Proses Pengadaan dan
Standar Kontrak Pembangkit
Tenaga Listrik
Yang Memanfaatkan
Sumber Energi Terbarukan
Jakarta, 10 Agustus 2017
Dipresentasikan oleh :
Tohari Hadiat
KDIV EBT PT. PLN (Persero)
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
Prosedur Pengadaan
Pembangkit Tenaga Listrik Yang
Memanfaatkan Energi Terbarukan
1
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
2
Dilaksanakan oleh Unit
Distribusi/Wilayah
Dilaksanakan leh PLN Pusat cq DIVEBT
PLTA ≤ 10 MW PLTSa
PLTBm/PLTBg ≤ 10 MW PLT Hybrid
PLTS ≤ 10 MW PLTBm/PLTBg > 10 MW
PLTB ≤ 10 MW PLTS > 10 MW
PLTB > 10 MW
PLTA > 10 MW
PLTA Laut
PLTP
PLT Energi Baru (Gas Batubara,
Batubara Cair, Nuklir, dll)
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
2
1. Kriteria umum :
a. pasokan tenaga listrik dapat diterima oleh sistem ketenagalistrikan setempat;
b. menurunkan BPP Pembangkitan di sistem ketenagalistrikan setempat; dan/atau
c. memenuhi kebutuhan tenaga listrik di lokasi yang tidak ada sumber energi primer lain.
2. Untuk PLTBm atau PLTBg, PPL harus memiliki sumber pasokan bahan bakar (feedstock) yang cukup untuk
kelangsungan operasi PLTBm atau PLTBg selama masa PJBL.
3. PLTSa dilaksanakan oleh PPL yang telah ditetapkan oleh Pemerintah dan/atau Pemerintah Daerah dalam
rangka membantu Pemerintah dan/atau Pemerintah Daerah dalam mengatasi atau menangani persoalan
sampah kota.
4. PLTP dilaksanakan PPL yang memiliki wilayah kerja panas bumi sesuai dengan cadangan terbukti setelah
eksplorasi.
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
TAHAPAN PENYUSUNAN DPT
Menentukan instruksi kepada Calon Penyedia
Menentukan Jadwal Kualifikasi
Menentukan Ruang Lingkup Pekerjaan
 Spesifikasi Teknis / Ruang Lingkup objek
Kualifikasi
 Informasi Umum
 Persyaratan yang harus dipenuhi oleh calon penyedia
(Administrasi, Keuangan & Teknis)
 Metode Peyampaian Dokumen Aplikasi
 Metode Evaluasi & Penilaian Kualifikasi
 Jadwal Pendaftaran
 Jadwal Pengambilan dokumen
 Jadwal Rapat penjelasan
 Jadwal Penyampaian Dokumen Aplikasi
 Jadwal Pengumuman Hasil Kualifikasi
 Pengumumman
 Pendaftaran
 Penjelasan Kualifikasi
 Pemasukan Dokumen Aplikasi
 Evaluasi Kualifikasi
 Berita Acara Hasil Kualifikasi
 Rekomendasi VfM Committee
 Pengumuman Hasil Kualifikasi
 Masa Sanggah
 Pengesahan Hasil Kualifikasi
 Penerbitan Tanda DPT
DAFTAR
PENYEDIA
TERSELEKSI
(DPT)
PENYUSUNAN
DOKUMEN
KUALIFIKASI
PROSES
KUALIFIKASI
Kriteria Pembelian Tenaga Listrik dari Pembangkit
Energi Terbarukan
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
TAHAPAN KUALIFIKASI DPT
Dalam pelaksanaannya dapat dibantu oleh pihak lain sesuai keahlian baik internal maupun
eksternal PLN.
PENGUMUMAN
KUALIFIKASI
PENDAFTARAN DAN
PENGAMBILAN
DOKUMEN
KUALIFIKASI
RAPAT PENJELASAN
KUALIFIKASI
PEMASUKAN
DOKUMEN APLIKASI
EVALUASI
KUALIFIKASI & DUE
DILIGENCE
BERITA ACARA
HASIL EVALUASI
KUALIFIKASI
REKOMENDASI VfM
COMMITTEE
PENGUMUMAN
HASIL KUALIFIKASI
MASA SANGGAH
PENGESAHAN HASIL
KUALIFIKASI
DPT
PENETAPAN HASIL
EVALAUSI OLEH
PENGGUNA
VFM ?
Y
N
Kriteria Pembelian Tenaga Listrik dari Pembangkit
Energi Terbarukan
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
2
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
Standar Kontrak (PJBL/PPA)
Pembangkit Tenaga Listrik Yang
Memanfaatkan Energi Terbarukan
1
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
Jangka waktu PPA paling lama 30 tahun sejak COD dengan mempertimbangkan jenis Pembangkit.
Draft PPA yang dibuat saat ini adalah sebagai berikut:
PPA Energi Baru dan Terbarukan (EBT)
• PLTS, PLTBm, PLTBg, PLTM adalah paling lama 25 tahun
• PLTA adalah paling lama 30 tahun
• PLTP dengan mempertimbangkan jangka waktu IPB (berdasarkan PP 7/2017)
Jangka Waktu PPA EBT
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
• Pola kerja sama menggunakan pola Build, Own Operate, Transfer (BOOT) yang mensyaratkan
Pembangkit harus diserahkan pada akhir masa PPA dalam kondisi yang baik (Operable Condition).
• Untuk PLTP, terkait dengan Wilayah Kerja Panas Bumi yang tidak dapat dialihkan (IPB dilarang untuk
dialihkan berdasarkan Pasal 27(1) UU 21/2004), PLN memiliki opsi untuk membeli proyek selain
melalui pengalihan asset (pembangkit dan fasilitasnya) maka dapat melalui pengalihan saham(-saham)
dalam Penjual.
Pola Kerja Sama
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
• Komponen A pada harga jual tenaga listrik dihitung berdasarkan nilai investasi yang
didepresiasi paling sedikit 20 tahun, dengan demikian dapat diartikan bahwa setelah 20
tahun nilai buku dari Pembangkit menjadi 0.
• Depresiasi ini dapat menjadi patokan dalam hal membuat harga perkiraan sendiri (HPS).
• Ketentuan ini tidak terefleksikan dalam PPA secara eksplisit namun dapat dijadikan pedoman
ketika pelaksanaan pengadaan.
Depresiasi Nilai Investasi Komponen A
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
Per
• Percepatan COD merupakan hak PLN dan harus atas permintaan PLN, dimana apabila disetujui oleh Penjual maka Penjual berhak
mendapatkan insentif. Persetujuan tersebut harus diberikan dalam waktu 30 hari sejak permintaan dari PLN.
• Permintaan percepatan COD dari PLN dapat mempertimbangkan kesiapan dari transmisi PLN atau dapat dibangun on-time sebelum
Pembangkit mencapai COD.
• Insentif diberikan dalam bentuk pembelian listrik dengan skema Take and Pay sejak aktual COD hingga Required COD (RCOD). Jangka
waktu PPA akan tetap dimulai sejak RCOD.
• PLN dan Penjual akan menandatangani berita acara terkait pelaksanaan percepatan COD, termasuk kegiatan - kegiatan terkait,
seperti kewajiban PLN untuk back-feeding, sinkronisasi dan dimulainya komisioning.
• Ketentuan LD akan tetap berlaku apabila Penjual tidak dapat mencapai COD pada jadwal yang telah disepakati, dengan perhitungan
[[Tarif (Component A+B) atau BPP] x Kapasitas Kontrak x AF x 24 jam yang dikenakan tiap hari keterlambatan.
Insentif Percepatan Commercial Operation Date (COD)
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
Jumlah
LD yang
dikenaka
• Jumlah LD yang dikenakan ke PLN dalam bentuk Deemed Dispatch yaitu listrik tidak
