 kN/m – 22.2 66.7 89.0 Equivalent load diagram 66.7 kN m 13.0 kN/m 88.9 kN – 107.0 Kn V diagran
  • 13. 13 0.5 0.5 88.9x9×6^2 88.9×9^2 ×6 13.0×15^2 15^2 15^2 12 =128 = -192 = 244 –244 –194.7 244 –97 122 –38.5 –38.5 –66.7 –327.5 327.5 0 66.7 DF 88.9 FEM Bal CO Bal Total 13.0 In the previous table, Bal = Balanced CO = Carry Over moment DF = Distribution Factor FEM = Fixed End Moment 4) Plot the M2 diagram. Calculate moment at supports by moment distribution
  • 14. 14 M2 (kN m) ec (m) – 66.7 0.06 327.0 0.294 0.0 0.184 Calculate values of ec at support. The values of ec are calculated from ec= M2/Pe. M2 diagram (kN m) Profile of CGS Pressure line 0.06 0.136 0.294 0.184 327.0 -66.7 66.7 knm 0 88.9 kn 13kn/ m
  • 15. 15