6. CMDA expansion areas - Kancheepuram
STEPS FOR CMDA TO START FUNCTION IN ADDED AREAS 6
7. Planning area Status of master plan
Present Area
under Master
Plan in sq.km
Additional
proposed area in
sq.km
1
Mamallapuram
Composite LPA
MP consent on 20.06.2013 277.6 -
2
Gummidipoondi
Composite LPA
MP consent on 19.05.2000 84.0 116.6
3
Kancheepuram
Composite LPA
MP consent on 14.07.2006 144.66 170.69
4
Mamallapuram
NTDA
MP consent 29.11.2011 12.57 -
5
Chengalpattu
Single LPA
MP consent on 13.07.2006 6.1 721.4
6
Tiruvallur Single
LPA
MP consent on 31.12.2013 12.3 659.9
7
Tiruttani Single
LPA
MP consent on 25.07.2007 12.42 53.9
8
Arakkonam
Single LPA
MP consent on 29.12.2000 9.1 98.3
Master Plan status in CMDA expansion area
STEPS FOR CMDA TO START FUNCTION IN ADDED AREAS 7
8. Contd…
● Existing Master plans apply for core areas alone, Masterplans for
expanded CLPA areas are under progress
● Further, areas within expansion but not having consented master
plan, then in such areas PP cannot be issued by CMDA until Master
Plan is prepared and got consent of the Govt.
● Hence, there must be an arrangement for issuing PP in such non-
plan areas shall be planned prior to CMDA start functioning in the
expansion area.
STEPS FOR CMDA TO START FUNCTION IN ADDED AREAS 8
9. Contd..
● CMDA to be ready with work allocation for the staffs of new zonal
offices.
● CMDA to set up the new office premises for zonal offices.
● Handing over of D.Dis. and R.Dis. files may happen after 10 to 20
days from the actual date of start functioning of CMDA office.
● K.Dis. and L.Dis. files may be disposed by the present district DTCP
office or to be handed over to CMDA new office depending on the
time limit available for each of such files.
● Transfer of Assets and Liabilities of the 8 Planning Authorities to
happen.
STEPS FOR CMDA TO START FUNCTION IN ADDED AREAS 9
10. Among the assessed 90 posts, CMDA has
i. proposed to fill up 57 posts through redeployment from DTCP
which will be through change in nomenclature of the 57 posts of
DTCP.
ii. proposed to surrender 13 posts of DTCP.
iii. proposed to call for willingness from existing staff of DTCP for
absorption in CMDA and to depute officials /staff of DTCP to
CMDA.
In this regard, the following remarks are submitted.
SCANTY CADRE STRENGTH OF DTCP
CMDA expansion required staff strength
10
11. ● In1974, DTCP functioned with the 622 cadre strength of posts in 8
offices
● During 1993, the cadre strength was increased from 622 to 801 posts
in 31 offices
● When the districts got bifurcated during previous years, new regional
offices like Tiruvallur regional office, Perambalur regional office etc.,
were created by re-distribution again
SCANTY CADRE STRENGTH OF DTCP
Scanty cadre strength of DTCP
11
12. SL.
No
Period FORMATION OF OFFICES
No. of
Office
No. of
Posts
Remarks
1974-
1993
i. From 1970, onwards
existing
Regional Office =8.
8 622
1
1993-
2000
i. From 1993, onwards Local
ii. Planning Authorities -18.
From 1993, New Town
Development Authority - 5
31 801
2
2001-
2006
-- 31 801 -
3 2007
i. Formation of New Regional
Offices -3
Thanjavur Region,
Dharmapuri Region,
Perambalur Region.
34
(31+3)
801
Without creation of new posts
and redeployment of existing
cadre strength
4 2013
i. Formation of New Regional
Office -1
Tiruvallur Region
ii. Formation of Karur LPA -1
35
(34+1)
801
Without creation of new posts
and redeployment of existing
cadre strength
SCANTY CADRE STRENGTH OF DTCP
DTCP’s staff strength re-distribution
12
13. SL.
No
Period FORMATION OF OFFICES
No. of
Office
No. of
Posts
Remarks
5 2018
i. Formation of New
Regional Office -1
Tiruppur Region
35 801
Without creation of new posts
and redeployment of existing
cadre strength
6 2019
i. Head Office
ii. Regional Office-13
iii. LPA office-18
iv. NTDA office-5
v. Law officer post
creation
35
801 -
6 +1
=79
6
Creation of one law officer in
lieu of 5 blue printer posts and
one micro film technician post
7 2020
Restructure of existing
Regional / NTDA's/LPA's
and created 37 New District
Offices & Head office,
Chennai
38 796
Without creation of new posts
and redeployment of existing
cadre strength
SCANTY CADRE STRENGTH OF DTCP
DTCP’s staff strength re-distribution
13
14. Contd….
● When regional offices were restructured during 2019, to be one office
at each district again re-distribution was made.
