2. METROLINX LAND ACKNOWLEDGMENT
2
“Metrolinx acknowledges that it operates on the traditional territory of Indigenous
Peoples including the Anishnabeg, the Haudenosaunee and the Wendat peoples.
In particular these lands are covered by 20 Treaties, and we have a responsibility
to recognize and value the rights of Indigenous Nations and Peoples and conduct
business in a manner that is built on the foundation of trust, respect and
collaboration.
Metrolinx is committed to building meaningful relationships with Indigenous
Peoples, and to working towards meaningful reconciliation with the original
caretakers of this land. “
4. LEASIDE STATION UPDATE
4
Activity Location Approx. Date & Duration
Station Box Construction
Sign band installations, tiling,
elevator/escalator assembly, mechanical
electrical works
Underneath Eglinton Avenue within the
Station Box
Underway into Spring 2022
Main Entrance Construction
Glazing, tiling, ceiling installations,
elevator/escalator assembly
South east corner of Bayview Ave and
Eglinton Ave
Underway into Spring 2022
• 24-hour work ongoing Monday - Saturday
through mid 2022
Secondary Entrance Construction
Architectural finishes and mechanical
electrical works
North west corner of Bayview Ave and
Eglinton Ave
Underway into Spring 2022
• 24-hour work ongoing Monday - Saturday
through mid 2022
Road Decking Removals and Road
Restoration Works
South side of Eglinton Avenue East, west of
Bayview Avenue
As early as Monday March 21, 2022 for
approximately two (2) weeks
6. TRAFFIC CONFIGURATION – ROAD DECKING REMOVALS AND RESTORATION
6
As early as Monday March 21, 2022 for approximately one (1) week
DRAFT MAP
This graphic is subject to change
11. LAIRD STATION UPDATE
11
Activity Location Approx. Date & Duration
Main Entrance Construction
Concrete pours, tile installations, glazing,
painting, architectural finishes, electrical
installations, deliveries and landscaping
works
South-west corner of Laird Drive and
Eglinton Avenue East
Ongoing into Spring 2022
Secondary Entrance Construction
Concrete pours, tile installations, glazing,
architectural finishes, deliveries and
landscaping works.
South-east corner of Laird Drive and
Eglinton Avenue East
Ongoing into Spring 2022
Station Box Construction
Mechanical and electrical installations, sign
band installation, architectural finishes
Beneath Eglinton Avenue East Ongoing into Spring 2022
15. EAST OF LAIRD ONGOING WORKS
15
• Vehicle Testing
• Leslie Retaining Wall construction
• Brentcliffe Retaining Wall landscaping restoration works
• East Brentfliffe Retaining Wall construction
EAST BRENTFLIFFE RETAINING WALL
CONSTRUCTION IN PROGRESS
LESLIE RETAINING WALL
CONSTRUCTION IN PROGRESS