CENTRE FOR ENERGY, PETROLEUM AND MINERAL LAW AND POLICY
STATEMENT OF ORIGINALITY
FOR RESEARCH PAPERS
NAME OF STUDENT: Zaid Mahayni
MATRICULATION NUMBER: 009943036
PROGRAMME: LL.M. in Petroleum Law and Policy
TITLE OF THE RESEARCH PAPER:
Negotiating BOT Arrangements: A Sponsor's Checklist in Ensuring
Bankability
ABSTRACT OF THE RESEARCH PAPER:
Contract is the law of the parties to a BOT project. Banks will not accept to lend to a
project company that is bearing heavy obligations, which cannot be assumed. The project
must be viable. Other parties to a BOT project such as the host government, the
construction company and the offtaker must all carry a reasonable amount of the risks.
This paper will examine the typical contracts of a BOT arrangement and will describe the
terms that must be included to enhance bankability. The sponsors must be conscious that
without consideration to bankability, the project may just never materialize.
WORD COUNT: 4,020
PRESENTED TO: Professor Stephen Dow
TITLE OF THE COURSE: International Project Finance (GB 353)
I, Zaid Mahayni, have read the Code of Practice regarding plagiarism contained in the
Students’ Introductory Handbook. I realise that this Code governs the way in which the
Centre for Petroleum and Mineral Law and Policy regards and treats the issue of
plagiarism. I have understood the Code and in particular I am aware of the consequences,
which may follow if I breach that code.
Signed:________________
Date:__________________
Matriculation Number 00 99 43 036
1
Table of Contents
List of Abbreviations------------------------------------------------------------------ 2
1. Introduction-------------------------------------------------------------------------- 3
2. The Pre-Development Phase ------------------------------------------------------ 4
2.1 General Considerations----------------------------------------------------------- 4
2.2 Consents ---------------------------------------------------------------------------- 6
2.3 The Shareholders’ Agreements-------------------------------------------------- 7
2.4 The Concession Agreement------------------------------------------------------ 8
3. The Construction Phase: Negotiation of the Construction Contract--------- 10
3.1 Reputation of the Contractor ---------------------------------------------------- 10
3.2 Design and Cost of the Construction ------------------------------------------- 10
3.3 Completion Obligations ---------------------------------------------------------- 11
3.4 Quality of the Construction ------------------------------------------------------ 12
4. The Operation Phase --------------------------------------------------------------- 13
4.1 Operation and Maintenance Agreements -------------------------------------- 13
4.2 Input Agreements ----------------------------------------------------------------- 15
4.3 Output Agreements --------------------------------------------------------------- 16
5. Conclusion--------------------------------------------------------------------------- 17
Annex A--------------------------------------------------------------------------------- 19
Bibliography---------------------------------------------------------------------------- 20
Matriculation Number 00 99 43 036
2
List of Abbreviations
BOT------------------------------------------- Build-Operate-Transfer
CAR------------------------------------------- CEPMLP Annual Review
CEPMLP ------------------------------------- Centre for Energy, Petroleum and Mineral Law
and Policy
CLMBLR ------------------------------------ Columbia Business Law Review
INTXBL-------------------------------------- International Tax and Business Lawyer
IOGFR---------------------------------------- International Oil and Gas Finance Review
JENRL---------------------------------------- Journal of Energy & Natural Resources Law
OGLTR--------------------------------------- Oil and Gas Law and Taxation Review
PE --------------------------------------------- Petroleum Economist
PFY ------------------------------------------- Project Finance Yearly
PLI/Comm ----------------------------------- Practising Law Institute Commercial Law and
Practice Course Handbook Series
PFI -------------------------------------------- Project Finance International
UNCITRAL --------------------------------- United Nations Commission on International
Trade Law
Matriculation Number 00 99 43 036
3
1. Introduction
In the 1970s Governments had difficulty funding large public works due to fiscal
shortcomings. Not only, it didn’t have the means to build new structures but it also could
not maintain already existing structures. The private sector was indeed needed but not in
a way that would jeopardize State control over certain industries: transportation, energy,
water, etc.1
BOT schemes (Build – Own – Transfer), developed in 1984 by Turkey, seemed
a very attractive solution to the problem. It offered a great compromise between the
interests of the private parties (make profits) and those of the governments (direct control
of certain industries).
Under the BOT scheme, a concession is granted to a concession holder
(sponsor). The sponsor is empowered with the right to build a specified infrastructure,
operate it for a determined period and at the end of the period transfer it back, at no cost,
to the person that originally granted the concession. The duration of the concession may
be established in either one of two ways. It may either be an expiry date, fixed in time, or
it could be a variable date, dependent upon the recovery by the concessionaire of a certain
amount of revenue or profit.2
The BOT structure involves a large amount of parties and an important number
of contracts.3
The sponsor is the centre of practically all of these contracts.
The sponsor must first be created. This will involve the signing of a consortium
agreement and a shareholders’ agreement between the individual constituents of the
sponsor.
1
Adefulu, A., Downstream Energy Financing in Developing Countries: Are BOTs the Answer?,
3 [1999] 3 CAR, http://www.dundee.ac.uk/cepmlp/main/html/car_article1.html.
2
Ibid.
3
Please refer to annex A for the representation of a typical BOT structure.
Matriculation Number 00 99 43 036
4
Apart from the concession agreement, the sponsor must also sign a loan
agreement, a construction contract, an operation contract, a supply contract and a sales
contract. This list is not exhaustive and will vary from a project to another.
In negotiating these contracts, the sponsor is faced with important constraints.
One would be that lenders must be satisfied with the overall project in order to make an
investment decision. The lenders will therefore impose on the sponsor their own
parameters and conditions in the negotiation of agreements with the other parties. This
paper will examine the contractual terms that the sponsor must negotiate in order to
secure a loan and hence, render the project “bankable”.
This paper will be structured in three main sections, according to the
development phases of a typical BOT project: the pre-development phase, the
construction phase and the operational phase. The development phase will cover the
consents needed, the shareholder’s agreement and the concession agreement. The
construction phase will cover the construction contract. And, finally, the operational
phase will cover the operation and maintenance agreement, the input agreement with
suppliers and the output agreement with purchasers.
2. The Pre-Development Phase
2.1 General Considerations
It is important to keep in mind that BOT arrangements are a form of project
finance. This implies that the lenders look primarily at the earnings of the project as the
source from which the loan is payed. Credit assessment should therefore be mostly axed
towards the project and not towards the creditworthiness of the borrowers. The fact that
BOTs are a type of project finance also implies that lenders have only limited recourse
against the borrowers since security taken by the banks is mainly confined to the assets of
Matriculation Number 00 99 43 036
5
the project.4
For these reasons, lenders will carefully scrutinize all contracts to make sure
that the loan can in fact be repaid.
As a general rule, banks will refuse to carry risks that cannot be quantified or
assessed.5
Banks will therefore not tolerate investments in politically risky regions. This
risk is not only an issue in third world countries and developing countries. In fact, even
democratic countries can contain political risk. For example, one significant factor that
led to the abandonment of the Channel Tunnel project in 1975 was the 1974 change in the
UK government from Conservative to Labour. With this change, support to the project
was lost at a critical stage.6
As a rule, bankability will require a solid legal infrastructure. According to
Robert Pritchard, the solidity of a legal system is dependent upon three components:
“1) The first and most basic is the guarantee of the rule of law, manifested by a
published and stable body of laws, readily interpretable and supported by effective
administrative bodies and judicial recourse.
2) The second is an efficient body of business laws to support a market economy. These
include the right to own property, the right to pledge assets in order to raise capital, and
readily enforceable contract laws to govern business relationships.
3) The third is a specific law to authorise and delineate a process of competitive
procurement and to support the resulting arrangements.”7
Lenders will accept to carry general changes in law (e.g. the rate of profit tax).
However, these will not tolerate the risk of changes in law that are designed to
specifically discriminate against the project company.8
The sponsors of a BOT project may sometimes obtain by the government
assurances that legal changes will be restricted. However, the value of such assurances
4
UNCITRAL, Possible Future Work: Build-Operate-Transfer Projects, Twenty-Ninth Session,
A/CN.9/424, April 19, 1996, http://www.uncitral.org/english/sessions/unc/unc-29/acn9-424.htm.
5
G., Vinter, Project Finance: A Legal Guide, Second Edition, p. 85.
6
C., Walker, and A. J., Smith, eds., Privatized Infrastructure: the BOT Approach, pp. 150-151.
7
R., Pritchard, Downstream Energy Financing and the Limitations of BOT Projects, [1997] 5
OGLTR 149, p. 151.
8
G., Vinter, supra note 5, p. 78.
Matriculation Number 00 99 43 036
6
can be doubtful since governments can later decide to adopt a different policy.9
The
lenders will hence have to look for a clear sign by the government in question to
encourage long-term investment.10
Lenders will also avoid investing in projects situated in areas prone to violence,
wars or even labour disputes. For instance, the June 4, 1989, Tiananmen Square incident
delayed until 1991 the syndication of loans for the Guangzhou-Shenzhen-Zhuhai
superhighway.11
A few words on the force majeure clause12
should be said at this point even
though it will be analysed in detail throughout this paper. Basically, lenders want to keep
the project company rolling. Hence, force majeure has to be negotiated generously in
favour of the project company and strictly in favour of contracting parties: (construction
company, suppliers and purchasers).
On the issue of currency, banks will be wary of projects in countries with poor
currency stability or with strict currency convertibility restrictions.13
Hedging contracts
can be a possible solution. Otherwise, the offtaker should bear the risk. Usually, this will
be done through an increase of the tariff payable in local currency.14
2.2 Consents
Authorizations and consents issued by governmental bodies other than the one
awarding the concession must be negotiated so that they are given for the duration of the
project. Moreover, regulators should not be able to alter the terms of the authorizations.
Banks will want to see the association of any permit delivered with the project and not
9
C., Walker, and A. J., Smith, eds., supra note 6, p. 151.
10
UNCITRAL, supra note 4.
11
C., Walker, and A. J., Smith, eds., supra note 6, p. 151.
12
“Force majeure is a commercial law concept (alien to loan agreements) which exonerates a
