SlideShare a Scribd company logo
REPORT FOR 
COST CONTROL TECHNIQUES 
JUNE 2014 
By Madhava reddy / Doha Qatar
Table of contents 
1.0 Abstract 
2.0 Introduction 
3.0 Cost control in construction 
4.0 Wastage of Materials 
5.0 Control on Plant and Equipment's 
6.0 Productivity of Labor 
7.0 Time vs. cost relation ship 
8.0 Cost control techniques to be used at site 
9.0 Control of Materials 
10 .0 Use of Equipment 
11 .0 Recommendations 
12 .0 Control of Materials Wastage 
13.0 Control on Plant and Equipment 
14.0 Control and improve labor productivity 
15.0 Conclusion
1.0 Abstract 
Most of the civil projects over have suffered from the cost and time 
overruns due to factors stemming from poor cost control during the 
design and project implementation stages. 
As per Monitoring and studying the cost control techniques being not 
used by the individual Project Managers at all sites, the problems faced 
and proposed solutions. Identify seven commonly used cost control 
techniques which include schedules, budget, inspection, meetings, 
reports, records, monitoring & evaluations.
2.0 Introduction 
Project Managers are find difficulty in controlling project costs due to 
problems which include delays by clients to release money, delay to 
make a decision, lack of materials and equipment, bad weather, 
overlapping of activities, unclear and incomplete drawings, making good 
defective works, and generally failure to control the productivity of 
resources. Others of were due to interference by clients, high labor 
turnover, and insufficient knowledge on cost control techniques. And 
another is noticed unable to establish that the problem was actually not 
the techniques to use but rather the lack of knowledge of the techniques, 
the poor management of the cost control methodology, and the general 
poor commanding on site organization (engineers) the management is 
interested in obtaining fully functional facilities completed in time, cost, 
quality and scope. And they are able to construct within the estimated 
time and budget, to prove to the clients that the right standards and scope 
as an excellent contractor in Qatar . Cost control is a process where the 
construction cost of the project is managed through the best methods and 
techniques so that the Management does not suffer losses when carrying 
out the activities of the project. One of the aims of cost control is to 
construct at the cheapest possible costs consistent with the project 
objectives. 
Ultimately the decision of the Project manager that something should be 
done differently and the translation of that decision into practice are the 
actions to observes that it is of little use after a process has been 
completed to discover that its cost was actually too much. Most project 
managers are find difficulty in controlling costs on their construction 
sites due to a number of problems which include preparation, lapse in 
management and control, over budgeting, poor materials, labor shortages, 
increased cost of materials, delays in deliveries, wastage of materials, 
unexpected weather changes, loss of materials, insecurity and poor 
communication. This results into cost and time overruns, conflicts, and 
sometimes abandoning projects. therefore carried out to identify the cost 
control techniques used propose effective
3.0 Cost control In construction 
During the execution of a project, The project Mangers to follow the 
strictly procedures for project control and record keeping become 
indispensable tools to managers by involving the other participants 
(Engineers) in the construction process. According to cost control can be 
achieved by selecting the right man for the right job, the right equipment 
and tools for the right work and the right quality of materials, in the right 
quantity, from the right source, at the right price and delivered at the right 
time. Managers are expected to be well equipped to execute the project, 
with due consideration to the quality of work, yet within the estimated 
cost and time limits.
4.0 Wastage of Materials 
One of the big problems of Turn key Projects suffer large amount of 
materials wastage due to varying circumstances problem requires a 
supervisor to constantly be on the lookout for the losses. According to 
wastage of materials can take place during the procurement process. 
storage, and during utilization. Wastage during procurement can result 
from one or more of the following causes: buying materials of wrong 
specifications, buying more than the actual requirements to cater for 
unrealistic and unforeseen eventualities, untimely buying of short-life 
materials, improper and unnecessary handling of materials, and . 
Wastage during storage can occur due to the other reasons are take 
place during the procurement process. storage, and during utilization. 
Wastage during procurement, deterioration due to incorrect storage, 
incorrect maintenance and short-shelf life and losses due to exposure to 
extreme climatic conditions. Other causes are lack of pre-work 
preparation and coordination, improper accounting and poor 
storekeeping, negligent and careless attitude of the supervisor, high rate 
