Legacy
Migration/Modernization
Application Series
August 10th, 2016
Presenters
• Dan Burger, P.E., C.E.M. – Business Development Market Manager
Having over 12 years of direct experience in the migration and modernization of various
control system platforms, including the planning, engineering, and cutover. He holds a P.E. in
Control Systems Engineering and is a Certified Energy Manager.
• James Riccardi, P.E. – Group Manager, California Projects
Over 24 years of automation experience including design, implementation, commissioning
and validation of various controls platforms across different industries. Jim has previously
worked with Air Products and Bailey Controls. He has led projects throughout the US and
Asia. He has been with RoviSys since 2000 and is currently based in Ventura, CA.
Given today's slow economic growth, reduced plant
engineering and maintenance staffing and tight
capital budget constraints, understanding how best
to propose, plan, execute and allocate limited
resources for successful process control system
migrations is imperative for manufacturers seeking to
maintain or increase productivity and efficiency.
Business Environment
Project Justification
• Financial
• Safety
• Production Increases
• Maintenance Efficiencies
• Integration with Business Systems
. 4
Lobbying for Support
• You are the visionary, determine your approach
• Preach the specific benefits
• Ask peers for their input
• Build a plan and revise as needed
• Consult a partner
• Generate a FEED Study w/ cost estimate
Why migrate now?
• Legacy Systems are hard to maintain
• Limited Spare Parts (and failures increase…)
• Old PC hardware and Operating Systems
• Communications and diagnostics limitations
• People who know them are retiring
• New tools connect to new systems
• Legacy Systems are generally closed architecture
• Historians, Advanced Control, MES for Plant Pax
Payback $$
• Increasing cost of
• Spare Parts
• Trained Support (internal + external)
• Support Agreements
• Unplanned Downtime
• Improved visibility into operations
• More efficient operations
• New product/process/equipment
• Compliance
Migration Approach
1. Rip and Replace
2. Phased by system architecture
3. Phased by process area
4. With same system vendor / select new vendor
Project Definition
• Hands on System Audit
• High Level Migration Plan
• Savings/Payback
• FEL +/- 30% Estimate
• Authorization to Proceed?
• Bid Specs
• Select Vendors
• +/- 10% Estimates
• System procurement & Engineering
• Cutover
• Support
System Audit
• Eyes on Audit
• Hardware
• Code
• Interview
• Operations
• Maintenance
• Engineering
• Understand Goals and Challenges
Migration Plan
• High level design
• Rip & Replace or Phased Migration?
• Priorities
• HMI unsupportable
• Stock Prep can’t run
• New Coater on the way
• Who will drive?
• How to justify?
Front End Loading
• Audit drives FEL Estimates
• I/O counts
• HMI Requirements
• E&I Upgrades required?
• New network?
• Installation challenges
• System Architecture & BOM
• Schedule
• Resource Loading
Choose Approach Carefully!
Why Consider Phased Migration?
Rip & Replace Phased
Manpower Larger team Hit and run
Downtime Longer Outage Many Outages
Risk Higher Lower
Faith All in Focused Effort
Cash Flow One Year Gradual
Cost Most cost effective Higher overall cost
Payback Improvement NOW Time is money
Glass Plant Virtualized Plant PAx
End User - System Architecture
Manufacturing Zone
Site Manufacturing
Operations and Control
Level 3
Demiliterized Zone
(DMZ)
Enterprise Zone
Levels 4 and 5
Cell/Area Zone
Levels 0–2
Internet
FIBER
FIBER
FIBER
FIBER
FIBER
VLAN
VLAN
FIBER
FIBER
Enterprise Zone
Provided by End
User IT
HMI Server
(Primary) MES/Historian Server
Engineering
Workstation #1
HMI Server
(Secondary)
VLAN
FIBER
FIBER
Enterprise Zone
Office PC’s
VLAN
FT View SE HMI Clients (QTY 5):
`
`
`
VLAN
PanelView+ (Qty 5)
FIBER
Engineering
Workstation #2
VLAN
Terminal Server
(Primary)
VLAN
Terminal Server
(Secondary)
VLAN Domain Controller
(Primary)
VLAN
Domain Controller
(Secondary)
VLAN
NOTE: Maximum
allowed length of
Cat 6 cable is 100
meters (330ft)
VLAN
FT View SE HMI Clients (QTY 2):
`
`
`
VLAN
HIST01
ENG01
ENG02
TS01
TS02
DOM01
DOM02
Cisco 3750X
Switch Stack
DLR Representation
Is Symbolic
Only...See Area
Pages For Specifics
VLAN
Ctrl Area 3
Ctrl Area 3 Device Level
Ring
RIO – Area 3 2
VLAN
RIO – Area 3 1
VLAN
`
FT View SE HMI Client
HMI STRATIX
CLX – Area 3 0A CLX – Area 3 0B
DLR Representation
Is Symbolic
Only...See Area
Pages For Specifics
VLAN
Area 4 PLC 4.0
with GracePort Interface
Ctrl Area 4
Ctrl Area 4 Device Level
Ring
RIO – Area 4 2
VLAN
CLX – Area 4 0A CLX – Area 4 0B
RIO – Area 4 3
Area 4 PLC 4.1
FIBER
RIO – Area 4 1
Scale Weight (Qty 12)
