SlideShare a Scribd company logo
8 Technical Report Structural Engineering International 1/2013
Chhatrapati Shivaji International Airport—Integrated
Terminal Building
Charles Besjak, SE, PE, Director; Preetam Biswas, PE, Associate Director; Alexandra Thewis, PE; Raymond Sweeney;
Damayanti Chaudhuri, PE; Skidmore, Owings & Merrill LLP, New York, NY 10005, USA. Contact: preetam.biswas@som.com
DOI: 10.2749/101686613X13363929988296
an overall truss depth of only 4 m. In
response to site constraints and prox-
imity of the existing operational ter-
minal building, the mega-columns are
also designed to serve as hoist mecha-
nisms such that the entire roof can be
constructed without tower cranes. The
Terminal Building also includes the
largest and longest cable wall system
in the world. The structural studies
completed include solid finite element
analysis of connections to optimize
material efficiency. Furthermore, the
structural design prioritizes modular
construction for economy and facili-
tation of an accelerated construction
schedule.
Keywords: airport terminal; long-span
roof; unidirectional cable wall; struc-
tural efficiency; phased construction.
Introduction
Mumbai International Airport Limited,
owner-operator of Chhatrapati Shivaji
International Airport at Mumbai, is cur-
rently building a new Integrated Termi-
nal Building that combines international
and domestic operations at one of the
busiest airports in India in order to
achieve 24-h utilization.This 410 000 m2
terminal building is being constructed
at the location of the existing terminal
with minimal disruption to its opera-
tions. An international consultant with
vast experience in designing airport
terminals around the globe was chosen
as the principal architect and engineer
for the new building. One of the largest
construction firms in India was chosen
as the local designer and general con-
tractor for the project. The Terminal
Building is being constructed in phases
where Phase 1 includes construction of
the western pier, and Phase 2 includes
construction of the Headhouse zone.
Upon completion of Phases 1 and 2,
the building will become operational
and Phase 3 will commence, which
consists of the demolition of the exist-
ing terminal building and the construc-
tion of the eastern pier. Following the
completion of Phase 3 in 2014, the new
terminal, shown in Fig. 1, will serve
approximately 40 million passengers
annually.
Abstract
The new Integrated Terminal Building
at Mumbai’s Chhatrapati Shivaji
International Airport combines inter-
national and domestic operations at
one of the busiest airports in India.
The 410 000 m2
building, being con-
structed at the site of the existing
terminal, will achieve a capacity of
40 million passengers per annum upon
completion in 2014.
The primary design feature of the
building is a long-span roof covering a
total of 70 000 m2
over various func-
tional requirements, making it one of
the largest roofs in the world without
an expansion joint. The Headhouse
Roof, supported by only 30 columns
spaced at 64 m in the North–South
direction and at 34 m in the East–West
direction, produces a large column-
free space ideal for an airport. By
increasing the depth of the trusses near
the columns and running trusses in
both an orthogonal grid and a 45° grid,
large spacing and cantilevers of 40 m
along the perimeter are achieved with
In anticipation of the forthcoming IABSE Symposium in
Kolkata in September 2013, this special issue of Structural
Engineering International presents a series of projects in or
related to India. As varied as the country itself, the follow-
ing eight technical papers present structures ranging from an
underground cavern to a research station in Antarctica.
In the first paper—and highlighted on the front cover—the
new terminal building of the Mumbai airport is described,
including the elaborate roof and wall system.This is followed
by two projects in and around New Delhi: a new signature
cable-stayed bridge with its backwardly inclined pylon and
the addition of a cable roof system for the retrofit of a sta-
dium. A brief history of landmark bridges constructed over
major rivers in India and the challenges faced in their con-
struction is then elaborated. Next, the construction of one
of the world’s deepest caverns for the storage of liquefied
petroleum gas in Visakhapatnam is detailed, followed by a
description of the new Indian research station on the world’s
southern-most continent, Antarctica. Back on the Indian
subcontinent and aboveground, the last two papers present
a light-weight, double layered cable-net roof system for the
retrofit of a swimming facility, as well as a 10 km-long infra-
structure project in the technology hub of Bangalore.
The Indian Group of IABSE is looking forward to welcom-
ing delegates to the 36th IABSE Symposium, in Kolkata from
24 to 27 September 2013 entitled “Long Span Bridges and
Roofs—Development, Design and Implementation”. More
information on this symposium, as well as other upcoming
IABSE events can be found on the IABSE website under
www.iabse.org/Events.
B. C. Roy, Vice-President of IABSE, Chair of Scientific Committee
of 2013 IABSE Symposium in Kolkata
Ann Schumacher, Editorial Board, Structural Engineering
International
Introduction: Recent Structures in India
Structural Engineering International 1/2013 Technical Report 9
Owing to the scale and project occu-
pancy, the client directive was to meet
the requirements of the Indian codes
as well as satisfy requirements of the
International and American codes.
This was achieved by evaluation of the
most stringent conditions at all stages
of design and analysis. Early in the
design process, an evaluation of local
construction techniques, available
construction materials and availabil-
ity of skilled labor played an impor-
tant role in the choice of the building
materials. Concrete was selected as
the primary building material for the
base building, while steel was used for
the structural framing of the roof in
order to achieve a lightweight system
with large column-free spaces. The
construction site of the new terminal
building is located within close prox-
imity of the existing terminal that had
to remain operational during construc-
tion, which resulted in an elongated
X-shaped plan utilizing repetitive,
modular designs that accommodate
construction phasing and permit rapid
construction.
Long-Span Structural Steel
Headhouse Roof
The primary design feature of the
Terminal Building is a long-span roof
covering the departures roadway,
check-in hall, security, and passport
control functions. The architectural
cladding of the roof and ceiling fea-
tures a molded surface and sky-
lights over the column locations and
throughout the terminal ceiling, allow-
ing natural light to flood into the main
hall. The Headhouse Roof, covering
70 000 m2
and spanning over seven
individual concrete base structures, is
supported by only 30 composite mega-
columns. Beyond typical gravity and
seismic loads on the roof, special load-
ing considerations were taken for the
cable wall which applies a significant
wind load to the roof structure and
whose cables are pre-stressed against
the roof trusses at the northern end
of the terminal. The wind loading also
presented challenges as a significant
portion of the Headhouse Roof is
open to the outdoors and behaves as
a canopy.
In order to create one of the largest
roofs in the world without an expan-
sion joint, the roof mega-columns and
steel roof structure were kept com-
pletely independent from the base
concrete structures below. Large
openings in the concrete base struc-
ture allow the mega-columns to pass
through as well as create architec-
tural design features. This allows the
Headhouse Roof structure to move
independently in response to loads,
particularly expansion and contraction
caused by temperature variation. This
thermal gradient is applied to the steel
in the structural analysis model and
accounted for in the design of the roof
members.
In response to the functional require-
ment of the space below the roof, the
entire Headhouse Roof is supported
on just 30 composite mega-columns.
Following requests from the client,
the design team sought to minimize
the number of columns in the depar-
ture halls. However, the final design
surpassed this constraint and resulted
in a departure hall entirely free of
columns through the use of com-
posite mega-columns spaced 64 m
in one direction and 34 m in the per-
pendicular direction. The structural
system for the Headhouse Roof is
akin to a two-way flat slab system.
Increasing the depth of the trusses near
the columns and running trusses in an
orthogonal grid as well as along a 45°
grid results in an overall truss depth of
4 m for the roof system. The greater
truss depths near the columns create
“column pod” areas which seamlessly
integrate into the pyramidal skylights
that serve as major architectural fea-
tures. All of these aspects of the
Headhouse Roof can be seen in the
structural model in Fig. 2 as well as in
the construction photographs of Fig. 4.
The lateral system for the Headhouse
Roof comprises steel moment-resisting
frames consisting of composite mega-
columns and long-span steel roof
trusses. Frame action is achieved
between the primary roof trusses and
the composite mega-columns in the
North–South direction and between
the secondary roof trusses and the
composite mega-columns in the East–
West direction. Additional trusses
running at 45° to the orthogonal grid
provide additional stability and dia-
phragm stiffness. The weaving of the
orthogonal and diagonal trusses, in
addition to ensuring diaphragm action
of the roof, was also extremely useful
Fig. 1: Architectural renderings (clockwise from top left) plan view of integrated terminal
building; approach roadway at departure level; check-in concourse; aerial view of
integrated terminal building
Future
development
Arrivals
forecourt
Headhouse:
departure, arrivals,
immigration
and baggage claim
Concourse, retail and
baggage handling
Pier gates
10 Technical Report Structural Engineering International 1/2013
in reducing the system depth for the
entirely cantilevered perimeter zone of
the Headhouse Roof. This resulted in
up to 40 m cantilevers at certain loca-
tions with a truss depth of only 4 m.
The orientation of the steel wide-
flange members of the trusses along
the orthogonal grid were rotated 90°
such that flanges were aligned verti-
cally, while the steel members of the
trusses along the diagonal grid were
aligned with the flanges horizontally
for simplification of connections with
multiple trusses. Nonlinear, solid finite
element analysis was carried out for
the design of major connections for
optimum use of materials. The meshed
three-dimensional geometry of the
connections (Fig. 3a) was loaded at
the connection work point with forces
directly obtained from the overall
Headhouse Roof analysis model. Rigid
link elements from the work point
transfer the load to the connection
end faces (where the steel members
are attached to columns, beams, etc.),
and von Mises stress gradients were
obtained and studied to verify that no
part of the connection exceeded the
steel yield stress (Fig. 3b).
The behavior of the 40 m tall canti-
levered composite mega-columns was
studied using nonlinear buckling anal-
yses for each individual mega-column.
The composite mega-columns consist
of a built-up steel cruciform shape
encased in 2,7 m diameter of concrete
for the majority of its height. Once
the column reaches the height of the
column pod bottom chord connection,
it transforms into a bare steel cruci-
form shape and tapers to the column
pod top chord connection (Fig. 4).
The P–M (axial-moment) interaction
