2. Unit-2- Continuous Beams
Steps Calculations/ procedure Reference
1 Cross sectional Dimensions
Effective depth = π . =
Adopt, effective cover= dc = 50mm
Thus, D= dc + deffe
width of beam = width of wall (generally 230, 300 etc.)
2 Loadsο
Dead Load
(a) Self weight of beam = b x D x 25
(b) DL on beam = (given in kN/m)
Total DL = g = (a) + (b)
Live Load = q = (given in kN/m)
***Ultimate loadsο
Dead load = gu = 1.5 x g
Live load = qu = 1.5 x q
3 Design Bending Moment and Shear Forceο
ο· Maximum -ve BM at interior supports
π = πππππππππππ‘ Γ π Γ πΏ + πππππππππππ‘ Γ π Γ πΏ
ο· Maximum +ve BM at Center of span
π = πππππππππππ‘ Γ π Γ πΏ + πππππππππππ‘ Γ π Γ πΏ
ο· Maximum Shear at support (next to end)
π = πππππππππππ‘ Γ π Γ πΏ + πππππππππππ‘ Γ π Γ πΏ
Table no. 12 and 13 of IS 456:2000, pp36
ο· C1, C2, C3ο column of respective table
4 Reinforcementο
Find Steel for M-ve and M+ve π΄ =
.
1 β 1 β
.
ππ
Select diameter (Π€), find area (A Π€) and number of bars
No. of bars=
.
Dia. (Π€) 8 10 12 16 20 25
Area (A Π€) 50 78 113 201 314 490
5 Shear reinforcementο
Find π = Check π β€ π
Clause no 40.1, IS 456: 2000
Table no.20 , IS 456: 2000
Find π
If % of steel is not given find Pt% as under
Table no.19 , IS 456: 2000
C 1 C 2 C 3 C 4 C 4 C 3 C 2 C 1
C 1 C 2 C 2 C 1
C 3 C 4 C 3
B M C O E F F IC IE N T (C O L U M N N O . IN T A B L E 1 2 )
S F C O E F F IC IE N T (C O L U M N N O . IN T A B L E 1 3 )
4. For redistribution of Momentsο
Step no. 3 Changes as below
Find Fixed end moment for each beam AB, BC, CD,β¦. πΉπΈπ =
Find Span moments for each beam AB, BC, CD,β¦. ππππ ππππππ‘π =
Create table Find Final Span moments and End Moments:
Support B C (if required)
process
Span Moment
FEM
(average of AB
& BC)
Span Moment
FEM
(average of CB
& CD)
Span Moment
X1 X2 X3 X4 X5
R %
redistribution
-X1 * R/100
-X3 * R/100
-X5 * R/100
-X3 * R/100
Carry over
-X3 * R/100*(1/2)
-X1 * R/100*(1/2)
-X5 * R/100*(1/2)
-X3 * R/100*(1/2)
Final Moment
Sum sum sum sum Sum
Span Moment
Support
Moment
Span Moment
Support
Moment
Span Moment
5. Unit No.3 - Design of Circular Water Tank
Flexible Base / Not casted monolithically /Not restrained at base
Step No. Calculation /Procedure Referance
1. Thk of Wall
a) 150 mm
b) 30mm per m depth + 50 mm
Provide greater of a) & b)
2. Hoop Tension π =
. .
where πΎ = 9.81ππ/π
3. Find Ast required for 1 m ht.
π΄ =
Minimum steel required = 0.3 % of gross area.
4. Select diameter (Π€) of bar and find spacing
Dia. (Π€) 8 10 12 16 20 25
Area (A Π€) 50 78 113 201 314 490
Spacing = S =
Γ
.
β¦β¦. ο Provide spacing less than actual required.
Provide this steel near both the face.
5. Actual Ast Provided
π΄ . =
π΄ Γ 1000
π
6. Tensile Stress in Concrete
πΆ = ( Γ ) (( ) )
πΉππ π20, πΆ = 1.2 π/ππ , b = 1000,
π΄ = π΄ .
Table 1, IS 3370 Part 2 , PP.7
7. Vertical Distribution Steel
At least 0.3% of gross area.
=
0.3
100
Γ 1000 Γ π‘
Select diameter (Π€) of bar and find spacing
8. Base Slab
i) 150 mm thick slab
Top mesh and bottom mesh of steel 10 ππ β @ 300 ππ .
