  1. 1. City CouncilJanuary 3, 2012
  2. 2. Hickory Water Supply Update January 3, 2012
  3. 3. Project Contracts• Well Field Piping• Transmission Main• Pump Station and Well Field Development• Treatment Plant
  4. 4. Well Field Pipelines• 50,700 feet of 20”, 16”, 12” and 8” pipe.• Notice to Proceed: October 4, 2011• Completion Date: November 1, 2012• Work Progress • Right of Way Clearing: Complete • Fence Relocations: Complete • Pipe & material delivery: Jan 4, 2012 • Trenching & pipe installation: Jan 2012
  5. 5. Transmission Main• 62 miles of 30” pipe• Contract Awarded: October 4, 2011• Notice to Proceed: January 2012• Completion: June 2013• Work Schedule • R.O.W. preparation begins: Jan. 2012 • Pipe deliveries begin: Jan. 2012 • Pipe installation begins: Feb. 2012
  6. 6. Pump Station & Well Field Development• 6 million gallon per day booster pump station• Nine (9) 150 to 200 Hp well pumps• Project Design: 90% Complete• Advertise for Bids: March 2012• Award By Council: May 2012• Notice to Proceed: June 2012• Completion: June 2013
  7. 7. Treatment Plant• Purpose: Remove Radium 226-228 to EPA standard of 5 pCi/L• Pilot testing of treatment methods: • Ion Exchange: Completed 2011 • Reverse Osmosis
  8. 8. R.O. Pilot Plant• Test performance of 3 different R.O. membranes• Pilot test period: 90 days• Startup: January 2012• Report to TCEQ on results: May 2012• Treatment Plant Construction: • Begin Construction: 2013 • Completion: June 2014