dialirkan akibat kesalahan PLN. Formula dari LD per hari keterlambatan adalah [[Tarif
(Component A+B) atau BPP] x Kapasitas Kontrak x AF x 24 jam, yang akan dikenakan
sejak Required COD.
• Untuk Pembangkit Intermitten, Tarif atau BPP pada perhitungan di atas dikalikan 50%.
Jumlah Proporsional Liquidated Damage (LD)
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
PENALTI PERHITUNGAN JUMLAH PENALTI
Penalti Availibility Factor atau
Capability Factor
Dihitung berdasarkan perhitungan pada Appendix G dengan ketentuan tidak boleh melebihi
10 % dari Komponen A pada Periode Penagihan terkait
Penalti Outage Factor Dihitung berdasarkan perhitungan pada Appendix G dengan ketentuan tidak boleh melebihi
10 % dari Komponen A pada Periode Penagihan terkait (termasuk Penalti untuk AF)
Penalti tara kalor (Heat Rate) Dihitung berdasarkan perhitungan pada Appendix G
Penalti kegagalan memikul
mega volt ampere reactive
(MVAR)
Rp 1.191 kVArh dikalikan dengan selisih Reactive Power yang dimintakan oleh Pusat
Pengaturan dan reactive Power yang dihasilkan secara aktual untuk setiap jam kegagalan
Penalti kegagalan menjaga
frekuensi
Mengurangkan 4 jam dikalikan dengan kapasitas kontrak dan AF pada Periode Penagihan
terkait
Penalti kecepatan naik turun
beban (ramp rate)
Dihitung berdasarkan perhitungan pada Appendix G
Note: pengenaan penalty disesuaikan berdasarkan jenis pembangkit, untuk pembangkit EBT, tidak semua penalti dapat
diaplikasikan, diantaranya penalti Heat Rate dan ramp rate.
Pinalti untuk Performa Pekerjaan
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
PLN wajib
membeli
tenaga listrik
sesuai
dengan PPA
• PLN wajib membeli tenaga listrik sesuai dengan PPA selama periode tertentu dengan memperhatikan masa pengembalian pinjaman
kepada lenders (skema Take or Pay).
• Masa Take or Pay adalah selama 15 tahun sejak COD, sedangkan Pembangkit Intermitte adalah selama 20 tahun sejak COD. Setelahnya,
untuk sisa jangka waktu PPA akan diterapkan Take and Pay.
• Dalam periode Take and Pay diberlakukan annual committed energy (sebagai refleksi CF yang disebut dalam Permen ESDM 10/2017),
yakni Total Take and Pay Energi dengan perhitungan NDClatest x 80% x PHa x (25 - nTOP) / 1,000,000. Untuk Pembangkit Intermitten,
jumlah Total Take and Pay Energi akan ditentukan oleh PLN.
Untuk energi yang dihasilkan oleh Penjual dan diterima oleh diatas Total Take and Pay Energi maka tarif dari kelebihan energi tersebut
akan dikalikan 50%.
Apabila PLN tidak dapat mengambil Total Take and Pay Energy, maka jangka waktu PPA akan ditambahkan hingga paling lama 5 tahun,
dengan ketentuan jangka waktu PPA tidak lebih dari 30 tahun.
Dalam masa Take and Pay, deemed dispatch dan Penalty AF/CF dan OF (apabila diaplikasikan) tidak berlaku.
Skema Transaksi (Take Or Pay dan Take And Pay)
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
DE
DEEMED DISPATCH
Deemed Dispatch diberikan apabila terjadi kejadian (dalam periode Take or Pay), sbb:
1. PLN (i) tidak dapat menerima tenaga listrik karena kesalahan PLN; atau (ii) kerusakan terhadap Sistem Jaringan PLN (bukan karena
FM) berdampak pada penyaluran tenaga listrik oleh Penjual.
Berlaku grace period selama 48 jam untuk setiap kejadian dan 14 hari untuk perbaikan terhadap Sistem Jaringan PLN, sedangkan
untuk PPA intermittten grace period tersebut adalah 180 jam agregat tiap tahunnya.
(Point 2 dan 3 hanya berlaku untuk Pembangkit Intermitten)
2. Terjadi Natural Force Majeure terhadap Sistem Jaringan PLN berdampak pada penyaluran tenaga listrik oleh Penjual.
Berlaku setelah grace period 16 hari agregat untuk tiap tahunnya (termasuk kejadian Natural Force Majeure dan perbaikan
kerusakan jaringan).
3. Terjadi Political Force Majeur berupa tindakan pemerintah yang sewenang – wenang (Unjustified Government Act)
Berlaku setelah grace period 30 hari (tanpa Deemed Dispatch) untuk membantu Penjual menyelesaikan masalah yang dihadapi
utamanya ditingkat local government.
Note: Dalam grace period, PLN tidak diwajibkan untuk membayar Deemed Dispatch.
Risk Sharing
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
NATURAL
FORCE
MAJEURE
NATURAL FORCE MAJEURE
Apabila terjadi Natural Force Majeur maka:
• Sebelum COD, apabila Natural FM terjadi dan berdampak pada PLN dan Penjual maka Milestone Schedule akan disesuaikan.
• Setelah COD, apabila Natural FM terjadi dan berdampak pada PLN dan Penjual maka jangka waktu PPA dapat diperpanjang sesuai
dengan lama kejadian FM tersebut. Perpanjangan jangka waktu disesuaikan dengan periode pembayaran (apabila terjadi dalam
periode Take or Pay maka periode Take or Pay yang diperpanjang), dengan ketentuan, jangka waktu PPA tidak akan melebihi 30
tahun.
Risk Sharing
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
HA
HARGA PEMBELIAN PROYEK AKIBAT TERMINASI KARENA KESALAHAN PLN
• Selama jangka waktu PPA, dalam hal terjadi terminasi karena kesalahan PLN maka PLN wajib membeli Proyek dengan harga Pembelian.
• Sebelum COD = (Outstanding Debt + Interest) + (Equity + Return)
• Setelah COD = ෍
x=0
n−1
DC × AFpy × CCR+CCRT × Fy
1+r x
+ Outstanding Debt + Interest
• Sedangkan untuk Pembangkit Intermitten adalah sbb:
• Sebelum COD = PLN wajib membeli Proyek dengan harga pembelian sejumlah (Outstanding Debt + Interest) + (Equity + Return)
• Take or Pay Period = PLN wajib membeli Proyek dengan harga pembelian sejumlah ෍
𝑥=0
𝑛−1
AEp× (PEB(A) + PSF) × 𝐹𝑦
1+𝑟 𝑥
× 1/RDb + Outstanding Debt
+ Interest
• Take and Pay Period = PLN memiliki opsi untuk membeli Proyek dengan harga pembelian sejumlah ෍
x=0
n−1
AEp×(PEB(A)+ PSF) × Fy
1+r x
× 1/RDb
Risk Sharing
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
PLN
memiliki
kewajiban
untuk
• PLN memiliki kewajiban untuk memberikan laporan kepada Menteri ESDM terkait:
(i) Operasi sistem bulanan termasuk pelanggaran terhadap Aturan Jaringan PLN;
(ii) Terjadi Pengakhiran PPA; dan
(iii) Pengalihan hak atas kepemilikan dalam Penjual (setelah COD).
Laporan Kepada Menteri ESDM
Kerja Nyata, Terangi Nusantara
CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited.
1. PLTS
2. PLTBm/PLTBg
3. PLTB
4. PLTMH
5. PLTSa