x12
FIBER
x5
FT View SE HMI Client (Qty2)
VLAN x2
`
RIO – Area 4 4
FIBERArea 4 PLC 4.2
DLR STRATIX
HMI STRATIX
VLAN
AREA 5 PLC CABINET
Ctrl Area 5
Ctrl Area 5 Device Level
Ring
RIO – Area 5 2
VLAN
CLX – Area 5 0A CLX – Area 5 0B
MODBUS
RIO – Area 5 1
MODBUS
Ctrl Area 5 Drives (Qty 2)
Spang SCR – Power Control (Qty 7)
MODBUS x7
Spang SCR – Power Control (Qty 8)
MODBUS x8
SPANG Network Enclosure
MicroLogix 1100 ATS (Qty 2)
x2
FIBER
Scale Weight (Qty 2)
Power Logic Monitor (Qty 6)MODBUS x6
x2
FIBER VLAN
VLAN
MB STRATIX
DLR STRATIX
HMI STRATIX
DLR Representation
Is Symbolic
Only...See Area
Pages For Specifics
VLAN
Ctrl Area 1
Ctrl Area 1 Device Level
Ring
Drives (Qty 9)
RIO – Area 1 2
VLAN
CLX – Area 1 0A CLX – Area 1 0B
RIO – Area 1 3
Area 1 MCC
FIBER
MODBUS
RIO – Area 1 1
MODBUS
Drives (Qty 2)
FIBER
Spang SCR – Power Control (Qty 16)
MODBUS x16
Spang SCR – Power Control (Qty 16)
MODBUS x16
SPANG Network Enclosure
HMI STRATIX
MB STRATIX
DLR Representation
Is Symbolic
Only...See Area
Pages For Specifics
VLAN
Ctrl Area 2
Ctrl Area 2 Device Level
Ring
SLC 5/05 – Gas Safety A
SLC 5/05 – Gas Safety B
Drives (Qty 20)
MicroLogix 1100 ATS (Qty 6)
RIO – Area 2 1 RIO – Area 2 2
FIBER
RIO – Area 2 4
RIO – Area 2 4
Power Logic Monitor (Qty 8)
Generator Control Panel
Area 2 PLC 1.2
Area 2 PLC 1.1
with GracePort Interface
VLAN
CLX – Area 2 0A CLX – Area 2 0B
Gas Safety Panel
MODBUS
MODBUS
MODBUS x8
x6
Drives (Qty 4)
FIBER
VLAN
`
FT View SE HMI Client
HMI STRATIX
FN_DLRSTRX
MB STRATIX
DLR Representation
Is Symbolic
Only...See Area
Pages For Specifics
`
FT View SE HMI Client
`
FT View SE HMI Client
`
FT View SE HMI Client
DLR Representation
Is Symbolic
Only...See Area
Pages For Specifics
1200 I/O, 5 Areas, 8 Consoles, MES/Historian, 30 Drives, Virtualized
Paper Machine Phased Migration
2000 I/O, 3 Areas, 10 Consoles, PI Addressing, Virtualized
Glass Plant Paper Mill
I/O total 1385 2100
Remote I/O enclosures 0 21
PCU's 4 PCU, 8 MFP 4 PCU, 9 MFC
CLX Controllers 5 Redundant Pair 3
HMI Consoles 12 10
HMI Graphics 25 plus 15 custom popups 99 plus 40 popup faceplates
Interfaces
Resolver Interface Module, 20 30 +
ModbusTCP devices, 30+ PowerFlex
Drives (new), 50+ HART xmtrs/actuators PI, GE Drives, PLC5, ModBus
Historian x x
Drives PowerFlex, in new scope GE Serial Interface
Optimimzation x interface to VAX
PI scope New, FTHistorian yes, to be comverted to FTHistorian
Schedule
Strategy
System Price
$ changes
RoviSys first full Plant Pax Plant Pax look with custom CMs for Bailey
Custom faceplates & CMs Work with Bailey configs during phasing
Virtualized Servers Virtualized Servers
Client specify VM Rockwell design for high availability
simple, less expensive, 2 servers 3 servers, Vsphere selects Server for reliability
support not as convenient push button' backups
Glass Plant Paper Mill
I/O total 1385 2100
Remote I/O enclosures 0 21
PCU's 4 PCU, 8 MFP 4 PCU, 9 MFC
CLX Controllers 5 Redundant Pair 3
HMI Consoles 12 10
HMI Graphics 25 plus 15 custom popups 99 plus 40 popup faceplates
Interfaces
Resolver Interface Module, 20 30 +
ModbusTCP devices, 30+ PowerFlex
Drives (new), 50+ HART xmtrs/actuators PI, GE Drives, PLC5, ModBus
Historian x x
Drives PowerFlex, in new scope GE Serial Interface
Optimimzation x interface to VAX
PI scope New, FTHistorian yes, to be comverted to FTHistorian
Schedule install 12 mon after order 2 year plus cutover plan
Strategy Rip & Replace Phased Migration
System Price $1.4MM $1.9MM
$ changes $150K $350K
RoviSys first full Plant Pax Plant Pax look with custom CMs for Bailey
Custom faceplates & CMs Work with Bailey configs during phasing
Virtualized Servers Virtualized Servers
Client specify VM Rockwell design for high availability
simple, less expensive, 2 servers 3 servers, Vsphere selects Server for reliability
support not as convenient push button' backups
Summary
• Plan
• Audit
• Update Documentation
• Migration Plan and FEL Pricing
• Look for Payback
• Operations
• Maintenance & Support
• Long term operational benefits
• Understand what drives your company’s decisions
• Partner with someone who has seen it all
Questions?
Thank you for Attending!
Who are we?...
The RoviSys Company
• Founded in 1989
• ~600 Employees
• Rockwell Automation Solution Partner
• Certified Member CSIA, Control and Information System Integrators Association
• Rockwell’s Bailey Migration Tools, cables, and OLDI cATM-BLY90
• Rockwell Cable Solutions to DCS I/O Terminations; Bailey, APACS, RS3, etc.
• Automation and Information Systems
Contact Information
• Dan Burger, P.E., C.E.M. – Business Development Market Manager
Dan.burger@rovisys.com
(330)936-1112
• James Riccardi, P.E. – Group Manager, California Projects
Riccardi@rovisys.com
(330)472-3034