curve and stability analysis was per-
formed for each segment of the col-
umn as well as for the overall stability
of the complete mega-column system.
These analyses were deemed neces-
sary, because the code-prescribed
design methods do not accurately
correspond to the behavior of these
columns.
Unidirectional Cable Wall
System
Another unique feature of this pro-
ject is the cable wall exterior clad-
ding system. The Terminal Building
features two separate cable wall sys-
tems totaling over 1 km in length
and 11 000 m2
in area, making it the
longest and largest cable wall in the
world. It includes a number of unique
features that create various challenges
in the design and detailing of the
structure. Both cable walls comprise
unidirectional cables spanning verti-
cally between two levels of the termi-
nal structure. At the Departure Level,
the use of unidirectional cables was
necessitated by the fact that the cable
roof completely envelops the terminal
Headhouse, eliminating the possibil-
ity of any horizontal anchorage points.
In addition, as the cable wall circles
the Headhouse, it crosses four inde-
pendent base structures and reduces
in height from 15 to 6 m. Expansion
joints were installed in locations where
the cable wall crossed separate struc-
tures to allow individual segments of
the wall to move independently. On
the east and west sides, the cable wall
spans to the cantilevered edge of the
Headhouse Roof, up to 40 m from
the nearest mega-column. The large
cantilevers result in significant deflec-
tion at the roof edge, which proved
to be a challenging situation. With
34 m
Span
64 m
Span
40 m Cantilever
40 m Cantilever
9 m Truss depth
4 m Truss depth
(a)
(b)
64 m Truss span
Roadway
Waffle slab
Fig. 2: (a) Three-dimensional structural model of Headhouse Roof framing; (b) section
through Headhouse Roof
Fig. 3: Three-dimensional solid finite element analysis model of column pod top node
connection: (a) three-dimensional finite element mesh of column pod top node; (b) finite
element von Mises stress results of column pod top node (N/m2
)
3D Von mises stress
Contour plot
Element stresses
Simple average
(a) (b)
3,500E+05
3,150E+05
2,756E+05
2,363E+05
1,969E+05
1,575E+05
1,181E+05
7,875E+04
3,938E+04
0,000E+00
No result
Max = 4,023E+05 (Global 374172)
Min = 2,390E+03 (Global 383417)
Structural Engineering International 1/2013 Technical Report 11
the cables anchored to the roof, large
roof deflections would cause a loss of
pretension in the cables and failure of
the system. As a result, a back-up sys-
tem has been introduced consisting of
composite columns cantilevered from
the base structure below and intercon-
nected with structural steel girders at
the top and bottom of the wall. The
cables span between these girders, and
the top of the back-up system is later-
ally supported by the Headhouse Roof
above with dampers at composite
column locations. This system allows
for differential movements between
the edge of the Headhouse Roof and
the base structure without the loss of
cable pretension. The various cable
support conditions are highlighted in
Fig. 5a and can be seen in the construc-
tion photographs in Fig. 6.
In addition to its size and length, the
cable wall includes a number of fea-
tures rarely seen in cable wall struc-
tures. A large portion of the wall
follows the curvature of the plan of
the Headhouse Roof, a feature only
achievable because the cable wall
consists solely of vertical cables. At
the two ends of the north portion of
the wall, there are absolute corners.
The allowable deflection typical of
cable walls would have caused the
two portions of the walls to collide
at this location. To prevent this from
occurring, the corner cables are rein-
forced with horizontal stiffener plates
connected between the cable and the
corner column of the back-up sys-
tem. Variations in height, changes in
anchoring conditions, and the inclu-
sion of corners, curves, and entrance
vestibules all worked to necessitate a
very precise design of cable preten-
sion. Owing to the shape and scale of
the Headhouse Roof and the cable
wall, a wind tunnel study (Fig. 5b) was
carried out to accurately determine
the cable wall cladding pressures as
well as the structural roof loads for
the Headhouse Roof. After establish-
ing the appropriate gravity and wind
loads, a finite element analysis model,
as shown in Fig. 5c, was built includ-
ing the cables and support structure.
Through a geometrically nonlinear
static analysis, the deflection and axial
force of each cable was determined. In
locations where deflections exceeded
L/50, the pretension force in the cable
was increased, and cable diameters
were selected to meet the axial force
demands. A primary concern dur-
ing the design of the cable wall was
preventing warping of the cable wall
insulated glass units (IGUs). Warping
Fig. 5: (a) Cable wall plan and support conditions; (b) Headhouse Roof and cable wall
wind tunnel study model; (c) cable wall structural analysis model with back-up systems
330 m
Expansion
joint
Expansion
joint
Expansion
joint
Expansion
joint
155 m
Cable wall corner
condition
(a)
(b)
(c)
Cable wall corner
condition
170 m
170 m
Variable height cable
wall with backup system
Variable height cable
wall with backup system
Curved cable wall
as clearstory
15 M High cable wall
with vestibules
Fig. 4: Headhouse Roof construction photographs: top, terminal building panorama;
Headhouse roof to left, May 2012; middle, Headhouse Roof over departure level road-
way, February 2012; bottom, stages of column pod installation
12 Technical Report Structural Engineering International 1/2013
Fig. 6: Cable wall construction photographs (clockwise from top left) varying-height cable
wall with steel column back-up system; cable wall at entrance vestibule; departure level
cable wall with column pod beyond; curved cable wall along clerestory zone; departure
level cable wall connected directly to Headhouse Roof
metal deck slabs in-filled between
concrete moment frame systems. At
all locations, the regular grid system
has resulted in the repetitive use of
concrete formwork and economy in
construction.
Along the perimeter of the terminal,
security requirements mandated cer-
tain clearances between the build-
ing and aircraft, as well as a vertical
separation of departing and arriving
passengers. To provide this separa-
tion at the terminal while maintaining
a single point of aircraft entry, steel
fixed bridges connect the terminal
to the aerobridges. The fixed bridges
utilize a truss system along the edges
with a minimal number of touchdown
locations to provide maximum flexibil-
ity below for airside traffic movement.
Owing to the constraints of the site, the
layout of the Terminal Building is such
that areas with internal functions occur
in the levels below the departures
roadways adjacent to the Arrivals Hall.
The roadway system therefore had to
be isolated from the Terminal Building
structural framing below to minimize
vibration and to maintain acceptable
acoustic levels in the occupied spaces
below. The structural system for the
roadways consists of reinforced con-
crete moment-resisting frames of the
base building below in conjunction
with pre-stressed, pre-cast reinforced
concrete long-span I-beams supported
on isolation pads. A cast-in-place rein-
forced concrete slab interconnects
the I-beams and acts as a diaphragm.
Given that the roadway slab is exposed
to the elements, it was designed to
allow for movement due to tempera-
ture changes; the pre-cast I-beams are
fixed at one end and free to slide at the
other end. The roadway is exposed to
the elements and large temperature
changes, but with interior space below
the roadway, expansion joints in the
roadway slab had to be water-tight.
To meet this requirement, these joints
were located at 17 m intervals to mini-
mize the width of the joint.
The design of the parking structure
brought along a number of aesthetic
and functional challenges. Designers
did not want an imposing structure,
but difficult geological conditions lim-
ited the depth of excavation. Working
within these constraints, the parking
structure utilizes a shallow floor fram-
ing system with two-way concrete flat
plate with concrete shear walls for lat-
eral support. The compact nine-level
parking garage meets all of its parking
occurs when the four joints of the
rectangular glass units do not lie in
the same plane, and it can cause the
seal between IGUs to break. Based
on the allowable shear deformation
of the IGUs, the out-of-plane deflec-
tion was limited to L/100, where L is
the shorter length of the rectangular
unit. To prevent warping of the IGUs,
the largest values of pretension are
required in areas with sharp geometric
changes, such as the vestibules and at
the wall corners. Based on these con-
ditions, cable diameters vary from 25
to 37 mm and pretension values range
from 150 to 400 kN.
Multiple System Concrete Base
Structure
The Terminal Building is divided
into the Pier and Gate Zone, Retail
Zone, Headhouse Roof Zone, and
the Frontage Road Zone. Despite its
immense size, the Terminal Building
requires only two grid systems to cover
the entire footprint of the building.An
orthogonal 8,5 × 8 m2
grid was adopted
for the entire central facility, which
provided optimal use of space for the
baggage handling facilities. Meanwhile,
the grid utilized for the Gate Zone
was a 9 × 11 m2
continuous linear and
radial grid along the periphery of the
building.
The concrete base structure of the
Terminal Building employs three
distinct structural floor systems in
response to functional zones with
varying optimal clear-span require-
ments. In the linear and radial Gate
Zone, a regular, repetitive one-way
concrete beam and slab system has
been utilized. At locations which gen-
erate heavy passenger congestion such
as the Baggage Claim Hall, functional
requirements called for a relatively
column-free space. This was achieved
by placing columns within the bag-
gage claim belts and having a clear
span between belts resulting in struc-
tural framing bays of 17 × 16 m2
and
employing a waffle slab system for
the floor framing above. In the Retail
Zone, where maximum flexibility for
floor openings and future renova-
tions was desired, the floor system
utilizes steel framing with composite
Structural Engineering International 1/2013 Technical Report 13
requirements within the stipulated
height so that its roof aligns with the
Departure Level and serves as a green
roof for the visitor area.
Concluding Remarks
The design of the Terminal Building
placed a high priority on material effi-
ciency and ease of construction. All
parts of the building utilized repeti-
tive, modular designs that accommo-
date construction phasing and permit
rapid construction. Ensuring the sta-
bility of the individual portions of
the Terminal Building throughout
SEI Data Block
SEI Data Block
Owner and operator:
Mumbai International Airport Limited
Architect, structural engineer, and MEP
engineer:
Skidmore, Owings & Merrill LLP
Local designer and general contractor:
Larson and Toubro Limited
Steel (t): Approximately 22 000
Concrete (m3
): Approximately 520 000
Estimated cost (USD million): 1200
Service date: November 2013
the phased construction was an
important consideration in select-
ing the building’s structural systems.
Construction of Phase 1 began in 2008
and was completed in early 2012. By
November 2013, both Phases 1 and 2
of the Terminal Building are expected
to be fully operational, and at that
time the remaining portion of the
existing terminal is to be demolished
and construction will begin on Phase
3, the gate areas on the eastern pier.
Upon completion in 2014, the termi-
nal will serve 40 million passengers
per annum.

