SlideShare a Scribd company logo
A Case Study for Substation Lightning Strike Risk Evaluation
Stephen Chuang
111 Dunsmuir Street #400, Vancouver, BC V6B 5W3
604-6644123
Stephen.chuang@amecfw.com
Abstract
Shielding of substations from direct lightning strokes is a common practice used to protect equipment
from damage and reduce the number of system outages caused by lightning. However, when a substation
is being upgraded, installation of lightning masts and shielding wires across the substation for full
coverage may not be realistic as the necessary outages may not be available.
This paper is a case study for the lightning shielding design of a substation transformer addition and
feeder section expansion project. By analyzing the lightning exposure level of the area and risk evaluation
of direct lightning strokes to a substation, it is possible to design from a practical perspective of
approaching substantial but not complete shielding coverage of the station; hence reduce the outage zone
required during construction.
This case study also provides recommendations for future lightning protection design for existing
(brownfield) substation.
Index Terms – Fixed angle method, ground flash density, lightning mast, risk evaluation, rolling
sphere method, shield wire, substation.
1.0 Introduction
In early 2012, Amec Foster Wheeler started a capacity addition project. The area of the substation was
expanded to accommodate a new 25 kV feeder section and a new 69 kV/25 kV power transformer where
the fixed angle method was originally used to protect the substation when it was built in 1964.
The project scope included upgrading the substation lightning projection to use the rolling sphere method,
in accordance with IEEE 998 and to conform to the owner’s latest engineering standards on lightning
protection and enhance the coverage of the expanded new substation area.
Rolling sphere is a simplified technique for applying the electrogeometric theory to the shielding of
substations. The technique involves rolling an imaginary sphere of prescribed radius over the surface of a
substation. The sphere rolls up and over (and is supported by) lightning masts, shield wires, fences, and
other grounded metal objects intended for lightning shielding. A piece of equipment is protected from a
direct stroke if it remains below the curved surface of the sphere by virtue of the sphere being elevated by
shield wires or other devices. Equipment that touches the sphere or penetrates its surface is not protected
[1].
Following the calculation method provided in IEEE 998, Annex B, the design for the rolling sphere
method would require six lightning masts with shield wire around the perimeter and crisscrossing the
switchyard. Figure 1 shows the station fully covered from lightning strikes with masts and shield wires by
using rolling sphere method.
The detailed design was progressed using the rolling sphere method. However, it was noted in the
constructability review with the client that the outage on transformer T2 might not be available at the time
of construction. To avoid the risk of delaying the project and modifying the design greatly, Amec Foster
Wheeler performed a detailed study of the possibility of switching to the fixed angle method using the
pre-determined locations of lightning masts and surrounding shield wires that were selected based on the
rolling sphere method. A risk evaluation between the rolling sphere method and the fixed angle method,
as well as the failure rate of each method, were performed and are noted in later sections.
Figure 1: Lightning Protection for the Substation - Rolling Sphere Method
2.0 Shielding Coverage with Fixed Angle Method
Fixed angle method is a technique that uses vertical angles to determine the number, position, and height
of shielding wires or masts. The protection angle is selected based on the acceptable level of exposure.
This fixed angle of protection forms a cone around masts or spires. The protection zone around shield
wires forms a triangular prism beneath shield wire.
For the fixed angle method, the value of the angle alpha that is commonly used is 45 degrees. Both 30
degrees and 45 degrees are widely used for angle beta [1]. Horvath [2] suggests a protective angle of 40
degrees to 45 degrees for heights up to 15 m, 30 degrees for heights between 15 and 25 m, and less than
20 degrees for heights to 50 m. With this recommendations, a failure rate of 0.1 to 0.2 shielding
failures/100 km/year was assumed.