9 Detailing
See attached
6. Rigid Base / casted monolithically / restrained at base
Approximate Method
Step No. Calculation /Procedure Referance
1. Height of cantilever effect: ππ 1 π π€βππβππ£ππ ππ πππππ‘ππ
2. Hoop Tension π =
.( ).
where, πΎ = 9.81ππ/π
3. Find Ast required for 1 m ht.
π΄ =
Minimum steel required = 0.3 % of gross area.
4. Select diameter (Π€) of bar and find spacing
Dia. (Π€) 8 10 12 16 20 25
Area (A Π€) 50 78 113 201 314 490
Spacing = S =
Γ
.
β¦β¦. ο Provide spacing less than actual required.
Provide this steel near both the face.
5. Actual Ast Provided, π΄ . =
Γ
6. Find thickness of Wall(t)
Tensile Stress in Concrete
πΆ = ( Γ ) (( ) )
πΉππ π20, πΆ = 1.2 π/ππ , b = 1000,
π΄ = π΄ .
Table 1, IS 3370 Part 2 , PP.7
7. Vertical Distribution Steel
At least 0.3% of gross area.
=
0.3
100
Γ 1000 Γ π‘
Select diameter (Π€) of bar and find spacing
8. Design of Bottom cantilever part ( For h )
Max. moment due to cantilever effect π = ( Γ π Γ β) Γ
Where, b = (πΎ Γ π»)
9. Area of Steel
π΄
π
π Γ π Γ π
π β πΉπππ πππππ 2 ππ. 8
π = 115 πΉππ πΉπ β 250
π = 150 πΉππ πΉπ β 415
π = 205 πΉππ πΉπ β 500
10. Haunch Reinforcement
Haunch Reinforcement= Min. steel= (0.3% Γ π Γ π)
11. Base Slab
i) 150 mm thick slab
Top mesh and bottom mesh of steel 10 ππ β @ 300 ππ .
12 Detailing
See attached
7. Rigid Base / casted monolithically / restrained at base
I S code Method
Step No. Calculation /Procedure Referance
1. Thk. Of wall (i) 150mm (ii) 30mm per M depth +50mm
Find π»
π·π‘
2. Hoop Tension π =
.( ).
where, πΎ = 9.81ππ/π
3. Find Ast required for 1 m ht.
π΄ =
Minimum steel required = 0.3 % of gross area.
4. Select diameter (Π€) of bar and find spacing
Dia. (Π€) 8 10 12 16 20 25
Area (A Π€) 50 78 113 201 314 490
Spacing = S =
Γ
.
β¦β¦. ο Provide spacing less than actual required.
Provide this steel near both the face.
5. Actual Ast Provided π΄ . =
Γ
6. Find thickness of Wall(t)
Tensile Stress in Concrete
πΆ = ( Γ ) (( ) )
πΉππ π20, πΆ = 1.2 π/ππ , b = 1000,
π΄ = π΄ .
Table 1, IS 3370 Part 2 , PP.7
7. Vertical Distribution Steel: At least 0.3% of gross area =
.
Γ 1000 Γ π‘
Select diameter (Π€) of bar and find spacing
8. Design of Bottom cantilever part ( For h )
Max. moment due to cantilever effect = π = ( Γ π Γ β) Γ
Where, b = (πΎ Γ π»)
9. Area of Steel, π΄
Γ Γ
π = 115 πΉππ πΉπ β 250, π = 150 πΉππ πΉπ β 415,
π = 205 πΉππ πΉπ β 500
π β πΉπππ πππππ 2 ππ. 8
10. Distribution Steel, = Γ (0.3% Γ π Γ π)
b=1000 , d=effective depth
11. Base Slab, = 150 mm thk
Top mesh and bottom mesh of steel 10 ππ β @ 300 ππ .