More Related Content

Similar to c0d73-presentasi-dirdan-i.pdf

PAPARAN BIMTEK NARSUM 1 DJKN.pdf
PAPARAN BIMTEK NARSUM 1 DJKN.pdfPAPARAN BIMTEK NARSUM 1 DJKN.pdf
PAPARAN BIMTEK NARSUM 1 DJKN.pdfFero Liju Syafanta
 
PENGADAAN bARANG DAN JASA LKPP
PENGADAAN bARANG DAN JASA LKPPPENGADAAN bARANG DAN JASA LKPP
PENGADAAN bARANG DAN JASA LKPPBenhard Sitinjak
 
PMK Volatil NAKER Balai K3 Bandung (1).pptx
PMK Volatil NAKER Balai K3 Bandung (1).pptxPMK Volatil NAKER Balai K3 Bandung (1).pptx
PMK Volatil NAKER Balai K3 Bandung (1).pptxangga progrest
 
Contoh Soal M5 Pengelolaan Kontrak PBJP #1.pdf
Contoh Soal M5 Pengelolaan Kontrak PBJP #1.pdfContoh Soal M5 Pengelolaan Kontrak PBJP #1.pdf
Contoh Soal M5 Pengelolaan Kontrak PBJP #1.pdfsisibocil7
 
POKOK POKOK PERUBAHAN PERATURAN PENGADAAN NOMOR 12 TAHUN 2021
POKOK POKOK PERUBAHAN PERATURAN PENGADAAN NOMOR 12 TAHUN 2021POKOK POKOK PERUBAHAN PERATURAN PENGADAAN NOMOR 12 TAHUN 2021
POKOK POKOK PERUBAHAN PERATURAN PENGADAAN NOMOR 12 TAHUN 2021Nurul Angreliany
 
Tahap Administrasi Proyek
Tahap Administrasi ProyekTahap Administrasi Proyek
Tahap Administrasi ProyekTri Hidayat
 
Contract Renewal, Amandement & Cancellation _Training "PROCUREMENT Contract &...
Contract Renewal, Amandement & Cancellation _Training "PROCUREMENT Contract &...Contract Renewal, Amandement & Cancellation _Training "PROCUREMENT Contract &...
Contract Renewal, Amandement & Cancellation _Training "PROCUREMENT Contract &...Kanaidi ken
 
overview perpres 1618
overview perpres 1618overview perpres 1618
overview perpres 1618zuhrimail
 
(Rev)Paparan Dir_17 Okt- Revisi Ke-2 Perpres 16_2018.pptx
(Rev)Paparan Dir_17 Okt- Revisi Ke-2 Perpres 16_2018.pptx(Rev)Paparan Dir_17 Okt- Revisi Ke-2 Perpres 16_2018.pptx
(Rev)Paparan Dir_17 Okt- Revisi Ke-2 Perpres 16_2018.pptxMazHary2
 
Presentasi ptk 066 gross split 2019
Presentasi ptk 066 gross split   2019Presentasi ptk 066 gross split   2019
Presentasi ptk 066 gross split 2019FIKRI ARIF
 