The protective angle used for this substation is α = 45⁰, β = 45⁰. Using the lightning mast locations
determined by the rolling sphere method, the coverage area in figure 2 indicates that a large portion of the
25 kV switchyard remains exposed. Although the risk evaluation in the later sections shows that this is
acceptable for this location, adding an additional mast to improve the coverage was also considered
(figure 3).
Figure 2: Lightning Shield Coverage Area, α = 45⁰, β = 45⁰
Figure 3: Lightning Shield Coverage Area, α = 45⁰, β = 45⁰, with a Lightning Mast
Table 1 shows the amount of unshielded area within the substation with two different scenarios.
Options Coverage Area (m2
)
Option 1: α = 45⁰, β = 45⁰, with a lightning mast 1010
Option 2: α = 45⁰, β = 45⁰, without lightning mast 1581
Table 1: Unshielded Area with Fixed Angle Method
3.0 Risk Evaluation
The risk of a direct strike to equipment associated with each lightning protection method is directly
related to the lightning activity at the location, exposure rate of the selected scheme, and total equipment
area being protected.
3.1 Lightning Activity at the Location
Lightning activity is based on historical data and quantified as the ground flash density (GFD), which is
the number of lightning strikes per square km per year. The Canadian Lightning Detection Network has
been collecting data between 1999 to 2013. The GFD at the project site is:
NK = 0.04 flashes/km2
/year [3]
3.2 Exposure Rate of the Selected Scheme
Without direct stroke lightning protection, the failure rate is determined by the number of flashes
predicted to strike within the station area [1].
As shown in figure 4, the equipment area of the substation is 2930 m2
or 0.002930 km2
and thus the total
expected strikes within the substation is:
X = 0.04 flashes/km2
/year x 0.002930 km2
X = 1.172 x 10-4
flashes/year or 8,532 years between flashes
3.3 Tolerable Risk for a Substation
IEC Standard 62305-2 – 2010 [5] identifies the tolerable risk RT for a substation, where the risk level is
affected by different types of losses. Referring to table 2, the risk level for a substation is defined in L2,
loss of service to the public, RT = 10-3
[4].
Types of loss RT (y-1
)
L1 Loss of human life or permanent injuries 10-5
L2 Loss of service to the public 10-3
L3 Loss of cultural heritage 10-4
L4 Loss of economic value Cost/benefit comparison
Table 2 – Typical Values of Tolerable Risk RT
Based on the risk evaluation and low incidence of strikes in this region, the overall risk with the station
unprotected can be kept within acceptable risk levels per IEC 62305-2.
Figure 4: Substation Equipment Area
4.0 Risk Evaluation for Each Method
4.1 Rolling Sphere Method
The rolling sphere method is typically small with a 0.05% failure rate [1]. If masts and shield wires were
installed as per the original design, the probability of a strike reaching the equipment or bus is:
X = 1.172 x 10-4
flashes/year x 0.0005
X = 5.86 x 10-8
flashes/year or 17,064,846 years between flashes that strike the equipment or bus
4.2 Fixed Angle Methods
A normally accepted failure rate for α and β = 45⁰ is approximately 0.2% [1]. Complete coverage using
fixed angle with α and β = 45⁰ results in the probability of a strike reaching the equipment or bus:
X = 1.172 x 10-4
flashes/year x 0.002
X = 2.344 x 10-7
flashes/year or 4,266,211 years between flashes
Since the fixed angle method design is based on the pre-determined location of lightning masts and
surrounding shield wires that were selected based on the rolling sphere method, the station will be
partially exposed.
4.2.1 Risk Evaluation with an Additional Lightning Spire, Option 1
Referring to figure 3, the unshielded area within the substation is 1349 m2
and the shielded area is 1581
m2
.
The probability of a lightning strike within the unshielded area is:
X = 0.04 flashes/km2
/year x 0.001349 km2
X = 5.396 x 10-5
strikes/year
The probability of a strike hitting the shielded area is:
X = 0.04 flashes/km2
/year x 0.001581 km2
x 0.002
X = 1.265 x 10-7
strikes/year
Combining these probabilities, we have:
Total probability of strike = 5.396 x 10-5
+ 1.265 x 10-7
= 5.409 x 10-5
strikes/year or 18,489 years
between strikes.
4.2.2 Risk Evaluation with Fixed Angle Method of α = 45⁰, β = 45⁰ only, Option 2
Referring to figure 2, without the lightning spire, the unshielded area within the substation is 1920 m2
and
the shielded area is 1010 m2
.
The probability of a strike hitting the unshielded area is:
X = 0.04 flashes/km2
/year x 0.001920 km2