party to a contract from the consequences of a failure to perform his obligations by supervening
events.” Definition reproduced from: G., Vinter, supra note 5, p. 88.
13
Baker & McKenzie, Project Finance: The Guide to Financing Power Projects, pp. 24-25.
14
G., Vinter, supra note 5, p. 79.
Matriculation Number 00 99 43 036
7
with the project company. This way, the project may keep running if the banks decide to
enforce their security.15
2.3 The Shareholders’ Agreements
Banks will impose certain requirements on shareholders’ agreements or even on
the company’s constitutional documents. It is not in their interest to see any deterioration
of relationships between the shareholders. This is especially possible where the body of
shareholders includes the host government or the construction contractor. Therefore,
detailed rules on conflicts of interests, non-competition, pre-emption rights must be
established.16
Moreover, banks will usually insist that the shareholders’ agreements establish
contingent capital contributions by the sponsors. Indeed, it is rare for banks to provide
alone all capital needed for the project. Basically, the relevant sponsors will enter into an
equity agreement with the banks whereby they agree to subscribe capital in the project
company at specified amounts and timing.17
As scholars have noted it, equity ownership will provide an incentive to the
sponsors to stay actively involved in the project.18
Often, it will be required that equity contributions be made up-front. However,
in practice banks will tolerate phased and sometimes even back-ended contributions if the
creditworthiness of the sponsors is satisfactory.19
Also, contributions might sometimes be
in kind. However, valuation of individual contributions may prove difficult especially in
emerging markets with no free markets and exchange control mechanisms. 20
15
Ibid, p. 94
16
G., Vinter, supra note 5, p. 34.
17
P. R., Wood, Project Finance, Subordinated Debt and State Loans, p. 19.
18
Baker & McKenzie, supra note 13, p. 29.
19
G., Vinter, supra note 5, p. 34.
20
Ibid., p. 34.
Matriculation Number 00 99 43 036
8
It should be noted that if the banks are asked to lend extra amounts of money for
cost overruns, then it will usually be required that the sponsors make equity injections
into the project company in accordance with the project’s initial debt:equity ratio.21
Similarly, the sponsors might be required to inject equity into the project if
insurance companies refuse to provide cover. This will often be the case with untested
materials and machinery used in the project. For example, insurance companies refused
to provide cover for General Electric’s new 9F turbines that were, at the time, still during
the commissioning phase. Since lenders did not want to carry the risk, project sponsors
were obliged to provide themselves loans to the project company to repair possible
damage during the commissioning of the turbines.22
Banks will often keep, in the case of a default under the loan agreement, the
possibility to terminate the loan agreement and to call in any equity contributions not yet
made. Also, if the concession is terminated, due to a default by the government for
example, then, any compensation to be paid should be enough to repay the banks.23
2.4 The Concession Agreement
The concession is essentially a licence granted by a governmental or quasi-
governmental body. Typically, national law will establish a specific procedure for the
selection of the project company. Under some national systems, it is in principle
obligatory to use the public tendering system. Under others, unsolicited proposals are
generally accepted.24
Under the public tendering system, the relevant body of law will detail the
content of any invitation to tender and will establish criteria for the evaluation of the
21
Ibid., p. 96.
22
Ibid., p. 96.
23
Ibid., p. 95.
24
UNCITRAL, supra note 4.
Matriculation Number 00 99 43 036
9
tenders. In the case of unsolicited proposals, laws may provide a procedural framework to
govern all negotiations.25
It should be noted that, most often, the project company is not yet established
when the project consortium is selected. Therefore, laws will usually impose on the
project consortium the obligation to establish itself legally within a specific period of
time. Failure to do so will permit the government in question to select another
consortium.26
There are certain terms that the sponsors must negotiate so that the whole project
looks more acceptable to the banks. First of all, the terms of the concession must be fixed
for the life of the project. Secondly, there must not be any unreasonably onerous terms
imposed on the sponsors unless these can be passed on to a certain degree to other
contracting parties. For instance, liquidated damages provisions included in the
concession agreement might be excessively high, however these can be passed through to
the construction contractors.27
Furthermore, the grantor of the concession should accept the risks of any
changes in law. For example, if stricter environmental legislation delays project
completion, then all adequate extensions should be made available.28
The clauses on termination must also be carefully considered. Typically, the
grounds for termination are: mutual consent to terminate, end of the concession period,
death, dissolution of the concessionaire, bankruptcy of the concessionaire and
repurchase.29
The enforcement of any bank security should not be able to terminate the
25
Ibid.
26
Ibid.
27
G., Vinter, supra note 5, p. 96.
28
Ibid.
29
UNCITRAL, supra note 4.
Matriculation Number 00 99 43 036
10
concession agreement. Force majeure also should not terminate the concession and the
appropriate extension periods should be accorded. 30
If the concession agreement is indeed terminated, then the banks should be able
to step-in and claim the transfer of the concession. Also, if any compensation is to be
paid, due to a default by the host government for example, then the amounts in question
should be sufficient to reimburse the banks.31
3. The Construction Phase
Construction contracts involve a number of considerations specific to BOT
projects.The banks will look for the following in a construction contract:
3.1 Reputation of the Contractor
The identity of the constructor is primordial. The banks will insist on having a
credit-worthy contractor with a solid reputation in the field. This is to ensure that all
contracted obligations can indeed be assumed. It is important to note that under some
legal jurisdictions, the sponsors will not be able to sue sub-contractors that are not party
to the main construction contract.
3.2 Design and Cost of the Construction
The construction contract, typically, will have to be a turnkey design. It should
be able to reflect the back-to-back arrangements with other interdependent contracts such
as the output and the operation and maintenance agreements.32
Another option could be
to create a construction consortium composed of all contracting parties. The advantages
of such a solution is that responsibility is shared and does not rest on the shoulders of one
single party.33
30
G., Vinter, supra note 5, p. 97.
31
UNCITRAL, supra note 4.
32
Electronic Construction Law Journal (ECLJ), Build Own Operate Transfer (BOOT) Projects,
http://www.mcmullan.net/eclj/BOT.html.
Matriculation Number 00 99 43 036
11
The contract cost of construction should be fixed and should be open to the least
possible number of re-evaluations. The price should be paid in one lump sum upon
completion. If this cannot be negotiated then the contract may establish stage payments
on specific achievement milestones. These milestones should have some reference to the
work done and must contain as much price retention as possible. 34
3.3 Completion Obligations
On the issue of completion, the contract must fix a date in time at which this
must occur. Traditionally in BOT contracting practice, if the construction contractor is
responsible for any delays, then no extension should be allowed and no extra payments
should be made. Force majeure events justifying delays should be limited. If a contracted
force majeure event does actually occur, then the principle should be to allow an
extension but no extra amounts of money.35
If it is the sponsors themselves that cause delays then the situation is more
complex. Typically, the sponsors will have to bear the risk and provide any delay costs.
However, the financial capacity of the special project vehicle is often limited. The banks
will therefore want to see the risk on more ‘supportive’ shoulders. One solution would be
to back-to-back the obligations of the sponsor with take-or-pay provisions in the output
agreement.36
The banks also want to define completion under the construction contract as
dependent upon completion under the concession contract. Contractors will feel
uncomfortable to include such a clause, especially since they are not part to the
concession agreement. Nevertheless, banks will insist on such back-to-back provisions
and their inclusion will definitely enhance bankability.37
33
G., Vinter, supra note 5, p. 46.
34
Ibid., p. 98.
35
Electronic Construction Law Journal (ECLJ), supra note 32.
36
Ibid.
Matriculation Number 00 99 43 036
12
If the constructor has not completed the project by the fixed date, then liquidated
damages should be paid. These should at least be able to repay, for a reasonable period,
the interest payments on the loan.38
To avoid problems between the contracting parties,
the construction schedule should be generous and should include sufficient schedule
cushions to cover risks of delays.39
Interestingly, under some legal jurisdictions, constructors benefit from an
automatic security on the project once construction is completed. Such a security does not
need to be published and will have, for a certain proportion, priority on other securities. If
these legal rules are suppletive, then the banks must ensure that the contract is drafted in
a way that their own securities are prioritized.40
3.4 Quality of the Construction
The construction contract must establish specific rules in case of a failure by the
constructor to deliver the project as specified. Underperformance may lead to serious
consequences especially to the government and to the banks. On the one hand, the
government might have structured its capital expenditure program on the successful
completion of the project. On the other hand, banks may see their security on the project
diminished.41
As a general rule, the sponsors will be entitled to liquidated damages depending
on the level of underperformance. These damages should include consequential losses
incurred in other agreements such as the output agreement, the operation and
maintenance agreements and even the loan agreement. Therefore, the constructor might
be exposed to damages exceeding the value of the contract.42
37
G., Vinter, supra note 5, pp. 49-50.
38
Ibid., pp. 99-100.
39
Baker & McKenzie, supra note 13, p. 34.
40
Civil Code of Quebec, Articles 2726, 2727 and 2952.
41
Electronic Construction Law Journal (ECLJ), supra note 32.
42
Ibid.
Matriculation Number 00 99 43 036
13
The requirements of the completion tests should be clearly enunciated in the
contract. An independent qualified engineer should certify the performance of the
equipment used in the project.43
The contractor should offer extensive guarantees and these should last for a
reasonable amount of time after completion. Usually, guarantees will last two years for
mechanical and electrical work and five years for civil work.44
The banks should be able to step in the contract if certain events arise, such as
the termination of the loan or output agreements. A step-in right in favour of the banks is
actually beneficial to the constructor as well. Indeed, through step-in, the constructor sees
the execution of the sponsors’ contracted obligations.45
4. The Operational Phase
In the examination of the operational phase, three main types of agreements
must be discussed: the operation and maintenance agreements, the input agreement (often
referred to as the supply agreement) and the output agreement (often referred to as the
offtake agreement). These will be presented in the following sections.