of deterioration due to long storage at the place of work, and over-issues 
from the central stores and failures to return unused surplus 
materials to the stores. some unavoidable wastages are inherent during 
utilization, but excessive wastage is of concern to the management as it 
affects the productivity adversely, with consequences of extra costs. 
Most problems relating to material wastage revolve around 
requisitioning and ordering, receipt and checking of deliveries from 
suppliers, offloading and handling, storing and protecting, and issuing, 
distributing and use of materials.
5.0 Control on Plant and equipment 
In construction, some tasks are labor intensive, some predominantly 
employ equipment, and some use a combination of both. While the 
actual work done and the associated labor is accounted by the 
supervisor concerned, the equipment and productivity control is 
undertaken to determine its employment time, the output achieved, and 
its productivity at site. 
The main purpose of the control is to minimize wastage in utilization so 
that the overall construction would probably reduce the cost of 
construction by about 30% which would likely 
In construction, some tasks are labor intensive, some predominantly 
employ equipment, and some use a combination of both. While the 
actual work done and the associated labor is accounted by the 
supervisor concerned, the equipment and productivity control is 
undertaken to determine its employment time, the output achieved, and 
its productivity at site The main purpose of the control is to minimize 
wastage in utilization so that the overall project cost is not affected 
observed that industrializing construction would probably reduce the 
cost of construction by about 30% which would likely
6.0 Productivity of labor 
Labor productivity achieved at the site for a given work provides a 
measure of the laborer's efficiency and effectiveness and the level 
of site organisation. It shows the total time for which the laborer 
was employed at work, the time he was productive on work and 
the time he remained unproductive. Craftsmen use about 40% of 
available time on productive activities, and about 33% of the time 
on non-value adding activities Productive times are wasted for 
various reasons such as idle waiting, unnecessary travelling, late 
starting, early quitting, Labor productivity achieved at the site for 
a given work provides a measure of the laborer's efficiency and 
effectiveness and the level of unscheduled breaks, and delays in 
the receipt of tolls, delays to receive materials and work 
instructions. productivity and other metrics were done by 
Alinaitwe, and the results indicated hat the working relationship 
7.0 Time-cost Relationship 
The relationship between time and cost is a very important 
aspect in the control of costs on site as any variation in time 
has automatic implication on cost. It is important to report 
and record all the works involving materials, plant and labor 
on sites. This enables the contractor be able to know the 
costs and expenses of the resources used on site and compare 
with the initial cost budget. Various report techniques used 
include; daily or weekly and monthly recording, schedule 
control, site daily diary report and the project budget.
8.0 Materials 
The causes of material wastages on sites were found to include poor 
supervision of operatives, poor handling of materials, misuse of materials, 
poor storage and stacking of materials, delivery of excess material on site, 
poor site organization, late delivery of materials, poor coordination of 
management and technical side, poor time management, bad weather 
conditions, use of unskilled 
9.0 Use of Equipment 
Equipment Use on Site obtained equipment on site by hiring. No contractor 
obtained equipment by purchasing as most of the activities were manually 
carried out. Mechanized construction of buildings is insignificant 
productivity can be improved by substituting labour with equipment.
10.0 RECOMMENDATIONS 
The Main problem of sites by not using the cost control techniques , to 
improve effective Management of the techniques and avoid laxity in 
supervision . It is therefore strongly recommended for all the sites 
should constantly attend refresher courses in construction project 
management as the study identified lack of knowledge of the cost 
control and Project Management, further more In almost all sites, 
workers were not aware of the performance targets implying there were 
lack of knowledge and communication lapses between supervisors and 
workers. Cost is a product of the use of project resources and the only 
better way of controlling the cost of projects is best handled right at the 
initial stage. 
During implementation, procedures of cost control of resources only 
helps in detecting variances and formulating corrective measures other 
than waiting until work has been completed . 
The other problems are noticed by the Management that led to delays 
and subsequent failure to construct within budget included: low 
resources productivity, lack of materials and equipment's ( late 