X = 7.68 x 10-5
strikes/year
The probability of a strike hitting the shielded area is:
X = 0.04 flashes/km2
/year x 0.001010 km2
x 0.002
X = 8.1 x 10-8
strikes/year
Combining these probabilities, we have:
Total probability of strike = 7.68 x 10-5
+ 8.1 x 10-8
= 7.69 x 10-5
strikes/year or 13,007 years between
strikes.
5.0 Comparison between Rolling Sphere Method and Fixed Angle Method
The rolling sphere method provides superior protection from strikes to the substation’s equipment,
however, the low historical GFD and the small equipment area mean there is a low anticipated frequency
of strikes within the equipment area. The comparison proves that fixed angle method with α and β = 45⁰
reduces the strike probability to a value which is several orders of magnitude below accepted values of RT
= 10-3
y-1
.
Table 3 shows the comparison of failure rate among each method.
IEC
62305-2
L3
No
Lightning
Protection
Lightning
Protection -
Rolling Sphere
Method
Lightning
Protection – Fixed
Angle Method,
Option 1
Lightning
Protection –
Fixed Angle
Method, Option 2
Failure Rate
(y-1
)
10-3
1.2 x 10-4
5.9 x 10-8
5.4 x 10-5
7.7 x 10-5
Table 3: Comparison of Failure Rates for Various Protection Methods
5.1 Comparison between Fixed Angle Method Option 1 and Option 2
Option 1 offers greater lightning shielding coverage. However, the costs and construction risks of
installing a 15.2 m tower inside the substation, together with the low incidence of strikes in this region
makes option 2 more favorable.
Although option 2 has a higher probability of having lightning strike on the equipment or bus, the
likelihood of such an event is still extremely small. Furthermore, one should also consider for the fact that
most instances of a strike to equipment or bus would not lead to a full station outage if N-1 redundancy is
available. Replacing the damaged equipment is likely the worst case scenario if lightning were to strike it.
Table 4 gives a comparison between these two options.
Option 1 – New 60 ft. Spire Option 2 – No Change to Existing Design,
only perimeter masts and shield wires and existing
internal spires
Pros  Greater station protection.
 Lower probability of direct
strike to equipment
 Adequate station protection achieved (several
magnitudes lower than IEC 62305-2)
 Does not need to modify existing design
 Have the option of using rolling sphere
method should an outage be available during
construction
 No additional cost if rolling sphere method
cannot be implemented during construction
Cons  Installing the spire would
require outages.
 Increased congestion in the
switchyard due to new spire
 Construction costs and risks
erecting spire near equipment
 Higher probability of future strikes to
equipment compared to option 1
Table 4: Comparison between Option 1 and Option 2
6.0 Conclusion
The risk evaluations performed in this case study are useful for future projects. Fixed angle method may
be suggested as a mean of lightning protection to the client where their facilities are located in areas with
low incidence of lightning strikes.
This case study also serves as a good example of the considerations for upgrading lighting protection
schemes within brownfield substations. It highlights the importance of preparing the construction staging
plan in the early stages of projects. Being able to identify the availability of required outages allows the
design team to ensure their design is constructible. Any modification due to unforeseen circumstances
during construction often means the delay of schedule, as well as significant amount of costs.
It is also important to agree upon a minimum acceptable failure rate for substations with the owner and
operator based on the substation size and importance of the station to help determine the overall required
system protection levels. This allows alternative lightning protection design methods, such as the fixed
angle method, to be considered.
7.0 References
[1] “IEEE Guide for Direct Lightning Stroke Shielding of Substations,” IEEE Std. 998-2012, 2012.
[2] Horvath, T., Computation of Lightning Protection, Taunton, Somerset, England: Research Studies
Press, 1991.
[3] “Lightning Activity in Canadian Cities,” 4 July 2013. [Online]. Available: https://ec.gc.ca/foudre-
lightning/default.asp?lang=En&n=4871AAE6-1.
[4] “Protection against lightning – Part 2: Risk Management, “ IEC 62305-2:2010, 2010.
[5] “IEC International Standard,
Protection Against Lightning – Part
2: Risk Management,” IEC 62305-2,
Edition 2.0, 2010-12.

