The document provides a progress update on various components of a water infrastructure project, including the transmission main, booster pump station and well field, groundwater treatment, and new groundwater wells. For the transmission main, digging, laying, and burying of pipes is 80% complete. At the booster pump station and well field, foundations are underway and well cleaning is in progress, with potential delays due to longer than expected cleaning times. Design of the groundwater treatment plant is anticipated to be complete at the end of April. Engineering for new wells is also underway.