SlideShare a Scribd company logo
Utility Plant Upgrade
with Redundant, PlantPAx Platform
Tom Brown – Program Manager, Banks Integration Group, Inc.
June 8, 2016
Agenda
Lessons Learned
System Design
System Selection Process
Project Overview
Banks Integration Group Background
 Who is Banks Integration Group?
 Rockwell Automation Solution Partner
 Focus on Process Automation primarily in Life Sciences
 Located in Northern California – Servicing the West Coast
Project Overview
 Central Process Utility Plant – CPUP
Refrigerated Water
(5) Chillers
(6) Cooling Towers
Compressed Air
(4) 300 HP Compressors
Control System Upgrade Justification
 Mixed I/O between RW and CA systems
 Obsolete PLC and HMI Hardware with numerous code issues
 Winview HMI platform on desktop PCs with PLC-5® controllers
 Dead code and legacy configuration still on system due to difficulty of
making changes to existing system
 No remote access or individual user logins
 DH+ communication bandwidth issues
 Controllers/Racks in with 480V power on compressors or MCC’s
Original Control System Architecture
 Hardware
 2 Allen-Bradley ® 5/80 PLC’s shared between the RW/CA systems
 4 Allen-Bradley SLC PLC’s, one per compressor
 2 HMI Stations shared between buildings
 Software
 RSLogix™ 5, RSLogix 500
 Winview HMI Software
 Network
 3 DH+ networks spanning several buildings
 1 SCADA and Inter-Processor Communications Network
 2 Remote I/O Networks with a Modbus Interface
Project Challenges
 The control system is large and spread across many buildings
 Project impacted 22 control panels (either new or existing) required
the upgrade of 7 VFDs
 100% uptime on all utilities throughout the upgrade
 Existing process equipment had a large number of existing failures
 Large number of drawings and documents
Project Challenges
 Desire to use new technologies
 Server Virtualization
 Pre- tested control modules – Process Objects for Life Science
 Ethernet/IP (DLR) instead of existing campus ControlNet standard
Agenda
Lessons Learned
System Design
System Selection Process
Project Overview
System Selection
 Client specified a Rockwell Automation Control System
 Two Pre-design studies were completed to select the best approach for
the upgrade
 PlantPAx® for Life Science Study
 Network Comparison Study
PlantPAx for Life Science Study
 Study Objective
 Evaluate if PlantPAx Process Objects were a “good fit” for the utilities
upgrade
 Are they robust?
 Are they modular?
 Do they increase visibility and ease of troubleshooting?
 Banks Integration Group gave an interactive presentation discussing the
advantages and disadvantages of the Process Objects
PlantPax for Life Science
Rockwell Automation Library – “Out of the Box”
Advantages of PlantPAx for Life
Science Solution
 Aligned with S88.01 Batch Control Standard
 Able to divide equipment by Area and Unit
 Decreased programming and validation cost
 Modules are preprogrammed and customized for the life sciences
 Modules are pre-tested by Rockwell
 Increased system visibility
 PlantPAx built-in displays give operations the ability to more easily
troubleshoot abnormal conditions
Process Objects for Life Science
Benefits
 Pre-programmed modules
Process Objects for Life Science
Benefits
 Pre-validated following GAMP Life Cycle Model
Process Objects for Life Science
Benefits
 Increased visibility
Process Objects for Life Science
Benefits
 Reusable Global Object Library
Process Objects for Life Science
Benefits
Disadvantages of PlantPAx for Life
Science Solution
 With flexibility comes increased complexity
 Each module is designed to accommodate several device
configurations, which leads to a more complicated configuration
 Module PLC code is locked
 PlantPAx Process Objects for Life Science is licensed per PLC
 Faceplates were more complicated than existing design
Network Comparison Study
 Collaborated with Rockwell Automation Network & Security Services
 Network Study Objective
 Evaluate control system network technologies for:
 Peer-to-peer communications
 I/O Communications
 Scope Deliverables
 Merits and disadvantages of EtherNet/IP and ControlNet
 Network diagrams and design
 Network Calculations
 Summary and recommendation
Network Calculations – ControlNet
 Network Bandwidth Calculation – 16.5% Utilization
Network Calculations – EtherNet/IP
 Network Bridge Module is the bottleneck – 17.9% Utilization
Ultimately Chose EtherNet/IP
 EtherNet/IP with a Device Level Ring topology
 Three networks created based on equipment
 Refrigerated Water
 Compressed Air
 Shared Equipment
 Fiber media used in segments connecting buildings or distances greater
than 300 ft.
DLR Design
DLR Diagnostics
 Status screen created for each network
Agenda
Lessons Learned
System Design
System Selection Process
Project Overview
System Design
System Design
SCADA Architecture
SCADA Components
 Virtual servers hosted on an HP
blade server system
 Wyse Thin Clients
 Wyse ThinOS, based on Linux
platform
 Touch screen OIT’s
New Control System Architecture
 Hardware
 2 Redundant ControlLogix® L73 processors for the RW system
 1 ControlLogix L72 processor for the CA Supervisor system
 4 ControlLogix L72 processors, one per compressor
 6 HMI Client Stations distributed between 3 buildings
 RW and CA I/O is completely segregated
 Software
 RSLogix 5000, v20.03
 FactoryTalk View SE, v7.00.00
 Network
 All PLC’s now on Automation Network
 3 Device Level Rings (DLR’s) used for Remote I/O and VFD’s
PlantPAx Simplified the System
 Existing System
 PLC code - 5000 rungs
 HMI - 1050 graphics
 Electrical Drawings - 400
 Updated System
 PLC code – 2000 rungs
 HMI – 143 graphics
 77 Process Object graphics
 66 Custom graphics
 Electrical Drawings - 450
System Features
 Remote Interface
 Remote connections via Terminal Server
 View only connection via FactoryTalk® Viewpoint
 System Redundancy
 SCADA Servers, PLC’s, Network Power Supplies
 Network and Power Supply Diagnostics
 Node Based Security
 Ethernet VFD’s providing increased visibility for troubleshooting
Agenda
Lessons Learned
System Design
System Selection Process
Project Overview
Lessons Learned
 As-Built existing design documents prior to starting detailed design
 Graphic Standards for Common Plant Interface
 VM’s allowed for easy “on-site” migration
 Working with local Electrical Subcontractor eased installation
Lessons Learned
 Executing a DLR Hardware FAT reduced startup time
Questions
Tom Brown – Program Manager, Banks Integration Group, Inc.
June 8, 2016