More Related Content

Similar to Case Study - Lightning Protection

L16 radiation shielding
L16  radiation shieldingL16  radiation shielding
L16 radiation shielding
Mahbubul Hassan
 
A Review and study of the design technique of Microstrip Patch Antenna Techno...
A Review and study of the design technique of Microstrip Patch Antenna Techno...A Review and study of the design technique of Microstrip Patch Antenna Techno...
A Review and study of the design technique of Microstrip Patch Antenna Techno...
IJERA Editor
 
Schneider electric : Neutral Earthing
Schneider electric : Neutral EarthingSchneider electric : Neutral Earthing
Schneider electric : Neutral Earthing
Eduardo Higino
 
ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...
ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...
ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...
SyamsirAbduh2
 
ORBITAL ESE ACTIVE LIGHTNING ARRESTER
ORBITAL ESE ACTIVE LIGHTNING ARRESTERORBITAL ESE ACTIVE LIGHTNING ARRESTER
ORBITAL ESE ACTIVE LIGHTNING ARRESTER
REIDIUS ELECTRIC COMPANY
 
IRJET- A Review: Microstrip Antenna
IRJET-  	  A Review: Microstrip AntennaIRJET-  	  A Review: Microstrip Antenna
IRJET- A Review: Microstrip Antenna
IRJET Journal
 
Design and Analysis of M-Shape Microstrip Patch Antenna for Wireless Communic...
Design and Analysis of M-Shape Microstrip Patch Antenna for Wireless Communic...Design and Analysis of M-Shape Microstrip Patch Antenna for Wireless Communic...
Design and Analysis of M-Shape Microstrip Patch Antenna for Wireless Communic...
IJCSIS Research Publications
 
IDENTIFICATION OF TOWER AND BOOM-WAKES USING COLLOCATED ANEMOMETERS AND LIDAR...
IDENTIFICATION OF TOWER AND BOOM-WAKES USING COLLOCATED ANEMOMETERS AND LIDAR...IDENTIFICATION OF TOWER AND BOOM-WAKES USING COLLOCATED ANEMOMETERS AND LIDAR...
IDENTIFICATION OF TOWER AND BOOM-WAKES USING COLLOCATED ANEMOMETERS AND LIDAR...
IAEME Publication
 
Smart india inteligence india presentation by jmv lps
Smart india inteligence india presentation by jmv lpsSmart india inteligence india presentation by jmv lps
Smart india inteligence india presentation by jmv lps
Mahesh Chandra Manav
 
Impact and analytical study of the patch and slot for antenna design
Impact and analytical study of the patch and slot for antenna designImpact and analytical study of the patch and slot for antenna design
Impact and analytical study of the patch and slot for antenna design
eSAT Journals
 
Impact and analytical study of the patch and slot for
Impact and analytical study of the patch and slot forImpact and analytical study of the patch and slot for
Impact and analytical study of the patch and slot for
eSAT Publishing House
 
2015 nfpa 70 e changes
2015 nfpa 70 e changes2015 nfpa 70 e changes
2015 nfpa 70 e changes
Arc Flash Training
 
IRJET- Microstrip Patch Antenna Design for Military Applications
IRJET- Microstrip Patch Antenna Design for Military ApplicationsIRJET- Microstrip Patch Antenna Design for Military Applications
IRJET- Microstrip Patch Antenna Design for Military Applications
IRJET Journal
 
IRJET- Circularly Polarized Ultra Wide Band Ring Shaped DGS Microstrip An...
IRJET-  	  Circularly Polarized Ultra Wide Band Ring Shaped DGS Microstrip An...IRJET-  	  Circularly Polarized Ultra Wide Band Ring Shaped DGS Microstrip An...
IRJET- Circularly Polarized Ultra Wide Band Ring Shaped DGS Microstrip An...
IRJET Journal
 
Designing a microstrip patch antenna - operating at 1.518Ghz.
Designing a microstrip  patch antenna - operating at 1.518Ghz.Designing a microstrip  patch antenna - operating at 1.518Ghz.
Designing a microstrip patch antenna - operating at 1.518Ghz.
IRJET Journal
 
Converting Solidly to HRG
Converting Solidly to HRGConverting Solidly to HRG
Converting Solidly to HRG
Edmundo Perich
 
Arc flash analysis and electrical hazards
Arc flash analysis and electrical hazardsArc flash analysis and electrical hazards
Arc flash analysis and electrical hazards
VB Engineering
 
Design and implementation of microstrip antenna for
Design and implementation of microstrip antenna forDesign and implementation of microstrip antenna for
Design and implementation of microstrip antenna for
eSAT Publishing House
 