More Related Content

What's hot

S57 Optimacs processor - S5 to S7 PLC upgrades
S57 Optimacs processor - S5 to S7 PLC upgradesS57 Optimacs processor - S5 to S7 PLC upgrades
S57 Optimacs processor - S5 to S7 PLC upgradesOptima Control Solutions
 
DCS Introduction
DCS IntroductionDCS Introduction
DCS Introduction
PranavAutomation
 
West Pro Series Brochure
West Pro Series BrochureWest Pro Series Brochure
West Pro Series Brochure
West Control Solutions
 
Trixboxbeta - One stop solution for all your design problems
Trixboxbeta - One stop solution for all your design problemsTrixboxbeta - One stop solution for all your design problems
Trixboxbeta - One stop solution for all your design problemscontroltrix
 
Session 07 - PLC Architecture
Session 07 - PLC ArchitectureSession 07 - PLC Architecture
Session 07 - PLC Architecture
VidyaIA
 
Beran APM720 Monitoring System
Beran APM720 Monitoring SystemBeran APM720 Monitoring System
Beran APM720 Monitoring System
MachineryWatch.Com, Inc.
 
Technical slides tia_portal_v15_en
Technical slides tia_portal_v15_enTechnical slides tia_portal_v15_en
Technical slides tia_portal_v15_en
Deepak kumar
 
Aurora Multimedia - company product competitive advantages
Aurora Multimedia -  company product competitive advantagesAurora Multimedia -  company product competitive advantages
Aurora Multimedia - company product competitive advantages
pattywanzer
 
CDMA1X Pilot Panorama introduction
CDMA1X Pilot Panorama introductionCDMA1X Pilot Panorama introduction
CDMA1X Pilot Panorama introduction
Tempus Telcosys
 
PLC Based Annunciation System
PLC Based Annunciation SystemPLC Based Annunciation System
PLC Based Annunciation SystemFasih Ahmed
 
PLC Based Annunciation System Report
PLC Based Annunciation System ReportPLC Based Annunciation System Report
PLC Based Annunciation System ReportFasih Ahmed
 
IBM Flex System FC3171 8Gb SAN Switch and Pass-thru
IBM Flex System FC3171 8Gb SAN Switch and Pass-thruIBM Flex System FC3171 8Gb SAN Switch and Pass-thru
IBM Flex System FC3171 8Gb SAN Switch and Pass-thru
IBM India Smarter Computing
 
FreePBX Disaster Recovery
FreePBX Disaster RecoveryFreePBX Disaster Recovery
FreePBX Disaster Recovery
Hossein Yavari
 
Session 17 - SCADA Introduction
Session 17 - SCADA IntroductionSession 17 - SCADA Introduction
Session 17 - SCADA Introduction
VidyaIA
 

What's hot (15)

S57 Optimacs processor - S5 to S7 PLC upgrades
S57 Optimacs processor - S5 to S7 PLC upgradesS57 Optimacs processor - S5 to S7 PLC upgrades
S57 Optimacs processor - S5 to S7 PLC upgrades
 
DCS Introduction
DCS IntroductionDCS Introduction
DCS Introduction
 
West Pro Series Brochure
West Pro Series BrochureWest Pro Series Brochure
West Pro Series Brochure
 
Trixboxbeta - One stop solution for all your design problems
Trixboxbeta - One stop solution for all your design problemsTrixboxbeta - One stop solution for all your design problems
Trixboxbeta - One stop solution for all your design problems
 
Session 07 - PLC Architecture
Session 07 - PLC ArchitectureSession 07 - PLC Architecture
Session 07 - PLC Architecture
 
Beran APM720 Monitoring System
Beran APM720 Monitoring SystemBeran APM720 Monitoring System
Beran APM720 Monitoring System
 
Technical slides tia_portal_v15_en
Technical slides tia_portal_v15_enTechnical slides tia_portal_v15_en
Technical slides tia_portal_v15_en
 
Aurora Multimedia - company product competitive advantages
Aurora Multimedia -  company product competitive advantagesAurora Multimedia -  company product competitive advantages
Aurora Multimedia - company product competitive advantages
 
CDMA1X Pilot Panorama introduction
CDMA1X Pilot Panorama introductionCDMA1X Pilot Panorama introduction
CDMA1X Pilot Panorama introduction
 
PLC Based Annunciation System
PLC Based Annunciation SystemPLC Based Annunciation System
PLC Based Annunciation System
 
PLC Based Annunciation System Report
PLC Based Annunciation System ReportPLC Based Annunciation System Report
PLC Based Annunciation System Report
 
BTS Key Mgt
BTS Key MgtBTS Key Mgt
BTS Key Mgt
 
IBM Flex System FC3171 8Gb SAN Switch and Pass-thru
IBM Flex System FC3171 8Gb SAN Switch and Pass-thruIBM Flex System FC3171 8Gb SAN Switch and Pass-thru
IBM Flex System FC3171 8Gb SAN Switch and Pass-thru
 
FreePBX Disaster Recovery
FreePBX Disaster RecoveryFreePBX Disaster Recovery
FreePBX Disaster Recovery
 
Session 17 - SCADA Introduction
Session 17 - SCADA IntroductionSession 17 - SCADA Introduction
Session 17 - SCADA Introduction
 

Viewers also liked

Jun 29 - 2016-MultiFactorAuthentication
Jun 29 - 2016-MultiFactorAuthentication Jun 29 - 2016-MultiFactorAuthentication
Jun 29 - 2016-MultiFactorAuthentication banerjeea
 
Making a Pain-free Migration to Unified Communications
Making a Pain-free Migration to Unified CommunicationsMaking a Pain-free Migration to Unified Communications
Making a Pain-free Migration to Unified Communications
ReadWrite
 
Legacy Migration Overview
Legacy Migration OverviewLegacy Migration Overview
Legacy Migration Overview
Bambordé Baldé
 
Migrating to cisco unified communications manager 9.1
Migrating to cisco unified communications manager 9.1Migrating to cisco unified communications manager 9.1
Migrating to cisco unified communications manager 9.1
Michael Ganschuk
 
Lsmw final with comments
Lsmw final with commentsLsmw final with comments
Lsmw final with commentsrajyalakshmi10
 