More Related Content

What's hot

Literature study- koyembedu chennai
Literature study- koyembedu chennaiLiterature study- koyembedu chennai
Literature study- koyembedu chennai
Abinaya Ramakrishnan
 
Hyderabad convention centre
Hyderabad convention centreHyderabad convention centre
Hyderabad convention centre
appysuppy
 
Petronas towers
Petronas towersPetronas towers
Petronas towers
Palak Khandelwal
 
Architectural Appraisal - CII- Sohrabji Godrej Green Business Centre Hyderabad
Architectural Appraisal  - CII- Sohrabji Godrej Green Business Centre HyderabadArchitectural Appraisal  - CII- Sohrabji Godrej Green Business Centre Hyderabad
Architectural Appraisal - CII- Sohrabji Godrej Green Business Centre Hyderabad
Prastara Architects
 
Indian Habitat Centre
Indian Habitat CentreIndian Habitat Centre
Indian Habitat Centre
Krishna Jhawar
 
high rise buildings case study
high rise buildings case studyhigh rise buildings case study
high rise buildings case study
Shreelekha Kulkarni
 
Central Bus Station, Vadodara
Central Bus Station, VadodaraCentral Bus Station, Vadodara
Central Bus Station, Vadodara
Mridul Bhandari
 
Indian habitat centre (6)
Indian habitat centre (6)Indian habitat centre (6)
Indian habitat centre (6)
tivar rose
 
Bharat Bhavan, Bhopal
Bharat Bhavan, BhopalBharat Bhavan, Bhopal
Bharat Bhavan, Bhopal
Divya Suresh
 
Architecture Thesis Topics List
Architecture Thesis Topics ListArchitecture Thesis Topics List
Architecture Thesis Topics List
Bachelor Thesis
 
college campus Case study
college campus Case studycollege campus Case study
college campus Case study
Adyasha Adyasha
 
Bangalore international exhibition centre case study
Bangalore international exhibition centre case studyBangalore international exhibition centre case study
Bangalore international exhibition centre case study
self employer
 
Shanghai Tower.pdf
Shanghai Tower.pdfShanghai Tower.pdf
Shanghai Tower.pdf
SanskritiJindal4
 
Hyderabad international convention centre
Hyderabad international convention centreHyderabad international convention centre
Hyderabad international convention centre
richa bihari
 
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Prateek Srivastava
 
The interlace singapore
The interlace singaporeThe interlace singapore
Bus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt showBus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt show
kiranightly
 
Santiago Calatrava
 Santiago Calatrava Santiago Calatrava
Santiago Calatrava
vikashsaini78
 
Dilli haat janakpuri
Dilli haat janakpuriDilli haat janakpuri
Dilli haat janakpuri
BISHAL KHANAL
 
Vancouver convention centre
Vancouver convention centre Vancouver convention centre
Vancouver convention centre
Pranjal Raj singh
 

What's hot (20)

Literature study- koyembedu chennai
Literature study- koyembedu chennaiLiterature study- koyembedu chennai
Literature study- koyembedu chennai
 
Hyderabad convention centre
Hyderabad convention centreHyderabad convention centre
Hyderabad convention centre
 
Petronas towers
Petronas towersPetronas towers
Petronas towers
 
Architectural Appraisal - CII- Sohrabji Godrej Green Business Centre Hyderabad
Architectural Appraisal  - CII- Sohrabji Godrej Green Business Centre HyderabadArchitectural Appraisal  - CII- Sohrabji Godrej Green Business Centre Hyderabad
Architectural Appraisal - CII- Sohrabji Godrej Green Business Centre Hyderabad
 
Indian Habitat Centre
Indian Habitat CentreIndian Habitat Centre
Indian Habitat Centre
 
high rise buildings case study
high rise buildings case studyhigh rise buildings case study
high rise buildings case study
 
Central Bus Station, Vadodara
Central Bus Station, VadodaraCentral Bus Station, Vadodara
Central Bus Station, Vadodara
 
Indian habitat centre (6)
Indian habitat centre (6)Indian habitat centre (6)
Indian habitat centre (6)
 
Bharat Bhavan, Bhopal
Bharat Bhavan, BhopalBharat Bhavan, Bhopal
Bharat Bhavan, Bhopal
 
Architecture Thesis Topics List
Architecture Thesis Topics ListArchitecture Thesis Topics List
Architecture Thesis Topics List
 
college campus Case study
college campus Case studycollege campus Case study
college campus Case study
 
Bangalore international exhibition centre case study
Bangalore international exhibition centre case studyBangalore international exhibition centre case study
Bangalore international exhibition centre case study
 