Matriks perbedaan perpres nomor 54 2010 dan perpres nomor 4 2015
Matriks perbedaan perpres nomor 54 2010 dan perpres nomor 4 2015Matriks perbedaan perpres nomor 54 2010 dan perpres nomor 4 2015
Matriks perbedaan perpres nomor 54 2010 dan perpres nomor 4 2015Eko Wachyu
 
Pola KERJA SAMA BUMN_KSP, BOT, BOO, dll
Pola KERJA SAMA BUMN_KSP, BOT, BOO, dllPola KERJA SAMA BUMN_KSP, BOT, BOO, dll
Pola KERJA SAMA BUMN_KSP, BOT, BOO, dllKanaidi ken
 
Sekilas perpajakan bagi bendaharawan
Sekilas perpajakan bagi bendaharawanSekilas perpajakan bagi bendaharawan
Sekilas perpajakan bagi bendaharawanKppkp Bangil
 
Kajian Hukum dan Kelembagaan. Solid Waste Management Project
Kajian Hukum dan Kelembagaan. Solid Waste Management ProjectKajian Hukum dan Kelembagaan. Solid Waste Management Project
Kajian Hukum dan Kelembagaan. Solid Waste Management ProjectOswar Mungkasa
 
Materi Public Hearing RPMK Penundaan_Pengangsuran.pdf
Materi Public Hearing RPMK Penundaan_Pengangsuran.pdfMateri Public Hearing RPMK Penundaan_Pengangsuran.pdf
Materi Public Hearing RPMK Penundaan_Pengangsuran.pdfariefyusuf11
 
PPT - Dr Surya Darma METI- OECD Stakeholder Dialogue on Mobilising Clean Ener...
PPT - Dr Surya Darma METI- OECD Stakeholder Dialogue on Mobilising Clean Ener...PPT - Dr Surya Darma METI- OECD Stakeholder Dialogue on Mobilising Clean Ener...
PPT - Dr Surya Darma METI- OECD Stakeholder Dialogue on Mobilising Clean Ener...OECD Environment
 

Similar to c0d73-presentasi-dirdan-i.pdf (20)

PAPARAN BIMTEK NARSUM 1 DJKN.pdf
PAPARAN BIMTEK NARSUM 1 DJKN.pdfPAPARAN BIMTEK NARSUM 1 DJKN.pdf
PAPARAN BIMTEK NARSUM 1 DJKN.pdf
 
PENGADAAN bARANG DAN JASA LKPP
PENGADAAN bARANG DAN JASA LKPPPENGADAAN bARANG DAN JASA LKPP
PENGADAAN bARANG DAN JASA LKPP
 
PMK Volatil NAKER Balai K3 Bandung (1).pptx
PMK Volatil NAKER Balai K3 Bandung (1).pptxPMK Volatil NAKER Balai K3 Bandung (1).pptx
PMK Volatil NAKER Balai K3 Bandung (1).pptx
 
Direktur Aneka EBT.pdf
Direktur Aneka EBT.pdfDirektur Aneka EBT.pdf
Direktur Aneka EBT.pdf
 
Contoh Soal M5 Pengelolaan Kontrak PBJP #1.pdf
Contoh Soal M5 Pengelolaan Kontrak PBJP #1.pdfContoh Soal M5 Pengelolaan Kontrak PBJP #1.pdf
Contoh Soal M5 Pengelolaan Kontrak PBJP #1.pdf
 
POKOK POKOK PERUBAHAN PERATURAN PENGADAAN NOMOR 12 TAHUN 2021
POKOK POKOK PERUBAHAN PERATURAN PENGADAAN NOMOR 12 TAHUN 2021POKOK POKOK PERUBAHAN PERATURAN PENGADAAN NOMOR 12 TAHUN 2021
POKOK POKOK PERUBAHAN PERATURAN PENGADAAN NOMOR 12 TAHUN 2021
 
Tahap Administrasi Proyek
Tahap Administrasi ProyekTahap Administrasi Proyek
Tahap Administrasi Proyek
 
Contract Renewal, Amandement & Cancellation _Training "PROCUREMENT Contract &...
Contract Renewal, Amandement & Cancellation _Training "PROCUREMENT Contract &...Contract Renewal, Amandement & Cancellation _Training "PROCUREMENT Contract &...
Contract Renewal, Amandement & Cancellation _Training "PROCUREMENT Contract &...
 
overview perpres 1618
overview perpres 1618overview perpres 1618
overview perpres 1618
 
Hasil Ujian Peserta 1
Hasil Ujian Peserta 1Hasil Ujian Peserta 1
Hasil Ujian Peserta 1
 
(Rev)Paparan Dir_17 Okt- Revisi Ke-2 Perpres 16_2018.pptx
(Rev)Paparan Dir_17 Okt- Revisi Ke-2 Perpres 16_2018.pptx(Rev)Paparan Dir_17 Okt- Revisi Ke-2 Perpres 16_2018.pptx
(Rev)Paparan Dir_17 Okt- Revisi Ke-2 Perpres 16_2018.pptx
 
Presentasi ptk 066 gross split 2019
Presentasi ptk 066 gross split   2019Presentasi ptk 066 gross split   2019
Presentasi ptk 066 gross split 2019
 
Matriks perbedaan perpres nomor 54 2010 dan perpres nomor 4 2015
Matriks perbedaan perpres nomor 54 2010 dan perpres nomor 4 2015Matriks perbedaan perpres nomor 54 2010 dan perpres nomor 4 2015
Matriks perbedaan perpres nomor 54 2010 dan perpres nomor 4 2015
 
Pola KERJA SAMA BUMN_KSP, BOT, BOO, dll
Pola KERJA SAMA BUMN_KSP, BOT, BOO, dllPola KERJA SAMA BUMN_KSP, BOT, BOO, dll
Pola KERJA SAMA BUMN_KSP, BOT, BOO, dll
 
Sekilas perpajakan bagi bendaharawan
Sekilas perpajakan bagi bendaharawanSekilas perpajakan bagi bendaharawan
Sekilas perpajakan bagi bendaharawan
 