Arc flash q
Arc flash qArc flash q
Arc flash q
guestf8e1f7
 
Multiband Circular Microstrip Patch Antenna for WLAN Application
	Multiband Circular Microstrip Patch Antenna for WLAN Application	Multiband Circular Microstrip Patch Antenna for WLAN Application
Multiband Circular Microstrip Patch Antenna for WLAN Application
theijes
 

Similar to Case Study - Lightning Protection (20)

L16 radiation shielding
L16  radiation shieldingL16  radiation shielding
L16 radiation shielding
 
A Review and study of the design technique of Microstrip Patch Antenna Techno...
A Review and study of the design technique of Microstrip Patch Antenna Techno...A Review and study of the design technique of Microstrip Patch Antenna Techno...
A Review and study of the design technique of Microstrip Patch Antenna Techno...
 
Schneider electric : Neutral Earthing
Schneider electric : Neutral EarthingSchneider electric : Neutral Earthing
Schneider electric : Neutral Earthing
 
ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...
ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...
ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...
 
ORBITAL ESE ACTIVE LIGHTNING ARRESTER
ORBITAL ESE ACTIVE LIGHTNING ARRESTERORBITAL ESE ACTIVE LIGHTNING ARRESTER
ORBITAL ESE ACTIVE LIGHTNING ARRESTER
 
IRJET- A Review: Microstrip Antenna
IRJET-  	  A Review: Microstrip AntennaIRJET-  	  A Review: Microstrip Antenna
IRJET- A Review: Microstrip Antenna
 
Design and Analysis of M-Shape Microstrip Patch Antenna for Wireless Communic...
Design and Analysis of M-Shape Microstrip Patch Antenna for Wireless Communic...Design and Analysis of M-Shape Microstrip Patch Antenna for Wireless Communic...
Design and Analysis of M-Shape Microstrip Patch Antenna for Wireless Communic...
 
IDENTIFICATION OF TOWER AND BOOM-WAKES USING COLLOCATED ANEMOMETERS AND LIDAR...
IDENTIFICATION OF TOWER AND BOOM-WAKES USING COLLOCATED ANEMOMETERS AND LIDAR...IDENTIFICATION OF TOWER AND BOOM-WAKES USING COLLOCATED ANEMOMETERS AND LIDAR...
IDENTIFICATION OF TOWER AND BOOM-WAKES USING COLLOCATED ANEMOMETERS AND LIDAR...
 
Smart india inteligence india presentation by jmv lps
Smart india inteligence india presentation by jmv lpsSmart india inteligence india presentation by jmv lps
Smart india inteligence india presentation by jmv lps
 
Impact and analytical study of the patch and slot for antenna design
Impact and analytical study of the patch and slot for antenna designImpact and analytical study of the patch and slot for antenna design
Impact and analytical study of the patch and slot for antenna design
 
Impact and analytical study of the patch and slot for
Impact and analytical study of the patch and slot forImpact and analytical study of the patch and slot for
Impact and analytical study of the patch and slot for
 
2015 nfpa 70 e changes
2015 nfpa 70 e changes2015 nfpa 70 e changes
2015 nfpa 70 e changes
 
IRJET- Microstrip Patch Antenna Design for Military Applications
IRJET- Microstrip Patch Antenna Design for Military ApplicationsIRJET- Microstrip Patch Antenna Design for Military Applications
IRJET- Microstrip Patch Antenna Design for Military Applications
 
IRJET- Circularly Polarized Ultra Wide Band Ring Shaped DGS Microstrip An...
IRJET-  	  Circularly Polarized Ultra Wide Band Ring Shaped DGS Microstrip An...IRJET-  	  Circularly Polarized Ultra Wide Band Ring Shaped DGS Microstrip An...
IRJET- Circularly Polarized Ultra Wide Band Ring Shaped DGS Microstrip An...
 
Designing a microstrip patch antenna - operating at 1.518Ghz.
Designing a microstrip  patch antenna - operating at 1.518Ghz.Designing a microstrip  patch antenna - operating at 1.518Ghz.
Designing a microstrip patch antenna - operating at 1.518Ghz.
 