Shanghai Tower.pdf
Shanghai Tower.pdfShanghai Tower.pdf
Shanghai Tower.pdf
 
Hyderabad international convention centre
Hyderabad international convention centreHyderabad international convention centre
Hyderabad international convention centre
 
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
 
The interlace singapore
The interlace singaporeThe interlace singapore
The interlace singapore
 
Bus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt showBus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt show
 
Santiago Calatrava
 Santiago Calatrava Santiago Calatrava
Santiago Calatrava
 
Dilli haat janakpuri
Dilli haat janakpuriDilli haat janakpuri
Dilli haat janakpuri
 
Vancouver convention centre
Vancouver convention centre Vancouver convention centre
Vancouver convention centre
 

Similar to Chhatrapati Shivaji International Airport—Integrated Terminal Building

IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET Journal
 
IRJET- Comparative Study of Tube in Tube Structure and Frame Tube Structure
IRJET- Comparative Study of Tube in Tube Structure and Frame Tube StructureIRJET- Comparative Study of Tube in Tube Structure and Frame Tube Structure
IRJET- Comparative Study of Tube in Tube Structure and Frame Tube Structure
IRJET Journal
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Mary Montoya
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written Report
Yap Xin
 
A Study On Pre-Engineered Building – A Construction Technique
A Study On Pre-Engineered Building – A Construction TechniqueA Study On Pre-Engineered Building – A Construction Technique
A Study On Pre-Engineered Building – A Construction Technique
IJERA Editor
 
Internship report
Internship reportInternship report
Internship report
Abdullah Jawaid
 
Highrise buildings....
Highrise buildings....Highrise buildings....
Highrise buildings....
MSulmanSarwar
 
Parametric Study of Double Layer Steel Dome with Reference to Span to Height ...
Parametric Study of Double Layer Steel Dome with Reference to Span to Height ...Parametric Study of Double Layer Steel Dome with Reference to Span to Height ...
Parametric Study of Double Layer Steel Dome with Reference to Span to Height ...
International Journal of Science and Research (IJSR)
 
Btech
BtechBtech
Btech
kerneng
 
The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013
engineeringwatch
 
Application of Advanced formwork system for High rise buildings in Chennai, I...
Application of Advanced formwork system for High rise buildings in Chennai, I...Application of Advanced formwork system for High rise buildings in Chennai, I...
Application of Advanced formwork system for High rise buildings in Chennai, I...
IRJET Journal
 
IRJET- Comparative Analysis of RCC Structure and Tube-in-Tube Structure
IRJET-  	  Comparative Analysis of RCC Structure and Tube-in-Tube StructureIRJET-  	  Comparative Analysis of RCC Structure and Tube-in-Tube Structure
IRJET- Comparative Analysis of RCC Structure and Tube-in-Tube Structure
IRJET Journal
 
Case study on steel structure Shrikant
Case study on steel structure  ShrikantCase study on steel structure  Shrikant
Case study on steel structure Shrikant
ShriKant49
 
HEYDER ALIVEY CULTURE CENTER - STRUCTURE ANALYSIS
HEYDER ALIVEY CULTURE CENTER - STRUCTURE ANALYSIS HEYDER ALIVEY CULTURE CENTER - STRUCTURE ANALYSIS
HEYDER ALIVEY CULTURE CENTER - STRUCTURE ANALYSIS
Mohammed Naeem Darwish
 
IRJET- Prerequisite & Utilities of Pre-Construction Buildings in Modern Days ...
IRJET- Prerequisite & Utilities of Pre-Construction Buildings in Modern Days ...IRJET- Prerequisite & Utilities of Pre-Construction Buildings in Modern Days ...
IRJET- Prerequisite & Utilities of Pre-Construction Buildings in Modern Days ...
IRJET Journal
 
IRJET- A Performance Study of (G+20) RCC Structure using Framed Bundled B...
IRJET-  	  A Performance Study of (G+20) RCC Structure using Framed Bundled B...IRJET-  	  A Performance Study of (G+20) RCC Structure using Framed Bundled B...
IRJET- A Performance Study of (G+20) RCC Structure using Framed Bundled B...
IRJET Journal
 
Skyscrapers
SkyscrapersSkyscrapers
Skyscrapers
Mohamed Elsayed
 
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSISFORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
IRJET Journal
 
Ay32747751
Ay32747751Ay32747751
Ay32747751
IJMER
 
Effect of configuration on lateral displacement and cost of the structure for...
Effect of configuration on lateral displacement and cost of the structure for...Effect of configuration on lateral displacement and cost of the structure for...
Effect of configuration on lateral displacement and cost of the structure for...
eSAT Journals
 

Similar to Chhatrapati Shivaji International Airport—Integrated Terminal Building (20)

IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
 
IRJET- Comparative Study of Tube in Tube Structure and Frame Tube Structure
IRJET- Comparative Study of Tube in Tube Structure and Frame Tube StructureIRJET- Comparative Study of Tube in Tube Structure and Frame Tube Structure
IRJET- Comparative Study of Tube in Tube Structure and Frame Tube Structure
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written Report
 
A Study On Pre-Engineered Building – A Construction Technique
A Study On Pre-Engineered Building – A Construction TechniqueA Study On Pre-Engineered Building – A Construction Technique
A Study On Pre-Engineered Building – A Construction Technique
 
Internship report
Internship reportInternship report
Internship report
 
Highrise buildings....
Highrise buildings....Highrise buildings....
Highrise buildings....
 
Parametric Study of Double Layer Steel Dome with Reference to Span to Height ...
Parametric Study of Double Layer Steel Dome with Reference to Span to Height ...Parametric Study of Double Layer Steel Dome with Reference to Span to Height ...
Parametric Study of Double Layer Steel Dome with Reference to Span to Height ...
 
Btech
BtechBtech
Btech
 
The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013
 
Application of Advanced formwork system for High rise buildings in Chennai, I...
Application of Advanced formwork system for High rise buildings in Chennai, I...Application of Advanced formwork system for High rise buildings in Chennai, I...
Application of Advanced formwork system for High rise buildings in Chennai, I...
 
IRJET- Comparative Analysis of RCC Structure and Tube-in-Tube Structure
IRJET-  	  Comparative Analysis of RCC Structure and Tube-in-Tube StructureIRJET-  	  Comparative Analysis of RCC Structure and Tube-in-Tube Structure
IRJET- Comparative Analysis of RCC Structure and Tube-in-Tube Structure
 
Case study on steel structure Shrikant
Case study on steel structure  ShrikantCase study on steel structure  Shrikant
Case study on steel structure Shrikant
 
HEYDER ALIVEY CULTURE CENTER - STRUCTURE ANALYSIS
HEYDER ALIVEY CULTURE CENTER - STRUCTURE ANALYSIS HEYDER ALIVEY CULTURE CENTER - STRUCTURE ANALYSIS
HEYDER ALIVEY CULTURE CENTER - STRUCTURE ANALYSIS
 
IRJET- Prerequisite & Utilities of Pre-Construction Buildings in Modern Days ...
IRJET- Prerequisite & Utilities of Pre-Construction Buildings in Modern Days ...IRJET- Prerequisite & Utilities of Pre-Construction Buildings in Modern Days ...
IRJET- Prerequisite & Utilities of Pre-Construction Buildings in Modern Days ...
 
IRJET- A Performance Study of (G+20) RCC Structure using Framed Bundled B...
IRJET-  	  A Performance Study of (G+20) RCC Structure using Framed Bundled B...IRJET-  	  A Performance Study of (G+20) RCC Structure using Framed Bundled B...
IRJET- A Performance Study of (G+20) RCC Structure using Framed Bundled B...
 
Skyscrapers
SkyscrapersSkyscrapers
Skyscrapers
 
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSISFORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
 
Ay32747751
Ay32747751Ay32747751
Ay32747751
 
Effect of configuration on lateral displacement and cost of the structure for...
Effect of configuration on lateral displacement and cost of the structure for...Effect of configuration on lateral displacement and cost of the structure for...
Effect of configuration on lateral displacement and cost of the structure for...
 

