SlideShare a Scribd company logo
Design Considerations Of Earth Dams
Rosul Ahmed & Lujain Haider
An earth dam is a dam built with highly compacted earth. This dam is
classified as a type of embankment dam, being built in the shape of an
embankment or wedge which blocks a waterway. These dams have
been built by various human societies for centuries, and they continue
to be produced in some regions of the world when they appear to be
suitable for the location and intended use.
The characteristics of the particular site have a greater
influence on the design of an earth dam than they do other
engineering structure .the and locations of the soils available
for the construction of the embankment may dominate the
entire design ,although in most cases the soils must be
considered in conjunction with conditions such as the nature
of the foundation, the climate of the region , the size and
shape of the valley.
 A thorough exploration of the foundation and abutment, and an
evaluation of the quantities and characteristics off all the embankment
construction materials available within a reasonable distance of the site.
 A study of all the conditions which may influence the design.
 The selection of possible trail design.
 An analysis of the safety of the trail design.
 The modification of the designs in order to meet minimum stability
requirements.
 The preparation of detailed cost estimation.
 The final selection of design which seems to offer the best combination of
economy , safety And convenience in construction.
On of the principle economic advantages of the earth dam is that nature has already
fabricated the construction materials and placed them free of charge at the site. In
some cases only one type of soil is readily available ,and the principle design
problem is to determine the most economical dam that can be made from it.
 If it is an impervious soil, the design consist of a homogeneous embankment with
only a small amount of pervious material to control internal seepage .
 If it is a pervious sand and gravel , a dam with a very thin core may be used where
enough impervious is available to make a core.
 At the other extreme are sites with a great number of varied soils which can be
incorporated in different combinations into the embankment. In such case it in
advisable to plan a zoned dam with the finer and more impervious materials
placed in an internal core, and the coarser materials utilized to provide strength
and drainage in upstream and downstream zones.
 where two types of soils occur in horizontal layers in the same borrow pit, they
can either excavated selectively and placed in different zones of the dam or
excavated together and blended into single material with intermediate properties.
Removal Of Oversized Cobbles:
•The largest cobble used in an embankment for example the core the
max. diameter is set at 5 or 6 in and for embankment sections up to
diameter of 24 in .
•If the soil for the core of the dam contains only a few percent of
oversized cobbles, the purpose of removing them is to improve the
compaction and quality of the embankment .but if the soil contained
a large quantity of oversized cobbles, two other benefits may be
obtained :
The embankment can be made more impervious and the oversized
cobbles can become an important source of material for the
construction of free-draining zones .
The design of a dam is affected by climate, because of the importance of he
weather during the construction period.
 In regions where construction must be carried on during a rainy season, it
is often preferable to design the dam with a sloping upstream core instead
of a central core.
 In arid or semiarid regions it is much easier than in wet climates to control
the construction water content of fine-grained soils.
It possible to build an earth dam on almost any kind of foundation.
The foundation characteristics may or may not have a large
influence on the embankment design.
 The embankment that is on a foundation of soil with low shear strength
must usually be made broader and with flatter sloped than would
otherwise e required .
 For pervious soil foundation either a seepage cutoff must be provided or
the under seepage must be controlled to avoid the danger of the piping.
 In the case of the rock foundations ,special design details are used to seal
the core of the dam to the rock.
The shape and size of the valley at the dam site may have an important
influence on the design of the dam in a number of ways . In board valleys
with gently sloping abutments, the embankment section is not usually
much influenced by either design or construction problems.
 In narrow valleys or in valleys with steep abutments ,special design
provisions may be necessary.
 In very narrow valleys the area of the construction surface is small ,and
large quantities of equipment cannot be used efficiently.
 For dams in very narrow valleys with steep walls, it may be necessary to
use piping-resistant cores ,special filters, or other design details which will
minimize the danger of embankment cracking due to differential
settlement.
1-Homogeneous dams:
 Homogenous are constructed entirely or almost entirely of a single
embankment material.
 Homogenous embankments are used most often in dams of low to
moderate height.
 Homogenous dams are usually composed of impervious or semi-
pervious soils, but many successful embankment have been built of
relatively pervious sands and sand-gravel mixture.
 Any homogenous dam with a height of more than about 20-25 ft.
should have provided with some type of downstream drain
constructed of material appreciably more pervious than the
embankment soil.
The design of the downstream drainage system is governed
mainly by the height of the dam, the cost and availability of
pervious material and permeability of the foundation.
 For low dams , a simple drain of the type can be used .toe
drains such as this were installed in some of the oldest
homogenous dams in an effort to prevent softening.
 Horizontal drain blankets widely used for dams of moderate
height.
 Higher homogenous have been constructed with inclined and
vertical “chimney” drains .although “chemeny” drains were
used on some very old dams.
There are several conditions which may make a thin core dam the
best design for a given site. Where there is an ample supply of
pervious embankment material but only a limited supply of soil
suitable for an impervious core, the designer may have no other
choice than a thin core dam. Where there are ample supplies of
both pervious and impervious soil, a thin core dam be more
economical or more easily constructed for a combination of
reasons :
1- The unit cost of placing pervious material may be less than that of
placing the available impervious materials.
2- The embankment volume can be made smaller in a thin core dam
than in any other.
3- The weather and the construction time available may not permit
the use of a large zone of impervious material
.
 In this type of dam the core may be sloped upstream or placed in a vertical
position near the center of the embankment.
 The pervious zones are constructed either of sand or gravel or of rock
obtained by quarrying or screening earth rock mixtures.
 The problem of determining the min. safe thickness is not amenable to
theoretical treatment and no definite rules can be given.
It is governed for practical purposes by the following factors :
1- The tolerable seepage loss.
2- The min. width which will permit proper construction.
3- The type of material available for the core and shells.
4- The design of the proposed filter layers.
5- precedent on similar projects.
The min. allowable core thickness should always depend to a great extent on
the plasticity and gradation of the core material .
Advantages of vertical and slopping cores in earth dams
are :
1- the higher pressure will exist on the contact between the core and the
foundation and will provide more protection against the possibility of
leakage along the contact.
2- The thickness of the vertical core is slightly greater for a given quantity of
impervious soil than thickness of slopping cores .
3- The filter layers between the core and the upstream and the downstream
pervious zones can be made thinner with less difficulty in construction
than the filter layers for vertical core dams.
Disadvantages of the slopping core is that the location of the area of the
contact between the core and the foundation depends on the depth of
foundation excavation .
 For the great majority of earth dams, the embankment is
constructed with the same design section (the same zoning and the
slopes) over the hole length.
 At some sites, however, have been divided into two or more
sections and different design used in each.
 For dams of short length there is usually little or no reason for
changing the design, but for long dams several circumstances may
make different sections advisable . For example, different portions
of the dam may have different foundation condition or different
heights .