Converting Solidly to HRG
Converting Solidly to HRGConverting Solidly to HRG
Converting Solidly to HRG
 
Arc flash analysis and electrical hazards
Arc flash analysis and electrical hazardsArc flash analysis and electrical hazards
Arc flash analysis and electrical hazards
 
Design and implementation of microstrip antenna for
Design and implementation of microstrip antenna forDesign and implementation of microstrip antenna for
Design and implementation of microstrip antenna for
 
Arc flash q
Arc flash qArc flash q
Arc flash q
 
Multiband Circular Microstrip Patch Antenna for WLAN Application
	Multiband Circular Microstrip Patch Antenna for WLAN Application	Multiband Circular Microstrip Patch Antenna for WLAN Application
Multiband Circular Microstrip Patch Antenna for WLAN Application
 

Recently uploaded

BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 

Recently uploaded (20)

BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 

Case Study - Lightning Protection

  • 1. A Case Study for Substation Lightning Strike Risk Evaluation Stephen Chuang 111 Dunsmuir Street #400, Vancouver, BC V6B 5W3 604-6644123 Stephen.chuang@amecfw.com Abstract Shielding of substations from direct lightning strokes is a common practice used to protect equipment from damage and reduce the number of system outages caused by lightning. However, when a substation is being upgraded, installation of lightning masts and shielding wires across the substation for full coverage may not be realistic as the necessary outages may not be available. This paper is a case study for the lightning shielding design of a substation transformer addition and feeder section expansion project. By analyzing the lightning exposure level of the area and risk evaluation of direct lightning strokes to a substation, it is possible to design from a practical perspective of approaching substantial but not complete shielding coverage of the station; hence reduce the outage zone required during construction. This case study also provides recommendations for future lightning protection design for existing (brownfield) substation. Index Terms – Fixed angle method, ground flash density, lightning mast, risk evaluation, rolling sphere method, shield wire, substation.
  • 2. 1.0 Introduction In early 2012, Amec Foster Wheeler started a capacity addition project. The area of the substation was expanded to accommodate a new 25 kV feeder section and a new 69 kV/25 kV power transformer where the fixed angle method was originally used to protect the substation when it was built in 1964. The project scope included upgrading the substation lightning projection to use the rolling sphere method, in accordance with IEEE 998 and to conform to the owner’s latest engineering standards on lightning protection and enhance the coverage of the expanded new substation area. Rolling sphere is a simplified technique for applying the electrogeometric theory to the shielding of substations. The technique involves rolling an imaginary sphere of prescribed radius over the surface of a substation. The sphere rolls up and over (and is supported by) lightning masts, shield wires, fences, and other grounded metal objects intended for lightning shielding. A piece of equipment is protected from a direct stroke if it remains below the curved surface of the sphere by virtue of the sphere being elevated by shield wires or other devices. Equipment that touches the sphere or penetrates its surface is not protected [1]. Following the calculation method provided in IEEE 998, Annex B, the design for the rolling sphere method would require six lightning masts with shield wire around the perimeter and crisscrossing the switchyard. Figure 1 shows the station fully covered from lightning strikes with masts and shield wires by using rolling sphere method. The detailed design was progressed using the rolling sphere method. However, it was noted in the constructability review with the client that the outage on transformer T2 might not be available at the time of construction. To avoid the risk of delaying the project and modifying the design greatly, Amec Foster Wheeler performed a detailed study of the possibility of switching to the fixed angle method using the pre-determined locations of lightning masts and surrounding shield wires that were selected based on the rolling sphere method. A risk evaluation between the rolling sphere method and the fixed angle method, as well as the failure rate of each method, were performed and are noted in later sections.