More from Anupama Krishnan

CONTEMPORARY CARE: PATTERN TRANSLATIONS FOR AN INTERGENERATIONAL EXCHANGE Chr...
CONTEMPORARY CARE: PATTERN TRANSLATIONS FOR AN INTERGENERATIONAL EXCHANGE Chr...CONTEMPORARY CARE: PATTERN TRANSLATIONS FOR AN INTERGENERATIONAL EXCHANGE Chr...
CONTEMPORARY CARE: PATTERN TRANSLATIONS FOR AN INTERGENERATIONAL EXCHANGE Chr...
Anupama Krishnan
 
PP question bank
PP question bankPP question bank
PP question bank
Anupama Krishnan
 
ALLIED DESIGN QUESTION BANK
ALLIED DESIGN QUESTION BANKALLIED DESIGN QUESTION BANK
ALLIED DESIGN QUESTION BANK
Anupama Krishnan
 
Vinzol
VinzolVinzol
Professional practice vth year
Professional practice vth yearProfessional practice vth year
Professional practice vth year
Anupama Krishnan
 
Professional practise question bank
Professional practise question bankProfessional practise question bank
Professional practise question bank
Anupama Krishnan
 
Formation of cooperative society
Formation of cooperative societyFormation of cooperative society
Formation of cooperative society
Anupama Krishnan
 
India Easement Act
India Easement ActIndia Easement Act
India Easement Act
Anupama Krishnan
 
Depreciation and sinking fund
Depreciation and sinking fundDepreciation and sinking fund
Depreciation and sinking fund
Anupama Krishnan
 
Elements of valuation
Elements of valuationElements of valuation
Elements of valuation
Anupama Krishnan
 
Value and sinking fund
Value and sinking fundValue and sinking fund
Value and sinking fund
Anupama Krishnan
 
Dilapidation report
Dilapidation reportDilapidation report
Dilapidation report
Anupama Krishnan
 
FAIR MARKET VALUE
FAIR MARKET VALUEFAIR MARKET VALUE
FAIR MARKET VALUE
Anupama Krishnan
 
Allied design answer bank
Allied design answer bankAllied design answer bank
Allied design answer bank
Anupama Krishnan
 
Role as an architect in MHADA
Role as an architect in MHADARole as an architect in MHADA
Role as an architect in MHADA
Anupama Krishnan
 
TDR and fungible FSI
TDR and fungible FSITDR and fungible FSI
TDR and fungible FSI
Anupama Krishnan
 
Professional practise
Professional practiseProfessional practise
Professional practise
Anupama Krishnan
 
Explain the various factors that influence a structure?
Explain the various factors that influence a structure?Explain the various factors that influence a structure?
Explain the various factors that influence a structure?
Anupama Krishnan
 
LEGISLATIVE STRUCRURE OF MMR:
LEGISLATIVE STRUCRURE OF MMR:LEGISLATIVE STRUCRURE OF MMR:
LEGISLATIVE STRUCRURE OF MMR:
Anupama Krishnan
 
Building services optimization
Building services optimizationBuilding services optimization
Building services optimization
Anupama Krishnan
 

More from Anupama Krishnan (20)

CONTEMPORARY CARE: PATTERN TRANSLATIONS FOR AN INTERGENERATIONAL EXCHANGE Chr...
CONTEMPORARY CARE: PATTERN TRANSLATIONS FOR AN INTERGENERATIONAL EXCHANGE Chr...CONTEMPORARY CARE: PATTERN TRANSLATIONS FOR AN INTERGENERATIONAL EXCHANGE Chr...
CONTEMPORARY CARE: PATTERN TRANSLATIONS FOR AN INTERGENERATIONAL EXCHANGE Chr...
 
PP question bank
PP question bankPP question bank
PP question bank
 
ALLIED DESIGN QUESTION BANK
ALLIED DESIGN QUESTION BANKALLIED DESIGN QUESTION BANK
ALLIED DESIGN QUESTION BANK
 
Vinzol
VinzolVinzol
Vinzol
 
Professional practice vth year
Professional practice vth yearProfessional practice vth year
Professional practice vth year
 
Professional practise question bank
Professional practise question bankProfessional practise question bank
Professional practise question bank
 
Formation of cooperative society
Formation of cooperative societyFormation of cooperative society
Formation of cooperative society
 
India Easement Act
India Easement ActIndia Easement Act
India Easement Act
 
Depreciation and sinking fund
Depreciation and sinking fundDepreciation and sinking fund
Depreciation and sinking fund
 
Elements of valuation
Elements of valuationElements of valuation
Elements of valuation
 
Value and sinking fund
Value and sinking fundValue and sinking fund
Value and sinking fund
 
Dilapidation report
Dilapidation reportDilapidation report
Dilapidation report
 
FAIR MARKET VALUE
FAIR MARKET VALUEFAIR MARKET VALUE
FAIR MARKET VALUE
 
Allied design answer bank
Allied design answer bankAllied design answer bank
Allied design answer bank
 
Role as an architect in MHADA
Role as an architect in MHADARole as an architect in MHADA
Role as an architect in MHADA
 
TDR and fungible FSI
TDR and fungible FSITDR and fungible FSI
TDR and fungible FSI
 
Professional practise
Professional practiseProfessional practise
Professional practise
 
Explain the various factors that influence a structure?
Explain the various factors that influence a structure?Explain the various factors that influence a structure?
Explain the various factors that influence a structure?
 
LEGISLATIVE STRUCRURE OF MMR:
LEGISLATIVE STRUCRURE OF MMR:LEGISLATIVE STRUCRURE OF MMR:
LEGISLATIVE STRUCRURE OF MMR:
 
Building services optimization
Building services optimizationBuilding services optimization
Building services optimization
 

Recently uploaded

一比一原版阿肯色大学毕业证(UCSF毕业证书)如何办理
一比一原版阿肯色大学毕业证(UCSF毕业证书)如何办理一比一原版阿肯色大学毕业证(UCSF毕业证书)如何办理
一比一原版阿肯色大学毕业证(UCSF毕业证书)如何办理
bo44ban1
 
Discovering the Best Indian Architects A Spotlight on Design Forum Internatio...
Discovering the Best Indian Architects A Spotlight on Design Forum Internatio...Discovering the Best Indian Architects A Spotlight on Design Forum Internatio...
Discovering the Best Indian Architects A Spotlight on Design Forum Internatio...
Designforuminternational
 
UXpert_Report (UALR Mapping Renewal 2022).pdf
UXpert_Report (UALR Mapping Renewal 2022).pdfUXpert_Report (UALR Mapping Renewal 2022).pdf
UXpert_Report (UALR Mapping Renewal 2022).pdf
anthonylin333
 
一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样
一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样
一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样
881evgn0
 
按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理
按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理
按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理
kuapy
 
一比一原版马来西亚世纪大学毕业证成绩单一模一样
一比一原版马来西亚世纪大学毕业证成绩单一模一样一比一原版马来西亚世纪大学毕业证成绩单一模一样
一比一原版马来西亚世纪大学毕业证成绩单一模一样
k4krdgxx
 
ARENA - Young adults in the workplace (Knight Moves).pdf
ARENA - Young adults in the workplace (Knight Moves).pdfARENA - Young adults in the workplace (Knight Moves).pdf
ARENA - Young adults in the workplace (Knight Moves).pdf
Knight Moves
 
Graphic Design Tools and Software .pptx
Graphic Design Tools and Software   .pptxGraphic Design Tools and Software   .pptx
Graphic Design Tools and Software .pptx
Virtual Real Design
 
Introduction to User experience design for beginner
Introduction to User experience design for beginnerIntroduction to User experience design for beginner
Introduction to User experience design for beginner
ellemjani
 
International Upcycling Research Network advisory board meeting 4
International Upcycling Research Network advisory board meeting 4International Upcycling Research Network advisory board meeting 4
International Upcycling Research Network advisory board meeting 4
Kyungeun Sung
 
NHL Stenden University of Applied Sciences Diploma Degree Transcript
NHL Stenden University of Applied Sciences Diploma Degree TranscriptNHL Stenden University of Applied Sciences Diploma Degree Transcript
NHL Stenden University of Applied Sciences Diploma Degree Transcript
lhtvqoag
 
Manual ISH (International Society of Hypertension)
Manual ISH (International Society of Hypertension)Manual ISH (International Society of Hypertension)
Manual ISH (International Society of Hypertension)
bagmai
 
