PRESENTED BY:
 PRASHANT GUPTA [201511005010080]
FACULTY MEMBER:
 Er RAJ DEEPAK SIR
They are pictorial charts developed by Henry Gantt around
1900.
It consists of two coordinate axes:
Horizontal axis representing the time elapsed
Vertical axis represents the jobs to be performed.
Jobs are represented in the form of bars
Length of bar indicates the time required for completion of
job.
Analysis of project
Breaking the project into various activities.
Time required to finish each activity.
Place the activities in technical sequence.
Diagram is adjusted according to the target date.
Following chart for a project which has five distinct jobs
(a,b,c,d,e) and the time duration are 20, 15, 30, 15 and 5
days.
20
15
30
15
5
0 5 10 15 20 25 30 35
A
B
C
D
E
A B C D E
Series 1 20 15 30 15 5
Series 1
Series 1
It is simple to draw.
No trained/skilled personnel are required to make the
chart.
The progress achieved at site is expressed in terms of
percentage.
It provides a visual representation of the entire project.
Project progress
Time uncertainty
It does not facilitates the work of controlling,
monitoring and updating the project.
Only major activities are shown in bar charts
Therefore bar chart are not very useful for big projects.
..

Bar chart

  • 1.
    PRESENTED BY:  PRASHANTGUPTA [201511005010080] FACULTY MEMBER:  Er RAJ DEEPAK SIR
  • 2.
    They are pictorialcharts developed by Henry Gantt around 1900. It consists of two coordinate axes: Horizontal axis representing the time elapsed Vertical axis represents the jobs to be performed. Jobs are represented in the form of bars Length of bar indicates the time required for completion of job.
  • 3.
    Analysis of project Breakingthe project into various activities. Time required to finish each activity. Place the activities in technical sequence. Diagram is adjusted according to the target date.
  • 4.
    Following chart fora project which has five distinct jobs (a,b,c,d,e) and the time duration are 20, 15, 30, 15 and 5 days. 20 15 30 15 5 0 5 10 15 20 25 30 35 A B C D E A B C D E Series 1 20 15 30 15 5 Series 1 Series 1
  • 5.
    It is simpleto draw. No trained/skilled personnel are required to make the chart. The progress achieved at site is expressed in terms of percentage. It provides a visual representation of the entire project.
  • 6.
    Project progress Time uncertainty Itdoes not facilitates the work of controlling, monitoring and updating the project. Only major activities are shown in bar charts Therefore bar chart are not very useful for big projects.
  • 7.