procuring), alterations by the clients to give instructions from clients 
and consultants to delay work as they waited to give site instructions . 
Other problems were due to delayed payments by clients, overlapping 
of activities, make good defective work, unclear details on the 
drawings, and delay by local authority to inspect the works. the greatest 
cause that faced of delay of payments projects due to late release of 
money by clients.
11.0 Cost Control Techniques Used in Building 
Sites 
1.0 Work Programmes 
Contractors used schedules to monitor progress and financial 
performance. It is a good method since work progress can be 
measured and related to cost. 
2.0 Inspection of Works 
Inspection of works and comparison made with the 
budget. Sometimes subject to judgment, hence lacking 
3.0 The project Budgets 
Cost attached to responsibility centers with work targets to be 
accomplished. It’s used in relation to schedules makes it the best tool 
for cost control. 
4.0 Site Meetings 
Meeting held to review the progress of work and compare to the 
monetary allocations. Good as it provides some motivation to 
workers and all stakeholders are up to date on the performance of 
work 
5.0 Record Keeping 
Documentation of activities carried out to enable early detection of 
deviations from the set standard 
6.0 Monitoring Work andCost Performance 
Clients, consultants and the contractors used monitoring tools of 
schedules, budgets, inspection and feedbacks to keep a watch on the 
cost performance. With use of the right tools of control, it produces 
good results 
7.0 Evaluation of Works 
Carried Out Quantification of works and comparing with the costs in 
the bill of quantities. Inspection was also reportedly used to evaluate 
works. This helps to ascertain that the progress of work is on the right 
track. 
8.0 Others 
Sites that did not have particular method to use.
12.0 Control of Materials wastage 
It is proposed that materials wastage should be reduced by ensuring that: 
Materials are delivered as required to cut site storage time, materials 
delivered are those specified, issuing just the right amount of material 
with only a reasonable allowance for wastage to workmen, ensuring that 
workmen are not producing excessive amount of off-cuts, ( specially 
tiles ) allocating and preparing storage areas so that when materials are 
stored, they do not deteriorate. Employing a reliable store keeper who is 
able to maintain well kept booking system, double signing of delivery 
notes, and spot checks for materials deliveries are all desirable to 
minimise wastage. And safe guard issuing of items by store men and 
keeping records of all the materials on site including employing full-time 
security guards. Sites should be hoarded with alarm systems installed 
around key materials around the site and including ensuring that the 
whole site is lit up at night. 
13.0 Control on Plant and equipment 
The use of machines at building sites are insignificant yet the 
mechanization of construction can reduce the cost of buildings by 30%. 
Contractors are encouraged to adopt the use of machine as it has the 
advantages of speeding up work, saving labour, producing better quality 
works and are economical in a number of cases besides being able to do 
what cannot be done manually. Once brought to sites, machines should 
be maximally utilized as any redundant time can lead to high cost
14.0 Control and improve labor productivity 
To improve on the labour productivity on sites by recording laborer's 
work progress, daily work evaluation, recruitment of laborer's with the 
right skills for the job, substituting laborer's with equipment, and having 
schedules and proper control procedure and records in place. A good 
working environment should also be created with work motivation and 
proper communication system included. Regular inspections by the 
engineers /foramens at site and early detection of variances using 
standard productivity are highly recommended. Without a good quality 
plan, project control cannot be achieved. Project control requires efficient, 
effective and vigilant processes and actions to ensure its successful 
accomplishment.
15.0 CONCLUSION 
The aim of this study was to study the cost control techniques used 
by the Project Mangers on-going projects and propose measures 
that will enable projects to be completed as budgeted. The seven 
cost control techniques used by contractors on their sites were 
found to include use of: schedules, the project budget, inspection of 
works, cost reports, site meetings, monitoring of cost and work 
performance and quantity evaluation using the bills of quantities, 
and others did not have well defined techniques or did not even 
know there were traditional cost control procedures. 
It was noted that unable to establish concrete evidences that 
actually the stated techniques were effectively used as documents 
to prove the applications were found lacking or not there at all. The 
survey was able to firmly state that, “the problem of cost control is 
actually the lack of knowledge and inadequate with the poor 
management of construction resources at sites ”.