AHMED TALAAT ARCHITECTURE PORTFOLIO .pdf
AHMED TALAAT ARCHITECTURE PORTFOLIO .pdfAHMED TALAAT ARCHITECTURE PORTFOLIO .pdf
AHMED TALAAT ARCHITECTURE PORTFOLIO .pdf
talaatahm
 
定制美国西雅图城市大学毕业证学历证书原版一模一样
定制美国西雅图城市大学毕业证学历证书原版一模一样定制美国西雅图城市大学毕业证学历证书原版一模一样
定制美国西雅图城市大学毕业证学历证书原版一模一样
qo1as76n
 
原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样
原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样
原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样
hw2xf1m
 
LGBTQIA Pride Month presentation Template
LGBTQIA Pride Month presentation TemplateLGBTQIA Pride Month presentation Template
LGBTQIA Pride Month presentation Template
DakshGudwani
 
NHR Engineers Portfolio 2023 2024 NISHANT RATHI
NHR Engineers Portfolio 2023 2024 NISHANT RATHINHR Engineers Portfolio 2023 2024 NISHANT RATHI
NHR Engineers Portfolio 2023 2024 NISHANT RATHI
NishantRathi18
 
Heuristics Evaluation - How to Guide.pdf
Heuristics Evaluation - How to Guide.pdfHeuristics Evaluation - How to Guide.pdf
Heuristics Evaluation - How to Guide.pdf
Jaime Brown
 
一比一原版马里兰大学毕业证(UMD毕业证书)如何办理
一比一原版马里兰大学毕业证(UMD毕业证书)如何办理一比一原版马里兰大学毕业证(UMD毕业证书)如何办理
一比一原版马里兰大学毕业证(UMD毕业证书)如何办理
9lq7ultg
 
哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样
哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样
哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样
qo1as76n
 

Recently uploaded (20)

一比一原版阿肯色大学毕业证(UCSF毕业证书)如何办理
一比一原版阿肯色大学毕业证(UCSF毕业证书)如何办理一比一原版阿肯色大学毕业证(UCSF毕业证书)如何办理
一比一原版阿肯色大学毕业证(UCSF毕业证书)如何办理
 
Discovering the Best Indian Architects A Spotlight on Design Forum Internatio...
Discovering the Best Indian Architects A Spotlight on Design Forum Internatio...Discovering the Best Indian Architects A Spotlight on Design Forum Internatio...
Discovering the Best Indian Architects A Spotlight on Design Forum Internatio...
 
UXpert_Report (UALR Mapping Renewal 2022).pdf
UXpert_Report (UALR Mapping Renewal 2022).pdfUXpert_Report (UALR Mapping Renewal 2022).pdf
UXpert_Report (UALR Mapping Renewal 2022).pdf
 
一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样
一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样
一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样
 
按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理
按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理
按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理
 
一比一原版马来西亚世纪大学毕业证成绩单一模一样
一比一原版马来西亚世纪大学毕业证成绩单一模一样一比一原版马来西亚世纪大学毕业证成绩单一模一样
一比一原版马来西亚世纪大学毕业证成绩单一模一样
 
ARENA - Young adults in the workplace (Knight Moves).pdf
ARENA - Young adults in the workplace (Knight Moves).pdfARENA - Young adults in the workplace (Knight Moves).pdf
ARENA - Young adults in the workplace (Knight Moves).pdf
 
Graphic Design Tools and Software .pptx
Graphic Design Tools and Software   .pptxGraphic Design Tools and Software   .pptx
Graphic Design Tools and Software .pptx
 
Introduction to User experience design for beginner
Introduction to User experience design for beginnerIntroduction to User experience design for beginner
Introduction to User experience design for beginner
 
International Upcycling Research Network advisory board meeting 4
International Upcycling Research Network advisory board meeting 4International Upcycling Research Network advisory board meeting 4
International Upcycling Research Network advisory board meeting 4
 
NHL Stenden University of Applied Sciences Diploma Degree Transcript
NHL Stenden University of Applied Sciences Diploma Degree TranscriptNHL Stenden University of Applied Sciences Diploma Degree Transcript
NHL Stenden University of Applied Sciences Diploma Degree Transcript
 
Manual ISH (International Society of Hypertension)
Manual ISH (International Society of Hypertension)Manual ISH (International Society of Hypertension)
Manual ISH (International Society of Hypertension)
 
AHMED TALAAT ARCHITECTURE PORTFOLIO .pdf
AHMED TALAAT ARCHITECTURE PORTFOLIO .pdfAHMED TALAAT ARCHITECTURE PORTFOLIO .pdf
AHMED TALAAT ARCHITECTURE PORTFOLIO .pdf
 
定制美国西雅图城市大学毕业证学历证书原版一模一样
定制美国西雅图城市大学毕业证学历证书原版一模一样定制美国西雅图城市大学毕业证学历证书原版一模一样
定制美国西雅图城市大学毕业证学历证书原版一模一样
 
原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样
原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样
原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样
 
LGBTQIA Pride Month presentation Template
LGBTQIA Pride Month presentation TemplateLGBTQIA Pride Month presentation Template
LGBTQIA Pride Month presentation Template
 
NHR Engineers Portfolio 2023 2024 NISHANT RATHI
NHR Engineers Portfolio 2023 2024 NISHANT RATHINHR Engineers Portfolio 2023 2024 NISHANT RATHI
NHR Engineers Portfolio 2023 2024 NISHANT RATHI
 
Heuristics Evaluation - How to Guide.pdf
Heuristics Evaluation - How to Guide.pdfHeuristics Evaluation - How to Guide.pdf
Heuristics Evaluation - How to Guide.pdf
 
一比一原版马里兰大学毕业证(UMD毕业证书)如何办理
一比一原版马里兰大学毕业证(UMD毕业证书)如何办理一比一原版马里兰大学毕业证(UMD毕业证书)如何办理
一比一原版马里兰大学毕业证(UMD毕业证书)如何办理
 
哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样
哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样
哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样
 

