Method of Statement - Road furniture works
1. Project Name PQP Document No.:
PROJECT QUALITY PLAN
WORK INSTRUCTION
DOCUMENT NO.:
104
6.28 WORK INSTRUCTION FOR ROAD FURNITURE
OBJECTIVE
To outline the work instruction by which road furniture are carried out.
SCOPE
The work instruction shall apply for all civil engineering projects.
RESPONSIBILITIES
Site Agent & Site Supervisor
MATERIALS
Signages, Guardrail, Road kerb, road paint, thermoplastic, etc.
HANDLING AND STORAGE OF MATERIALS
a) Handling : Unload materials using mobile crane or any method where.
applicable / suitable at the site
b) Storage : Store at the storage yard or store room where necessary.
PLANT, MACHINERY & EQUIPMENT
Backhoe, digging tools, spatula, wheelbarrow, etc. where applicable
DEFINITIONS
-Nil-
PREPARATORY WORK
Step 1
Obtain relevant approved construction drawings from structural Consultant / Engineer.
Step 2
Set out the location with reference pegging lines and level.
2. Project Name PQP Document No.:
PROJECT QUALITY PLAN
WORK INSTRUCTION
DOCUMENT NO.:
105
Step 3
Inspect the road furniture goods received at site. Ensure the quantity, symbol, words are
in place. Use Receiving Inspection Checklist (RIC) during inspection.
INSTALLATION OF ROAD FURNITURE
๏ท Road Signage
Step 1
Put the signage at every location where it was determine.
Step 2
Dig the holes where the signage to erect. Ensure the offset from road edge is
enough according to the drawing and specification.
Step 3
Erect the signage and ensure the facing in right direction. Plumb the
verticality using spirit level.
Step 4
Stake or support the signage for temporary stand.
Step 5
Concrete the base according to specification.
Step 6
Carry out joint inspection with the Subcontractor on road furniture completed and
obtain acceptance.
๏ท Road Marking (Thermoplastic)
Step 1
Prepare the mix of thermoplastic material (refer to Manufacturers Instruction)
Step 2
Measure total width of road to determine the center line of the road. Mark
centerline along the road using chalk for certain interval depends on radius of
road curve and type of roads.
3. Project Name PQP Document No.:
PROJECT QUALITY PLAN
WORK INSTRUCTION
DOCUMENT NO.:
106
Step 3
Lay a rope along beside (the offset depends on the width of the line) the
centerline marked to get a smooth line.
Step 4
Put the processed painting mix into the โroad marking trolleyโ . Push the trolley
along the rope and guides by a string at the trolley. Set the thickness of the paint
and amount of glass powder according to requirement. Allow the paint to
hardened to the time period specified by the Manufacturer.
Step 5
Carry out joint inspection with the Subcontractor on road furniture completed.
๏ท Road Kerb
Step 1
From the reference line setup, excavate to base level of the kerb. Check the level
by spirit level to ensure the depth.
Step 2
Place concrete base and lay the kerb onto the concrete. Adjust the kerb to the
required level. Fill mortar in the joint.
Step 3
Apply prime coat paint to the kerb and continue with 2 layer of paints as per
specification. After all the laying done and the kerb ready to receive painting.
Step 4
Carry out joint inspection with the Subcontractor on road furniture works
completed.