More Related Content

What's hot

Drainage Engineering (cross drainage structures)
Drainage Engineering (cross drainage structures)Drainage Engineering (cross drainage structures)
Drainage Engineering (cross drainage structures)
Latif Hyder Wadho
 
Reservoir capacity, Reservoir sedimentation and control
Reservoir capacity, Reservoir sedimentation  and controlReservoir capacity, Reservoir sedimentation  and control
Reservoir capacity, Reservoir sedimentation and control
deep shah
 
Reservoir sedimentation
Reservoir sedimentationReservoir sedimentation
Reservoir sedimentation
Pramoda Raj
 
Gravity dam
Gravity damGravity dam
Gravity dam
GAURAV. H .TANDON
 
Gravity dam
Gravity damGravity dam
Earthen Dam
Earthen DamEarthen Dam
Canal regulation works. m4pptx
Canal regulation works. m4pptxCanal regulation works. m4pptx
Canal regulation works. m4pptx
Bibhabasu Mohanty
 
Spillways
SpillwaysSpillways
4. Construction and design criteria Earthen Dams.pptx
4. Construction and design criteria Earthen Dams.pptx4. Construction and design criteria Earthen Dams.pptx
4. Construction and design criteria Earthen Dams.pptx
Abhilashvishwakrama
 
Earthen dam
Earthen damEarthen dam
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
GAURAV. H .TANDON
 
Reservoir Planning
Reservoir PlanningReservoir Planning
Reservoir Planning
Sunny Agarwal
 
Reservoir
ReservoirReservoir
Diversion head works
Diversion head worksDiversion head works
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
Aditya Mistry
 