4.1 Operation and Maintenance Agreements
Here again, banks will require a reputed and financially sound operator. The
resources and capital available can therefore greatly enhance bankability.46
There are many ways to structure the operation and maintenance of a project.
Firstly, the project company can carry out itself the operation and maintenance. Secondly,
a third party can, by contract, carry out these functions. Or, thirdly, operation and
43
Baker & McKenzie, supra note 13, p. 52.
44
G., Vinter, supra note 5, p. 99.
45
Electronic Construction Law Journal (ECLJ), supra note 32.
46
Baker & McKenzie, supra note 13, p. 58.
Matriculation Number 00 99 43 036
14
maintenance duties can be shared between the project company and a third party.47
Whoever is in charge must be given adequate incentive to properly run the required
duties.48
The operator will have a contractual role on the project even before the project is
transferred. Indeed, the operator will be asked to estimate the necessary staffing levels,
work programs and administrative structures.49
Describing the obligations of the operator in the contract is not an easy task.
This is especially true due to the multiplicity of duties and due to the long-term nature of
the contract. Circumstances may change with time and it is difficult to predict the factors
that can come into play.50
Moreover, the contract must determine whether the operator
must achieve minimum operating levels and standards, spelled out in the contract, or,
whether the operator is bound instead by general operating obligations such as those
implied in ‘good utility practice clauses’.51
The penalties in case of a fault should be severe. The provisions on default
should be clear and detailed. For example, the operator may be responsible for poor
output, availability or for unreasonable number of outages. If the default is too great or
inexcusably extended in time, then the sponsors and even the banks should be able to
either step-in or terminate the contract.
If, on the other hand, the obligations of the operator are increased by external
factors such as changes in law for example, then the operator should not be justified to
benefit from an increase in payment entitlements. The contract price should be fixed as
much as possible.
47
G., Vinter, supra note 5, p. 61.
48
Ibid., p. 101.
49
Electronic Construction Law Journal (ECLJ), supra note 32.
50
Ibid.
Matriculation Number 00 99 43 036
15
4.2 Input Agreements
As Graham Vinter notes:
“It is important to realise that one man’s supply contract is another man’s offtake
agreement.”52
Therefore, what is said in this section is extremely relevant to the topic of the
next section on output agreements. Here, the following points can be said:
The availability of a reliable supply source is essential to the success of any
BOT project. To achieve this, the banks will often insist on a detailed appraisal of
adequacy of fuel reserves53
or on the accessibility to other sources of supply. Supplies
may be either purchased under long-term contracts or from the open market. One
disadvantage of buying from an open market is that the prices are not as stable as those
under long-term contracts.54
Ideally, the supply contract should not contain take-or-pay provisions as they
can become very onerous especially if they become more expensive than open market
(spot market) prices. This is especially possible in a market undergoing liberalisation and
in which competition is being introduced. If take-or-pay provisions are inevitable, then
price re-evaluation clauses should be included on a reasonable basis.
The force majeure should be drafted in a way that the supplier is not easily
justified to interrupt contracted obligations. On the other hand, it must be drafted in a way
that incorporates elements of other project contracts. In other words, the force majeure
clause should include such things as a terminated concession rights, delays in
construction, etc.
51
G., Vinter, supra note 5, p. 63.
52
Ibid., p. 65
53
Baker & McKenzie, supra note 13, p. 65.
54
Ibid., pp. 60-61.
Matriculation Number 00 99 43 036
16
Ideally, the supplier should take full responsibility for compensating the project
company for revenues lost or liabilities incurred due to supply failure. In practice,
however, suppliers will only accept responsibility for the additional cost of replacement
fuel.55
4.3 Output Agreements
The output agreement, or the offtake agreement is key to the success of any
BOT project. Every BOT project has a good or service produced that needs to be sold.
The negotiated price must be enough to pay for the entire project. It must also give the
adequate rate of return sought. As the Electronic Construction Law Journal (ECLJ) notes:
“The viability of the project and in particular its bankability will depend upon the
reliability of the cashflow under the offtake agreement, and the government agency and
sponsor performing their respective obligations.”56
It must be reminded that the product or service can be either sold on a spot basis
or can be sold to an individual offtaker. If it is sold in a spot market, then the contract will
be dependent on the rules of the spot market in question and might vary on a case-by-case
basis. This paper will rather analyse the long-term offtake agreement, which usually is
negotiated with a government agency. Certainly, the offtaker must be creditworthy and
must have the capacity to pay.
The aim of the sponsors and of the banks is to minimise market risks in order to
guarantee the profitability of the project. The practice has shown that for this purpose the
cashflow must be structured in two parts, an availability fee and a usage fee.57
The availability fee must cover all or a substantial part of the fixed costs. On the
other hand, the usage fee will be mainly composed of variable costs.58
55
Ibid., p. 63.
56
Electronic Construction Law Journal (ECLJ), supra note 32.
57
Ibid.
58
Ibid.
Matriculation Number 00 99 43 036
17
The higher the negotiated availability fee, the lower the market risks. The fixed
costs in the calculation of availability are re-estimated every year. These are, as a general
rule, composed of such thing as:59
- the amount of the banks’ loan due to be repaid in that year including the interests;
- the non-variable operating costs for that year;
- taxes payable by the project company for that year;
- insurance premiums payable in that year;
- the project company’s overheads for that year;
- the equity return for that year.
On the other hand, variable costs are mainly composed of such things as the cost
of fuel and other input elements. It must be stressed that all costs, fixed and variable
must be passed through to the offtaker. Moreover, take-or-pay provisions should
definitely be included.60
The tariff charged to the final offtaker must be adjusted in the case of unforeseen
circumstances. If, for example, a new environmental legislation imposes higher costs
then, these must be passed through to the offtaker. It is not the occurrence of any event
that justifies an adjustment. Obviously, this is left to negotiation of course. However,
such things as tax changes are not usually included in the list of events.61
As for the force majeure clause, it must be negotiated in a way that the offtaker
carries as much of the risk as possible. Basically, the sponsors’ negotiation plan must be
aimed at the payment of tariffs whether or not the project is producing.
5. Conclusion
As Philip Wood remarks,
59
G., Vinter, supra note 5, p. 73.
60
Electronic Construction Law Journal (ECLJ), supra note 32.
61
Ibid.
Matriculation Number 00 99 43 036
18
“Banks lending to a BOT project will ensure that both the performance and financial
obligations of the project company to the grantor are matched by corresponding
obligations on the part of the sub-contractors owed to the project company and that the
relevant sub-contracts impose no greater liability on the project company to the sub-
contractor than that owed by the grantor to the project company under the concession
agreement.”62
The project company should not be over-burdened with obligations and should
not carry an unreasonable amount of risks. If this is the case, the banks’ security on the
project company is likely to be reduced. It must be reminded that BOT arrangements are
a form of project finance. Banks want to make sure that the cashflow is adequate for the
reimbursement of the loan along with the interests.
The sponsors must negotiate BOT arrangements in accordance with the terms of
the banks. Otherwise, these will just find the whole deal unattractive.
62
P. R., Wood, supra note 17, pp. 11-12.
Matriculation Number 00 99 43 036
19
Annex A
The Typical Structure of a BOT Project
(Reproduced from C., Walker, and A. J., Smith, eds., Privatized Infrastructure: the BOT Approach, p. 5)
Matriculation Number 00 99 43 036
20
Bibliography
1. Secondary Sources
1.1 Books
Baker & McKenzie, Project Finance: The Guide to Financing Power Projects, (England:
Euromoney Publications, 1996).
Bodie, Z., and, Merton, R. C., Finance, Preliminary Edition, (Upper Saddle River, New
Jersey: Prentice-Hall Inc., 1998).
Brealey, R. A., and Myers, S., C., Principles of Corporate Finance, Sixth Edition,
(London, England: McGraw-Hill Companies, 2000).
Milbank, Twees, Hadley & McCloy, Project Finance:The Guide to Financing
International Oil and Gas Projects, (England: Euromoney Publications, 1996).
Vinter, G., Project Finance: A Legal Guide, Second Edition, (London, England: Sweet &
Maxwell, 1998).
Walker, C., and Smith, A. J., eds., Privatized Infrastructure: the BOT Approach,
(London, England: Thomas Telford Publications, 1995).
Wood, P. R., Project Finance, Subordinated Debt and State Loans, (London, England:
Sweet & Maxwell, 1995).
1.2 Articles
Beardsworth, J. Jr., Negotiating Power Purchase Agreements: Fundamentals for Risk
Allocation and Dispute Resolution, [1995] 707 PLI/Comm 27.
Berry, C., Criteria for Successful Project Financing, 1991/1992 PFY 15.
Brown, T., et al., The Shandong PRC Milestonem [1999] 165 PFI 52.
Davidson, P., Political Risk Insurance – Commercial, 1991/1992 PFY 43.
Dow, S., and Andrews-Speed, P., Considerations for Foreign Investors in China’s
Electricity Sector, [1998] OGLTR
Ingham, R., Risk Management, 1991/1992 PFY 35.
Issen, R., et al., Malaysia’s Johor Water Privatisation Project: A BOT Success Story,
1991/1992 PFY 23
Matriculation Number 00 99 43 036
21
Keeley, P., J., Project Financing for International Independent Power Facilities:
Management of Risks, [1996] 14:4 JENRL 445.
Mauel, J. G., Common Contractual Risk Allocations in International Power Projects,
[1996] 1996 CLMBLR 37.
McCormick, R. S., Legal Issues in Project Finance,
Moroney, G., J., Project Financing in Emerging Markets: Success Factors in Volatile
Markets, IOGFR 29.
Peppiatt, S., Introduction to Power Station Project Financing, [1995] 13 INTXBL 46.
Pritchard, R., Downstream Energy Financing and the Limitations of BOT Projects,
[1997] 5 OGLTR 149.
Prowse, N., and Rowson, M., Project Finance in Turkey: The BOT Model, [1999] 1
OGLTR 29.
Roberts, P., Bankable Gas Sales Agreements in the Project Financing of Offshore Gas
Production Projects, [1998] 16:2 JENRL 200.
Siegl, C. F. J., How to Get the Best Out of Your Bank, 1991/1992 PFY 75.
Syrett, S., The Future of Project Finance, 1991/1992 PFY 11.
Townsend, D., Powering Ahead, April 2000 PE 14.
Vinoski & Associates, Revenue Collection Experiences and Insight, [1999] 165 PFI 82.
Wallin, S., and, Fairfull, H., Financing Power Generation Projects in Central and
Eastern Europe, 1991/1992 PFY 46.
1.3 Internet Sources
Adefulu, A., Downstream Energy Financing in Developing Countries: Are BOTs the
Answer?, [1999] 3 CAR, http://www.dundee.ac.uk/cepmlp/main/html/car_article1.html
Electronic Construction Law Journal (ECLJ), Build Own Operate Transfer (BOOT)
Projects, http://www.mcmullan.net/eclj/BOT.html
UNCITRAL, Possible Future Work: Build-Operate-Transfer Projects, Twenty-Ninth
Session, A/CN.9/424, April 19, 1996, http://www.uncitral.org/english/sessions/unc/unc-
29/acn9-424.htm
Matriculation Number 00 99 43 036
22
Watanabe, H., On the Road to Independent Power Producer (IPP),
http://www.cosapi.com.pe/instituciones/cepeja/cepeja4/watanabe.html