Introducing MFX for z/OS 2.1 & ZPSaver Suite
Introducing MFX for z/OS 2.1 & ZPSaver SuiteIntroducing MFX for z/OS 2.1 & ZPSaver Suite
Introducing MFX for z/OS 2.1 & ZPSaver Suite
Precisely
 
Mainframe Optimization in 2017
Mainframe Optimization in 2017Mainframe Optimization in 2017
Mainframe Optimization in 2017
Precisely
 
Legacy Systems in Software Engineering SE26
Legacy Systems in Software Engineering SE26Legacy Systems in Software Engineering SE26
Legacy Systems in Software Engineering SE26koolkampus
 
Enterprise Integration Patterns Revisited (EIP) for the Era of Big Data, Inte...
Enterprise Integration Patterns Revisited (EIP) for the Era of Big Data, Inte...Enterprise Integration Patterns Revisited (EIP) for the Era of Big Data, Inte...
Enterprise Integration Patterns Revisited (EIP) for the Era of Big Data, Inte...
Kai Wähner
 
Migrating Legacy Applications to AWS Cloud: Strategies and Challenges
Migrating Legacy Applications to AWS Cloud: Strategies and ChallengesMigrating Legacy Applications to AWS Cloud: Strategies and Challenges
Migrating Legacy Applications to AWS Cloud: Strategies and Challenges
OSSCube
 
EAI example
EAI exampleEAI example
EAI example
Prabhath Suminda
 
Systems Migration
Systems MigrationSystems Migration
Systems Migrationrichchihlee
 
Database migration
Database migrationDatabase migration
Database migration
Sankar Patnaik
 
Enterprise Application Integration Technologies
Enterprise Application Integration TechnologiesEnterprise Application Integration Technologies
Enterprise Application Integration Technologies
Peter R. Egli
 
Slaying The Legacy Dragon: Practical Lessons in Replacing Old Software
Slaying The Legacy Dragon: Practical Lessons in Replacing Old SoftwareSlaying The Legacy Dragon: Practical Lessons in Replacing Old Software
Slaying The Legacy Dragon: Practical Lessons in Replacing Old Software
Tim Berglund
 
Data Center Migration
Data Center MigrationData Center Migration
Data Center MigrationThomas Martin
 
AWS Migration Planning Roadmap
AWS Migration Planning RoadmapAWS Migration Planning Roadmap
AWS Migration Planning Roadmap
Amazon Web Services
 
ORACLE EBS R12 UPGRADE
ORACLE EBS R12 UPGRADEORACLE EBS R12 UPGRADE
ORACLE EBS R12 UPGRADE
Dinesh Gupta
 
Preparing a data migration plan: A practical guide
Preparing a data migration plan: A practical guidePreparing a data migration plan: A practical guide
Preparing a data migration plan: A practical guide
ETLSolutions
 

Viewers also liked (19)

Jun 29 - 2016-MultiFactorAuthentication
Jun 29 - 2016-MultiFactorAuthentication Jun 29 - 2016-MultiFactorAuthentication
Jun 29 - 2016-MultiFactorAuthentication
 
Making a Pain-free Migration to Unified Communications
Making a Pain-free Migration to Unified CommunicationsMaking a Pain-free Migration to Unified Communications
Making a Pain-free Migration to Unified Communications
 
Legacy Migration Overview
Legacy Migration OverviewLegacy Migration Overview
Legacy Migration Overview
 
Migrating to cisco unified communications manager 9.1
Migrating to cisco unified communications manager 9.1Migrating to cisco unified communications manager 9.1
Migrating to cisco unified communications manager 9.1
 
Lsmw final with comments
Lsmw final with commentsLsmw final with comments
Lsmw final with comments
 
Introducing MFX for z/OS 2.1 & ZPSaver Suite
Introducing MFX for z/OS 2.1 & ZPSaver SuiteIntroducing MFX for z/OS 2.1 & ZPSaver Suite
Introducing MFX for z/OS 2.1 & ZPSaver Suite
 
Mainframe Optimization in 2017
Mainframe Optimization in 2017Mainframe Optimization in 2017
Mainframe Optimization in 2017
 
Legacy Systems in Software Engineering SE26
Legacy Systems in Software Engineering SE26Legacy Systems in Software Engineering SE26
Legacy Systems in Software Engineering SE26
 
Enterprise Integration Patterns Revisited (EIP) for the Era of Big Data, Inte...
Enterprise Integration Patterns Revisited (EIP) for the Era of Big Data, Inte...Enterprise Integration Patterns Revisited (EIP) for the Era of Big Data, Inte...
Enterprise Integration Patterns Revisited (EIP) for the Era of Big Data, Inte...
 
Migrating Legacy Applications to AWS Cloud: Strategies and Challenges
Migrating Legacy Applications to AWS Cloud: Strategies and ChallengesMigrating Legacy Applications to AWS Cloud: Strategies and Challenges
Migrating Legacy Applications to AWS Cloud: Strategies and Challenges
 
EAI example
EAI exampleEAI example
EAI example
 
Systems Migration
Systems MigrationSystems Migration
Systems Migration
 
Database migration
Database migrationDatabase migration
Database migration
 
Enterprise Application Integration Technologies
Enterprise Application Integration TechnologiesEnterprise Application Integration Technologies
Enterprise Application Integration Technologies
 
Slaying The Legacy Dragon: Practical Lessons in Replacing Old Software
Slaying The Legacy Dragon: Practical Lessons in Replacing Old SoftwareSlaying The Legacy Dragon: Practical Lessons in Replacing Old Software
Slaying The Legacy Dragon: Practical Lessons in Replacing Old Software
 
Data Center Migration
Data Center MigrationData Center Migration
Data Center Migration
 
AWS Migration Planning Roadmap
AWS Migration Planning RoadmapAWS Migration Planning Roadmap
AWS Migration Planning Roadmap
 
ORACLE EBS R12 UPGRADE
ORACLE EBS R12 UPGRADEORACLE EBS R12 UPGRADE
ORACLE EBS R12 UPGRADE
 
Preparing a data migration plan: A practical guide
Preparing a data migration plan: A practical guidePreparing a data migration plan: A practical guide
Preparing a data migration plan: A practical guide
 