Plate load test
Plate load testPlate load test
Plate load test
M Dinesh kumar
 
Types of spillways
Types of spillwaysTypes of spillways
Types of spillways
saibabu48
 
5 Reservoir Planning
5 Reservoir Planning5 Reservoir Planning
5 Reservoir Planning
pradeepkumawat4142
 
Canal outlets
Canal outletsCanal outlets
Canal outlets
saibabu48
 
Spillway gates
Spillway gatesSpillway gates
Spillway gates
murali mohan
 

What's hot (20)

Drainage Engineering (cross drainage structures)
Drainage Engineering (cross drainage structures)Drainage Engineering (cross drainage structures)
Drainage Engineering (cross drainage structures)
 
Reservoir capacity, Reservoir sedimentation and control
Reservoir capacity, Reservoir sedimentation  and controlReservoir capacity, Reservoir sedimentation  and control
Reservoir capacity, Reservoir sedimentation and control
 
Reservoir sedimentation
Reservoir sedimentationReservoir sedimentation
Reservoir sedimentation
 
Gravity dam
Gravity damGravity dam
Gravity dam
 
Gravity dam
Gravity damGravity dam
Gravity dam
 
Earthen Dam
Earthen DamEarthen Dam
Earthen Dam
 
Canal regulation works. m4pptx
Canal regulation works. m4pptxCanal regulation works. m4pptx
Canal regulation works. m4pptx
 
Spillways
SpillwaysSpillways
Spillways
 
4. Construction and design criteria Earthen Dams.pptx
4. Construction and design criteria Earthen Dams.pptx4. Construction and design criteria Earthen Dams.pptx
4. Construction and design criteria Earthen Dams.pptx
 
Earthen dam
Earthen damEarthen dam
Earthen dam
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Reservoir Planning
Reservoir PlanningReservoir Planning
Reservoir Planning
 
Reservoir
ReservoirReservoir
Reservoir
 
Diversion head works
Diversion head worksDiversion head works
Diversion head works
 
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
 
Plate load test
Plate load testPlate load test
Plate load test
 
Types of spillways
Types of spillwaysTypes of spillways
Types of spillways
 
5 Reservoir Planning
5 Reservoir Planning5 Reservoir Planning
5 Reservoir Planning
 
Canal outlets
Canal outletsCanal outlets
Canal outlets
 
Spillway gates
Spillway gatesSpillway gates
Spillway gates
 

Similar to Design consideration Of Earth Dams

Dams and control works
Dams and control worksDams and control works
Dams and control works
julian21323
 
Lecture-6 Earthdams.pptx
Lecture-6 Earthdams.pptxLecture-6 Earthdams.pptx
Lecture-6 Earthdams.pptx
AleemNawaz6
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
Pile foundation
Pile foundationPile foundation
Pile foundation
Aglaia Connect
 
GEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMS
GEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMSGEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMS
GEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMS
LorevieOlaes
 
Notes on introduction and design of caissons
Notes on introduction and design of caissonsNotes on introduction and design of caissons
Notes on introduction and design of caissons
VICTOR A. KIPLAGAT
 
porous and previous roads
porous and previous roadsporous and previous roads
porous and previous roads
Shubham Singh [NITK]
 
pile wall
pile wallpile wall
pile wall
SALEM MOHAMMED
 
Dams
DamsDams
Dams
DamsDams
1.PILE FOUNDATION (ACE) 2160601 GTU
1.PILE FOUNDATION (ACE) 2160601 GTU1.PILE FOUNDATION (ACE) 2160601 GTU
1.PILE FOUNDATION (ACE) 2160601 GTU
VATSAL PATEL
 
Factors to consider in foundation design
Factors to consider in foundation designFactors to consider in foundation design
Factors to consider in foundation design
Mushtaq Zaib
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
ajinkya gaikwad
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
vietcgxd
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
ANKITAARORA85
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
Chin Tze Wei
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
Shao Xun Sean Thun
 
Construction Technology Report
Construction Technology ReportConstruction Technology Report
Construction Technology Report
Shao Xun Sean Thun
 
4. COFFERDAM (ACE) 2160601 GTU
4. COFFERDAM (ACE) 2160601 GTU4. COFFERDAM (ACE) 2160601 GTU
4. COFFERDAM (ACE) 2160601 GTU
VATSAL PATEL
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
Gaurang Kakadiya
 