More Related Content

What's hot

Chapter19 financinginfrastructureprojects
Chapter19 financinginfrastructureprojectsChapter19 financinginfrastructureprojects
Chapter19 financinginfrastructureprojects
AKSHAYA0000
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
Delhi Technological University
 
Infrastructure Finance Fundamentals (ADN Capital Ventures)
Infrastructure Finance Fundamentals (ADN Capital Ventures)Infrastructure Finance Fundamentals (ADN Capital Ventures)
Infrastructure Finance Fundamentals (ADN Capital Ventures)Adam Nicolopoulos
 
Risk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsRisk Mitigation In Construction Contracts
Risk Mitigation In Construction Contracts
IRJET Journal
 
19. financing infrastrucutre projects
19. financing infrastrucutre projects19. financing infrastrucutre projects
19. financing infrastrucutre projectsIshita Shah
 
Bot(build operate transfr)
Bot(build operate transfr)Bot(build operate transfr)
Bot(build operate transfr)
Kritika Garg
 
Project Finance Session 02
Project Finance   Session 02Project Finance   Session 02
Project Finance Session 02
Bodenbr
 
Project Finance - Session 7
Project Finance - Session 7Project Finance - Session 7
Project Finance - Session 7
Bodenbr
 
Surety Bonds
Surety BondsSurety Bonds
Surety Bonds
Yajush Sonar
 
Understanding "BOT" projects
Understanding "BOT" projectsUnderstanding "BOT" projects
Understanding "BOT" projects
Prashanth Ravada
 
Project Finance Session 02
Project Finance   Session 02Project Finance   Session 02
Project Finance Session 02
Bodenbr
 
An introduction to project finance
An introduction to project financeAn introduction to project finance
An introduction to project finance
Anurag Jaiswal
 
Project Financing
Project FinancingProject Financing
Project Financing
kcbradley
 
Procurement & contract.(bot)
Procurement & contract.(bot)Procurement & contract.(bot)
Procurement & contract.(bot)
rajlaxmipardeshi
 
51432284 project-finance
51432284 project-finance51432284 project-finance
51432284 project-financeamritakamarath
 
Solar Project Finance: Turning Sunlight Into Green
Solar Project Finance: Turning Sunlight Into Green Solar Project Finance: Turning Sunlight Into Green
Solar Project Finance: Turning Sunlight Into Green
Rick Borry
 
Build, operate & transfer
Build, operate & transferBuild, operate & transfer
Build, operate & transfer
Saurav Kumar
 
Project Finance Session 01
Project Finance Session 01Project Finance Session 01
Project Finance Session 01
Bodenbr
 
Project Financing in Public Projects
Project Financing in Public ProjectsProject Financing in Public Projects
Project Financing in Public Projects
Xinyi (Sophia) Xue
 
Steven glaze kansas city gives simple guidance for you in home improvement.
Steven glaze kansas city gives simple guidance for you in home improvement.Steven glaze kansas city gives simple guidance for you in home improvement.
Steven glaze kansas city gives simple guidance for you in home improvement.
General Contractor / Home Improvement Specialist
 

What's hot (20)

Chapter19 financinginfrastructureprojects
Chapter19 financinginfrastructureprojectsChapter19 financinginfrastructureprojects
Chapter19 financinginfrastructureprojects
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
Infrastructure Finance Fundamentals (ADN Capital Ventures)
Infrastructure Finance Fundamentals (ADN Capital Ventures)Infrastructure Finance Fundamentals (ADN Capital Ventures)
Infrastructure Finance Fundamentals (ADN Capital Ventures)
 
Risk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsRisk Mitigation In Construction Contracts
Risk Mitigation In Construction Contracts
 
19. financing infrastrucutre projects
19. financing infrastrucutre projects19. financing infrastrucutre projects
19. financing infrastrucutre projects
 
Bot(build operate transfr)
Bot(build operate transfr)Bot(build operate transfr)
Bot(build operate transfr)
 
Project Finance Session 02
Project Finance   Session 02Project Finance   Session 02
Project Finance Session 02
 
Project Finance - Session 7
Project Finance - Session 7Project Finance - Session 7
Project Finance - Session 7
 
Surety Bonds
Surety BondsSurety Bonds
Surety Bonds
 
Understanding "BOT" projects
Understanding "BOT" projectsUnderstanding "BOT" projects
Understanding "BOT" projects
 
Project Finance Session 02
Project Finance   Session 02Project Finance   Session 02
Project Finance Session 02
 
An introduction to project finance
An introduction to project financeAn introduction to project finance
An introduction to project finance
 
Project Financing
Project FinancingProject Financing
Project Financing
 
Procurement & contract.(bot)
Procurement & contract.(bot)Procurement & contract.(bot)
Procurement & contract.(bot)
 
51432284 project-finance
51432284 project-finance51432284 project-finance
51432284 project-finance
 
Solar Project Finance: Turning Sunlight Into Green
Solar Project Finance: Turning Sunlight Into Green Solar Project Finance: Turning Sunlight Into Green
Solar Project Finance: Turning Sunlight Into Green
 
Build, operate & transfer
Build, operate & transferBuild, operate & transfer
Build, operate & transfer
 
Project Finance Session 01
Project Finance Session 01Project Finance Session 01
Project Finance Session 01
 
Project Financing in Public Projects
Project Financing in Public ProjectsProject Financing in Public Projects
Project Financing in Public Projects
 
Steven glaze kansas city gives simple guidance for you in home improvement.
Steven glaze kansas city gives simple guidance for you in home improvement.Steven glaze kansas city gives simple guidance for you in home improvement.
Steven glaze kansas city gives simple guidance for you in home improvement.
 