12 Detailing
See attached
8. t
H
h
# -(dia)- mm@ -(spacing)- c/c
Hoop Tension Steel
(refer step no. 4)
# -(dia)- mm@ -(spacing)- c/c
Distribution Steel
(refer step no. 7)
Horizontal Steel
Vertical Steel
# -(dia)- mm@ -(spacing)- c/c
(refer step no. 8)
Base slab steel
thk. of
base slab
Detailing of circular water tank with flexible base
t
H
h
# -(dia)- mm@ -(spacing)- c/c
Hoop Tension Steel
(refer step no. 4)
# -(dia)- mm@ -(spacing)- c/c
Distribution Steel
(refer step no. 7)
Horizontal Steel
Vertical Steel
# -(dia)- mm@ -(spacing)- c/c
(refer step no. 11)
Base slab steel
thk. of
base slab
Detailing of circular water tank with rigid base
# -(dia)- mm@ -(spacing)- c/c
Haunch Reinforcement
(refer step no. 10)
# -(dia)- mm@ -(spacing)- c/c
Cantilever BM Steel
(refer step no. 9)
Vertical Steel
9. Design of Rectangular or Square Water Tank
Step No. Calculation /Procedure
1 Design constants
π β ππππ π‘ππππ ππ. 21 πΌπ 456: 2000
π β πΌπ 3370 ππππ‘ πΌπΌο for Fe250=115, Fe415=150, Fe500=205
π = 280/(3π ),
π = ,
π = 1 β (π/3)
2. Thk. Of wall (i) 150mm (ii) 30mm per M depth +50mm (iii) 60mmper meter length
of side
Provide maximum of (i) to (iii)
3 Design of Short wall
(a) Mid span section:
ο· π =
.( ).
where L-length of longer wall
ο· π =
.( ).
ππ
where l-length of short wall
ο· πππ‘ π΅π = π β ππ₯ where x = (t/2)-cover
ο· Steel for net BM π΄
Γ Γ
ο· Steel for pull π΄
ο· Total Steel = π΄ = π΄ + π΄
(b) Corner section:
ο· π =
.( ).
where L-length of longer wall
ο· π =
.( ).
ππ
where l-length of short wall
ο· πππ‘ π΅π = π β ππ₯ where x = (t/2)-cover
ο· Steel for net BM π΄
Γ Γ
ο· Steel for pull π΄
ο· Total Steel = π΄ = π΄ + π΄
4 Design of Long wall
(c) Mid span section:
ο· π =
.( ).
where l-length of short wall
ο· π =
.( ).
ππ
where L-length of long wall
ο· πππ‘ π΅π = π β ππ₯ where x = (t/2)-cover
ο· Steel for net BM π΄
Γ Γ
ο· Steel for pull π΄
ο· Total Steel = π΄ = π΄ + π΄
(d) Corner section:
ο· π =
.( ).
where l -length of short wall
ο· π =
.( ).
ππ
where L-length of long wall
ο· πππ‘ π΅π = π β ππ₯ where x = (t/2)-cover
ο· Steel for net BM π΄
Γ Γ
10. ο· Steel for pull π΄
ο· Total Steel = π΄ = π΄ + π΄
5 Design of Vertical Steel in both wall
Max. moment (cantilever effect) = π = ( Γ πΎ Γ π» Γ β) Γ
π΄ =
π
π Γ π Γ π
Minimum steel required = 0.3 % of gross area.
Ast > Astmin
6 Base Slab, = 200 mm thk
Top mesh and bottom mesh of steel 12 ππ β @ 300 ππ .
7 Detailing
See attached
l
L
L1 L1
L2 L2
S1S2
S1S2
PLAN
11. t
H
h
Distribution Steel
Horizontal Steel
Vertical Steel
Base slab steel
thk. of
base slab
SECTION "L1-L1"
Cantilever BM Steel
Vertical Steel
SECTION "S1-S1"
LONG WALL SHORT WALL
Inner Face of wall
* *
*
* change steel in above case as per wall
t
H
h
Distribution Steel
Horizontal Steel
Vertical Steel
Base slab steel
thk. of
base slab
Cantilever BM Steel
Vertical Steel
SECTION "L2-L2" SECTION "S2-S2"
LONG WALL SHORT WALL
Outer face of wall
* change steel in above case as per wall
*
* *
12. Unit No.4 - Analysis of Prestress.
Cases/ Cable Profiles Calculation / Procedure
1. Tendon placed
concentric
Stress at top edge = +
Stress at bottom edge = β
2. Tendon placed at an
eccentricity
Stress at top edge = + β
.
Stress at bottom edge = β +
.
Where π = at mid span (where, w = DL udl + LL udl)
π = 0 at end section
3. Prestress with Bent
Tendon
Stress at top edge = +
Stress at bottom edge = β
Where π =
( ).