More Related Content

What's hot

Ni week 2018 DMC presentation IoT
Ni week 2018 DMC presentation IoTNi week 2018 DMC presentation IoT
Ni week 2018 DMC presentation IoTDMC, Inc.
 
Open programmable architecture for java enabled network devices
Open programmable architecture for java enabled network devicesOpen programmable architecture for java enabled network devices
Open programmable architecture for java enabled network devicesTal Lavian Ph.D.
 
Open Programmable Architecture for Java-enabled Network Devices
Open Programmable Architecture for Java-enabled Network DevicesOpen Programmable Architecture for Java-enabled Network Devices
Open Programmable Architecture for Java-enabled Network DevicesTal Lavian Ph.D.
 
Qualifying a high performance memory subsysten for Functional Safety
Qualifying a high performance memory subsysten for Functional SafetyQualifying a high performance memory subsysten for Functional Safety
Qualifying a high performance memory subsysten for Functional SafetyPankaj Singh
 
Key Projects Completed at Vodafone
Key Projects Completed at VodafoneKey Projects Completed at Vodafone
Key Projects Completed at VodafonePaul Walton
 
Network rollout-solution-brochure
Network rollout-solution-brochureNetwork rollout-solution-brochure
Network rollout-solution-brochureTaha77
 
Supervisory control and data acquisition
Supervisory control and data acquisitionSupervisory control and data acquisition
Supervisory control and data acquisitionudaykmr
 
Cyber Security in Substation Automation (IEC 61850)
Cyber Security in Substation Automation (IEC 61850)Cyber Security in Substation Automation (IEC 61850)
Cyber Security in Substation Automation (IEC 61850)Nikandrov Maxim
 
Platform Observability and Infrastructure Closed Loops
Platform Observability and Infrastructure Closed LoopsPlatform Observability and Infrastructure Closed Loops
Platform Observability and Infrastructure Closed LoopsLiz Warner
 
Industrial Ethernet Facts - The 5 major technologies
Industrial Ethernet Facts - The 5 major technologiesIndustrial Ethernet Facts - The 5 major technologies
Industrial Ethernet Facts - The 5 major technologiesStephane Potier
 