More Related Content

What's hot

REDUCING INDIRECT COSTS IN MANUFACTURING INDUSTRIES
REDUCING INDIRECT COSTS IN MANUFACTURING INDUSTRIESREDUCING INDIRECT COSTS IN MANUFACTURING INDUSTRIES
REDUCING INDIRECT COSTS IN MANUFACTURING INDUSTRIES
faizyelectrical
 
Cost reduction & cost control
Cost reduction & cost controlCost reduction & cost control
Cost reduction & cost control
sachin padwal
 
Cost control and cost reduction
Cost control and cost reductionCost control and cost reduction
Cost control and cost reduction
Md Perwez
 
Cost Control & Cost Reduction ppt
Cost Control & Cost Reduction pptCost Control & Cost Reduction ppt
Cost Control & Cost Reduction ppt
mayank mulchandani
 
Warwick Lean Agenda Aug Wk1 July 12 2010
Warwick Lean  Agenda Aug Wk1  July 12 2010Warwick Lean  Agenda Aug Wk1  July 12 2010
Warwick Lean Agenda Aug Wk1 July 12 2010
ExerciseLeanLLC
 
Production planning and control module 3 (OM)
Production planning and control module 3 (OM)Production planning and control module 3 (OM)
Production planning and control module 3 (OM)
ChathamkulamInstitut
 
Target,kizen costing and abc..
Target,kizen costing and abc..Target,kizen costing and abc..
Target,kizen costing and abc..
Manpreet Mahal
 
Factory cost reduction strategies
Factory cost reduction strategiesFactory cost reduction strategies
Factory cost reduction strategies
BakeryBazar .com
 
Cost Control
Cost ControlCost Control
Cost Control
mudduckk
 
CU Operations Management module 5
CU Operations Management module 5CU Operations Management module 5
CU Operations Management module 5
ChathamkulamInstitut
 
Uniform costing
Uniform costingUniform costing
Uniform costing
Rajpal Saipogu
 
Cost management
Cost managementCost management
Cost management
shkadry
 
10 Cost Reduction
10 Cost Reduction10 Cost Reduction
10 Cost Reduction
Krishna Kant
 
Value analysis
Value analysisValue analysis
Value analysis
Khakindra Duwal
 
Cu mba operation managment module 4 calicut university
Cu mba operation managment module 4 calicut universityCu mba operation managment module 4 calicut university
Cu mba operation managment module 4 calicut university
ChathamkulamInstitut
 
Materials handling and quality assurance ( Operations Management )
Materials handling and quality assurance ( Operations Management )Materials handling and quality assurance ( Operations Management )
Materials handling and quality assurance ( Operations Management )
ChathamkulamInstitut
 
Costing techniques
Costing techniquesCosting techniques
Costing techniques
Kapp Edge Solutions Pvt Ltd
 
Operations management module 1 ( calicut university )
Operations management module 1 ( calicut university )Operations management module 1 ( calicut university )
Operations management module 1 ( calicut university )
ChathamkulamInstitut
 
Cost & Management Accounting Techniques
Cost & Management Accounting TechniquesCost & Management Accounting Techniques
Cost & Management Accounting Techniques
Stroke Keys
 
Product Life Cycle Costing
Product Life Cycle CostingProduct Life Cycle Costing
Product Life Cycle Costing
Tanvirul Islam
 

What's hot (20)

REDUCING INDIRECT COSTS IN MANUFACTURING INDUSTRIES
REDUCING INDIRECT COSTS IN MANUFACTURING INDUSTRIESREDUCING INDIRECT COSTS IN MANUFACTURING INDUSTRIES
REDUCING INDIRECT COSTS IN MANUFACTURING INDUSTRIES
 
Cost reduction & cost control
Cost reduction & cost controlCost reduction & cost control
Cost reduction & cost control
 
Cost control and cost reduction
Cost control and cost reductionCost control and cost reduction
Cost control and cost reduction
 
Cost Control & Cost Reduction ppt
Cost Control & Cost Reduction pptCost Control & Cost Reduction ppt
Cost Control & Cost Reduction ppt
 
Warwick Lean Agenda Aug Wk1 July 12 2010
Warwick Lean  Agenda Aug Wk1  July 12 2010Warwick Lean  Agenda Aug Wk1  July 12 2010
Warwick Lean Agenda Aug Wk1 July 12 2010
 
Production planning and control module 3 (OM)
Production planning and control module 3 (OM)Production planning and control module 3 (OM)
Production planning and control module 3 (OM)
 
Target,kizen costing and abc..
Target,kizen costing and abc..Target,kizen costing and abc..
Target,kizen costing and abc..
 
