Ministry of Water Resources & Electricity
Dams ImplementatIon UnIt
GENERAL DIRECTORATE OF PROJECTS
DAM COMPLEX OF UPPER
ATBARA PROJECT
Brief Introduction to Contracts& Planning Works
ENG.Awad Hamdan
Contracts & Planning Department
1.Contract
1.1 Definition:
A voluntary, deliberate, and legally binding agreement
between two or more competent parties
Contracts & Planning Department
1.Cotracts
1.2 Contract’s Essentials
• Offer
• Acceptance
• Objective
• Obligations
• Consideration
• Competent Parties
Contracts & Planning Department
2. Project
2.1 Definition
Set of one or more activities that should be
performed within a period of time , budget
and quality.
Contracts & Planning Department
Contracts & Planning Department
Project planning is the process that defines the project
activities and end products that will be performed and
describes how the activities will be accomplished. The
purpose of project planning is to define each major
task, estimate the time and resources required, and
provide a framework for management review and
control.
2. Project
2.3 Project Planning
Contracts & Planning Department
project planning activities Scope:
• To define the specific work to be performed and
goals that define and bind the project.
• to define the Estimates to be documented for
planning, tracking, and controlling the project.
• to define Commitments that are planned,
documented, and agreed to by affected groups.
• Project alternatives, assumptions, and constraints.
2. Project
2. Project
The planning process includes steps to estimate the
size of the project, estimate the technical scope of
the effort, estimate the resources required to
complete the project, produce a schedule, identify
and assess risks, and negotiate commitments.
Contracts & Planning Department
2. Project
Repetition of the previous steps is necessary to
establish the project plan. Typically, several
iterations of the planning process are performed
before a plan is actually completed.
Contracts & Planning Department
3. Construction Projects
3.1 Construction Project Parties
• Client (Employer)
• Consultant (Engineer)
• Contractor
3.2 Contractual Relationship Between Parties
• Employer-Consultant Contract
• Employer-Contractor Contract
Contracts & Planning Department
4. Project’s Constraints
Contracts & Planning Department
• Measurement Contract
• Lump-sum Contract
• Direct Labour Contract
• Cost Plus Contract
•
•
•
•
Based on Price Determination
5. Types of Contracts
Contracts & Planning Department
100%
• Lump-sum Contract
• Measurement Contract
• Cost Plus Contract
• Direct Labour Contract
0% 100%
5. Types of Contracts
0%
Contractor’s RiskType of ContractEmployer’s Risk
Contracts & Planning Department
Contracts & Planning Department
Measurement for payment of drilling holes in any
material will be made per linear metre actually drilled
and when specified per hole drilled for setting up the
drilling machine, shifting it from one borehole to
another, within the site limits, including erection,
dismantling and linking with energy and water sources.
No measurement is made for re-drilling when grouting is
carried-out by progress procedure.
6. MEASUREMENT AND PAYMENT Of Drilling Works
Contracts & Planning Department
All boreholes stopped due to fault of the Contractor
before reaching the depth required by the Engineer will
not be considered for payment.
6. MEASUREMENT AND PAYMENT Of Drilling Works
Contracts & Planning Department
Measurement for payment of water tests will be the
number of water tests satisfactorily carried-out in 5 m
sections or smaller than 5 m at the Engineer's request.
Measurement for drainage hole will be made on the
same basis as drilling.
Measurement of grouting work will be made per hole
drilled; when specified for handling and setting up the
grouting equipment and the removal of the same per
section grouted, and per kilo of dry material actually
injected.
6. MEASUREMENT AND PAYMENT Of Drilling Works
1. Drawings
2. Specification
3. Bills of Quantities
4. Conditions of Contract
5. Instructions to Tenderers
6. Soil Investigation Report
1.
2.
3.
4.
5.
6.
7. Contract’s Document
4.1
Contracts & Planning Department
4.2
7.
8.
9.
10.
7. Agreement
8. Letter of Acceptance
9. Memorandum of Understanding
10.Contractor’s Schedules
Contracts & Planning Department
7. Contract’s Document
‫ةةةةة‬ ‫ةةةةةةة‬ ‫ةةةة‬ ‫ةةة‬ ‫ةةةةة‬
‫ةةةةةةةة‬
‫ة‬‫ة‬‫ةةة‬
Contracts & Planning Department
Wishing you A Fruitful Training
Period at DCUAP
‫ةةةةةة‬ ‫ةةةة‬ ‫ة‬

More Related Content

What's hot

contract procedure
contract procedurecontract procedure
contract procedure
hasyimah ismail
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
Hossein Khodaverdi M.Eng
 
Project Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementProject Management Diagnostics for Time Management
Project Management Diagnostics for Time Management
April Davies, MA, CAPM
 