B5 g2 enhanced+protection+functionality+with+iec+61850+and+goose
B5 g2 enhanced+protection+functionality+with+iec+61850+and+gooseB5 g2 enhanced+protection+functionality+with+iec+61850+and+goose
B5 g2 enhanced+protection+functionality+with+iec+61850+and+gooseOmeal Ahmed
 
Industrial Ethernet, Part 2: Case Studies
Industrial Ethernet,Part 2: Case StudiesIndustrial Ethernet,Part 2: Case Studies
Industrial Ethernet, Part 2: Case StudiesControlEng
 
Unified methodology for effective correlation of soc power
Unified methodology for effective correlation of soc powerUnified methodology for effective correlation of soc power
Unified methodology for effective correlation of soc powerPankaj Singh
 
Overcoming challenges of_verifying complex mixed signal designs
Overcoming challenges of_verifying complex mixed signal designsOvercoming challenges of_verifying complex mixed signal designs
Overcoming challenges of_verifying complex mixed signal designsPankaj Singh
 
Asset Insight Manager Introduction 2014 (2)
Asset Insight Manager Introduction 2014 (2)Asset Insight Manager Introduction 2014 (2)
Asset Insight Manager Introduction 2014 (2)Dean Bishop
 
Distributed Control System
Distributed Control SystemDistributed Control System
Distributed Control System3abooodi
 
CaseStudy_EnergyETC
CaseStudy_EnergyETCCaseStudy_EnergyETC
CaseStudy_EnergyETCSteve Jones
 
Nakina NOS Overview
Nakina NOS OverviewNakina NOS Overview
Nakina NOS Overviewhal2005
 
Plant check Mobile Operator Rounds English
Plant check Mobile Operator Rounds EnglishPlant check Mobile Operator Rounds English
Plant check Mobile Operator Rounds EnglishYakup Bozkurt
 

What's hot (20)

Ni week 2018 DMC presentation IoT
Ni week 2018 DMC presentation IoTNi week 2018 DMC presentation IoT
Ni week 2018 DMC presentation IoT
 
Open programmable architecture for java enabled network devices
Open programmable architecture for java enabled network devicesOpen programmable architecture for java enabled network devices
Open programmable architecture for java enabled network devices
 
Open Programmable Architecture for Java-enabled Network Devices
Open Programmable Architecture for Java-enabled Network DevicesOpen Programmable Architecture for Java-enabled Network Devices
Open Programmable Architecture for Java-enabled Network Devices
 
Qualifying a high performance memory subsysten for Functional Safety
Qualifying a high performance memory subsysten for Functional SafetyQualifying a high performance memory subsysten for Functional Safety
Qualifying a high performance memory subsysten for Functional Safety
 
Key Projects Completed at Vodafone
Key Projects Completed at VodafoneKey Projects Completed at Vodafone
Key Projects Completed at Vodafone
 
Network rollout-solution-brochure
Network rollout-solution-brochureNetwork rollout-solution-brochure
Network rollout-solution-brochure
 
Supervisory control and data acquisition
Supervisory control and data acquisitionSupervisory control and data acquisition
Supervisory control and data acquisition
 
Cyber Security in Substation Automation (IEC 61850)
Cyber Security in Substation Automation (IEC 61850)Cyber Security in Substation Automation (IEC 61850)
Cyber Security in Substation Automation (IEC 61850)
 
Platform Observability and Infrastructure Closed Loops
Platform Observability and Infrastructure Closed LoopsPlatform Observability and Infrastructure Closed Loops
Platform Observability and Infrastructure Closed Loops
 
Industrial Ethernet Facts - The 5 major technologies
Industrial Ethernet Facts - The 5 major technologiesIndustrial Ethernet Facts - The 5 major technologies
Industrial Ethernet Facts - The 5 major technologies
 
Chromatography Data System: Expand to the Enterprise
Chromatography Data System: Expand to the Enterprise Chromatography Data System: Expand to the Enterprise
Chromatography Data System: Expand to the Enterprise
 
B5 g2 enhanced+protection+functionality+with+iec+61850+and+goose
B5 g2 enhanced+protection+functionality+with+iec+61850+and+gooseB5 g2 enhanced+protection+functionality+with+iec+61850+and+goose
B5 g2 enhanced+protection+functionality+with+iec+61850+and+goose
 
Industrial Ethernet, Part 2: Case Studies
Industrial Ethernet,Part 2: Case StudiesIndustrial Ethernet,Part 2: Case Studies
Industrial Ethernet, Part 2: Case Studies
 