Factory cost reduction strategies
Factory cost reduction strategiesFactory cost reduction strategies
Factory cost reduction strategies
 
Cost Control
Cost ControlCost Control
Cost Control
 
CU Operations Management module 5
CU Operations Management module 5CU Operations Management module 5
CU Operations Management module 5
 
Uniform costing
Uniform costingUniform costing
Uniform costing
 
Cost management
Cost managementCost management
Cost management
 
10 Cost Reduction
10 Cost Reduction10 Cost Reduction
10 Cost Reduction
 
Value analysis
Value analysisValue analysis
Value analysis
 
Cu mba operation managment module 4 calicut university
Cu mba operation managment module 4 calicut universityCu mba operation managment module 4 calicut university
Cu mba operation managment module 4 calicut university
 
Materials handling and quality assurance ( Operations Management )
Materials handling and quality assurance ( Operations Management )Materials handling and quality assurance ( Operations Management )
Materials handling and quality assurance ( Operations Management )
 
Costing techniques
Costing techniquesCosting techniques
Costing techniques
 
Operations management module 1 ( calicut university )
Operations management module 1 ( calicut university )Operations management module 1 ( calicut university )
Operations management module 1 ( calicut university )
 
Cost & Management Accounting Techniques
Cost & Management Accounting TechniquesCost & Management Accounting Techniques
Cost & Management Accounting Techniques
 
Product Life Cycle Costing
Product Life Cycle CostingProduct Life Cycle Costing
Product Life Cycle Costing
 

Similar to Cost controll techniques rev .02 copy

cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
Newman Jonathan
 
042 integrating lean construction
042 integrating lean construction042 integrating lean construction
042 integrating lean construction
drdej19
 
042 iIntegrating Lean Construction
042 iIntegrating Lean Construction042 iIntegrating Lean Construction
042 iIntegrating Lean Construction
Dr Fereidoun Dejahang
 
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
ahsansaeed78
 
Cost and time overruns in indian construction industry
Cost and time overruns in indian construction industryCost and time overruns in indian construction industry
Cost and time overruns in indian construction industry
Angad Partap Singh Bali
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
IRJET Journal
 
Boosting Field Efficiency with advanced Construction Field Productivity Softw...
Boosting Field Efficiency with advanced Construction Field Productivity Softw...Boosting Field Efficiency with advanced Construction Field Productivity Softw...
Boosting Field Efficiency with advanced Construction Field Productivity Softw...
iFieldsmart Technologies
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
IRJET Journal
 
Resume_SBA_180515
Resume_SBA_180515Resume_SBA_180515
Resume_SBA_180515
SHYAM BABU AGARWAL
 
Resume sba 180515
Resume sba 180515Resume sba 180515
Resume sba 180515
SHYAM BABU AGARWAL
 
IRJET- Maintenance Management of Construction Equipment on Construction P...
IRJET-  	  Maintenance Management of Construction Equipment on Construction P...IRJET-  	  Maintenance Management of Construction Equipment on Construction P...
IRJET- Maintenance Management of Construction Equipment on Construction P...
IRJET Journal
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of Delay
IRJET Journal
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
pisal3
 
A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning
Olivia Wilson
 
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
IRJET Journal
 
Commissioning and Operations
Commissioning and OperationsCommissioning and Operations
Commissioning and Operations
Achal Gupta
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET Journal
 
1.7 project management
1.7 project management1.7 project management
1.7 project management
exemplar2401
 
1-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp011-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp01
Amy Roman
 
Construction management I lecture note (QUS 3166).pptx
Construction management I lecture note  (QUS 3166).pptxConstruction management I lecture note  (QUS 3166).pptx
Construction management I lecture note (QUS 3166).pptx
JacquesTwubahimana1
 

Similar to Cost controll techniques rev .02 copy (20)

cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
 
042 integrating lean construction
042 integrating lean construction042 integrating lean construction
042 integrating lean construction
 
042 iIntegrating Lean Construction
042 iIntegrating Lean Construction042 iIntegrating Lean Construction
042 iIntegrating Lean Construction
 
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
 
Cost and time overruns in indian construction industry
Cost and time overruns in indian construction industryCost and time overruns in indian construction industry
Cost and time overruns in indian construction industry
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
 