● No additional posts were sanctioned to this department for the past
30 years.
● Now department has expanded into 37 District offices with the
existing staff strength.
SCANTY CADRE STRENGTH OF DTCP 14
15. Total District
Size in Sq.Km
Existing
CMDA Area
in sq.km
Proposed
CMDA Area
in Sq.Km
Remaining
Area vested
with DTCP in
Sq.km
Kancheepuram 1704.79 112.00 1063.00 529.79
Ranipet 2234.32 263.55 1970.77
Chengalpet 2592.64 147.42 1319.79 1272.85
Tiruvallur 3427.00 637.00 2448.42 341.58
Total 9958.75 896.42 5094.76 4114.99
In areas other than CMDA expansion area in each district
DTCP needs to continue to function with Skeleton strength.
SCANTY CADRE STRENGTH OF DTCP
Requirement of DTCP offices addition to CMDA
expansion
15
16. Area Jurisdiction details for newly created UDA’s
Sl.No.
Name of the
District
Total District
area in Sq.km
Geographical area in sq.km for
merger
Remaining
District area
in Sq.Km
Present LPA/
NTDA area
Proposed UDA
area
1 Coimbatore 4732 1531.57 1531.57 3200.43
2 Madurai 3710 1254.93 1254.93 2455.07
3 Tiruppur 5187 1031.67 1031.67 4155.33
4 Krishnagiri 5129 734.07 1071.79 4057.21
SCANTY CADRE STRENGTH OF DTCP 16
17. UDA Formation
● As per the announcements, 4 UDA’s are formed
i. Coimbatore
ii. Madurai
iii. Tiruppur
iv. Hosur
● Sizeable cadre strength to be spared for the UDAs. (Tentatively 70
post based on Govt approval of UDA staff pattern)
● Simultaneously regional offices for the rest of the district for the area
other than the UDA need to continue to function as separate offices
with Skeleton strength.
● Above could only be achieved by re-distribution of DTCP staff to be
gained from CMDA expansion areas
SCANTY CADRE STRENGTH OF DTCP 17
18. Staff Strength - Technical
S.No Name of Post Sanction
ed post
Filled vacant
1 Additional Director 1 0 1
2 Joint Director 7 4 3
3 Deputy Director 14 10 4
4 Assistant Director 48 45 3
5 SRA/RA 8 3 5
6 Architectural
Assistant/Planning
Assistant
27 24 3
7 Supervisor/D-II 82 76 6
8 others 346 196 150
TOTAL 534 359 175
• 175 staff positions are vacant (around 33%)
• DTCP is functioning through re-distribution of the above staff positions
18
19. Staff Strength-Ministerial
S.No Name of Post Sanction
ed post
Filled vacant
1 Law Officer 1 0 1
2 Junior Assistant 26 19 7
3 Steno typist 24 22 2
4 Typist` 34 33 1
5 Others 176 121 64
TOTAL 261 186 75
• 75 staff positions are vacant (around 29%)
• DTCP is functioning through re-distribution of the above staff positions
19
20. Retirement -2023 to 2027 in DTCP
S.No Year Retirement during
2023-2027
1 2023 25
2 2024 25
3 2025 32
4 2026 30
5 2027 21
Total 133
• During Jan 2023 -Dec 2024, 50 staffs are retiring.
• From 2023 -2027,133 staffs are retiring out 796 (17%)
• So there will be a huge vacuum in coming years to be effectively handled
SCANTY CADRE STRENGTH OF DTCP 20
21. Functioning of DTCP
With the present cadre strength, this department has to prepare
i. Regional plans,
ii. Master plans and
iii. Detailed development plans
iv. Preparation of heritage plans
v. Traffic plans
vi. Development plans for least urbanised taluks
vii. Hill Area Conservation,
viii. Coastal management,
ix. Guidance bureau,
x. MSME and
xi. To process the approval of layout, buildings and reclassification
works
The posts which are sanctioned is currently insufficient for efficient
functioning of this department.
SCANTY CADRE STRENGTH OF DTCP 21
22. • This department is now managing the works in the district offices with
the existing staff strength.
• Department has to initially support the need of urban development
authorities by sharing the staff on deputation.
• This could only be achieved by redistributing the staff in the present
offices at Chengalpattu, Kanchipuram, Tiruvallur and Ranipet
• Due to paucity of staff as pointed above, deputation/ redeployment/
surrender of staff to CMDA for the expansion area may not be
feasible.
Total sanctioned Technical staff 534
Vacancy 175 (33%)
SCANTY CADRE STRENGTH OF DTCP
Factual position of DTCP
22