Similar to Justifying Migration of legacy process control systems

VMworld 2014: What's New with View and PCoIL in Horizon 6
VMworld 2014: What's New with View and PCoIL in Horizon 6VMworld 2014: What's New with View and PCoIL in Horizon 6
VMworld 2014: What's New with View and PCoIL in Horizon 6
VMworld
 
PlantPAx system - what's new and what's next
PlantPAx system - what's new and what's nextPlantPAx system - what's new and what's next
PlantPAx system - what's new and what's next
IntelligentManufacturingInstitute
 
migrating your dcs system to plantpax-phpapp01
migrating your dcs system to plantpax-phpapp01migrating your dcs system to plantpax-phpapp01
migrating your dcs system to plantpax-phpapp01Shashi Ranjan Singh
 
Next Generation Address Management with VitalQIP - Alcatel-Lucent and Perficient
Next Generation Address Management with VitalQIP - Alcatel-Lucent and PerficientNext Generation Address Management with VitalQIP - Alcatel-Lucent and Perficient
Next Generation Address Management with VitalQIP - Alcatel-Lucent and PerficientPerficient, Inc.
 
Plan with confidence: Route to a successful Do178c multicore certification
Plan with confidence: Route to a successful Do178c multicore certificationPlan with confidence: Route to a successful Do178c multicore certification
Plan with confidence: Route to a successful Do178c multicore certification
Massimo Talia
 
Migdcs pp005 -en-e
Migdcs pp005 -en-eMigdcs pp005 -en-e
Migdcs pp005 -en-eahmed6000
 
How Automation And Intelligence Can Simplify Your High Availability
How Automation And Intelligence Can Simplify Your High AvailabilityHow Automation And Intelligence Can Simplify Your High Availability
How Automation And Intelligence Can Simplify Your High Availability
Precisely
 
AP02 - Apotex Pharma Controls Retrofit Improves Process ROKTechED2015.pdf
AP02 - Apotex Pharma Controls Retrofit Improves Process ROKTechED2015.pdfAP02 - Apotex Pharma Controls Retrofit Improves Process ROKTechED2015.pdf
AP02 - Apotex Pharma Controls Retrofit Improves Process ROKTechED2015.pdf
indinhasan
 
New Generation of IBM Power Systems Delivering value with Red Hat Enterprise ...
New Generation of IBM Power Systems Delivering value with Red Hat Enterprise ...New Generation of IBM Power Systems Delivering value with Red Hat Enterprise ...
New Generation of IBM Power Systems Delivering value with Red Hat Enterprise ...
Filipe Miranda
 
gesa_sol.ppt
gesa_sol.pptgesa_sol.ppt
gesa_sol.ppt
KunyukKunyuk1
 
VMworld 2013: US Air National Guard - DoD Private Cloud Initiative –How Virtu...
VMworld 2013: US Air National Guard - DoD Private Cloud Initiative –How Virtu...VMworld 2013: US Air National Guard - DoD Private Cloud Initiative –How Virtu...
VMworld 2013: US Air National Guard - DoD Private Cloud Initiative –How Virtu...
VMworld
 
Service-Level Objective for Serverless Applications
Service-Level Objective for Serverless ApplicationsService-Level Objective for Serverless Applications
Service-Level Objective for Serverless Applications
alekn
 
How to document campus IT infrastructures
How to document campus IT infrastructuresHow to document campus IT infrastructures
How to document campus IT infrastructures
Robert Cowham
 
Saurabh Singh - CV.DOC
Saurabh Singh - CV.DOCSaurabh Singh - CV.DOC
Saurabh Singh - CV.DOCsaurabh singh
 
CompactLogix-5380-Controller-Technical-Presentation.pdf
CompactLogix-5380-Controller-Technical-Presentation.pdfCompactLogix-5380-Controller-Technical-Presentation.pdf
CompactLogix-5380-Controller-Technical-Presentation.pdf
gerzael1
 
Migration Tools to Convert Your Legacy DCS
Migration Tools to Convert Your Legacy DCSMigration Tools to Convert Your Legacy DCS
Migration Tools to Convert Your Legacy DCS
Rockwell Automation
 
verygoodCS1000.ppt
verygoodCS1000.pptverygoodCS1000.ppt
verygoodCS1000.ppt
brianbrowne13
 
OCP Telco Engineering Workshop at BCE2017
OCP Telco Engineering Workshop at BCE2017OCP Telco Engineering Workshop at BCE2017
OCP Telco Engineering Workshop at BCE2017
Radisys Corporation
 
Presentation racsig 090730
Presentation racsig 090730Presentation racsig 090730
Presentation racsig 090730
maclean liu
 
Building the Case for System z Linux
Building the Case for System z LinuxBuilding the Case for System z Linux
Building the Case for System z Linux
Mainline's Knowledge Center
 

Similar to Justifying Migration of legacy process control systems (20)

VMworld 2014: What's New with View and PCoIL in Horizon 6
VMworld 2014: What's New with View and PCoIL in Horizon 6VMworld 2014: What's New with View and PCoIL in Horizon 6
VMworld 2014: What's New with View and PCoIL in Horizon 6
 
PlantPAx system - what's new and what's next
PlantPAx system - what's new and what's nextPlantPAx system - what's new and what's next
PlantPAx system - what's new and what's next
 
migrating your dcs system to plantpax-phpapp01
migrating your dcs system to plantpax-phpapp01migrating your dcs system to plantpax-phpapp01
migrating your dcs system to plantpax-phpapp01
 
Next Generation Address Management with VitalQIP - Alcatel-Lucent and Perficient
Next Generation Address Management with VitalQIP - Alcatel-Lucent and PerficientNext Generation Address Management with VitalQIP - Alcatel-Lucent and Perficient
Next Generation Address Management with VitalQIP - Alcatel-Lucent and Perficient
 