  • 3. Figure 1: Lightning Protection for the Substation - Rolling Sphere Method 2.0 Shielding Coverage with Fixed Angle Method Fixed angle method is a technique that uses vertical angles to determine the number, position, and height of shielding wires or masts. The protection angle is selected based on the acceptable level of exposure. This fixed angle of protection forms a cone around masts or spires. The protection zone around shield wires forms a triangular prism beneath shield wire. For the fixed angle method, the value of the angle alpha that is commonly used is 45 degrees. Both 30 degrees and 45 degrees are widely used for angle beta [1]. Horvath [2] suggests a protective angle of 40 degrees to 45 degrees for heights up to 15 m, 30 degrees for heights between 15 and 25 m, and less than 20 degrees for heights to 50 m. With this recommendations, a failure rate of 0.1 to 0.2 shielding failures/100 km/year was assumed. The protective angle used for this substation is α = 45⁰, β = 45⁰. Using the lightning mast locations determined by the rolling sphere method, the coverage area in figure 2 indicates that a large portion of the 25 kV switchyard remains exposed. Although the risk evaluation in the later sections shows that this is acceptable for this location, adding an additional mast to improve the coverage was also considered (figure 3).
  • 4. Figure 2: Lightning Shield Coverage Area, α = 45⁰, β = 45⁰
  • 5. Figure 3: Lightning Shield Coverage Area, α = 45⁰, β = 45⁰, with a Lightning Mast Table 1 shows the amount of unshielded area within the substation with two different scenarios. Options Coverage Area (m2 ) Option 1: α = 45⁰, β = 45⁰, with a lightning mast 1010 Option 2: α = 45⁰, β = 45⁰, without lightning mast 1581 Table 1: Unshielded Area with Fixed Angle Method
  • 6. 3.0 Risk Evaluation The risk of a direct strike to equipment associated with each lightning protection method is directly related to the lightning activity at the location, exposure rate of the selected scheme, and total equipment area being protected. 3.1 Lightning Activity at the Location Lightning activity is based on historical data and quantified as the ground flash density (GFD), which is the number of lightning strikes per square km per year. The Canadian Lightning Detection Network has been collecting data between 1999 to 2013. The GFD at the project site is: NK = 0.04 flashes/km2 /year [3] 3.2 Exposure Rate of the Selected Scheme Without direct stroke lightning protection, the failure rate is determined by the number of flashes predicted to strike within the station area [1]. As shown in figure 4, the equipment area of the substation is 2930 m2 or 0.002930 km2 and thus the total expected strikes within the substation is: X = 0.04 flashes/km2 /year x 0.002930 km2 X = 1.172 x 10-4 flashes/year or 8,532 years between flashes 3.3 Tolerable Risk for a Substation IEC Standard 62305-2 – 2010 [5] identifies the tolerable risk RT for a substation, where the risk level is affected by different types of losses. Referring to table 2, the risk level for a substation is defined in L2, loss of service to the public, RT = 10-3 [4]. Types of loss RT (y-1 ) L1 Loss of human life or permanent injuries 10-5 L2 Loss of service to the public 10-3 L3 Loss of cultural heritage 10-4 L4 Loss of economic value Cost/benefit comparison Table 2 – Typical Values of Tolerable Risk RT Based on the risk evaluation and low incidence of strikes in this region, the overall risk with the station unprotected can be kept within acceptable risk levels per IEC 62305-2.
  • 7. Figure 4: Substation Equipment Area 4.0 Risk Evaluation for Each Method 4.1 Rolling Sphere Method The rolling sphere method is typically small with a 0.05% failure rate [1]. If masts and shield wires were installed as per the original design, the probability of a strike reaching the equipment or bus is: X = 1.172 x 10-4 flashes/year x 0.0005 X = 5.86 x 10-8 flashes/year or 17,064,846 years between flashes that strike the equipment or bus 4.2 Fixed Angle Methods A normally accepted failure rate for α and β = 45⁰ is approximately 0.2% [1]. Complete coverage using fixed angle with α and β = 45⁰ results in the probability of a strike reaching the equipment or bus: X = 1.172 x 10-4 flashes/year x 0.002
  • 8. X = 2.344 x 10-7 flashes/year or 4,266,211 years between flashes Since the fixed angle method design is based on the pre-determined location of lightning masts and surrounding shield wires that were selected based on the rolling sphere method, the station will be partially exposed. 4.2.1 Risk Evaluation with an Additional Lightning Spire, Option 1 Referring to figure 3, the unshielded area within the substation is 1349 m2 and the shielded area is 1581 m2 . The probability of a lightning strike within the unshielded area is: X = 0.04 flashes/km2 /year x 0.001349 km2 X = 5.396 x 10-5 strikes/year The probability of a strike hitting the shielded area is: X = 0.04 flashes/km2 /year x 0.001581 km2 x 0.002 X = 1.265 x 10-7 strikes/year Combining these probabilities, we have: Total probability of strike = 5.396 x 10-5 + 1.265 x 10-7 = 5.409 x 10-5 strikes/year or 18,489 years between strikes. 4.2.2 Risk Evaluation with Fixed Angle Method of α = 45⁰, β = 45⁰ only, Option 2 Referring to figure 2, without the lightning spire, the unshielded area within the substation is 1920 m2 and the shielded area is 1010 m2 . The probability of a strike hitting the unshielded area is: X = 0.04 flashes/km2 /year x 0.001920 km2 X = 7.68 x 10-5 strikes/year The probability of a strike hitting the shielded area is: X = 0.04 flashes/km2 /year x 0.001010 km2 x 0.002 X = 8.1 x 10-8 strikes/year Combining these probabilities, we have: Total probability of strike = 7.68 x 10-5 + 8.1 x 10-8 = 7.69 x 10-5 strikes/year or 13,007 years between strikes.