+
W- Point load at center
w = DL udl + LL udl
4. Prestress with
Parabolic Tendon
Stress at top edge = +
Stress at bottom edge = β
Where π = and π€ =
.
13. Unit no. 5.- Losses in Prestress.
Cause Calculation / Procedure Pre-tension Post-
tension
1. Loss of stress due to
elastic shortening of
concrete
βπ = π. π
Where β
βπ = loss of prestress
m = modular ratio =
π = stress in concrete οΌ ο»
2. Loss of stress due to
creep of concrete
βπ = β . π. π if β is given in coefficient
Or
βπ = β . π . πΈ if β is given per π
ππ
οΌ οΌ
3. Loss of stress due to
shrinkage of concrete
βπ = πβπππππππ π π‘ππππ Γ πΈ
οΌ οΌ
4. Relaxation Loss 1% to 5 % of initial stress.
Or whichever value given in example οΌ οΌ
5. Loss due to anchorage
slip
βπ =
βπΌ . πΈ
πΏ
Where, βπΌ = effective slip
πΈ = Youngβs modulus for tendon
L = Length of Tendon
ο» οΌ
6. Loss due Friction
( Wobble effect /
length effect)
π = π (1 β ππΌ β ππ₯ )
Where -
π = prestressing force in tendon at any distance x
from jack.
π = prestressing force at jacking end.
π = co-efficient of friction in curve 0.55-for
smooth conc.& 0.30- for steel fixed in duct
πΌ = cumulative angle in radian
π= friction coefficient (0 to 0.0066 )
βπ = π . π. π₯
π = πΌπππ‘πππ ππππ π‘πππ π πππ πππππ
ο» οΌ
Total loss of stress βπ = β(1+2+3+4) β (2+3+4
+5+6)
% loss of stress
=
βπ
πΌπππ‘πππ ππ‘πππ π
Γ 100
14. Unit no. 6.
Design of Pre-stressed member (Beam)
Step Procedure (for Rectangular beam section)
1 Calculate live load moment - ML
π =
π€π
8
2 Section Modulus and width of Section: π =
Choose convenient depth, π = Γ π
Now find βbβ for section using formula, π =
3 Prestressing Force: π = Γ π΄
4 Steel requirementsο π΄ =
select dia. of wire and number of wires
5 Dead load Moment = MD
DL= w = b x d x 25 ο π =
6 Eccentricity (e)
π =
2 π + π
2 π
7 Drawing:
e
b
d
PP
L
Longitudinal Sectional Elevation
Section
15. Unit no. 6.
Design of Pre-stressed member (Beam)
Step Procedure (for Symmetrical I beam section)
1 Safe Stressesο
Concrete:
At transfer, safe compressive stress = fr = 0.5fck
At service, safe compressive stress = fc = 0.4fck
Permissible tensile stress = ft = 0.129 π
Steel: Safe stress in steel at service = 60% of ultimate stress
Ultimate stress = 1500N/sqmm
2
Calculate live load moment - π =
Dead load Moment = MD = 20% of ML
Total BM =Mt = MD +ML
3 Overall depth βdβ in mm ο π = π π
Where k = coefficient = 35 and Mt is in kNm
4 Prestressing Force (P)ο π =
.
5 Cross Sectional Properties:
ο· assume value of βxβ in range of 120 mm to 150mm
ο· Area of concrete required =π΄ = π/(0.5π )
ο· Find bf using calculated Ac, using equation below
π΄ = (π₯ Γ ππ) Γ 2 + (π β 2π₯) Γ π₯
ο· Provide bf greater than required
ο· Find Actual area provided = A
ο· Find Section modulus = Z = I/y
6 Steel requirements:
Area of tendons =As = (P/ safe stress in steel at service)
Choose suitable diameter of wire and find number of wires
Number of wires = As/ Area of single wire
π = ππ‘πππ π ππ π π‘πππ Γ πππ‘π’ππ π‘πππππ ππππ ππππ£ππππ
π =
π
πππ π ππππ‘ππ
=
π
(100 β % πππ π )
100
7 Check for stressesο
ο· Assume eccentricity (e) of cable at certain dist below NA
(a) At initial stresses , at transfer
π / = Β± β
.
< frβ¦..OK
(b) Final stresses, at services
π / = Β± Β± β
.
< fcβ¦.OK
8 Design Summary and drawing showing bf,d,e,x,P
x
x
xd
bf