Boosting Field Efficiency with advanced Construction Field Productivity Softw...
Boosting Field Efficiency with advanced Construction Field Productivity Softw...Boosting Field Efficiency with advanced Construction Field Productivity Softw...
Boosting Field Efficiency with advanced Construction Field Productivity Softw...
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
Resume_SBA_180515
Resume_SBA_180515Resume_SBA_180515
Resume_SBA_180515
 
Resume sba 180515
Resume sba 180515Resume sba 180515
Resume sba 180515
 
IRJET- Maintenance Management of Construction Equipment on Construction P...
IRJET-  	  Maintenance Management of Construction Equipment on Construction P...IRJET-  	  Maintenance Management of Construction Equipment on Construction P...
IRJET- Maintenance Management of Construction Equipment on Construction P...
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of Delay
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning
 
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
 
Commissioning and Operations
Commissioning and OperationsCommissioning and Operations
Commissioning and Operations
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
1.7 project management
1.7 project management1.7 project management
1.7 project management
 
1-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp011-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp01
 
Construction management I lecture note (QUS 3166).pptx
Construction management I lecture note  (QUS 3166).pptxConstruction management I lecture note  (QUS 3166).pptx
Construction management I lecture note (QUS 3166).pptx
 

Recently uploaded

Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
TaghreedAltamimi
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
bijceesjournal
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
SakkaravarthiShanmug
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
riddhimaagrawal986
 
An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...
IJECEIAES
 
integral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdfintegral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdf
gaafergoudaay7aga
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 

Recently uploaded (20)

Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
 
An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...
 
integral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdfintegral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdf
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 