Similar to Design consideration Of Earth Dams (20)

Dams and control works
Dams and control worksDams and control works
Dams and control works
 
Lecture-6 Earthdams.pptx
Lecture-6 Earthdams.pptxLecture-6 Earthdams.pptx
Lecture-6 Earthdams.pptx
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
GEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMS
GEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMSGEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMS
GEOLOGICAL CONDITIONS NECESSARY FOR CONSTRUCTION OF DAMS
 
Notes on introduction and design of caissons
Notes on introduction and design of caissonsNotes on introduction and design of caissons
Notes on introduction and design of caissons
 
porous and previous roads
porous and previous roadsporous and previous roads
porous and previous roads
 
pile wall
pile wallpile wall
pile wall
 
Dams
DamsDams
Dams
 
Dams
DamsDams
Dams
 
1.PILE FOUNDATION (ACE) 2160601 GTU
1.PILE FOUNDATION (ACE) 2160601 GTU1.PILE FOUNDATION (ACE) 2160601 GTU
1.PILE FOUNDATION (ACE) 2160601 GTU
 
Factors to consider in foundation design
Factors to consider in foundation designFactors to consider in foundation design
Factors to consider in foundation design
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Construction Technology Report
Construction Technology ReportConstruction Technology Report
Construction Technology Report
 
4. COFFERDAM (ACE) 2160601 GTU
4. COFFERDAM (ACE) 2160601 GTU4. COFFERDAM (ACE) 2160601 GTU
4. COFFERDAM (ACE) 2160601 GTU
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
 

Recently uploaded

Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
PuktoonEngr
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
Ratnakar Mikkili
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 

Recently uploaded (20)

Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 

Design consideration Of Earth Dams

  • 1. Design Considerations Of Earth Dams Rosul Ahmed & Lujain Haider
  • 2. An earth dam is a dam built with highly compacted earth. This dam is classified as a type of embankment dam, being built in the shape of an embankment or wedge which blocks a waterway. These dams have been built by various human societies for centuries, and they continue to be produced in some regions of the world when they appear to be suitable for the location and intended use.
  • 3. The characteristics of the particular site have a greater influence on the design of an earth dam than they do other engineering structure .the and locations of the soils available for the construction of the embankment may dominate the entire design ,although in most cases the soils must be considered in conjunction with conditions such as the nature of the foundation, the climate of the region , the size and shape of the valley.
  • 4.  A thorough exploration of the foundation and abutment, and an evaluation of the quantities and characteristics off all the embankment construction materials available within a reasonable distance of the site.  A study of all the conditions which may influence the design.  The selection of possible trail design.  An analysis of the safety of the trail design.  The modification of the designs in order to meet minimum stability requirements.  The preparation of detailed cost estimation.  The final selection of design which seems to offer the best combination of economy , safety And convenience in construction.
  • 5.
  • 6. On of the principle economic advantages of the earth dam is that nature has already fabricated the construction materials and placed them free of charge at the site. In some cases only one type of soil is readily available ,and the principle design problem is to determine the most economical dam that can be made from it.  If it is an impervious soil, the design consist of a homogeneous embankment with only a small amount of pervious material to control internal seepage .  If it is a pervious sand and gravel , a dam with a very thin core may be used where enough impervious is available to make a core.  At the other extreme are sites with a great number of varied soils which can be incorporated in different combinations into the embankment. In such case it in advisable to plan a zoned dam with the finer and more impervious materials placed in an internal core, and the coarser materials utilized to provide strength and drainage in upstream and downstream zones.  where two types of soils occur in horizontal layers in the same borrow pit, they can either excavated selectively and placed in different zones of the dam or excavated together and blended into single material with intermediate properties.
  • 7.
  • 8. Removal Of Oversized Cobbles: •The largest cobble used in an embankment for example the core the max. diameter is set at 5 or 6 in and for embankment sections up to diameter of 24 in . •If the soil for the core of the dam contains only a few percent of oversized cobbles, the purpose of removing them is to improve the compaction and quality of the embankment .but if the soil contained a large quantity of oversized cobbles, two other benefits may be obtained : The embankment can be made more impervious and the oversized cobbles can become an important source of material for the construction of free-draining zones .
  • 9.
  • 10. The design of a dam is affected by climate, because of the importance of he weather during the construction period.  In regions where construction must be carried on during a rainy season, it is often preferable to design the dam with a sloping upstream core instead of a central core.  In arid or semiarid regions it is much easier than in wet climates to control the construction water content of fine-grained soils.
  • 11. It possible to build an earth dam on almost any kind of foundation. The foundation characteristics may or may not have a large influence on the embankment design.  The embankment that is on a foundation of soil with low shear strength must usually be made broader and with flatter sloped than would otherwise e required .  For pervious soil foundation either a seepage cutoff must be provided or the under seepage must be controlled to avoid the danger of the piping.  In the case of the rock foundations ,special design details are used to seal the core of the dam to the rock.
  • 12.
  • 13. The shape and size of the valley at the dam site may have an important influence on the design of the dam in a number of ways . In board valleys with gently sloping abutments, the embankment section is not usually much influenced by either design or construction problems.  In narrow valleys or in valleys with steep abutments ,special design provisions may be necessary.  In very narrow valleys the area of the construction surface is small ,and large quantities of equipment cannot be used efficiently.  For dams in very narrow valleys with steep walls, it may be necessary to use piping-resistant cores ,special filters, or other design details which will minimize the danger of embankment cracking due to differential settlement.
  • 14. 1-Homogeneous dams:  Homogenous are constructed entirely or almost entirely of a single embankment material.  Homogenous embankments are used most often in dams of low to moderate height.  Homogenous dams are usually composed of impervious or semi- pervious soils, but many successful embankment have been built of relatively pervious sands and sand-gravel mixture.  Any homogenous dam with a height of more than about 20-25 ft. should have provided with some type of downstream drain constructed of material appreciably more pervious than the embankment soil.
  • 15. The design of the downstream drainage system is governed mainly by the height of the dam, the cost and availability of pervious material and permeability of the foundation.  For low dams , a simple drain of the type can be used .toe drains such as this were installed in some of the oldest homogenous dams in an effort to prevent softening.  Horizontal drain blankets widely used for dams of moderate height.  Higher homogenous have been constructed with inclined and vertical “chimney” drains .although “chemeny” drains were used on some very old dams.
  • 16.
  • 17. There are several conditions which may make a thin core dam the best design for a given site. Where there is an ample supply of pervious embankment material but only a limited supply of soil suitable for an impervious core, the designer may have no other choice than a thin core dam. Where there are ample supplies of both pervious and impervious soil, a thin core dam be more economical or more easily constructed for a combination of reasons : 1- The unit cost of placing pervious material may be less than that of placing the available impervious materials. 2- The embankment volume can be made smaller in a thin core dam than in any other. 3- The weather and the construction time available may not permit the use of a large zone of impervious material .
  • 18.
  • 19.  In this type of dam the core may be sloped upstream or placed in a vertical position near the center of the embankment.  The pervious zones are constructed either of sand or gravel or of rock obtained by quarrying or screening earth rock mixtures.  The problem of determining the min. safe thickness is not amenable to theoretical treatment and no definite rules can be given. It is governed for practical purposes by the following factors : 1- The tolerable seepage loss. 2- The min. width which will permit proper construction. 3- The type of material available for the core and shells. 4- The design of the proposed filter layers. 5- precedent on similar projects. The min. allowable core thickness should always depend to a great extent on the plasticity and gradation of the core material .
  • 20. Advantages of vertical and slopping cores in earth dams are : 1- the higher pressure will exist on the contact between the core and the foundation and will provide more protection against the possibility of leakage along the contact. 2- The thickness of the vertical core is slightly greater for a given quantity of impervious soil than thickness of slopping cores . 3- The filter layers between the core and the upstream and the downstream pervious zones can be made thinner with less difficulty in construction than the filter layers for vertical core dams. Disadvantages of the slopping core is that the location of the area of the contact between the core and the foundation depends on the depth of foundation excavation .
  • 21.  For the great majority of earth dams, the embankment is constructed with the same design section (the same zoning and the slopes) over the hole length.  At some sites, however, have been divided into two or more sections and different design used in each.  For dams of short length there is usually little or no reason for changing the design, but for long dams several circumstances may make different sections advisable . For example, different portions of the dam may have different foundation condition or different heights .
  • 22.
  • 23.