Chhatrapati Shivaji International Airport—Integrated Terminal Building

  • 1. 8 Technical Report Structural Engineering International 1/2013 Chhatrapati Shivaji International Airport—Integrated Terminal Building Charles Besjak, SE, PE, Director; Preetam Biswas, PE, Associate Director; Alexandra Thewis, PE; Raymond Sweeney; Damayanti Chaudhuri, PE; Skidmore, Owings & Merrill LLP, New York, NY 10005, USA. Contact: preetam.biswas@som.com DOI: 10.2749/101686613X13363929988296 an overall truss depth of only 4 m. In response to site constraints and prox- imity of the existing operational ter- minal building, the mega-columns are also designed to serve as hoist mecha- nisms such that the entire roof can be constructed without tower cranes. The Terminal Building also includes the largest and longest cable wall system in the world. The structural studies completed include solid finite element analysis of connections to optimize material efficiency. Furthermore, the structural design prioritizes modular construction for economy and facili- tation of an accelerated construction schedule. Keywords: airport terminal; long-span roof; unidirectional cable wall; struc- tural efficiency; phased construction. Introduction Mumbai International Airport Limited, owner-operator of Chhatrapati Shivaji International Airport at Mumbai, is cur- rently building a new Integrated Termi- nal Building that combines international and domestic operations at one of the busiest airports in India in order to achieve 24-h utilization.This 410 000 m2 terminal building is being constructed at the location of the existing terminal with minimal disruption to its opera- tions. An international consultant with vast experience in designing airport terminals around the globe was chosen as the principal architect and engineer for the new building. One of the largest construction firms in India was chosen as the local designer and general con- tractor for the project. The Terminal Building is being constructed in phases where Phase 1 includes construction of the western pier, and Phase 2 includes construction of the Headhouse zone. Upon completion of Phases 1 and 2, the building will become operational and Phase 3 will commence, which consists of the demolition of the exist- ing terminal building and the construc- tion of the eastern pier. Following the completion of Phase 3 in 2014, the new terminal, shown in Fig. 1, will serve approximately 40 million passengers annually. Abstract The new Integrated Terminal Building at Mumbai’s Chhatrapati Shivaji International Airport combines inter- national and domestic operations at one of the busiest airports in India. The 410 000 m2 building, being con- structed at the site of the existing terminal, will achieve a capacity of 40 million passengers per annum upon completion in 2014. The primary design feature of the building is a long-span roof covering a total of 70 000 m2 over various func- tional requirements, making it one of the largest roofs in the world without an expansion joint. The Headhouse Roof, supported by only 30 columns spaced at 64 m in the North–South direction and at 34 m in the East–West direction, produces a large column- free space ideal for an airport. By increasing the depth of the trusses near the columns and running trusses in both an orthogonal grid and a 45° grid, large spacing and cantilevers of 40 m along the perimeter are achieved with In anticipation of the forthcoming IABSE Symposium in Kolkata in September 2013, this special issue of Structural Engineering International presents a series of projects in or related to India. As varied as the country itself, the follow- ing eight technical papers present structures ranging from an underground cavern to a research station in Antarctica. In the first paper—and highlighted on the front cover—the new terminal building of the Mumbai airport is described, including the elaborate roof and wall system.This is followed by two projects in and around New Delhi: a new signature cable-stayed bridge with its backwardly inclined pylon and the addition of a cable roof system for the retrofit of a sta- dium. A brief history of landmark bridges constructed over major rivers in India and the challenges faced in their con- struction is then elaborated. Next, the construction of one of the world’s deepest caverns for the storage of liquefied petroleum gas in Visakhapatnam is detailed, followed by a description of the new Indian research station on the world’s southern-most continent, Antarctica. Back on the Indian subcontinent and aboveground, the last two papers present a light-weight, double layered cable-net roof system for the retrofit of a swimming facility, as well as a 10 km-long infra- structure project in the technology hub of Bangalore. The Indian Group of IABSE is looking forward to welcom- ing delegates to the 36th IABSE Symposium, in Kolkata from 24 to 27 September 2013 entitled “Long Span Bridges and Roofs—Development, Design and Implementation”. More information on this symposium, as well as other upcoming IABSE events can be found on the IABSE website under www.iabse.org/Events. B. C. Roy, Vice-President of IABSE, Chair of Scientific Committee of 2013 IABSE Symposium in Kolkata Ann Schumacher, Editorial Board, Structural Engineering International Introduction: Recent Structures in India
  • 2. Structural Engineering International 1/2013 Technical Report 9 Owing to the scale and project occu- pancy, the client directive was to meet the requirements of the Indian codes as well as satisfy requirements of the International and American codes. This was achieved by evaluation of the most stringent conditions at all stages of design and analysis. Early in the design process, an evaluation of local construction techniques, available construction materials and availabil- ity of skilled labor played an impor- tant role in the choice of the building materials. Concrete was selected as the primary building material for the base building, while steel was used for the structural framing of the roof in order to achieve a lightweight system with large column-free spaces. The construction site of the new terminal building is located within close prox- imity of the existing terminal that had to remain operational during construc- tion, which resulted in an elongated X-shaped plan utilizing repetitive, modular designs that accommodate construction phasing and permit rapid construction. Long-Span Structural Steel Headhouse Roof The primary design feature of the Terminal Building is a long-span roof covering the departures roadway, check-in hall, security, and passport control functions. The architectural cladding of the roof and ceiling fea- tures a molded surface and sky- lights over the column locations and throughout the terminal ceiling, allow- ing natural light to flood into the main hall. The Headhouse Roof, covering 70 000 m2 and spanning over seven individual concrete base structures, is supported by only 30 composite mega- columns. Beyond typical gravity and seismic loads on the roof, special load- ing considerations were taken for the cable wall which applies a significant wind load to the roof structure and whose cables are pre-stressed against the roof trusses at the northern end of the terminal. The wind loading also presented challenges as a significant portion of the Headhouse Roof is open to the outdoors and behaves as a canopy. In order to create one of the largest roofs in the world without an expan- sion joint, the roof mega-columns and steel roof structure were kept com- pletely independent from the base concrete structures below. Large openings in the concrete base struc- ture allow the mega-columns to pass through as well as create architec- tural design features. This allows the Headhouse Roof structure to move independently in response to loads, particularly expansion and contraction caused by temperature variation. This thermal gradient is applied to the steel in the structural analysis model and accounted for in the design of the roof members. In response to the functional require- ment of the space below the roof, the entire Headhouse Roof is supported on just 30 composite mega-columns. Following requests from the client, the design team sought to minimize the number of columns in the depar- ture halls. However, the final design surpassed this constraint and resulted in a departure hall entirely free of columns through the use of com- posite mega-columns spaced 64 m in one direction and 34 m in the per- pendicular direction. The structural system for the Headhouse Roof is akin to a two-way flat slab system. Increasing the depth of the trusses near the columns and running trusses in an orthogonal grid as well as along a 45° grid results in an overall truss depth of 4 m for the roof system. The greater truss depths near the columns create “column pod” areas which seamlessly integrate into the pyramidal skylights that serve as major architectural fea- tures. All of these aspects of the Headhouse Roof can be seen in the structural model in Fig. 2 as well as in the construction photographs of Fig. 4. The lateral system for the Headhouse Roof comprises steel moment-resisting frames consisting of composite mega- columns and long-span steel roof trusses. Frame action is achieved between the primary roof trusses and the composite mega-columns in the North–South direction and between the secondary roof trusses and the composite mega-columns in the East– West direction. Additional trusses running at 45° to the orthogonal grid provide additional stability and dia- phragm stiffness. The weaving of the orthogonal and diagonal trusses, in addition to ensuring diaphragm action of the roof, was also extremely useful Fig. 1: Architectural renderings (clockwise from top left) plan view of integrated terminal building; approach roadway at departure level; check-in concourse; aerial view of integrated terminal building Future development Arrivals forecourt Headhouse: departure, arrivals, immigration and baggage claim Concourse, retail and baggage handling Pier gates