Pokok2 ketentuan kprs80
Pokok2 ketentuan kprs80Pokok2 ketentuan kprs80
Pokok2 ketentuan kprs80
 
Kajian Hukum dan Kelembagaan. Solid Waste Management Project
Kajian Hukum dan Kelembagaan. Solid Waste Management ProjectKajian Hukum dan Kelembagaan. Solid Waste Management Project
Kajian Hukum dan Kelembagaan. Solid Waste Management Project
 
Materi Public Hearing RPMK Penundaan_Pengangsuran.pdf
Materi Public Hearing RPMK Penundaan_Pengangsuran.pdfMateri Public Hearing RPMK Penundaan_Pengangsuran.pdf
Materi Public Hearing RPMK Penundaan_Pengangsuran.pdf
 
PPT - Dr Surya Darma METI- OECD Stakeholder Dialogue on Mobilising Clean Ener...
PPT - Dr Surya Darma METI- OECD Stakeholder Dialogue on Mobilising Clean Ener...PPT - Dr Surya Darma METI- OECD Stakeholder Dialogue on Mobilising Clean Ener...
PPT - Dr Surya Darma METI- OECD Stakeholder Dialogue on Mobilising Clean Ener...
 
Presentasi
PresentasiPresentasi
Presentasi
 

Recently uploaded

Metode_Sampling bahan galian mineral.pptx
Metode_Sampling bahan galian mineral.pptxMetode_Sampling bahan galian mineral.pptx
Metode_Sampling bahan galian mineral.pptxHeriGeologist
 
Pengukuran Topografi menggunakan GPS Geodetik
Pengukuran Topografi menggunakan GPS GeodetikPengukuran Topografi menggunakan GPS Geodetik
Pengukuran Topografi menggunakan GPS Geodetikzulmushawir2
 
2. Bp. Suwardi-MATERI RAKOR DITJEN PLANOLOGI DAN TL.pptx
2. Bp. Suwardi-MATERI RAKOR DITJEN PLANOLOGI DAN TL.pptx2. Bp. Suwardi-MATERI RAKOR DITJEN PLANOLOGI DAN TL.pptx
2. Bp. Suwardi-MATERI RAKOR DITJEN PLANOLOGI DAN TL.pptxRahmanTaufiq4
 
Perencanaan Pelabuhan perikanan id.pptx
Perencanaan Pelabuhan perikanan  id.pptxPerencanaan Pelabuhan perikanan  id.pptx
Perencanaan Pelabuhan perikanan id.pptxNadhifMuhammad5
 
STRUKTUR KONSTRUKSI BANGUNAN TINGGI -.pptx
STRUKTUR KONSTRUKSI BANGUNAN TINGGI -.pptxSTRUKTUR KONSTRUKSI BANGUNAN TINGGI -.pptx
STRUKTUR KONSTRUKSI BANGUNAN TINGGI -.pptxanggawatmaja
 
PROSEDUR DALAM MELAKUKAN PERHITUNGAN PEKERJAAN PINTU.pptx
PROSEDUR DALAM MELAKUKAN PERHITUNGAN PEKERJAAN PINTU.pptxPROSEDUR DALAM MELAKUKAN PERHITUNGAN PEKERJAAN PINTU.pptx
PROSEDUR DALAM MELAKUKAN PERHITUNGAN PEKERJAAN PINTU.pptxadista7
 
703618627-PPT-INVESTIGASI-KECELAKAAN-KERJA.pptx
703618627-PPT-INVESTIGASI-KECELAKAAN-KERJA.pptx703618627-PPT-INVESTIGASI-KECELAKAAN-KERJA.pptx
703618627-PPT-INVESTIGASI-KECELAKAAN-KERJA.pptxarisvanrush
 

Recently uploaded (15)

obat aborsi Pangkal pinang Wa 082223109953 Jual obat aborsi Cytotec asli Di P...
obat aborsi Pangkal pinang Wa 082223109953 Jual obat aborsi Cytotec asli Di P...obat aborsi Pangkal pinang Wa 082223109953 Jual obat aborsi Cytotec asli Di P...
obat aborsi Pangkal pinang Wa 082223109953 Jual obat aborsi Cytotec asli Di P...
 
Metode_Sampling bahan galian mineral.pptx
Metode_Sampling bahan galian mineral.pptxMetode_Sampling bahan galian mineral.pptx
Metode_Sampling bahan galian mineral.pptx
 
Jual Obat Aborsi Jakarta Selatan 0822 2310 9953 Klinik Jual Obat Cytotec Asli...
Jual Obat Aborsi Jakarta Selatan 0822 2310 9953 Klinik Jual Obat Cytotec Asli...Jual Obat Aborsi Jakarta Selatan 0822 2310 9953 Klinik Jual Obat Cytotec Asli...
Jual Obat Aborsi Jakarta Selatan 0822 2310 9953 Klinik Jual Obat Cytotec Asli...
 
Pengukuran Topografi menggunakan GPS Geodetik
Pengukuran Topografi menggunakan GPS GeodetikPengukuran Topografi menggunakan GPS Geodetik
Pengukuran Topografi menggunakan GPS Geodetik
 
Jual Obat Aborsi Batam ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik Jual Ob...
Jual Obat Aborsi Batam ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik Jual Ob...Jual Obat Aborsi Batam ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik Jual Ob...
Jual Obat Aborsi Batam ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik Jual Ob...
 
2. Bp. Suwardi-MATERI RAKOR DITJEN PLANOLOGI DAN TL.pptx
2. Bp. Suwardi-MATERI RAKOR DITJEN PLANOLOGI DAN TL.pptx2. Bp. Suwardi-MATERI RAKOR DITJEN PLANOLOGI DAN TL.pptx
2. Bp. Suwardi-MATERI RAKOR DITJEN PLANOLOGI DAN TL.pptx
 
Jual Obat Aborsi Samarinda ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik Jua...
Jual Obat Aborsi Samarinda ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik Jua...Jual Obat Aborsi Samarinda ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik Jua...
Jual Obat Aborsi Samarinda ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik Jua...
 