Unified methodology for effective correlation of soc power
Unified methodology for effective correlation of soc powerUnified methodology for effective correlation of soc power
Unified methodology for effective correlation of soc power
 
Overcoming challenges of_verifying complex mixed signal designs
Overcoming challenges of_verifying complex mixed signal designsOvercoming challenges of_verifying complex mixed signal designs
Overcoming challenges of_verifying complex mixed signal designs
 
Asset Insight Manager Introduction 2014 (2)
Asset Insight Manager Introduction 2014 (2)Asset Insight Manager Introduction 2014 (2)
Asset Insight Manager Introduction 2014 (2)
 
Distributed Control System
Distributed Control SystemDistributed Control System
Distributed Control System
 
CaseStudy_EnergyETC
CaseStudy_EnergyETCCaseStudy_EnergyETC
CaseStudy_EnergyETC
 
Nakina NOS Overview
Nakina NOS OverviewNakina NOS Overview
Nakina NOS Overview
 
Plant check Mobile Operator Rounds English
Plant check Mobile Operator Rounds EnglishPlant check Mobile Operator Rounds English
Plant check Mobile Operator Rounds English
 

Similar to Central Process Utility Plant controls upgrade required 100% uptime

Industrial Automation rtPAC System
Industrial Automation  rtPAC SystemIndustrial Automation  rtPAC System
Industrial Automation rtPAC Systemsanjaya1984
 
Why rthplc v2
Why rthplc v2Why rthplc v2
Why rthplc v2tanima123
 
Custom Modular Extrusion
Custom Modular ExtrusionCustom Modular Extrusion
Custom Modular ExtrusionJeff West
 
OCP Telco Engineering Workshop at BCE2017
OCP Telco Engineering Workshop at BCE2017OCP Telco Engineering Workshop at BCE2017
OCP Telco Engineering Workshop at BCE2017Radisys Corporation
 
Aerospace maintenance facility increases utilization by 50%, saves money
Aerospace maintenance facility increases utilization by 50%, saves moneyAerospace maintenance facility increases utilization by 50%, saves money
Aerospace maintenance facility increases utilization by 50%, saves moneyIntelligentManufacturingInstitute
 
Bausch lomb leverages plant p ax_rev1
Bausch  lomb leverages plant p ax_rev1Bausch  lomb leverages plant p ax_rev1
Bausch lomb leverages plant p ax_rev1Brian Thomas
 
Advanced Supervision System for Coke Plants
Advanced Supervision System for Coke PlantsAdvanced Supervision System for Coke Plants
Advanced Supervision System for Coke PlantsSchneider Electric
 
2017 Atlanta Regional User Seminar - Virtualizing Industrial Control Systems ...
2017 Atlanta Regional User Seminar - Virtualizing Industrial Control Systems ...2017 Atlanta Regional User Seminar - Virtualizing Industrial Control Systems ...
2017 Atlanta Regional User Seminar - Virtualizing Industrial Control Systems ...OPAL-RT TECHNOLOGIES
 
RA Implementation of PlantPAx Systems.pptx
RA Implementation of PlantPAx Systems.pptxRA Implementation of PlantPAx Systems.pptx
RA Implementation of PlantPAx Systems.pptxAjay Gangakhedkar
 
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...Schneider Electric
 
RA TechED 2019 - PR03 - Implementation of PlantPAx Systems
RA TechED 2019 - PR03 - Implementation of PlantPAx SystemsRA TechED 2019 - PR03 - Implementation of PlantPAx Systems
RA TechED 2019 - PR03 - Implementation of PlantPAx SystemsRockwell Automation
 
5 pipeline arch_rationale
5 pipeline arch_rationale5 pipeline arch_rationale
5 pipeline arch_rationalevideos
 
Nagios Conference 2011 - Dave Williams - Nagios In The Real World - The Datac...
Nagios Conference 2011 - Dave Williams - Nagios In The Real World - The Datac...Nagios Conference 2011 - Dave Williams - Nagios In The Real World - The Datac...
Nagios Conference 2011 - Dave Williams - Nagios In The Real World - The Datac...Nagios
 
Michael_Joshua_Validation
Michael_Joshua_ValidationMichael_Joshua_Validation
Michael_Joshua_ValidationMichaelJoshua
 
