The document summarizes a study analyzing resource growth and cost/schedule overruns for 20 NASA missions from the past decade. It finds that on average, costs grew 76% and schedules grew 26% beyond initial estimates at the beginning of the preliminary design phase. This level of growth is consistent with the findings of an earlier 10-mission study. The document outlines the study's methodology of comparing estimated and actual values for mass, power, cost and schedule at key milestones. It also provides a table describing the 20 missions analyzed, which represent a variety of science objectives, acquisition methods and planetary vs. earth science.