Plan with confidence: Route to a successful Do178c multicore certification
Plan with confidence: Route to a successful Do178c multicore certificationPlan with confidence: Route to a successful Do178c multicore certification
Plan with confidence: Route to a successful Do178c multicore certification
 
Migdcs pp005 -en-e
Migdcs pp005 -en-eMigdcs pp005 -en-e
Migdcs pp005 -en-e
 
How Automation And Intelligence Can Simplify Your High Availability
How Automation And Intelligence Can Simplify Your High AvailabilityHow Automation And Intelligence Can Simplify Your High Availability
How Automation And Intelligence Can Simplify Your High Availability
 
AP02 - Apotex Pharma Controls Retrofit Improves Process ROKTechED2015.pdf
AP02 - Apotex Pharma Controls Retrofit Improves Process ROKTechED2015.pdfAP02 - Apotex Pharma Controls Retrofit Improves Process ROKTechED2015.pdf
AP02 - Apotex Pharma Controls Retrofit Improves Process ROKTechED2015.pdf
 
New Generation of IBM Power Systems Delivering value with Red Hat Enterprise ...
New Generation of IBM Power Systems Delivering value with Red Hat Enterprise ...New Generation of IBM Power Systems Delivering value with Red Hat Enterprise ...
New Generation of IBM Power Systems Delivering value with Red Hat Enterprise ...
 
gesa_sol.ppt
gesa_sol.pptgesa_sol.ppt
gesa_sol.ppt
 
VMworld 2013: US Air National Guard - DoD Private Cloud Initiative –How Virtu...
VMworld 2013: US Air National Guard - DoD Private Cloud Initiative –How Virtu...VMworld 2013: US Air National Guard - DoD Private Cloud Initiative –How Virtu...
VMworld 2013: US Air National Guard - DoD Private Cloud Initiative –How Virtu...
 
Service-Level Objective for Serverless Applications
Service-Level Objective for Serverless ApplicationsService-Level Objective for Serverless Applications
Service-Level Objective for Serverless Applications
 
How to document campus IT infrastructures
How to document campus IT infrastructuresHow to document campus IT infrastructures
How to document campus IT infrastructures
 
Saurabh Singh - CV.DOC
Saurabh Singh - CV.DOCSaurabh Singh - CV.DOC
Saurabh Singh - CV.DOC
 
CompactLogix-5380-Controller-Technical-Presentation.pdf
CompactLogix-5380-Controller-Technical-Presentation.pdfCompactLogix-5380-Controller-Technical-Presentation.pdf
CompactLogix-5380-Controller-Technical-Presentation.pdf
 
Migration Tools to Convert Your Legacy DCS
Migration Tools to Convert Your Legacy DCSMigration Tools to Convert Your Legacy DCS
Migration Tools to Convert Your Legacy DCS
 
verygoodCS1000.ppt
verygoodCS1000.pptverygoodCS1000.ppt
verygoodCS1000.ppt
 
OCP Telco Engineering Workshop at BCE2017
OCP Telco Engineering Workshop at BCE2017OCP Telco Engineering Workshop at BCE2017
OCP Telco Engineering Workshop at BCE2017
 
Presentation racsig 090730
Presentation racsig 090730Presentation racsig 090730
Presentation racsig 090730
 
Building the Case for System z Linux
Building the Case for System z LinuxBuilding the Case for System z Linux
Building the Case for System z Linux
 

More from Brian Thomas

Central Process Utility Plant controls upgrade required 100% uptime
Central Process Utility Plant controls upgrade required 100% uptimeCentral Process Utility Plant controls upgrade required 100% uptime
Central Process Utility Plant controls upgrade required 100% uptime
Brian Thomas
 
OnTrack CIP Validation
OnTrack CIP ValidationOnTrack CIP Validation
OnTrack CIP Validation
Brian Thomas
 
Produced Water Handling System Upgrade
Produced Water Handling System UpgradeProduced Water Handling System Upgrade
Produced Water Handling System Upgrade
Brian Thomas
 
Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)
Brian Thomas
 
Bausch lomb leverages plant p ax_rev1
Bausch  lomb leverages plant p ax_rev1Bausch  lomb leverages plant p ax_rev1
Bausch lomb leverages plant p ax_rev1
Brian Thomas
 
Food Safety Modernization Act (FSMA) regulatory requirements by FDA
Food Safety Modernization Act (FSMA) regulatory requirements by FDAFood Safety Modernization Act (FSMA) regulatory requirements by FDA
Food Safety Modernization Act (FSMA) regulatory requirements by FDA
Brian Thomas
 
Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...
Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...
Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...
Brian Thomas
 
DCS migration - zero downtime upgrade
DCS migration - zero downtime upgradeDCS migration - zero downtime upgrade
DCS migration - zero downtime upgrade
Brian Thomas
 
Zero downtime upgrate for dcs migration Thermo Systems
Zero downtime upgrate for dcs migration Thermo SystemsZero downtime upgrate for dcs migration Thermo Systems
Zero downtime upgrate for dcs migration Thermo Systems
Brian Thomas
 

More from Brian Thomas (9)

Central Process Utility Plant controls upgrade required 100% uptime
Central Process Utility Plant controls upgrade required 100% uptimeCentral Process Utility Plant controls upgrade required 100% uptime
Central Process Utility Plant controls upgrade required 100% uptime
 
OnTrack CIP Validation
OnTrack CIP ValidationOnTrack CIP Validation
OnTrack CIP Validation
 
Produced Water Handling System Upgrade
Produced Water Handling System UpgradeProduced Water Handling System Upgrade
Produced Water Handling System Upgrade
 
Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)
 
Bausch lomb leverages plant p ax_rev1
Bausch  lomb leverages plant p ax_rev1Bausch  lomb leverages plant p ax_rev1
Bausch lomb leverages plant p ax_rev1
 
Food Safety Modernization Act (FSMA) regulatory requirements by FDA
Food Safety Modernization Act (FSMA) regulatory requirements by FDAFood Safety Modernization Act (FSMA) regulatory requirements by FDA
Food Safety Modernization Act (FSMA) regulatory requirements by FDA
 
Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...
Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...
Sequencing solution with Logix Batch and Sequence Module (LBSM) & steam table...
 