InSource 2017 IIoT Roadshow: Collecting and Moving Data
InSource 2017 IIoT Roadshow: Collecting and Moving DataInSource 2017 IIoT Roadshow: Collecting and Moving Data
InSource 2017 IIoT Roadshow: Collecting and Moving DataInSource Solutions
 
Naveen nimmu sdn future of networking
Naveen nimmu sdn   future of networkingNaveen nimmu sdn   future of networking
Naveen nimmu sdn future of networkingOpenSourceIndia
 
Naveen nimmu sdn future of networking
Naveen nimmu sdn   future of networkingNaveen nimmu sdn   future of networking
Naveen nimmu sdn future of networkingsuniltomar04
 
migrating your dcs system to plantpax-phpapp01
migrating your dcs system to plantpax-phpapp01migrating your dcs system to plantpax-phpapp01
migrating your dcs system to plantpax-phpapp01Shashi Ranjan Singh
 

Similar to Central Process Utility Plant controls upgrade required 100% uptime (20)

Industrial Automation rtPAC System
Industrial Automation  rtPAC SystemIndustrial Automation  rtPAC System
Industrial Automation rtPAC System
 
Why rthplc v2
Why rthplc v2Why rthplc v2
Why rthplc v2
 
Custom Modular Extrusion
Custom Modular ExtrusionCustom Modular Extrusion
Custom Modular Extrusion
 
OCP Telco Engineering Workshop at BCE2017
OCP Telco Engineering Workshop at BCE2017OCP Telco Engineering Workshop at BCE2017
OCP Telco Engineering Workshop at BCE2017
 
Aerospace maintenance facility increases utilization by 50%, saves money
Aerospace maintenance facility increases utilization by 50%, saves moneyAerospace maintenance facility increases utilization by 50%, saves money
Aerospace maintenance facility increases utilization by 50%, saves money
 
Bausch lomb leverages plant p ax_rev1
Bausch  lomb leverages plant p ax_rev1Bausch  lomb leverages plant p ax_rev1
Bausch lomb leverages plant p ax_rev1
 
Advanced Supervision System for Coke Plants
Advanced Supervision System for Coke PlantsAdvanced Supervision System for Coke Plants
Advanced Supervision System for Coke Plants
 
gesa_sol.ppt
gesa_sol.pptgesa_sol.ppt
gesa_sol.ppt
 
2017 Atlanta Regional User Seminar - Virtualizing Industrial Control Systems ...
2017 Atlanta Regional User Seminar - Virtualizing Industrial Control Systems ...2017 Atlanta Regional User Seminar - Virtualizing Industrial Control Systems ...
2017 Atlanta Regional User Seminar - Virtualizing Industrial Control Systems ...
 
Dcs capabilities
Dcs capabilitiesDcs capabilities
Dcs capabilities
 
RA Implementation of PlantPAx Systems.pptx
RA Implementation of PlantPAx Systems.pptxRA Implementation of PlantPAx Systems.pptx
RA Implementation of PlantPAx Systems.pptx
 
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
 
RA TechED 2019 - PR03 - Implementation of PlantPAx Systems
RA TechED 2019 - PR03 - Implementation of PlantPAx SystemsRA TechED 2019 - PR03 - Implementation of PlantPAx Systems
RA TechED 2019 - PR03 - Implementation of PlantPAx Systems
 
5 pipeline arch_rationale
5 pipeline arch_rationale5 pipeline arch_rationale
5 pipeline arch_rationale
 
Nagios Conference 2011 - Dave Williams - Nagios In The Real World - The Datac...
Nagios Conference 2011 - Dave Williams - Nagios In The Real World - The Datac...Nagios Conference 2011 - Dave Williams - Nagios In The Real World - The Datac...
Nagios Conference 2011 - Dave Williams - Nagios In The Real World - The Datac...
 
Michael_Joshua_Validation
Michael_Joshua_ValidationMichael_Joshua_Validation
Michael_Joshua_Validation
 
InSource 2017 IIoT Roadshow: Collecting and Moving Data
InSource 2017 IIoT Roadshow: Collecting and Moving DataInSource 2017 IIoT Roadshow: Collecting and Moving Data
InSource 2017 IIoT Roadshow: Collecting and Moving Data
 
Naveen nimmu sdn future of networking
Naveen nimmu sdn   future of networkingNaveen nimmu sdn   future of networking
Naveen nimmu sdn future of networking
 