Rev207 matrixexcelfile
Rev207 matrixexcelfileRev207 matrixexcelfile
Rev207 matrixexcelfile
jbonvier
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sum
Est
 
Project closure
Project closureProject closure
Project closure
Gyaneshwar Suman
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
Harish Mahavar
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
Shivam Sood
 
Sunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract ClosureSunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract Closure
sunnycmui
 
Project End Report - Project Management template
Project End Report - Project Management template Project End Report - Project Management template
Project End Report - Project Management template
Simon Misiewicz
 
Civil Supervisor
Civil SupervisorCivil Supervisor
Civil Supervisor
Shady Eid
 
Risk assessment plan example
Risk assessment plan exampleRisk assessment plan example
Risk assessment plan example
Јелена Добановачки
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
Farhan Moosa
 
Bo Q Preamble Td2 3 Jan 20
Bo Q Preamble Td2 3  Jan 20Bo Q Preamble Td2 3  Jan 20
Bo Q Preamble Td2 3 Jan 20
guest5980d0
 
Coordinated project information (cpi)
Coordinated project information (cpi)Coordinated project information (cpi)
Coordinated project information (cpi)
Abdullahi MohammedLawal
 
Estimating seminar 1 slides
Estimating seminar 1 slidesEstimating seminar 1 slides
Estimating seminar 1 slides
Doreen Yeo
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
Dr K M SONI
 
project planning of water management
 project planning of water management project planning of water management
project planning of water management
Mir Mosharraf Hosain
 
Sample architectural drafting contract
Sample architectural drafting contractSample architectural drafting contract
Sample architectural drafting contract
Maysam Ghaffari
 
1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank 1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank
Thomas Magatu
 

What's hot (20)

contract procedure
contract procedurecontract procedure
contract procedure
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
Project Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementProject Management Diagnostics for Time Management
Project Management Diagnostics for Time Management
 
Rev207 matrixexcelfile
Rev207 matrixexcelfileRev207 matrixexcelfile
Rev207 matrixexcelfile
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sum
 
Project closure
Project closureProject closure
Project closure
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
 
Sunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract ClosureSunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract Closure
 
Project End Report - Project Management template
Project End Report - Project Management template Project End Report - Project Management template
Project End Report - Project Management template
 
Civil Supervisor
Civil SupervisorCivil Supervisor
Civil Supervisor
 
Risk assessment plan example
Risk assessment plan exampleRisk assessment plan example
Risk assessment plan example
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Bo Q Preamble Td2 3 Jan 20
Bo Q Preamble Td2 3  Jan 20Bo Q Preamble Td2 3  Jan 20
Bo Q Preamble Td2 3 Jan 20
 
Coordinated project information (cpi)
Coordinated project information (cpi)Coordinated project information (cpi)
Coordinated project information (cpi)
 
Estimating seminar 1 slides
Estimating seminar 1 slidesEstimating seminar 1 slides
Estimating seminar 1 slides
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
project planning of water management
 project planning of water management project planning of water management
project planning of water management
 
Sample architectural drafting contract
Sample architectural drafting contractSample architectural drafting contract
Sample architectural drafting contract
 
1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank 1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank
 

Similar to Contract adminstration and planning

Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Process of pre construction phase drawbacks
Process of pre construction phase drawbacksProcess of pre construction phase drawbacks
Process of pre construction phase drawbacks
glibson rojer
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
Dr K M SONI
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
ByishimoBTCChef
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
EdenBekele5
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
Keshav Seewraz
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
brainquisitive
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
Arissa Loh
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
R.R.G.S Bandara
 
Running head PMPM .docx
Running head PMPM                                          .docxRunning head PMPM                                          .docx
Running head PMPM .docx
charisellington63520
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
ahmong4
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
NithyaPotterhead
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
Forbes Chanakira
 
Contract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdfContract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdf
YeshiharegAlemu
 
Project management
Project managementProject management
Project management
Benjamin Tan
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
SHAZEBALIKHAN1
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
IRJET Journal
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case study
Freelancelanders
 

Similar to Contract adminstration and planning (20)

Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
Process of pre construction phase drawbacks
Process of pre construction phase drawbacksProcess of pre construction phase drawbacks
Process of pre construction phase drawbacks
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Running head PMPM .docx
Running head PMPM                                          .docxRunning head PMPM                                          .docx
Running head PMPM .docx
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
 
Contract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdfContract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdf
 
Project management
Project managementProject management
Project management
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case study
 

Recently uploaded

TIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptxTIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptx
CVCSOfficial
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
upoux
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Gas agency management system project report.pdf
Gas agency management system project report.pdfGas agency management system project report.pdf
Gas agency management system project report.pdf
Kamal Acharya
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
RamonNovais6
 
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
PIMR BHOPAL
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
morris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdfmorris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdf
ycwu0509
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
aryanpankaj78
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
PriyankaKilaniya
 