Cost controll techniques rev .02 copy

  • 1. REPORT FOR COST CONTROL TECHNIQUES JUNE 2014 By Madhava reddy / Doha Qatar
  • 2. Table of contents 1.0 Abstract 2.0 Introduction 3.0 Cost control in construction 4.0 Wastage of Materials 5.0 Control on Plant and Equipment's 6.0 Productivity of Labor 7.0 Time vs. cost relation ship 8.0 Cost control techniques to be used at site 9.0 Control of Materials 10 .0 Use of Equipment 11 .0 Recommendations 12 .0 Control of Materials Wastage 13.0 Control on Plant and Equipment 14.0 Control and improve labor productivity 15.0 Conclusion
  • 3. 1.0 Abstract Most of the civil projects over have suffered from the cost and time overruns due to factors stemming from poor cost control during the design and project implementation stages. As per Monitoring and studying the cost control techniques being not used by the individual Project Managers at all sites, the problems faced and proposed solutions. Identify seven commonly used cost control techniques which include schedules, budget, inspection, meetings, reports, records, monitoring & evaluations.
  • 4. 2.0 Introduction Project Managers are find difficulty in controlling project costs due to problems which include delays by clients to release money, delay to make a decision, lack of materials and equipment, bad weather, overlapping of activities, unclear and incomplete drawings, making good defective works, and generally failure to control the productivity of resources. Others of were due to interference by clients, high labor turnover, and insufficient knowledge on cost control techniques. And another is noticed unable to establish that the problem was actually not the techniques to use but rather the lack of knowledge of the techniques, the poor management of the cost control methodology, and the general poor commanding on site organization (engineers) the management is interested in obtaining fully functional facilities completed in time, cost, quality and scope. And they are able to construct within the estimated time and budget, to prove to the clients that the right standards and scope as an excellent contractor in Qatar . Cost control is a process where the construction cost of the project is managed through the best methods and techniques so that the Management does not suffer losses when carrying out the activities of the project. One of the aims of cost control is to construct at the cheapest possible costs consistent with the project objectives. Ultimately the decision of the Project manager that something should be done differently and the translation of that decision into practice are the actions to observes that it is of little use after a process has been completed to discover that its cost was actually too much. Most project managers are find difficulty in controlling costs on their construction sites due to a number of problems which include preparation, lapse in management and control, over budgeting, poor materials, labor shortages, increased cost of materials, delays in deliveries, wastage of materials, unexpected weather changes, loss of materials, insecurity and poor communication. This results into cost and time overruns, conflicts, and sometimes abandoning projects. therefore carried out to identify the cost control techniques used propose effective
  • 5. 3.0 Cost control In construction During the execution of a project, The project Mangers to follow the strictly procedures for project control and record keeping become indispensable tools to managers by involving the other participants (Engineers) in the construction process. According to cost control can be achieved by selecting the right man for the right job, the right equipment and tools for the right work and the right quality of materials, in the right quantity, from the right source, at the right price and delivered at the right time. Managers are expected to be well equipped to execute the project, with due consideration to the quality of work, yet within the estimated cost and time limits.
  • 6. 4.0 Wastage of Materials One of the big problems of Turn key Projects suffer large amount of materials wastage due to varying circumstances problem requires a supervisor to constantly be on the lookout for the losses. According to wastage of materials can take place during the procurement process. storage, and during utilization. Wastage during procurement can result from one or more of the following causes: buying materials of wrong specifications, buying more than the actual requirements to cater for unrealistic and unforeseen eventualities, untimely buying of short-life materials, improper and unnecessary handling of materials, and . Wastage during storage can occur due to the other reasons are take place during the procurement process. storage, and during utilization. Wastage during procurement, deterioration due to incorrect storage, incorrect maintenance and short-shelf life and losses due to exposure to extreme climatic conditions. Other causes are lack of pre-work preparation and coordination, improper accounting and poor storekeeping, negligent and careless attitude of the supervisor, high rate of deterioration due to long storage at the place of work, and over-issues from the central stores and failures to return unused surplus materials to the stores. some unavoidable wastages are inherent during utilization, but excessive wastage is of concern to the management as it affects the productivity adversely, with consequences of extra costs. Most problems relating to material wastage revolve around requisitioning and ordering, receipt and checking of deliveries from suppliers, offloading and handling, storing and protecting, and issuing, distributing and use of materials.
  • 7. 5.0 Control on Plant and equipment In construction, some tasks are labor intensive, some predominantly employ equipment, and some use a combination of both. While the actual work done and the associated labor is accounted by the supervisor concerned, the equipment and productivity control is undertaken to determine its employment time, the output achieved, and its productivity at site. The main purpose of the control is to minimize wastage in utilization so that the overall construction would probably reduce the cost of construction by about 30% which would likely In construction, some tasks are labor intensive, some predominantly employ equipment, and some use a combination of both. While the actual work done and the associated labor is accounted by the supervisor concerned, the equipment and productivity control is undertaken to determine its employment time, the output achieved, and its productivity at site The main purpose of the control is to minimize wastage in utilization so that the overall project cost is not affected observed that industrializing construction would probably reduce the cost of construction by about 30% which would likely
  • 8. 6.0 Productivity of labor Labor productivity achieved at the site for a given work provides a measure of the laborer's efficiency and effectiveness and the level of site organisation. It shows the total time for which the laborer was employed at work, the time he was productive on work and the time he remained unproductive. Craftsmen use about 40% of available time on productive activities, and about 33% of the time on non-value adding activities Productive times are wasted for various reasons such as idle waiting, unnecessary travelling, late starting, early quitting, Labor productivity achieved at the site for a given work provides a measure of the laborer's efficiency and effectiveness and the level of unscheduled breaks, and delays in the receipt of tolls, delays to receive materials and work instructions. productivity and other metrics were done by Alinaitwe, and the results indicated hat the working relationship 7.0 Time-cost Relationship The relationship between time and cost is a very important aspect in the control of costs on site as any variation in time has automatic implication on cost. It is important to report and record all the works involving materials, plant and labor on sites. This enables the contractor be able to know the costs and expenses of the resources used on site and compare with the initial cost budget. Various report techniques used include; daily or weekly and monthly recording, schedule control, site daily diary report and the project budget.