Naveen nimmu sdn future of networking
Naveen nimmu sdn   future of networkingNaveen nimmu sdn   future of networking
Naveen nimmu sdn future of networking
 
migrating your dcs system to plantpax-phpapp01
migrating your dcs system to plantpax-phpapp01migrating your dcs system to plantpax-phpapp01
migrating your dcs system to plantpax-phpapp01
 

More from Brian Thomas

Justifying Migration of legacy process control systems
Justifying Migration of legacy process control systemsJustifying Migration of legacy process control systems
Justifying Migration of legacy process control systemsBrian Thomas
 
OnTrack CIP Validation
OnTrack CIP ValidationOnTrack CIP Validation
OnTrack CIP ValidationBrian Thomas
 
Produced Water Handling System Upgrade
Produced Water Handling System UpgradeProduced Water Handling System Upgrade
Produced Water Handling System UpgradeBrian Thomas
 
Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Brian Thomas
 
Food Safety Modernization Act (FSMA) regulatory requirements by FDA
Food Safety Modernization Act (FSMA) regulatory requirements by FDAFood Safety Modernization Act (FSMA) regulatory requirements by FDA
Food Safety Modernization Act (FSMA) regulatory requirements by FDABrian Thomas
 
Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...
Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...
Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...Brian Thomas
 
DCS migration - zero downtime upgrade
DCS migration - zero downtime upgradeDCS migration - zero downtime upgrade
DCS migration - zero downtime upgradeBrian Thomas
 
Zero downtime upgrate for dcs migration Thermo Systems
Zero downtime upgrate for dcs migration Thermo SystemsZero downtime upgrate for dcs migration Thermo Systems
Zero downtime upgrate for dcs migration Thermo SystemsBrian Thomas
 

More from Brian Thomas (8)

Justifying Migration of legacy process control systems
Justifying Migration of legacy process control systemsJustifying Migration of legacy process control systems
Justifying Migration of legacy process control systems
 
OnTrack CIP Validation
OnTrack CIP ValidationOnTrack CIP Validation
OnTrack CIP Validation
 
Produced Water Handling System Upgrade
Produced Water Handling System UpgradeProduced Water Handling System Upgrade
Produced Water Handling System Upgrade
 
Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)
 
Food Safety Modernization Act (FSMA) regulatory requirements by FDA
Food Safety Modernization Act (FSMA) regulatory requirements by FDAFood Safety Modernization Act (FSMA) regulatory requirements by FDA
Food Safety Modernization Act (FSMA) regulatory requirements by FDA
 
Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...
Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...
Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...
 
DCS migration - zero downtime upgrade
DCS migration - zero downtime upgradeDCS migration - zero downtime upgrade
DCS migration - zero downtime upgrade
 
Zero downtime upgrate for dcs migration Thermo Systems
Zero downtime upgrate for dcs migration Thermo SystemsZero downtime upgrate for dcs migration Thermo Systems
Zero downtime upgrate for dcs migration Thermo Systems
 

Recently uploaded

What's New in Teams Calling, Meetings and Devices April 2024
What's New in Teams Calling, Meetings and Devices April 2024What's New in Teams Calling, Meetings and Devices April 2024
What's New in Teams Calling, Meetings and Devices April 2024Stephanie Beckett
 
"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor TurskyiFwdays
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...Product School
 
Demystifying gRPC in .Net by John Staveley
Demystifying gRPC in .Net by John StaveleyDemystifying gRPC in .Net by John Staveley
Demystifying gRPC in .Net by John StaveleyJohn Staveley
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxAbida Shariff
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Tobias Schneck
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...Product School
 
AI revolution and Salesforce, Jiří Karpíšek
AI revolution and Salesforce, Jiří KarpíšekAI revolution and Salesforce, Jiří Karpíšek
AI revolution and Salesforce, Jiří KarpíšekCzechDreamin
 
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)Julian Hyde
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...Product School
 
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo DiehlFuture Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo DiehlPeter Udo Diehl
 
UiPath Test Automation using UiPath Test Suite series, part 2
UiPath Test Automation using UiPath Test Suite series, part 2UiPath Test Automation using UiPath Test Suite series, part 2
UiPath Test Automation using UiPath Test Suite series, part 2DianaGray10
 
Introduction to Open Source RAG and RAG Evaluation
Introduction to Open Source RAG and RAG EvaluationIntroduction to Open Source RAG and RAG Evaluation
Introduction to Open Source RAG and RAG EvaluationZilliz
 