Recently uploaded (20)

TIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptxTIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptx
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Gas agency management system project report.pdf
Gas agency management system project report.pdfGas agency management system project report.pdf
Gas agency management system project report.pdf
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
 
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
morris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdfmorris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdf
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
 

Contract adminstration and planning

  • 1. Ministry of Water Resources & Electricity Dams ImplementatIon UnIt GENERAL DIRECTORATE OF PROJECTS DAM COMPLEX OF UPPER ATBARA PROJECT Brief Introduction to Contracts& Planning Works ENG.Awad Hamdan Contracts & Planning Department
  • 2. 1.Contract 1.1 Definition: A voluntary, deliberate, and legally binding agreement between two or more competent parties Contracts & Planning Department
  • 3. 1.Cotracts 1.2 Contract’s Essentials • Offer • Acceptance • Objective • Obligations • Consideration • Competent Parties Contracts & Planning Department
  • 4. 2. Project 2.1 Definition Set of one or more activities that should be performed within a period of time , budget and quality. Contracts & Planning Department
  • 5. Contracts & Planning Department Project planning is the process that defines the project activities and end products that will be performed and describes how the activities will be accomplished. The purpose of project planning is to define each major task, estimate the time and resources required, and provide a framework for management review and control. 2. Project 2.3 Project Planning
  • 6. Contracts & Planning Department project planning activities Scope: • To define the specific work to be performed and goals that define and bind the project. • to define the Estimates to be documented for planning, tracking, and controlling the project. • to define Commitments that are planned, documented, and agreed to by affected groups. • Project alternatives, assumptions, and constraints. 2. Project
  • 7. 2. Project The planning process includes steps to estimate the size of the project, estimate the technical scope of the effort, estimate the resources required to complete the project, produce a schedule, identify and assess risks, and negotiate commitments. Contracts & Planning Department
  • 8. 2. Project Repetition of the previous steps is necessary to establish the project plan. Typically, several iterations of the planning process are performed before a plan is actually completed. Contracts & Planning Department
  • 9. 3. Construction Projects 3.1 Construction Project Parties • Client (Employer) • Consultant (Engineer) • Contractor 3.2 Contractual Relationship Between Parties • Employer-Consultant Contract • Employer-Contractor Contract Contracts & Planning Department
  • 10. 4. Project’s Constraints Contracts & Planning Department
  • 11. • Measurement Contract • Lump-sum Contract • Direct Labour Contract • Cost Plus Contract • • • • Based on Price Determination 5. Types of Contracts Contracts & Planning Department
  • 12. 100% • Lump-sum Contract • Measurement Contract • Cost Plus Contract • Direct Labour Contract 0% 100% 5. Types of Contracts 0% Contractor’s RiskType of ContractEmployer’s Risk Contracts & Planning Department
  • 13. Contracts & Planning Department Measurement for payment of drilling holes in any material will be made per linear metre actually drilled and when specified per hole drilled for setting up the drilling machine, shifting it from one borehole to another, within the site limits, including erection, dismantling and linking with energy and water sources. No measurement is made for re-drilling when grouting is carried-out by progress procedure. 6. MEASUREMENT AND PAYMENT Of Drilling Works
  • 14. Contracts & Planning Department All boreholes stopped due to fault of the Contractor before reaching the depth required by the Engineer will not be considered for payment. 6. MEASUREMENT AND PAYMENT Of Drilling Works
  • 15. Contracts & Planning Department Measurement for payment of water tests will be the number of water tests satisfactorily carried-out in 5 m sections or smaller than 5 m at the Engineer's request. Measurement for drainage hole will be made on the same basis as drilling. Measurement of grouting work will be made per hole drilled; when specified for handling and setting up the grouting equipment and the removal of the same per section grouted, and per kilo of dry material actually injected. 6. MEASUREMENT AND PAYMENT Of Drilling Works
  • 16. 1. Drawings 2. Specification 3. Bills of Quantities 4. Conditions of Contract 5. Instructions to Tenderers 6. Soil Investigation Report 1. 2. 3. 4. 5. 6. 7. Contract’s Document 4.1 Contracts & Planning Department
  • 17. 4.2 7. 8. 9. 10. 7. Agreement 8. Letter of Acceptance 9. Memorandum of Understanding 10.Contractor’s Schedules Contracts & Planning Department 7. Contract’s Document
  • 18. ‫ةةةةة‬ ‫ةةةةةةة‬ ‫ةةةة‬ ‫ةةة‬ ‫ةةةةة‬ ‫ةةةةةةةة‬ ‫ة‬‫ة‬‫ةةة‬ Contracts & Planning Department Wishing you A Fruitful Training Period at DCUAP ‫ةةةةةة‬ ‫ةةةة‬ ‫ة‬