  • 3. 10 Technical Report Structural Engineering International 1/2013 in reducing the system depth for the entirely cantilevered perimeter zone of the Headhouse Roof. This resulted in up to 40 m cantilevers at certain loca- tions with a truss depth of only 4 m. The orientation of the steel wide- flange members of the trusses along the orthogonal grid were rotated 90° such that flanges were aligned verti- cally, while the steel members of the trusses along the diagonal grid were aligned with the flanges horizontally for simplification of connections with multiple trusses. Nonlinear, solid finite element analysis was carried out for the design of major connections for optimum use of materials. The meshed three-dimensional geometry of the connections (Fig. 3a) was loaded at the connection work point with forces directly obtained from the overall Headhouse Roof analysis model. Rigid link elements from the work point transfer the load to the connection end faces (where the steel members are attached to columns, beams, etc.), and von Mises stress gradients were obtained and studied to verify that no part of the connection exceeded the steel yield stress (Fig. 3b). The behavior of the 40 m tall canti- levered composite mega-columns was studied using nonlinear buckling anal- yses for each individual mega-column. The composite mega-columns consist of a built-up steel cruciform shape encased in 2,7 m diameter of concrete for the majority of its height. Once the column reaches the height of the column pod bottom chord connection, it transforms into a bare steel cruci- form shape and tapers to the column pod top chord connection (Fig. 4). The P–M (axial-moment) interaction curve and stability analysis was per- formed for each segment of the col- umn as well as for the overall stability of the complete mega-column system. These analyses were deemed neces- sary, because the code-prescribed design methods do not accurately correspond to the behavior of these columns. Unidirectional Cable Wall System Another unique feature of this pro- ject is the cable wall exterior clad- ding system. The Terminal Building features two separate cable wall sys- tems totaling over 1 km in length and 11 000 m2 in area, making it the longest and largest cable wall in the world. It includes a number of unique features that create various challenges in the design and detailing of the structure. Both cable walls comprise unidirectional cables spanning verti- cally between two levels of the termi- nal structure. At the Departure Level, the use of unidirectional cables was necessitated by the fact that the cable roof completely envelops the terminal Headhouse, eliminating the possibil- ity of any horizontal anchorage points. In addition, as the cable wall circles the Headhouse, it crosses four inde- pendent base structures and reduces in height from 15 to 6 m. Expansion joints were installed in locations where the cable wall crossed separate struc- tures to allow individual segments of the wall to move independently. On the east and west sides, the cable wall spans to the cantilevered edge of the Headhouse Roof, up to 40 m from the nearest mega-column. The large cantilevers result in significant deflec- tion at the roof edge, which proved to be a challenging situation. With 34 m Span 64 m Span 40 m Cantilever 40 m Cantilever 9 m Truss depth 4 m Truss depth (a) (b) 64 m Truss span Roadway Waffle slab Fig. 2: (a) Three-dimensional structural model of Headhouse Roof framing; (b) section through Headhouse Roof Fig. 3: Three-dimensional solid finite element analysis model of column pod top node connection: (a) three-dimensional finite element mesh of column pod top node; (b) finite element von Mises stress results of column pod top node (N/m2 ) 3D Von mises stress Contour plot Element stresses Simple average (a) (b) 3,500E+05 3,150E+05 2,756E+05 2,363E+05 1,969E+05 1,575E+05 1,181E+05 7,875E+04 3,938E+04 0,000E+00 No result Max = 4,023E+05 (Global 374172) Min = 2,390E+03 (Global 383417)
  • 4. Structural Engineering International 1/2013 Technical Report 11 the cables anchored to the roof, large roof deflections would cause a loss of pretension in the cables and failure of the system. As a result, a back-up sys- tem has been introduced consisting of composite columns cantilevered from the base structure below and intercon- nected with structural steel girders at the top and bottom of the wall. The cables span between these girders, and the top of the back-up system is later- ally supported by the Headhouse Roof above with dampers at composite column locations. This system allows for differential movements between the edge of the Headhouse Roof and the base structure without the loss of cable pretension. The various cable support conditions are highlighted in Fig. 5a and can be seen in the construc- tion photographs in Fig. 6. In addition to its size and length, the cable wall includes a number of fea- tures rarely seen in cable wall struc- tures. A large portion of the wall follows the curvature of the plan of the Headhouse Roof, a feature only achievable because the cable wall consists solely of vertical cables. At the two ends of the north portion of the wall, there are absolute corners. The allowable deflection typical of cable walls would have caused the two portions of the walls to collide at this location. To prevent this from occurring, the corner cables are rein- forced with horizontal stiffener plates connected between the cable and the corner column of the back-up sys- tem. Variations in height, changes in anchoring conditions, and the inclu- sion of corners, curves, and entrance vestibules all worked to necessitate a very precise design of cable preten- sion. Owing to the shape and scale of the Headhouse Roof and the cable wall, a wind tunnel study (Fig. 5b) was carried out to accurately determine the cable wall cladding pressures as well as the structural roof loads for the Headhouse Roof. After establish- ing the appropriate gravity and wind loads, a finite element analysis model, as shown in Fig. 5c, was built includ- ing the cables and support structure. Through a geometrically nonlinear static analysis, the deflection and axial force of each cable was determined. In locations where deflections exceeded L/50, the pretension force in the cable was increased, and cable diameters were selected to meet the axial force demands. A primary concern dur- ing the design of the cable wall was preventing warping of the cable wall insulated glass units (IGUs). Warping Fig. 5: (a) Cable wall plan and support conditions; (b) Headhouse Roof and cable wall wind tunnel study model; (c) cable wall structural analysis model with back-up systems 330 m Expansion joint Expansion joint Expansion joint Expansion joint 155 m Cable wall corner condition (a) (b) (c) Cable wall corner condition 170 m 170 m Variable height cable wall with backup system Variable height cable wall with backup system Curved cable wall as clearstory 15 M High cable wall with vestibules Fig. 4: Headhouse Roof construction photographs: top, terminal building panorama; Headhouse roof to left, May 2012; middle, Headhouse Roof over departure level road- way, February 2012; bottom, stages of column pod installation
  • 5. 12 Technical Report Structural Engineering International 1/2013 Fig. 6: Cable wall construction photographs (clockwise from top left) varying-height cable wall with steel column back-up system; cable wall at entrance vestibule; departure level cable wall with column pod beyond; curved cable wall along clerestory zone; departure level cable wall connected directly to Headhouse Roof metal deck slabs in-filled between concrete moment frame systems. At all locations, the regular grid system has resulted in the repetitive use of concrete formwork and economy in construction. Along the perimeter of the terminal, security requirements mandated cer- tain clearances between the build- ing and aircraft, as well as a vertical separation of departing and arriving passengers. To provide this separa- tion at the terminal while maintaining a single point of aircraft entry, steel fixed bridges connect the terminal to the aerobridges. The fixed bridges utilize a truss system along the edges with a minimal number of touchdown locations to provide maximum flexibil- ity below for airside traffic movement. Owing to the constraints of the site, the layout of the Terminal Building is such that areas with internal functions occur in the levels below the departures roadways adjacent to the Arrivals Hall. The roadway system therefore had to be isolated from the Terminal Building structural framing below to minimize vibration and to maintain acceptable acoustic levels in the occupied spaces below. The structural system for the roadways consists of reinforced con- crete moment-resisting frames of the base building below in conjunction with pre-stressed, pre-cast reinforced concrete long-span I-beams supported on isolation pads. A cast-in-place rein- forced concrete slab interconnects the I-beams and acts as a diaphragm. Given that the roadway slab is exposed to the elements, it was designed to allow for movement due to tempera- ture changes; the pre-cast I-beams are fixed at one end and free to slide at the other end. The roadway is exposed to the elements and large temperature changes, but with interior space below the roadway, expansion joints in the roadway slab had to be water-tight. To meet this requirement, these joints were located at 17 m intervals to mini- mize the width of the joint. The design of the parking structure brought along a number of aesthetic and functional challenges. Designers did not want an imposing structure, but difficult geological conditions lim- ited the depth of excavation. Working within these constraints, the parking structure utilizes a shallow floor fram- ing system with two-way concrete flat plate with concrete shear walls for lat- eral support. The compact nine-level parking garage meets all of its parking occurs when the four joints of the rectangular glass units do not lie in the same plane, and it can cause the seal between IGUs to break. Based on the allowable shear deformation of the IGUs, the out-of-plane deflec- tion was limited to L/100, where L is the shorter length of the rectangular unit. To prevent warping of the IGUs, the largest values of pretension are required in areas with sharp geometric changes, such as the vestibules and at the wall corners. Based on these con- ditions, cable diameters vary from 25 to 37 mm and pretension values range from 150 to 400 kN. Multiple System Concrete Base Structure The Terminal Building is divided into the Pier and Gate Zone, Retail Zone, Headhouse Roof Zone, and the Frontage Road Zone. Despite its immense size, the Terminal Building requires only two grid systems to cover the entire footprint of the building.An orthogonal 8,5 × 8 m2 grid was adopted for the entire central facility, which provided optimal use of space for the baggage handling facilities. Meanwhile, the grid utilized for the Gate Zone was a 9 × 11 m2 continuous linear and radial grid along the periphery of the building. The concrete base structure of the Terminal Building employs three distinct structural floor systems in response to functional zones with varying optimal clear-span require- ments. In the linear and radial Gate Zone, a regular, repetitive one-way concrete beam and slab system has been utilized. At locations which gen- erate heavy passenger congestion such as the Baggage Claim Hall, functional requirements called for a relatively column-free space. This was achieved by placing columns within the bag- gage claim belts and having a clear span between belts resulting in struc- tural framing bays of 17 × 16 m2 and employing a waffle slab system for the floor framing above. In the Retail Zone, where maximum flexibility for floor openings and future renova- tions was desired, the floor system utilizes steel framing with composite
  • 6. Structural Engineering International 1/2013 Technical Report 13 requirements within the stipulated height so that its roof aligns with the Departure Level and serves as a green roof for the visitor area. Concluding Remarks The design of the Terminal Building placed a high priority on material effi- ciency and ease of construction. All parts of the building utilized repeti- tive, modular designs that accommo- date construction phasing and permit rapid construction. Ensuring the sta- bility of the individual portions of the Terminal Building throughout SEI Data Block SEI Data Block Owner and operator: Mumbai International Airport Limited Architect, structural engineer, and MEP engineer: Skidmore, Owings & Merrill LLP Local designer and general contractor: Larson and Toubro Limited Steel (t): Approximately 22 000 Concrete (m3 ): Approximately 520 000 Estimated cost (USD million): 1200 Service date: November 2013 the phased construction was an important consideration in select- ing the building’s structural systems. Construction of Phase 1 began in 2008 and was completed in early 2012. By November 2013, both Phases 1 and 2 of the Terminal Building are expected to be fully operational, and at that time the remaining portion of the existing terminal is to be demolished and construction will begin on Phase 3, the gate areas on the eastern pier. Upon completion in 2014, the termi- nal will serve 40 million passengers per annum.