  • 9. 8.0 Materials The causes of material wastages on sites were found to include poor supervision of operatives, poor handling of materials, misuse of materials, poor storage and stacking of materials, delivery of excess material on site, poor site organization, late delivery of materials, poor coordination of management and technical side, poor time management, bad weather conditions, use of unskilled 9.0 Use of Equipment Equipment Use on Site obtained equipment on site by hiring. No contractor obtained equipment by purchasing as most of the activities were manually carried out. Mechanized construction of buildings is insignificant productivity can be improved by substituting labour with equipment.
  • 10. 10.0 RECOMMENDATIONS The Main problem of sites by not using the cost control techniques , to improve effective Management of the techniques and avoid laxity in supervision . It is therefore strongly recommended for all the sites should constantly attend refresher courses in construction project management as the study identified lack of knowledge of the cost control and Project Management, further more In almost all sites, workers were not aware of the performance targets implying there were lack of knowledge and communication lapses between supervisors and workers. Cost is a product of the use of project resources and the only better way of controlling the cost of projects is best handled right at the initial stage. During implementation, procedures of cost control of resources only helps in detecting variances and formulating corrective measures other than waiting until work has been completed . The other problems are noticed by the Management that led to delays and subsequent failure to construct within budget included: low resources productivity, lack of materials and equipment's ( late procuring), alterations by the clients to give instructions from clients and consultants to delay work as they waited to give site instructions . Other problems were due to delayed payments by clients, overlapping of activities, make good defective work, unclear details on the drawings, and delay by local authority to inspect the works. the greatest cause that faced of delay of payments projects due to late release of money by clients.
  • 11. 11.0 Cost Control Techniques Used in Building Sites 1.0 Work Programmes Contractors used schedules to monitor progress and financial performance. It is a good method since work progress can be measured and related to cost. 2.0 Inspection of Works Inspection of works and comparison made with the budget. Sometimes subject to judgment, hence lacking 3.0 The project Budgets Cost attached to responsibility centers with work targets to be accomplished. It’s used in relation to schedules makes it the best tool for cost control. 4.0 Site Meetings Meeting held to review the progress of work and compare to the monetary allocations. Good as it provides some motivation to workers and all stakeholders are up to date on the performance of work 5.0 Record Keeping Documentation of activities carried out to enable early detection of deviations from the set standard 6.0 Monitoring Work andCost Performance Clients, consultants and the contractors used monitoring tools of schedules, budgets, inspection and feedbacks to keep a watch on the cost performance. With use of the right tools of control, it produces good results 7.0 Evaluation of Works Carried Out Quantification of works and comparing with the costs in the bill of quantities. Inspection was also reportedly used to evaluate works. This helps to ascertain that the progress of work is on the right track. 8.0 Others Sites that did not have particular method to use.
  • 12. 12.0 Control of Materials wastage It is proposed that materials wastage should be reduced by ensuring that: Materials are delivered as required to cut site storage time, materials delivered are those specified, issuing just the right amount of material with only a reasonable allowance for wastage to workmen, ensuring that workmen are not producing excessive amount of off-cuts, ( specially tiles ) allocating and preparing storage areas so that when materials are stored, they do not deteriorate. Employing a reliable store keeper who is able to maintain well kept booking system, double signing of delivery notes, and spot checks for materials deliveries are all desirable to minimise wastage. And safe guard issuing of items by store men and keeping records of all the materials on site including employing full-time security guards. Sites should be hoarded with alarm systems installed around key materials around the site and including ensuring that the whole site is lit up at night. 13.0 Control on Plant and equipment The use of machines at building sites are insignificant yet the mechanization of construction can reduce the cost of buildings by 30%. Contractors are encouraged to adopt the use of machine as it has the advantages of speeding up work, saving labour, producing better quality works and are economical in a number of cases besides being able to do what cannot be done manually. Once brought to sites, machines should be maximally utilized as any redundant time can lead to high cost
  • 13. 14.0 Control and improve labor productivity To improve on the labour productivity on sites by recording laborer's work progress, daily work evaluation, recruitment of laborer's with the right skills for the job, substituting laborer's with equipment, and having schedules and proper control procedure and records in place. A good working environment should also be created with work motivation and proper communication system included. Regular inspections by the engineers /foramens at site and early detection of variances using standard productivity are highly recommended. Without a good quality plan, project control cannot be achieved. Project control requires efficient, effective and vigilant processes and actions to ensure its successful accomplishment.
  • 14. 15.0 CONCLUSION The aim of this study was to study the cost control techniques used by the Project Mangers on-going projects and propose measures that will enable projects to be completed as budgeted. The seven cost control techniques used by contractors on their sites were found to include use of: schedules, the project budget, inspection of works, cost reports, site meetings, monitoring of cost and work performance and quantity evaluation using the bills of quantities, and others did not have well defined techniques or did not even know there were traditional cost control procedures. It was noted that unable to establish concrete evidences that actually the stated techniques were effectively used as documents to prove the applications were found lacking or not there at all. The survey was able to firmly state that, “the problem of cost control is actually the lack of knowledge and inadequate with the poor management of construction resources at sites ”.

Editor's Notes

  1. March 2013