Viewers also liked

Dr. Zaid Mahayni - Draft Corporate Governance Regulations - 22 May 2016
Dr. Zaid Mahayni - Draft Corporate Governance Regulations - 22 May 2016Dr. Zaid Mahayni - Draft Corporate Governance Regulations - 22 May 2016
Dr. Zaid Mahayni - Draft Corporate Governance Regulations - 22 May 2016
Dr. Zaid Mahayni
 
Zaid Mahayni - Redetermination Provisions - CEPMLP 2000-2001
Zaid Mahayni - Redetermination Provisions - CEPMLP 2000-2001Zaid Mahayni - Redetermination Provisions - CEPMLP 2000-2001
Zaid Mahayni - Redetermination Provisions - CEPMLP 2000-2001
Dr. Zaid Mahayni
 
Zaid Mahayni - The Discretionary vs The Auction Licence Allocation Methods -...
Zaid Mahayni - The Discretionary vs The Auction Licence Allocation Methods  -...Zaid Mahayni - The Discretionary vs The Auction Licence Allocation Methods  -...
Zaid Mahayni - The Discretionary vs The Auction Licence Allocation Methods -...
Dr. Zaid Mahayni
 
Summary: Rules Governing Saudi Closed Joint Stock Companies
Summary: Rules Governing Saudi Closed Joint Stock CompaniesSummary: Rules Governing Saudi Closed Joint Stock Companies
Summary: Rules Governing Saudi Closed Joint Stock Companies
Dr. Zaid Mahayni
 
Zaid Mahayni - Middle East LNG exports - CEPMLP 2000-2001
Zaid Mahayni - Middle East LNG exports - CEPMLP 2000-2001Zaid Mahayni - Middle East LNG exports - CEPMLP 2000-2001
Zaid Mahayni - Middle East LNG exports - CEPMLP 2000-2001
Dr. Zaid Mahayni
 
Zaid Mahayni - Future of Take-or-Pay Provisions in a Liberalized European Gas...
Zaid Mahayni - Future of Take-or-Pay Provisions in a Liberalized European Gas...Zaid Mahayni - Future of Take-or-Pay Provisions in a Liberalized European Gas...
Zaid Mahayni - Future of Take-or-Pay Provisions in a Liberalized European Gas...
Dr. Zaid Mahayni
 
Zaid Mahayni - 2001 CEPMLP LLM Dissertation
Zaid Mahayni - 2001 CEPMLP LLM DissertationZaid Mahayni - 2001 CEPMLP LLM Dissertation
Zaid Mahayni - 2001 CEPMLP LLM DissertationDr. Zaid Mahayni
 
Zaid Mahayni - Protection of Ultimate Oil Recovery - CEPMLP 2000-2001
Zaid Mahayni - Protection of Ultimate Oil Recovery - CEPMLP 2000-2001Zaid Mahayni - Protection of Ultimate Oil Recovery - CEPMLP 2000-2001
Zaid Mahayni - Protection of Ultimate Oil Recovery - CEPMLP 2000-2001
Dr. Zaid Mahayni
 
KLL4313
KLL4313 KLL4313
KLL4313
KLIBEL
 
LLM2013 ReaDing oil&gas legal issues presentation
LLM2013 ReaDing oil&gas legal issues presentation LLM2013 ReaDing oil&gas legal issues presentation
LLM2013 ReaDing oil&gas legal issues presentation
ReadingLLMlegaleagles
 
LLM 2013 Reading oil&gas contract law
LLM 2013 Reading oil&gas contract lawLLM 2013 Reading oil&gas contract law
LLM 2013 Reading oil&gas contract law
ReadingLLMlegaleagles
 
Doing Business in Iran's Post-Sanction Era: Oil and Gas Industry
Doing Business in Iran's Post-Sanction Era: Oil and Gas IndustryDoing Business in Iran's Post-Sanction Era: Oil and Gas Industry
Doing Business in Iran's Post-Sanction Era: Oil and Gas Industry
HCLA - LEGAL NETWORK
 
Incoterms - Presented by Mahmoud Attia
Incoterms - Presented by Mahmoud AttiaIncoterms - Presented by Mahmoud Attia
Incoterms - Presented by Mahmoud Attia
Mahmoud Attia
 
Fiscal System for oil
Fiscal System for oilFiscal System for oil
Fiscal System for oilAnupam Basu
 
Build - Operate - Transfer
Build - Operate - TransferBuild - Operate - Transfer
Build - Operate - Transfer
Kshitij Gupta
 
Fiscal Risk Advancements in Petroleum Contracts
Fiscal Risk Advancements in Petroleum ContractsFiscal Risk Advancements in Petroleum Contracts
Fiscal Risk Advancements in Petroleum Contracts
Yasir Karam
 
Production sharing agreements vs service contracts from the view of an ioc
Production sharing agreements vs service contracts from the view of an iocProduction sharing agreements vs service contracts from the view of an ioc
Production sharing agreements vs service contracts from the view of an iocValentine Ataka
 
ASBESTOS, VERMICULITE, COURUNDUM, MAGNESITE, AND TALC DEPOSITS IN EGYPT
ASBESTOS, VERMICULITE, COURUNDUM, MAGNESITE, AND TALC DEPOSITS IN EGYPTASBESTOS, VERMICULITE, COURUNDUM, MAGNESITE, AND TALC DEPOSITS IN EGYPT
ASBESTOS, VERMICULITE, COURUNDUM, MAGNESITE, AND TALC DEPOSITS IN EGYPT
Geology Department, Faculty of Science, Tanta University
 

Viewers also liked (20)

Dr. Zaid Mahayni - Draft Corporate Governance Regulations - 22 May 2016
Dr. Zaid Mahayni - Draft Corporate Governance Regulations - 22 May 2016Dr. Zaid Mahayni - Draft Corporate Governance Regulations - 22 May 2016
Dr. Zaid Mahayni - Draft Corporate Governance Regulations - 22 May 2016
 
Zaid Mahayni - Redetermination Provisions - CEPMLP 2000-2001
Zaid Mahayni - Redetermination Provisions - CEPMLP 2000-2001Zaid Mahayni - Redetermination Provisions - CEPMLP 2000-2001
Zaid Mahayni - Redetermination Provisions - CEPMLP 2000-2001
 
Zaid Mahayni - The Discretionary vs The Auction Licence Allocation Methods -...
Zaid Mahayni - The Discretionary vs The Auction Licence Allocation Methods  -...Zaid Mahayni - The Discretionary vs The Auction Licence Allocation Methods  -...
Zaid Mahayni - The Discretionary vs The Auction Licence Allocation Methods -...
 
Summary: Rules Governing Saudi Closed Joint Stock Companies
Summary: Rules Governing Saudi Closed Joint Stock CompaniesSummary: Rules Governing Saudi Closed Joint Stock Companies
Summary: Rules Governing Saudi Closed Joint Stock Companies
 
Zaid Mahayni - Middle East LNG exports - CEPMLP 2000-2001
Zaid Mahayni - Middle East LNG exports - CEPMLP 2000-2001Zaid Mahayni - Middle East LNG exports - CEPMLP 2000-2001
Zaid Mahayni - Middle East LNG exports - CEPMLP 2000-2001
 
Zaid Mahayni - Future of Take-or-Pay Provisions in a Liberalized European Gas...
Zaid Mahayni - Future of Take-or-Pay Provisions in a Liberalized European Gas...Zaid Mahayni - Future of Take-or-Pay Provisions in a Liberalized European Gas...
Zaid Mahayni - Future of Take-or-Pay Provisions in a Liberalized European Gas...
 
Zaid Mahayni - 2001 CEPMLP LLM Dissertation
Zaid Mahayni - 2001 CEPMLP LLM DissertationZaid Mahayni - 2001 CEPMLP LLM Dissertation
Zaid Mahayni - 2001 CEPMLP LLM Dissertation
 
Zaid Mahayni - Protection of Ultimate Oil Recovery - CEPMLP 2000-2001
Zaid Mahayni - Protection of Ultimate Oil Recovery - CEPMLP 2000-2001Zaid Mahayni - Protection of Ultimate Oil Recovery - CEPMLP 2000-2001
Zaid Mahayni - Protection of Ultimate Oil Recovery - CEPMLP 2000-2001
 
KLL4313
KLL4313 KLL4313
KLL4313
 
LLM2013 ReaDing oil&gas legal issues presentation
LLM2013 ReaDing oil&gas legal issues presentation LLM2013 ReaDing oil&gas legal issues presentation
LLM2013 ReaDing oil&gas legal issues presentation
 
LLM 2013 Reading oil&gas contract law
LLM 2013 Reading oil&gas contract lawLLM 2013 Reading oil&gas contract law
LLM 2013 Reading oil&gas contract law
 
Doing Business in Iran's Post-Sanction Era: Oil and Gas Industry
Doing Business in Iran's Post-Sanction Era: Oil and Gas IndustryDoing Business in Iran's Post-Sanction Era: Oil and Gas Industry
Doing Business in Iran's Post-Sanction Era: Oil and Gas Industry
 
Incoterms - Presented by Mahmoud Attia
Incoterms - Presented by Mahmoud AttiaIncoterms - Presented by Mahmoud Attia
Incoterms - Presented by Mahmoud Attia
 
Fiscal System for oil
Fiscal System for oilFiscal System for oil
Fiscal System for oil
 
Build - Operate - Transfer
Build - Operate - TransferBuild - Operate - Transfer
Build - Operate - Transfer
 
LLM University of Reading 2013
LLM University of Reading 2013LLM University of Reading 2013
LLM University of Reading 2013
 
Psc
PscPsc
Psc
 
Fiscal Risk Advancements in Petroleum Contracts
Fiscal Risk Advancements in Petroleum ContractsFiscal Risk Advancements in Petroleum Contracts
Fiscal Risk Advancements in Petroleum Contracts
 
Production sharing agreements vs service contracts from the view of an ioc
Production sharing agreements vs service contracts from the view of an iocProduction sharing agreements vs service contracts from the view of an ioc
Production sharing agreements vs service contracts from the view of an ioc
 
ASBESTOS, VERMICULITE, COURUNDUM, MAGNESITE, AND TALC DEPOSITS IN EGYPT
ASBESTOS, VERMICULITE, COURUNDUM, MAGNESITE, AND TALC DEPOSITS IN EGYPTASBESTOS, VERMICULITE, COURUNDUM, MAGNESITE, AND TALC DEPOSITS IN EGYPT
ASBESTOS, VERMICULITE, COURUNDUM, MAGNESITE, AND TALC DEPOSITS IN EGYPT
 

Similar to Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001

Introduction to power station project financing
Introduction to power station project financingIntroduction to power station project financing
Introduction to power station project financing
Jean-Lévy Taine
 
Pgpm14 infrastructure development
Pgpm14 infrastructure developmentPgpm14 infrastructure development
Pgpm14 infrastructure development
sakariya88
 
Contractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsContractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure Projects
AM Publications
 
הסכמי BOT מאת עודד ווסוק
הסכמי BOT מאת עודד ווסוקהסכמי BOT מאת עודד ווסוק
הסכמי BOT מאת עודד ווסוק
ODEDVOSOUK
 
BOT Agreements
BOT AgreementsBOT Agreements
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
January 2018 newsletter
January 2018 newsletterJanuary 2018 newsletter
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...Amanda James
 
dokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfdokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdf
afadlalla
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
LAKSHITHA RAJAPAKSHA
 
Legal and regulatory aspect of project finance
Legal and regulatory aspect of project financeLegal and regulatory aspect of project finance
Legal and regulatory aspect of project financeGagan Varshney
 
6. what is project finance
6. what is project finance6. what is project finance
6. what is project finance
Luis Anibal Ortiz Rojas
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...Praveen Premkumar
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
SHKLaw
 
5714383.ppt
5714383.ppt5714383.ppt
5714383.ppt
GUDAGUDA
 
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECDISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
OECDGlobalRelations
 
Prieto Swain Placilla Duvall Diwik Aba 2009 Final
Prieto Swain Placilla Duvall Diwik Aba 2009 FinalPrieto Swain Placilla Duvall Diwik Aba 2009 Final
Prieto Swain Placilla Duvall Diwik Aba 2009 Final
Bob Prieto
 
PPP models.pptx
 PPP models.pptx PPP models.pptx
PPP models.pptx
SwatiMathur27
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
Arissa Loh
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTXRyan Hatton
 

Similar to Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001 (20)

Introduction to power station project financing
Introduction to power station project financingIntroduction to power station project financing
Introduction to power station project financing
 
Pgpm14 infrastructure development
Pgpm14 infrastructure developmentPgpm14 infrastructure development
Pgpm14 infrastructure development
 
Contractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsContractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure Projects
 
הסכמי BOT מאת עודד ווסוק
הסכמי BOT מאת עודד ווסוקהסכמי BOT מאת עודד ווסוק
הסכמי BOT מאת עודד ווסוק
 
BOT Agreements
BOT AgreementsBOT Agreements
BOT Agreements
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
January 2018 newsletter
January 2018 newsletterJanuary 2018 newsletter
January 2018 newsletter
 
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
 
dokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfdokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdf
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
Legal and regulatory aspect of project finance
Legal and regulatory aspect of project financeLegal and regulatory aspect of project finance
Legal and regulatory aspect of project finance
 
6. what is project finance
6. what is project finance6. what is project finance
6. what is project finance
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
5714383.ppt
5714383.ppt5714383.ppt
5714383.ppt
 
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECDISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
 
Prieto Swain Placilla Duvall Diwik Aba 2009 Final
Prieto Swain Placilla Duvall Diwik Aba 2009 FinalPrieto Swain Placilla Duvall Diwik Aba 2009 Final
Prieto Swain Placilla Duvall Diwik Aba 2009 Final
 
PPP models.pptx
 PPP models.pptx PPP models.pptx
PPP models.pptx
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTX
 

Recently uploaded

EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW  AN OVERVIEW in Malawi.pptxEMPLOYMENT LAW  AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
MwaiMapemba
 
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptxNATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
anvithaav
 
Debt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debtDebt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debt
ssuser0576e4
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
9ib5wiwt
 
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
o6ov5dqmf
 
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense CounselMilitary Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Thomas (Tom) Jasper
 
ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.
Daffodil International University
 
Bharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptxBharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptx
ShivkumarIyer18
 
Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...
Finlaw Consultancy Pvt Ltd
 
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdfDonald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
ssuser5750e1
 
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal CourtAbdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Gabe Whitley
 
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Syed Muhammad Humza Hussain
 
new victimology of indonesian law. Pptx.
new victimology of indonesian law. Pptx.new victimology of indonesian law. Pptx.
new victimology of indonesian law. Pptx.
niputusriwidiasih
 
Secure Your Brand: File a Trademark Today
Secure Your Brand: File a Trademark TodaySecure Your Brand: File a Trademark Today
Secure Your Brand: File a Trademark Today
Trademark Quick
 
Understanding about ITR-1 and Documentation
Understanding about ITR-1 and DocumentationUnderstanding about ITR-1 and Documentation
Understanding about ITR-1 and Documentation
CAAJAYKUMAR4
 
The Reserve Bank of India Act, 1934.pptx
The Reserve Bank of India Act, 1934.pptxThe Reserve Bank of India Act, 1934.pptx
The Reserve Bank of India Act, 1934.pptx
nehatalele22st
 
Ease of Paying Tax Law Republic Act 11976
Ease of Paying Tax Law Republic Act 11976Ease of Paying Tax Law Republic Act 11976
Ease of Paying Tax Law Republic Act 11976
PelayoGilbert
 
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
9ib5wiwt
 
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdfXYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
bhavenpr
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
9ib5wiwt
 

Recently uploaded (20)

EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW  AN OVERVIEW in Malawi.pptxEMPLOYMENT LAW  AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
 
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptxNATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
 
Debt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debtDebt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debt
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
 
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
 
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense CounselMilitary Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
 
ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.
 
Bharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptxBharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptx
 
Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...
 
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdfDonald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
 
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal CourtAbdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal Court
 
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
 
new victimology of indonesian law. Pptx.
new victimology of indonesian law. Pptx.new victimology of indonesian law. Pptx.
new victimology of indonesian law. Pptx.
 
Secure Your Brand: File a Trademark Today
Secure Your Brand: File a Trademark TodaySecure Your Brand: File a Trademark Today
Secure Your Brand: File a Trademark Today
 
Understanding about ITR-1 and Documentation
Understanding about ITR-1 and DocumentationUnderstanding about ITR-1 and Documentation
Understanding about ITR-1 and Documentation
 
The Reserve Bank of India Act, 1934.pptx
The Reserve Bank of India Act, 1934.pptxThe Reserve Bank of India Act, 1934.pptx
The Reserve Bank of India Act, 1934.pptx
 
Ease of Paying Tax Law Republic Act 11976
Ease of Paying Tax Law Republic Act 11976Ease of Paying Tax Law Republic Act 11976
Ease of Paying Tax Law Republic Act 11976
 
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
 
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdfXYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
 

Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001

  • 1. CENTRE FOR ENERGY, PETROLEUM AND MINERAL LAW AND POLICY STATEMENT OF ORIGINALITY FOR RESEARCH PAPERS NAME OF STUDENT: Zaid Mahayni MATRICULATION NUMBER: 009943036 PROGRAMME: LL.M. in Petroleum Law and Policy TITLE OF THE RESEARCH PAPER: Negotiating BOT Arrangements: A Sponsor's Checklist in Ensuring Bankability ABSTRACT OF THE RESEARCH PAPER: Contract is the law of the parties to a BOT project. Banks will not accept to lend to a project company that is bearing heavy obligations, which cannot be assumed. The project must be viable. Other parties to a BOT project such as the host government, the construction company and the offtaker must all carry a reasonable amount of the risks. This paper will examine the typical contracts of a BOT arrangement and will describe the terms that must be included to enhance bankability. The sponsors must be conscious that without consideration to bankability, the project may just never materialize. WORD COUNT: 4,020 PRESENTED TO: Professor Stephen Dow TITLE OF THE COURSE: International Project Finance (GB 353) I, Zaid Mahayni, have read the Code of Practice regarding plagiarism contained in the Students’ Introductory Handbook. I realise that this Code governs the way in which the Centre for Petroleum and Mineral Law and Policy regards and treats the issue of plagiarism. I have understood the Code and in particular I am aware of the consequences, which may follow if I breach that code. Signed:________________ Date:__________________
  • 2. Matriculation Number 00 99 43 036 1 Table of Contents List of Abbreviations------------------------------------------------------------------ 2 1. Introduction-------------------------------------------------------------------------- 3 2. The Pre-Development Phase ------------------------------------------------------ 4 2.1 General Considerations----------------------------------------------------------- 4 2.2 Consents ---------------------------------------------------------------------------- 6 2.3 The Shareholders’ Agreements-------------------------------------------------- 7 2.4 The Concession Agreement------------------------------------------------------ 8 3. The Construction Phase: Negotiation of the Construction Contract--------- 10 3.1 Reputation of the Contractor ---------------------------------------------------- 10 3.2 Design and Cost of the Construction ------------------------------------------- 10 3.3 Completion Obligations ---------------------------------------------------------- 11 3.4 Quality of the Construction ------------------------------------------------------ 12 4. The Operation Phase --------------------------------------------------------------- 13 4.1 Operation and Maintenance Agreements -------------------------------------- 13 4.2 Input Agreements ----------------------------------------------------------------- 15 4.3 Output Agreements --------------------------------------------------------------- 16 5. Conclusion--------------------------------------------------------------------------- 17 Annex A--------------------------------------------------------------------------------- 19 Bibliography---------------------------------------------------------------------------- 20
  • 3. Matriculation Number 00 99 43 036 2 List of Abbreviations BOT------------------------------------------- Build-Operate-Transfer CAR------------------------------------------- CEPMLP Annual Review CEPMLP ------------------------------------- Centre for Energy, Petroleum and Mineral Law and Policy CLMBLR ------------------------------------ Columbia Business Law Review INTXBL-------------------------------------- International Tax and Business Lawyer IOGFR---------------------------------------- International Oil and Gas Finance Review JENRL---------------------------------------- Journal of Energy & Natural Resources Law OGLTR--------------------------------------- Oil and Gas Law and Taxation Review PE --------------------------------------------- Petroleum Economist PFY ------------------------------------------- Project Finance Yearly PLI/Comm ----------------------------------- Practising Law Institute Commercial Law and Practice Course Handbook Series PFI -------------------------------------------- Project Finance International UNCITRAL --------------------------------- United Nations Commission on International Trade Law
  • 4. Matriculation Number 00 99 43 036 3 1. Introduction In the 1970s Governments had difficulty funding large public works due to fiscal shortcomings. Not only, it didn’t have the means to build new structures but it also could not maintain already existing structures. The private sector was indeed needed but not in a way that would jeopardize State control over certain industries: transportation, energy, water, etc.1 BOT schemes (Build – Own – Transfer), developed in 1984 by Turkey, seemed a very attractive solution to the problem. It offered a great compromise between the interests of the private parties (make profits) and those of the governments (direct control of certain industries). Under the BOT scheme, a concession is granted to a concession holder (sponsor). The sponsor is empowered with the right to build a specified infrastructure, operate it for a determined period and at the end of the period transfer it back, at no cost, to the person that originally granted the concession. The duration of the concession may be established in either one of two ways. It may either be an expiry date, fixed in time, or it could be a variable date, dependent upon the recovery by the concessionaire of a certain amount of revenue or profit.2 The BOT structure involves a large amount of parties and an important number of contracts.3 The sponsor is the centre of practically all of these contracts. The sponsor must first be created. This will involve the signing of a consortium agreement and a shareholders’ agreement between the individual constituents of the sponsor. 1 Adefulu, A., Downstream Energy Financing in Developing Countries: Are BOTs the Answer?, 3 [1999] 3 CAR, http://www.dundee.ac.uk/cepmlp/main/html/car_article1.html. 2 Ibid. 3 Please refer to annex A for the representation of a typical BOT structure.
  • 5. Matriculation Number 00 99 43 036 4 Apart from the concession agreement, the sponsor must also sign a loan agreement, a construction contract, an operation contract, a supply contract and a sales contract. This list is not exhaustive and will vary from a project to another. In negotiating these contracts, the sponsor is faced with important constraints. One would be that lenders must be satisfied with the overall project in order to make an investment decision. The lenders will therefore impose on the sponsor their own parameters and conditions in the negotiation of agreements with the other parties. This paper will examine the contractual terms that the sponsor must negotiate in order to secure a loan and hence, render the project “bankable”. This paper will be structured in three main sections, according to the development phases of a typical BOT project: the pre-development phase, the construction phase and the operational phase. The development phase will cover the consents needed, the shareholder’s agreement and the concession agreement. The construction phase will cover the construction contract. And, finally, the operational phase will cover the operation and maintenance agreement, the input agreement with suppliers and the output agreement with purchasers. 2. The Pre-Development Phase 2.1 General Considerations It is important to keep in mind that BOT arrangements are a form of project finance. This implies that the lenders look primarily at the earnings of the project as the source from which the loan is payed. Credit assessment should therefore be mostly axed towards the project and not towards the creditworthiness of the borrowers. The fact that BOTs are a type of project finance also implies that lenders have only limited recourse against the borrowers since security taken by the banks is mainly confined to the assets of
  • 6. Matriculation Number 00 99 43 036 5 the project.4 For these reasons, lenders will carefully scrutinize all contracts to make sure that the loan can in fact be repaid. As a general rule, banks will refuse to carry risks that cannot be quantified or assessed.5 Banks will therefore not tolerate investments in politically risky regions. This risk is not only an issue in third world countries and developing countries. In fact, even democratic countries can contain political risk. For example, one significant factor that led to the abandonment of the Channel Tunnel project in 1975 was the 1974 change in the UK government from Conservative to Labour. With this change, support to the project was lost at a critical stage.6 As a rule, bankability will require a solid legal infrastructure. According to Robert Pritchard, the solidity of a legal system is dependent upon three components: “1) The first and most basic is the guarantee of the rule of law, manifested by a published and stable body of laws, readily interpretable and supported by effective administrative bodies and judicial recourse. 2) The second is an efficient body of business laws to support a market economy. These include the right to own property, the right to pledge assets in order to raise capital, and readily enforceable contract laws to govern business relationships. 3) The third is a specific law to authorise and delineate a process of competitive procurement and to support the resulting arrangements.”7 Lenders will accept to carry general changes in law (e.g. the rate of profit tax). However, these will not tolerate the risk of changes in law that are designed to specifically discriminate against the project company.8 The sponsors of a BOT project may sometimes obtain by the government assurances that legal changes will be restricted. However, the value of such assurances 4 UNCITRAL, Possible Future Work: Build-Operate-Transfer Projects, Twenty-Ninth Session, A/CN.9/424, April 19, 1996, http://www.uncitral.org/english/sessions/unc/unc-29/acn9-424.htm. 5 G., Vinter, Project Finance: A Legal Guide, Second Edition, p. 85. 6 C., Walker, and A. J., Smith, eds., Privatized Infrastructure: the BOT Approach, pp. 150-151. 7 R., Pritchard, Downstream Energy Financing and the Limitations of BOT Projects, [1997] 5 OGLTR 149, p. 151. 8 G., Vinter, supra note 5, p. 78.
  • 7. Matriculation Number 00 99 43 036 6 can be doubtful since governments can later decide to adopt a different policy.9 The lenders will hence have to look for a clear sign by the government in question to encourage long-term investment.10 Lenders will also avoid investing in projects situated in areas prone to violence, wars or even labour disputes. For instance, the June 4, 1989, Tiananmen Square incident delayed until 1991 the syndication of loans for the Guangzhou-Shenzhen-Zhuhai superhighway.11 A few words on the force majeure clause12 should be said at this point even though it will be analysed in detail throughout this paper. Basically, lenders want to keep the project company rolling. Hence, force majeure has to be negotiated generously in favour of the project company and strictly in favour of contracting parties: (construction company, suppliers and purchasers). On the issue of currency, banks will be wary of projects in countries with poor currency stability or with strict currency convertibility restrictions.13 Hedging contracts can be a possible solution. Otherwise, the offtaker should bear the risk. Usually, this will be done through an increase of the tariff payable in local currency.14 2.2 Consents Authorizations and consents issued by governmental bodies other than the one awarding the concession must be negotiated so that they are given for the duration of the project. Moreover, regulators should not be able to alter the terms of the authorizations. Banks will want to see the association of any permit delivered with the project and not 9 C., Walker, and A. J., Smith, eds., supra note 6, p. 151. 10 UNCITRAL, supra note 4. 11 C., Walker, and A. J., Smith, eds., supra note 6, p. 151. 12 “Force majeure is a commercial law concept (alien to loan agreements) which exonerates a party to a contract from the consequences of a failure to perform his obligations by supervening events.” Definition reproduced from: G., Vinter, supra note 5, p. 88. 13 Baker & McKenzie, Project Finance: The Guide to Financing Power Projects, pp. 24-25. 14 G., Vinter, supra note 5, p. 79.
  • 8. Matriculation Number 00 99 43 036 7 with the project company. This way, the project may keep running if the banks decide to enforce their security.15 2.3 The Shareholders’ Agreements Banks will impose certain requirements on shareholders’ agreements or even on the company’s constitutional documents. It is not in their interest to see any deterioration of relationships between the shareholders. This is especially possible where the body of shareholders includes the host government or the construction contractor. Therefore, detailed rules on conflicts of interests, non-competition, pre-emption rights must be established.16 Moreover, banks will usually insist that the shareholders’ agreements establish contingent capital contributions by the sponsors. Indeed, it is rare for banks to provide alone all capital needed for the project. Basically, the relevant sponsors will enter into an equity agreement with the banks whereby they agree to subscribe capital in the project company at specified amounts and timing.17 As scholars have noted it, equity ownership will provide an incentive to the sponsors to stay actively involved in the project.18 Often, it will be required that equity contributions be made up-front. However, in practice banks will tolerate phased and sometimes even back-ended contributions if the creditworthiness of the sponsors is satisfactory.19 Also, contributions might sometimes be in kind. However, valuation of individual contributions may prove difficult especially in emerging markets with no free markets and exchange control mechanisms. 20 15 Ibid, p. 94 16 G., Vinter, supra note 5, p. 34. 17 P. R., Wood, Project Finance, Subordinated Debt and State Loans, p. 19. 18 Baker & McKenzie, supra note 13, p. 29. 19 G., Vinter, supra note 5, p. 34. 20 Ibid., p. 34.