Obat Aborsi jakarta WA 082223109953 Jual Obat Aborsi Cytotec Asli Di jakarta
Obat Aborsi jakarta WA 082223109953  Jual Obat Aborsi Cytotec Asli Di jakartaObat Aborsi jakarta WA 082223109953  Jual Obat Aborsi Cytotec Asli Di jakarta
Obat Aborsi jakarta WA 082223109953 Jual Obat Aborsi Cytotec Asli Di jakarta
 
Perencanaan Pelabuhan perikanan id.pptx
Perencanaan Pelabuhan perikanan  id.pptxPerencanaan Pelabuhan perikanan  id.pptx
Perencanaan Pelabuhan perikanan id.pptx
 
STRUKTUR KONSTRUKSI BANGUNAN TINGGI -.pptx
STRUKTUR KONSTRUKSI BANGUNAN TINGGI -.pptxSTRUKTUR KONSTRUKSI BANGUNAN TINGGI -.pptx
STRUKTUR KONSTRUKSI BANGUNAN TINGGI -.pptx
 
PROSEDUR DALAM MELAKUKAN PERHITUNGAN PEKERJAAN PINTU.pptx
PROSEDUR DALAM MELAKUKAN PERHITUNGAN PEKERJAAN PINTU.pptxPROSEDUR DALAM MELAKUKAN PERHITUNGAN PEKERJAAN PINTU.pptx
PROSEDUR DALAM MELAKUKAN PERHITUNGAN PEKERJAAN PINTU.pptx
 
Klinik Obat Aborsi Di Depok Wa 082223109953 Klinik Aborsi Di Depok
Klinik Obat Aborsi Di Depok Wa 082223109953 Klinik Aborsi Di DepokKlinik Obat Aborsi Di Depok Wa 082223109953 Klinik Aborsi Di Depok
Klinik Obat Aborsi Di Depok Wa 082223109953 Klinik Aborsi Di Depok
 
Obat Aborsi Sungai Penuh 082223109953 Jual Cytotec Asli Di Sungai Penuh
Obat Aborsi Sungai Penuh 082223109953 Jual Cytotec Asli Di Sungai PenuhObat Aborsi Sungai Penuh 082223109953 Jual Cytotec Asli Di Sungai Penuh
Obat Aborsi Sungai Penuh 082223109953 Jual Cytotec Asli Di Sungai Penuh
 
703618627-PPT-INVESTIGASI-KECELAKAAN-KERJA.pptx
703618627-PPT-INVESTIGASI-KECELAKAAN-KERJA.pptx703618627-PPT-INVESTIGASI-KECELAKAAN-KERJA.pptx
703618627-PPT-INVESTIGASI-KECELAKAAN-KERJA.pptx
 
Jual Obat Aborsi Jakarta Selatan 0822 2310 9953 Klinik Jual Obat Cytotec Asli...
Jual Obat Aborsi Jakarta Selatan 0822 2310 9953 Klinik Jual Obat Cytotec Asli...Jual Obat Aborsi Jakarta Selatan 0822 2310 9953 Klinik Jual Obat Cytotec Asli...
Jual Obat Aborsi Jakarta Selatan 0822 2310 9953 Klinik Jual Obat Cytotec Asli...
 