DCS migration - zero downtime upgrade
DCS migration - zero downtime upgradeDCS migration - zero downtime upgrade
DCS migration - zero downtime upgrade
 
Zero downtime upgrate for dcs migration Thermo Systems
Zero downtime upgrate for dcs migration Thermo SystemsZero downtime upgrate for dcs migration Thermo Systems
Zero downtime upgrate for dcs migration Thermo Systems
 

Recently uploaded

JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
Bhaskar Mitra
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
DianaGray10
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
Ralf Eggert
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
Product School
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Tobias Schneck
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
Frank van Harmelen
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
CatarinaPereira64715
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Thierry Lestable
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
Product School
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
Product School
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
Product School
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
Safe Software
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 

Recently uploaded (20)

JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 

Justifying Migration of legacy process control systems

  • 2. Presenters • Dan Burger, P.E., C.E.M. – Business Development Market Manager Having over 12 years of direct experience in the migration and modernization of various control system platforms, including the planning, engineering, and cutover. He holds a P.E. in Control Systems Engineering and is a Certified Energy Manager. • James Riccardi, P.E. – Group Manager, California Projects Over 24 years of automation experience including design, implementation, commissioning and validation of various controls platforms across different industries. Jim has previously worked with Air Products and Bailey Controls. He has led projects throughout the US and Asia. He has been with RoviSys since 2000 and is currently based in Ventura, CA.
  • 3. Given today's slow economic growth, reduced plant engineering and maintenance staffing and tight capital budget constraints, understanding how best to propose, plan, execute and allocate limited resources for successful process control system migrations is imperative for manufacturers seeking to maintain or increase productivity and efficiency. Business Environment
  • 4. Project Justification • Financial • Safety • Production Increases • Maintenance Efficiencies • Integration with Business Systems . 4
  • 5. Lobbying for Support • You are the visionary, determine your approach • Preach the specific benefits • Ask peers for their input • Build a plan and revise as needed • Consult a partner • Generate a FEED Study w/ cost estimate
  • 6. Why migrate now? • Legacy Systems are hard to maintain • Limited Spare Parts (and failures increase…) • Old PC hardware and Operating Systems • Communications and diagnostics limitations • People who know them are retiring • New tools connect to new systems • Legacy Systems are generally closed architecture • Historians, Advanced Control, MES for Plant Pax
  • 7. Payback $$ • Increasing cost of • Spare Parts • Trained Support (internal + external) • Support Agreements • Unplanned Downtime • Improved visibility into operations • More efficient operations • New product/process/equipment • Compliance
  • 8. Migration Approach 1. Rip and Replace 2. Phased by system architecture 3. Phased by process area 4. With same system vendor / select new vendor
  • 9. Project Definition • Hands on System Audit • High Level Migration Plan • Savings/Payback • FEL +/- 30% Estimate • Authorization to Proceed? • Bid Specs • Select Vendors • +/- 10% Estimates • System procurement & Engineering • Cutover • Support
  • 10. System Audit • Eyes on Audit • Hardware • Code • Interview • Operations • Maintenance • Engineering • Understand Goals and Challenges
  • 11. Migration Plan • High level design • Rip & Replace or Phased Migration? • Priorities • HMI unsupportable • Stock Prep can’t run • New Coater on the way • Who will drive? • How to justify?
  • 12. Front End Loading • Audit drives FEL Estimates • I/O counts • HMI Requirements • E&I Upgrades required? • New network? • Installation challenges • System Architecture & BOM • Schedule • Resource Loading Choose Approach Carefully!
  • 13. Why Consider Phased Migration? Rip & Replace Phased Manpower Larger team Hit and run Downtime Longer Outage Many Outages Risk Higher Lower Faith All in Focused Effort Cash Flow One Year Gradual Cost Most cost effective Higher overall cost Payback Improvement NOW Time is money