  • 9. 5.0 Comparison between Rolling Sphere Method and Fixed Angle Method The rolling sphere method provides superior protection from strikes to the substation’s equipment, however, the low historical GFD and the small equipment area mean there is a low anticipated frequency of strikes within the equipment area. The comparison proves that fixed angle method with α and β = 45⁰ reduces the strike probability to a value which is several orders of magnitude below accepted values of RT = 10-3 y-1 . Table 3 shows the comparison of failure rate among each method. IEC 62305-2 L3 No Lightning Protection Lightning Protection - Rolling Sphere Method Lightning Protection – Fixed Angle Method, Option 1 Lightning Protection – Fixed Angle Method, Option 2 Failure Rate (y-1 ) 10-3 1.2 x 10-4 5.9 x 10-8 5.4 x 10-5 7.7 x 10-5 Table 3: Comparison of Failure Rates for Various Protection Methods 5.1 Comparison between Fixed Angle Method Option 1 and Option 2 Option 1 offers greater lightning shielding coverage. However, the costs and construction risks of installing a 15.2 m tower inside the substation, together with the low incidence of strikes in this region makes option 2 more favorable. Although option 2 has a higher probability of having lightning strike on the equipment or bus, the likelihood of such an event is still extremely small. Furthermore, one should also consider for the fact that most instances of a strike to equipment or bus would not lead to a full station outage if N-1 redundancy is available. Replacing the damaged equipment is likely the worst case scenario if lightning were to strike it. Table 4 gives a comparison between these two options.
  • 10. Option 1 – New 60 ft. Spire Option 2 – No Change to Existing Design, only perimeter masts and shield wires and existing internal spires Pros  Greater station protection.  Lower probability of direct strike to equipment  Adequate station protection achieved (several magnitudes lower than IEC 62305-2)  Does not need to modify existing design  Have the option of using rolling sphere method should an outage be available during construction  No additional cost if rolling sphere method cannot be implemented during construction Cons  Installing the spire would require outages.  Increased congestion in the switchyard due to new spire  Construction costs and risks erecting spire near equipment  Higher probability of future strikes to equipment compared to option 1 Table 4: Comparison between Option 1 and Option 2 6.0 Conclusion The risk evaluations performed in this case study are useful for future projects. Fixed angle method may be suggested as a mean of lightning protection to the client where their facilities are located in areas with low incidence of lightning strikes. This case study also serves as a good example of the considerations for upgrading lighting protection schemes within brownfield substations. It highlights the importance of preparing the construction staging plan in the early stages of projects. Being able to identify the availability of required outages allows the design team to ensure their design is constructible. Any modification due to unforeseen circumstances during construction often means the delay of schedule, as well as significant amount of costs. It is also important to agree upon a minimum acceptable failure rate for substations with the owner and operator based on the substation size and importance of the station to help determine the overall required system protection levels. This allows alternative lightning protection design methods, such as the fixed angle method, to be considered.
  • 11. 7.0 References [1] “IEEE Guide for Direct Lightning Stroke Shielding of Substations,” IEEE Std. 998-2012, 2012. [2] Horvath, T., Computation of Lightning Protection, Taunton, Somerset, England: Research Studies Press, 1991. [3] “Lightning Activity in Canadian Cities,” 4 July 2013. [Online]. Available: https://ec.gc.ca/foudre- lightning/default.asp?lang=En&n=4871AAE6-1. [4] “Protection against lightning – Part 2: Risk Management, “ IEC 62305-2:2010, 2010. [5] “IEC International Standard, Protection Against Lightning – Part 2: Risk Management,” IEC 62305-2, Edition 2.0, 2010-12.