c0d73-presentasi-dirdan-i.pdf

  • 1. Proses Pengadaan dan Standar Kontrak Pembangkit Tenaga Listrik Yang Memanfaatkan Sumber Energi Terbarukan Jakarta, 10 Agustus 2017 Dipresentasikan oleh : Tohari Hadiat KDIV EBT PT. PLN (Persero)
  • 2. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. Prosedur Pengadaan Pembangkit Tenaga Listrik Yang Memanfaatkan Energi Terbarukan 1
  • 3. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. 2 Dilaksanakan oleh Unit Distribusi/Wilayah Dilaksanakan leh PLN Pusat cq DIVEBT PLTA ≤ 10 MW PLTSa PLTBm/PLTBg ≤ 10 MW PLT Hybrid PLTS ≤ 10 MW PLTBm/PLTBg > 10 MW PLTB ≤ 10 MW PLTS > 10 MW PLTB > 10 MW PLTA > 10 MW PLTA Laut PLTP PLT Energi Baru (Gas Batubara, Batubara Cair, Nuklir, dll)
  • 4. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. 2 1. Kriteria umum : a. pasokan tenaga listrik dapat diterima oleh sistem ketenagalistrikan setempat; b. menurunkan BPP Pembangkitan di sistem ketenagalistrikan setempat; dan/atau c. memenuhi kebutuhan tenaga listrik di lokasi yang tidak ada sumber energi primer lain. 2. Untuk PLTBm atau PLTBg, PPL harus memiliki sumber pasokan bahan bakar (feedstock) yang cukup untuk kelangsungan operasi PLTBm atau PLTBg selama masa PJBL. 3. PLTSa dilaksanakan oleh PPL yang telah ditetapkan oleh Pemerintah dan/atau Pemerintah Daerah dalam rangka membantu Pemerintah dan/atau Pemerintah Daerah dalam mengatasi atau menangani persoalan sampah kota. 4. PLTP dilaksanakan PPL yang memiliki wilayah kerja panas bumi sesuai dengan cadangan terbukti setelah eksplorasi.
  • 5. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. TAHAPAN PENYUSUNAN DPT Menentukan instruksi kepada Calon Penyedia Menentukan Jadwal Kualifikasi Menentukan Ruang Lingkup Pekerjaan  Spesifikasi Teknis / Ruang Lingkup objek Kualifikasi  Informasi Umum  Persyaratan yang harus dipenuhi oleh calon penyedia (Administrasi, Keuangan & Teknis)  Metode Peyampaian Dokumen Aplikasi  Metode Evaluasi & Penilaian Kualifikasi  Jadwal Pendaftaran  Jadwal Pengambilan dokumen  Jadwal Rapat penjelasan  Jadwal Penyampaian Dokumen Aplikasi  Jadwal Pengumuman Hasil Kualifikasi  Pengumumman  Pendaftaran  Penjelasan Kualifikasi  Pemasukan Dokumen Aplikasi  Evaluasi Kualifikasi  Berita Acara Hasil Kualifikasi  Rekomendasi VfM Committee  Pengumuman Hasil Kualifikasi  Masa Sanggah  Pengesahan Hasil Kualifikasi  Penerbitan Tanda DPT DAFTAR PENYEDIA TERSELEKSI (DPT) PENYUSUNAN DOKUMEN KUALIFIKASI PROSES KUALIFIKASI Kriteria Pembelian Tenaga Listrik dari Pembangkit Energi Terbarukan
  • 6. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. TAHAPAN KUALIFIKASI DPT Dalam pelaksanaannya dapat dibantu oleh pihak lain sesuai keahlian baik internal maupun eksternal PLN. PENGUMUMAN KUALIFIKASI PENDAFTARAN DAN PENGAMBILAN DOKUMEN KUALIFIKASI RAPAT PENJELASAN KUALIFIKASI PEMASUKAN DOKUMEN APLIKASI EVALUASI KUALIFIKASI & DUE DILIGENCE BERITA ACARA HASIL EVALUASI KUALIFIKASI REKOMENDASI VfM COMMITTEE PENGUMUMAN HASIL KUALIFIKASI MASA SANGGAH PENGESAHAN HASIL KUALIFIKASI DPT PENETAPAN HASIL EVALAUSI OLEH PENGGUNA VFM ? Y N Kriteria Pembelian Tenaga Listrik dari Pembangkit Energi Terbarukan
  • 7. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. 2
  • 8. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. Standar Kontrak (PJBL/PPA) Pembangkit Tenaga Listrik Yang Memanfaatkan Energi Terbarukan 1
  • 9. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. Jangka waktu PPA paling lama 30 tahun sejak COD dengan mempertimbangkan jenis Pembangkit. Draft PPA yang dibuat saat ini adalah sebagai berikut: PPA Energi Baru dan Terbarukan (EBT) • PLTS, PLTBm, PLTBg, PLTM adalah paling lama 25 tahun • PLTA adalah paling lama 30 tahun • PLTP dengan mempertimbangkan jangka waktu IPB (berdasarkan PP 7/2017) Jangka Waktu PPA EBT
  • 10. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. • Pola kerja sama menggunakan pola Build, Own Operate, Transfer (BOOT) yang mensyaratkan Pembangkit harus diserahkan pada akhir masa PPA dalam kondisi yang baik (Operable Condition). • Untuk PLTP, terkait dengan Wilayah Kerja Panas Bumi yang tidak dapat dialihkan (IPB dilarang untuk dialihkan berdasarkan Pasal 27(1) UU 21/2004), PLN memiliki opsi untuk membeli proyek selain melalui pengalihan asset (pembangkit dan fasilitasnya) maka dapat melalui pengalihan saham(-saham) dalam Penjual. Pola Kerja Sama
  • 11. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. • Komponen A pada harga jual tenaga listrik dihitung berdasarkan nilai investasi yang didepresiasi paling sedikit 20 tahun, dengan demikian dapat diartikan bahwa setelah 20 tahun nilai buku dari Pembangkit menjadi 0. • Depresiasi ini dapat menjadi patokan dalam hal membuat harga perkiraan sendiri (HPS). • Ketentuan ini tidak terefleksikan dalam PPA secara eksplisit namun dapat dijadikan pedoman ketika pelaksanaan pengadaan. Depresiasi Nilai Investasi Komponen A
  • 12. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. Per • Percepatan COD merupakan hak PLN dan harus atas permintaan PLN, dimana apabila disetujui oleh Penjual maka Penjual berhak mendapatkan insentif. Persetujuan tersebut harus diberikan dalam waktu 30 hari sejak permintaan dari PLN. • Permintaan percepatan COD dari PLN dapat mempertimbangkan kesiapan dari transmisi PLN atau dapat dibangun on-time sebelum Pembangkit mencapai COD. • Insentif diberikan dalam bentuk pembelian listrik dengan skema Take and Pay sejak aktual COD hingga Required COD (RCOD). Jangka waktu PPA akan tetap dimulai sejak RCOD. • PLN dan Penjual akan menandatangani berita acara terkait pelaksanaan percepatan COD, termasuk kegiatan - kegiatan terkait, seperti kewajiban PLN untuk back-feeding, sinkronisasi dan dimulainya komisioning. • Ketentuan LD akan tetap berlaku apabila Penjual tidak dapat mencapai COD pada jadwal yang telah disepakati, dengan perhitungan [[Tarif (Component A+B) atau BPP] x Kapasitas Kontrak x AF x 24 jam yang dikenakan tiap hari keterlambatan. Insentif Percepatan Commercial Operation Date (COD)