IESVE for Early Stage Design and Planning
IESVE for Early Stage Design and PlanningIESVE for Early Stage Design and Planning
IESVE for Early Stage Design and PlanningIES VE
 
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptxUnpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptxDavid Michel
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...Product School
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfCheryl Hung
 
Speed Wins: From Kafka to APIs in Minutes
Speed Wins: From Kafka to APIs in MinutesSpeed Wins: From Kafka to APIs in Minutes
Speed Wins: From Kafka to APIs in Minutesconfluent
 
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya HalderCustom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya HalderCzechDreamin
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...Product School
 

Recently uploaded (20)

What's New in Teams Calling, Meetings and Devices April 2024
What's New in Teams Calling, Meetings and Devices April 2024What's New in Teams Calling, Meetings and Devices April 2024
What's New in Teams Calling, Meetings and Devices April 2024
 
"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
 
Demystifying gRPC in .Net by John Staveley
Demystifying gRPC in .Net by John StaveleyDemystifying gRPC in .Net by John Staveley
Demystifying gRPC in .Net by John Staveley
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
AI revolution and Salesforce, Jiří Karpíšek
AI revolution and Salesforce, Jiří KarpíšekAI revolution and Salesforce, Jiří Karpíšek
AI revolution and Salesforce, Jiří Karpíšek
 
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo DiehlFuture Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
 
UiPath Test Automation using UiPath Test Suite series, part 2
UiPath Test Automation using UiPath Test Suite series, part 2UiPath Test Automation using UiPath Test Suite series, part 2
UiPath Test Automation using UiPath Test Suite series, part 2
 
Introduction to Open Source RAG and RAG Evaluation
Introduction to Open Source RAG and RAG EvaluationIntroduction to Open Source RAG and RAG Evaluation
Introduction to Open Source RAG and RAG Evaluation
 
IESVE for Early Stage Design and Planning
IESVE for Early Stage Design and PlanningIESVE for Early Stage Design and Planning
IESVE for Early Stage Design and Planning
 
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptxUnpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 
Speed Wins: From Kafka to APIs in Minutes
Speed Wins: From Kafka to APIs in MinutesSpeed Wins: From Kafka to APIs in Minutes
Speed Wins: From Kafka to APIs in Minutes
 
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya HalderCustom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
 