  • 14. Glass Plant Virtualized Plant PAx End User - System Architecture Manufacturing Zone Site Manufacturing Operations and Control Level 3 Demiliterized Zone (DMZ) Enterprise Zone Levels 4 and 5 Cell/Area Zone Levels 0–2 Internet FIBER FIBER FIBER FIBER FIBER VLAN VLAN FIBER FIBER Enterprise Zone Provided by End User IT HMI Server (Primary) MES/Historian Server Engineering Workstation #1 HMI Server (Secondary) VLAN FIBER FIBER Enterprise Zone Office PC’s VLAN FT View SE HMI Clients (QTY 5): ` ` ` VLAN PanelView+ (Qty 5) FIBER Engineering Workstation #2 VLAN Terminal Server (Primary) VLAN Terminal Server (Secondary) VLAN Domain Controller (Primary) VLAN Domain Controller (Secondary) VLAN NOTE: Maximum allowed length of Cat 6 cable is 100 meters (330ft) VLAN FT View SE HMI Clients (QTY 2): ` ` ` VLAN HIST01 ENG01 ENG02 TS01 TS02 DOM01 DOM02 Cisco 3750X Switch Stack DLR Representation Is Symbolic Only...See Area Pages For Specifics VLAN Ctrl Area 3 Ctrl Area 3 Device Level Ring RIO – Area 3 2 VLAN RIO – Area 3 1 VLAN ` FT View SE HMI Client HMI STRATIX CLX – Area 3 0A CLX – Area 3 0B DLR Representation Is Symbolic Only...See Area Pages For Specifics VLAN Area 4 PLC 4.0 with GracePort Interface Ctrl Area 4 Ctrl Area 4 Device Level Ring RIO – Area 4 2 VLAN CLX – Area 4 0A CLX – Area 4 0B RIO – Area 4 3 Area 4 PLC 4.1 FIBER RIO – Area 4 1 Scale Weight (Qty 12) x12 FIBER x5 FT View SE HMI Client (Qty2) VLAN x2 ` RIO – Area 4 4 FIBERArea 4 PLC 4.2 DLR STRATIX HMI STRATIX VLAN AREA 5 PLC CABINET Ctrl Area 5 Ctrl Area 5 Device Level Ring RIO – Area 5 2 VLAN CLX – Area 5 0A CLX – Area 5 0B MODBUS RIO – Area 5 1 MODBUS Ctrl Area 5 Drives (Qty 2) Spang SCR – Power Control (Qty 7) MODBUS x7 Spang SCR – Power Control (Qty 8) MODBUS x8 SPANG Network Enclosure MicroLogix 1100 ATS (Qty 2) x2 FIBER Scale Weight (Qty 2) Power Logic Monitor (Qty 6)MODBUS x6 x2 FIBER VLAN VLAN MB STRATIX DLR STRATIX HMI STRATIX DLR Representation Is Symbolic Only...See Area Pages For Specifics VLAN Ctrl Area 1 Ctrl Area 1 Device Level Ring Drives (Qty 9) RIO – Area 1 2 VLAN CLX – Area 1 0A CLX – Area 1 0B RIO – Area 1 3 Area 1 MCC FIBER MODBUS RIO – Area 1 1 MODBUS Drives (Qty 2) FIBER Spang SCR – Power Control (Qty 16) MODBUS x16 Spang SCR – Power Control (Qty 16) MODBUS x16 SPANG Network Enclosure HMI STRATIX MB STRATIX DLR Representation Is Symbolic Only...See Area Pages For Specifics VLAN Ctrl Area 2 Ctrl Area 2 Device Level Ring SLC 5/05 – Gas Safety A SLC 5/05 – Gas Safety B Drives (Qty 20) MicroLogix 1100 ATS (Qty 6) RIO – Area 2 1 RIO – Area 2 2 FIBER RIO – Area 2 4 RIO – Area 2 4 Power Logic Monitor (Qty 8) Generator Control Panel Area 2 PLC 1.2 Area 2 PLC 1.1 with GracePort Interface VLAN CLX – Area 2 0A CLX – Area 2 0B Gas Safety Panel MODBUS MODBUS MODBUS x8 x6 Drives (Qty 4) FIBER VLAN ` FT View SE HMI Client HMI STRATIX FN_DLRSTRX MB STRATIX DLR Representation Is Symbolic Only...See Area Pages For Specifics ` FT View SE HMI Client ` FT View SE HMI Client ` FT View SE HMI Client DLR Representation Is Symbolic Only...See Area Pages For Specifics 1200 I/O, 5 Areas, 8 Consoles, MES/Historian, 30 Drives, Virtualized
  • 15. Paper Machine Phased Migration 2000 I/O, 3 Areas, 10 Consoles, PI Addressing, Virtualized
  • 16. Glass Plant Paper Mill I/O total 1385 2100 Remote I/O enclosures 0 21 PCU's 4 PCU, 8 MFP 4 PCU, 9 MFC CLX Controllers 5 Redundant Pair 3 HMI Consoles 12 10 HMI Graphics 25 plus 15 custom popups 99 plus 40 popup faceplates Interfaces Resolver Interface Module, 20 30 + ModbusTCP devices, 30+ PowerFlex Drives (new), 50+ HART xmtrs/actuators PI, GE Drives, PLC5, ModBus Historian x x Drives PowerFlex, in new scope GE Serial Interface Optimimzation x interface to VAX PI scope New, FTHistorian yes, to be comverted to FTHistorian Schedule Strategy System Price $ changes RoviSys first full Plant Pax Plant Pax look with custom CMs for Bailey Custom faceplates & CMs Work with Bailey configs during phasing Virtualized Servers Virtualized Servers Client specify VM Rockwell design for high availability simple, less expensive, 2 servers 3 servers, Vsphere selects Server for reliability support not as convenient push button' backups
  • 17. Glass Plant Paper Mill I/O total 1385 2100 Remote I/O enclosures 0 21 PCU's 4 PCU, 8 MFP 4 PCU, 9 MFC CLX Controllers 5 Redundant Pair 3 HMI Consoles 12 10 HMI Graphics 25 plus 15 custom popups 99 plus 40 popup faceplates Interfaces Resolver Interface Module, 20 30 + ModbusTCP devices, 30+ PowerFlex Drives (new), 50+ HART xmtrs/actuators PI, GE Drives, PLC5, ModBus Historian x x Drives PowerFlex, in new scope GE Serial Interface Optimimzation x interface to VAX PI scope New, FTHistorian yes, to be comverted to FTHistorian Schedule install 12 mon after order 2 year plus cutover plan Strategy Rip & Replace Phased Migration System Price $1.4MM $1.9MM $ changes $150K $350K RoviSys first full Plant Pax Plant Pax look with custom CMs for Bailey Custom faceplates & CMs Work with Bailey configs during phasing Virtualized Servers Virtualized Servers Client specify VM Rockwell design for high availability simple, less expensive, 2 servers 3 servers, Vsphere selects Server for reliability support not as convenient push button' backups
  • 18. Summary • Plan • Audit • Update Documentation • Migration Plan and FEL Pricing • Look for Payback • Operations • Maintenance & Support • Long term operational benefits • Understand what drives your company’s decisions • Partner with someone who has seen it all
  • 20. Who are we?... The RoviSys Company • Founded in 1989 • ~600 Employees • Rockwell Automation Solution Partner • Certified Member CSIA, Control and Information System Integrators Association • Rockwell’s Bailey Migration Tools, cables, and OLDI cATM-BLY90 • Rockwell Cable Solutions to DCS I/O Terminations; Bailey, APACS, RS3, etc. • Automation and Information Systems
  • 21. Contact Information • Dan Burger, P.E., C.E.M. – Business Development Market Manager Dan.burger@rovisys.com (330)936-1112 • James Riccardi, P.E. – Group Manager, California Projects Riccardi@rovisys.com (330)472-3034