  • 13. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. Jumlah LD yang dikenaka • Jumlah LD yang dikenakan ke PLN dalam bentuk Deemed Dispatch yaitu listrik tidak dialirkan akibat kesalahan PLN. Formula dari LD per hari keterlambatan adalah [[Tarif (Component A+B) atau BPP] x Kapasitas Kontrak x AF x 24 jam, yang akan dikenakan sejak Required COD. • Untuk Pembangkit Intermitten, Tarif atau BPP pada perhitungan di atas dikalikan 50%. Jumlah Proporsional Liquidated Damage (LD)
  • 14. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. PENALTI PERHITUNGAN JUMLAH PENALTI Penalti Availibility Factor atau Capability Factor Dihitung berdasarkan perhitungan pada Appendix G dengan ketentuan tidak boleh melebihi 10 % dari Komponen A pada Periode Penagihan terkait Penalti Outage Factor Dihitung berdasarkan perhitungan pada Appendix G dengan ketentuan tidak boleh melebihi 10 % dari Komponen A pada Periode Penagihan terkait (termasuk Penalti untuk AF) Penalti tara kalor (Heat Rate) Dihitung berdasarkan perhitungan pada Appendix G Penalti kegagalan memikul mega volt ampere reactive (MVAR) Rp 1.191 kVArh dikalikan dengan selisih Reactive Power yang dimintakan oleh Pusat Pengaturan dan reactive Power yang dihasilkan secara aktual untuk setiap jam kegagalan Penalti kegagalan menjaga frekuensi Mengurangkan 4 jam dikalikan dengan kapasitas kontrak dan AF pada Periode Penagihan terkait Penalti kecepatan naik turun beban (ramp rate) Dihitung berdasarkan perhitungan pada Appendix G Note: pengenaan penalty disesuaikan berdasarkan jenis pembangkit, untuk pembangkit EBT, tidak semua penalti dapat diaplikasikan, diantaranya penalti Heat Rate dan ramp rate. Pinalti untuk Performa Pekerjaan
  • 15. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. PLN wajib membeli tenaga listrik sesuai dengan PPA • PLN wajib membeli tenaga listrik sesuai dengan PPA selama periode tertentu dengan memperhatikan masa pengembalian pinjaman kepada lenders (skema Take or Pay). • Masa Take or Pay adalah selama 15 tahun sejak COD, sedangkan Pembangkit Intermitte adalah selama 20 tahun sejak COD. Setelahnya, untuk sisa jangka waktu PPA akan diterapkan Take and Pay. • Dalam periode Take and Pay diberlakukan annual committed energy (sebagai refleksi CF yang disebut dalam Permen ESDM 10/2017), yakni Total Take and Pay Energi dengan perhitungan NDClatest x 80% x PHa x (25 - nTOP) / 1,000,000. Untuk Pembangkit Intermitten, jumlah Total Take and Pay Energi akan ditentukan oleh PLN. Untuk energi yang dihasilkan oleh Penjual dan diterima oleh diatas Total Take and Pay Energi maka tarif dari kelebihan energi tersebut akan dikalikan 50%. Apabila PLN tidak dapat mengambil Total Take and Pay Energy, maka jangka waktu PPA akan ditambahkan hingga paling lama 5 tahun, dengan ketentuan jangka waktu PPA tidak lebih dari 30 tahun. Dalam masa Take and Pay, deemed dispatch dan Penalty AF/CF dan OF (apabila diaplikasikan) tidak berlaku. Skema Transaksi (Take Or Pay dan Take And Pay)
  • 16. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. DE DEEMED DISPATCH Deemed Dispatch diberikan apabila terjadi kejadian (dalam periode Take or Pay), sbb: 1. PLN (i) tidak dapat menerima tenaga listrik karena kesalahan PLN; atau (ii) kerusakan terhadap Sistem Jaringan PLN (bukan karena FM) berdampak pada penyaluran tenaga listrik oleh Penjual. Berlaku grace period selama 48 jam untuk setiap kejadian dan 14 hari untuk perbaikan terhadap Sistem Jaringan PLN, sedangkan untuk PPA intermittten grace period tersebut adalah 180 jam agregat tiap tahunnya. (Point 2 dan 3 hanya berlaku untuk Pembangkit Intermitten) 2. Terjadi Natural Force Majeure terhadap Sistem Jaringan PLN berdampak pada penyaluran tenaga listrik oleh Penjual. Berlaku setelah grace period 16 hari agregat untuk tiap tahunnya (termasuk kejadian Natural Force Majeure dan perbaikan kerusakan jaringan). 3. Terjadi Political Force Majeur berupa tindakan pemerintah yang sewenang – wenang (Unjustified Government Act) Berlaku setelah grace period 30 hari (tanpa Deemed Dispatch) untuk membantu Penjual menyelesaikan masalah yang dihadapi utamanya ditingkat local government. Note: Dalam grace period, PLN tidak diwajibkan untuk membayar Deemed Dispatch. Risk Sharing
  • 17. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. NATURAL FORCE MAJEURE NATURAL FORCE MAJEURE Apabila terjadi Natural Force Majeur maka: • Sebelum COD, apabila Natural FM terjadi dan berdampak pada PLN dan Penjual maka Milestone Schedule akan disesuaikan. • Setelah COD, apabila Natural FM terjadi dan berdampak pada PLN dan Penjual maka jangka waktu PPA dapat diperpanjang sesuai dengan lama kejadian FM tersebut. Perpanjangan jangka waktu disesuaikan dengan periode pembayaran (apabila terjadi dalam periode Take or Pay maka periode Take or Pay yang diperpanjang), dengan ketentuan, jangka waktu PPA tidak akan melebihi 30 tahun. Risk Sharing
  • 18. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. HA HARGA PEMBELIAN PROYEK AKIBAT TERMINASI KARENA KESALAHAN PLN • Selama jangka waktu PPA, dalam hal terjadi terminasi karena kesalahan PLN maka PLN wajib membeli Proyek dengan harga Pembelian. • Sebelum COD = (Outstanding Debt + Interest) + (Equity + Return) • Setelah COD = ෍ x=0 n−1 DC × AFpy × CCR+CCRT × Fy 1+r x + Outstanding Debt + Interest • Sedangkan untuk Pembangkit Intermitten adalah sbb: • Sebelum COD = PLN wajib membeli Proyek dengan harga pembelian sejumlah (Outstanding Debt + Interest) + (Equity + Return) • Take or Pay Period = PLN wajib membeli Proyek dengan harga pembelian sejumlah ෍ 𝑥=0 𝑛−1 AEp× (PEB(A) + PSF) × 𝐹𝑦 1+𝑟 𝑥 × 1/RDb + Outstanding Debt + Interest • Take and Pay Period = PLN memiliki opsi untuk membeli Proyek dengan harga pembelian sejumlah ෍ x=0 n−1 AEp×(PEB(A)+ PSF) × Fy 1+r x × 1/RDb Risk Sharing
  • 19. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. PLN memiliki kewajiban untuk • PLN memiliki kewajiban untuk memberikan laporan kepada Menteri ESDM terkait: (i) Operasi sistem bulanan termasuk pelanggaran terhadap Aturan Jaringan PLN; (ii) Terjadi Pengakhiran PPA; dan (iii) Pengalihan hak atas kepemilikan dalam Penjual (setelah COD). Laporan Kepada Menteri ESDM
  • 20. Kerja Nyata, Terangi Nusantara
  • 21. CONFIDENTIAL !! Any use of this material without specific permission of PLN is strictly prohibited. 1. PLTS 2. PLTBm/PLTBg 3. PLTB 4. PLTMH 5. PLTSa