Central Process Utility Plant controls upgrade required 100% uptime

  • 1. Utility Plant Upgrade with Redundant, PlantPAx Platform Tom Brown – Program Manager, Banks Integration Group, Inc. June 8, 2016
  • 2. Agenda Lessons Learned System Design System Selection Process Project Overview
  • 3. Banks Integration Group Background  Who is Banks Integration Group?  Rockwell Automation Solution Partner  Focus on Process Automation primarily in Life Sciences  Located in Northern California – Servicing the West Coast
  • 4. Project Overview  Central Process Utility Plant – CPUP Refrigerated Water (5) Chillers (6) Cooling Towers Compressed Air (4) 300 HP Compressors
  • 5. Control System Upgrade Justification  Mixed I/O between RW and CA systems  Obsolete PLC and HMI Hardware with numerous code issues  Winview HMI platform on desktop PCs with PLC-5® controllers  Dead code and legacy configuration still on system due to difficulty of making changes to existing system  No remote access or individual user logins  DH+ communication bandwidth issues  Controllers/Racks in with 480V power on compressors or MCC’s
  • 6. Original Control System Architecture  Hardware  2 Allen-Bradley ® 5/80 PLC’s shared between the RW/CA systems  4 Allen-Bradley SLC PLC’s, one per compressor  2 HMI Stations shared between buildings  Software  RSLogix™ 5, RSLogix 500  Winview HMI Software  Network  3 DH+ networks spanning several buildings  1 SCADA and Inter-Processor Communications Network  2 Remote I/O Networks with a Modbus Interface
  • 7. Project Challenges  The control system is large and spread across many buildings  Project impacted 22 control panels (either new or existing) required the upgrade of 7 VFDs  100% uptime on all utilities throughout the upgrade  Existing process equipment had a large number of existing failures  Large number of drawings and documents
  • 8. Project Challenges  Desire to use new technologies  Server Virtualization  Pre- tested control modules – Process Objects for Life Science  Ethernet/IP (DLR) instead of existing campus ControlNet standard
  • 9. Agenda Lessons Learned System Design System Selection Process Project Overview
  • 10. System Selection  Client specified a Rockwell Automation Control System  Two Pre-design studies were completed to select the best approach for the upgrade  PlantPAx® for Life Science Study  Network Comparison Study
  • 11. PlantPAx for Life Science Study  Study Objective  Evaluate if PlantPAx Process Objects were a “good fit” for the utilities upgrade  Are they robust?  Are they modular?  Do they increase visibility and ease of troubleshooting?  Banks Integration Group gave an interactive presentation discussing the advantages and disadvantages of the Process Objects
  • 12. PlantPax for Life Science Rockwell Automation Library – “Out of the Box”
  • 13. Advantages of PlantPAx for Life Science Solution  Aligned with S88.01 Batch Control Standard  Able to divide equipment by Area and Unit  Decreased programming and validation cost  Modules are preprogrammed and customized for the life sciences  Modules are pre-tested by Rockwell  Increased system visibility  PlantPAx built-in displays give operations the ability to more easily troubleshoot abnormal conditions
  • 14. Process Objects for Life Science Benefits  Pre-programmed modules
  • 15. Process Objects for Life Science Benefits  Pre-validated following GAMP Life Cycle Model
  • 16. Process Objects for Life Science Benefits  Increased visibility
  • 17. Process Objects for Life Science Benefits  Reusable Global Object Library
  • 18. Process Objects for Life Science Benefits
  • 19. Disadvantages of PlantPAx for Life Science Solution  With flexibility comes increased complexity  Each module is designed to accommodate several device configurations, which leads to a more complicated configuration  Module PLC code is locked  PlantPAx Process Objects for Life Science is licensed per PLC  Faceplates were more complicated than existing design
  • 20. Network Comparison Study  Collaborated with Rockwell Automation Network & Security Services  Network Study Objective  Evaluate control system network technologies for:  Peer-to-peer communications  I/O Communications  Scope Deliverables  Merits and disadvantages of EtherNet/IP and ControlNet  Network diagrams and design  Network Calculations  Summary and recommendation
  • 21. Network Calculations – ControlNet  Network Bandwidth Calculation – 16.5% Utilization
  • 22. Network Calculations – EtherNet/IP  Network Bridge Module is the bottleneck – 17.9% Utilization
  • 23. Ultimately Chose EtherNet/IP  EtherNet/IP with a Device Level Ring topology  Three networks created based on equipment  Refrigerated Water  Compressed Air  Shared Equipment  Fiber media used in segments connecting buildings or distances greater than 300 ft.
  • 25. DLR Diagnostics  Status screen created for each network
  • 26. Agenda Lessons Learned System Design System Selection Process Project Overview
  • 30. SCADA Components  Virtual servers hosted on an HP blade server system  Wyse Thin Clients  Wyse ThinOS, based on Linux platform  Touch screen OIT’s
  • 31. New Control System Architecture  Hardware  2 Redundant ControlLogix® L73 processors for the RW system  1 ControlLogix L72 processor for the CA Supervisor system  4 ControlLogix L72 processors, one per compressor  6 HMI Client Stations distributed between 3 buildings  RW and CA I/O is completely segregated  Software  RSLogix 5000, v20.03  FactoryTalk View SE, v7.00.00  Network  All PLC’s now on Automation Network  3 Device Level Rings (DLR’s) used for Remote I/O and VFD’s
  • 32. PlantPAx Simplified the System  Existing System  PLC code - 5000 rungs  HMI - 1050 graphics  Electrical Drawings - 400  Updated System  PLC code – 2000 rungs  HMI – 143 graphics  77 Process Object graphics  66 Custom graphics  Electrical Drawings - 450
  • 33. System Features  Remote Interface  Remote connections via Terminal Server  View only connection via FactoryTalk® Viewpoint  System Redundancy  SCADA Servers, PLC’s, Network Power Supplies  Network and Power Supply Diagnostics  Node Based Security  Ethernet VFD’s providing increased visibility for troubleshooting
  • 34. Agenda Lessons Learned System Design System Selection Process Project Overview
  • 35. Lessons Learned  As-Built existing design documents prior to starting detailed design  Graphic Standards for Common Plant Interface  VM’s allowed for easy “on-site” migration  Working with local Electrical Subcontractor eased installation
  • 36. Lessons Learned  Executing a DLR Hardware FAT reduced startup time
  • 37. Questions Tom Brown – Program Manager, Banks Integration Group, Inc. June 8, 2016