  • 9. Matriculation Number 00 99 43 036 8 It should be noted that if the banks are asked to lend extra amounts of money for cost overruns, then it will usually be required that the sponsors make equity injections into the project company in accordance with the project’s initial debt:equity ratio.21 Similarly, the sponsors might be required to inject equity into the project if insurance companies refuse to provide cover. This will often be the case with untested materials and machinery used in the project. For example, insurance companies refused to provide cover for General Electric’s new 9F turbines that were, at the time, still during the commissioning phase. Since lenders did not want to carry the risk, project sponsors were obliged to provide themselves loans to the project company to repair possible damage during the commissioning of the turbines.22 Banks will often keep, in the case of a default under the loan agreement, the possibility to terminate the loan agreement and to call in any equity contributions not yet made. Also, if the concession is terminated, due to a default by the government for example, then, any compensation to be paid should be enough to repay the banks.23 2.4 The Concession Agreement The concession is essentially a licence granted by a governmental or quasi- governmental body. Typically, national law will establish a specific procedure for the selection of the project company. Under some national systems, it is in principle obligatory to use the public tendering system. Under others, unsolicited proposals are generally accepted.24 Under the public tendering system, the relevant body of law will detail the content of any invitation to tender and will establish criteria for the evaluation of the 21 Ibid., p. 96. 22 Ibid., p. 96. 23 Ibid., p. 95. 24 UNCITRAL, supra note 4.
  • 10. Matriculation Number 00 99 43 036 9 tenders. In the case of unsolicited proposals, laws may provide a procedural framework to govern all negotiations.25 It should be noted that, most often, the project company is not yet established when the project consortium is selected. Therefore, laws will usually impose on the project consortium the obligation to establish itself legally within a specific period of time. Failure to do so will permit the government in question to select another consortium.26 There are certain terms that the sponsors must negotiate so that the whole project looks more acceptable to the banks. First of all, the terms of the concession must be fixed for the life of the project. Secondly, there must not be any unreasonably onerous terms imposed on the sponsors unless these can be passed on to a certain degree to other contracting parties. For instance, liquidated damages provisions included in the concession agreement might be excessively high, however these can be passed through to the construction contractors.27 Furthermore, the grantor of the concession should accept the risks of any changes in law. For example, if stricter environmental legislation delays project completion, then all adequate extensions should be made available.28 The clauses on termination must also be carefully considered. Typically, the grounds for termination are: mutual consent to terminate, end of the concession period, death, dissolution of the concessionaire, bankruptcy of the concessionaire and repurchase.29 The enforcement of any bank security should not be able to terminate the 25 Ibid. 26 Ibid. 27 G., Vinter, supra note 5, p. 96. 28 Ibid. 29 UNCITRAL, supra note 4.
  • 11. Matriculation Number 00 99 43 036 10 concession agreement. Force majeure also should not terminate the concession and the appropriate extension periods should be accorded. 30 If the concession agreement is indeed terminated, then the banks should be able to step-in and claim the transfer of the concession. Also, if any compensation is to be paid, due to a default by the host government for example, then the amounts in question should be sufficient to reimburse the banks.31 3. The Construction Phase Construction contracts involve a number of considerations specific to BOT projects.The banks will look for the following in a construction contract: 3.1 Reputation of the Contractor The identity of the constructor is primordial. The banks will insist on having a credit-worthy contractor with a solid reputation in the field. This is to ensure that all contracted obligations can indeed be assumed. It is important to note that under some legal jurisdictions, the sponsors will not be able to sue sub-contractors that are not party to the main construction contract. 3.2 Design and Cost of the Construction The construction contract, typically, will have to be a turnkey design. It should be able to reflect the back-to-back arrangements with other interdependent contracts such as the output and the operation and maintenance agreements.32 Another option could be to create a construction consortium composed of all contracting parties. The advantages of such a solution is that responsibility is shared and does not rest on the shoulders of one single party.33 30 G., Vinter, supra note 5, p. 97. 31 UNCITRAL, supra note 4. 32 Electronic Construction Law Journal (ECLJ), Build Own Operate Transfer (BOOT) Projects, http://www.mcmullan.net/eclj/BOT.html.
  • 12. Matriculation Number 00 99 43 036 11 The contract cost of construction should be fixed and should be open to the least possible number of re-evaluations. The price should be paid in one lump sum upon completion. If this cannot be negotiated then the contract may establish stage payments on specific achievement milestones. These milestones should have some reference to the work done and must contain as much price retention as possible. 34 3.3 Completion Obligations On the issue of completion, the contract must fix a date in time at which this must occur. Traditionally in BOT contracting practice, if the construction contractor is responsible for any delays, then no extension should be allowed and no extra payments should be made. Force majeure events justifying delays should be limited. If a contracted force majeure event does actually occur, then the principle should be to allow an extension but no extra amounts of money.35 If it is the sponsors themselves that cause delays then the situation is more complex. Typically, the sponsors will have to bear the risk and provide any delay costs. However, the financial capacity of the special project vehicle is often limited. The banks will therefore want to see the risk on more ‘supportive’ shoulders. One solution would be to back-to-back the obligations of the sponsor with take-or-pay provisions in the output agreement.36 The banks also want to define completion under the construction contract as dependent upon completion under the concession contract. Contractors will feel uncomfortable to include such a clause, especially since they are not part to the concession agreement. Nevertheless, banks will insist on such back-to-back provisions and their inclusion will definitely enhance bankability.37 33 G., Vinter, supra note 5, p. 46. 34 Ibid., p. 98. 35 Electronic Construction Law Journal (ECLJ), supra note 32. 36 Ibid.
  • 13. Matriculation Number 00 99 43 036 12 If the constructor has not completed the project by the fixed date, then liquidated damages should be paid. These should at least be able to repay, for a reasonable period, the interest payments on the loan.38 To avoid problems between the contracting parties, the construction schedule should be generous and should include sufficient schedule cushions to cover risks of delays.39 Interestingly, under some legal jurisdictions, constructors benefit from an automatic security on the project once construction is completed. Such a security does not need to be published and will have, for a certain proportion, priority on other securities. If these legal rules are suppletive, then the banks must ensure that the contract is drafted in a way that their own securities are prioritized.40 3.4 Quality of the Construction The construction contract must establish specific rules in case of a failure by the constructor to deliver the project as specified. Underperformance may lead to serious consequences especially to the government and to the banks. On the one hand, the government might have structured its capital expenditure program on the successful completion of the project. On the other hand, banks may see their security on the project diminished.41 As a general rule, the sponsors will be entitled to liquidated damages depending on the level of underperformance. These damages should include consequential losses incurred in other agreements such as the output agreement, the operation and maintenance agreements and even the loan agreement. Therefore, the constructor might be exposed to damages exceeding the value of the contract.42 37 G., Vinter, supra note 5, pp. 49-50. 38 Ibid., pp. 99-100. 39 Baker & McKenzie, supra note 13, p. 34. 40 Civil Code of Quebec, Articles 2726, 2727 and 2952. 41 Electronic Construction Law Journal (ECLJ), supra note 32. 42 Ibid.
  • 14. Matriculation Number 00 99 43 036 13 The requirements of the completion tests should be clearly enunciated in the contract. An independent qualified engineer should certify the performance of the equipment used in the project.43 The contractor should offer extensive guarantees and these should last for a reasonable amount of time after completion. Usually, guarantees will last two years for mechanical and electrical work and five years for civil work.44 The banks should be able to step in the contract if certain events arise, such as the termination of the loan or output agreements. A step-in right in favour of the banks is actually beneficial to the constructor as well. Indeed, through step-in, the constructor sees the execution of the sponsors’ contracted obligations.45 4. The Operational Phase In the examination of the operational phase, three main types of agreements must be discussed: the operation and maintenance agreements, the input agreement (often referred to as the supply agreement) and the output agreement (often referred to as the offtake agreement). These will be presented in the following sections. 4.1 Operation and Maintenance Agreements Here again, banks will require a reputed and financially sound operator. The resources and capital available can therefore greatly enhance bankability.46 There are many ways to structure the operation and maintenance of a project. Firstly, the project company can carry out itself the operation and maintenance. Secondly, a third party can, by contract, carry out these functions. Or, thirdly, operation and 43 Baker & McKenzie, supra note 13, p. 52. 44 G., Vinter, supra note 5, p. 99. 45 Electronic Construction Law Journal (ECLJ), supra note 32. 46 Baker & McKenzie, supra note 13, p. 58.
  • 15. Matriculation Number 00 99 43 036 14 maintenance duties can be shared between the project company and a third party.47 Whoever is in charge must be given adequate incentive to properly run the required duties.48 The operator will have a contractual role on the project even before the project is transferred. Indeed, the operator will be asked to estimate the necessary staffing levels, work programs and administrative structures.49 Describing the obligations of the operator in the contract is not an easy task. This is especially true due to the multiplicity of duties and due to the long-term nature of the contract. Circumstances may change with time and it is difficult to predict the factors that can come into play.50 Moreover, the contract must determine whether the operator must achieve minimum operating levels and standards, spelled out in the contract, or, whether the operator is bound instead by general operating obligations such as those implied in ‘good utility practice clauses’.51 The penalties in case of a fault should be severe. The provisions on default should be clear and detailed. For example, the operator may be responsible for poor output, availability or for unreasonable number of outages. If the default is too great or inexcusably extended in time, then the sponsors and even the banks should be able to either step-in or terminate the contract. If, on the other hand, the obligations of the operator are increased by external factors such as changes in law for example, then the operator should not be justified to benefit from an increase in payment entitlements. The contract price should be fixed as much as possible. 47 G., Vinter, supra note 5, p. 61. 48 Ibid., p. 101. 49 Electronic Construction Law Journal (ECLJ), supra note 32. 50 Ibid.
  • 16. Matriculation Number 00 99 43 036 15 4.2 Input Agreements As Graham Vinter notes: “It is important to realise that one man’s supply contract is another man’s offtake agreement.”52 Therefore, what is said in this section is extremely relevant to the topic of the next section on output agreements. Here, the following points can be said: The availability of a reliable supply source is essential to the success of any BOT project. To achieve this, the banks will often insist on a detailed appraisal of adequacy of fuel reserves53 or on the accessibility to other sources of supply. Supplies may be either purchased under long-term contracts or from the open market. One disadvantage of buying from an open market is that the prices are not as stable as those under long-term contracts.54 Ideally, the supply contract should not contain take-or-pay provisions as they can become very onerous especially if they become more expensive than open market (spot market) prices. This is especially possible in a market undergoing liberalisation and in which competition is being introduced. If take-or-pay provisions are inevitable, then price re-evaluation clauses should be included on a reasonable basis. The force majeure should be drafted in a way that the supplier is not easily justified to interrupt contracted obligations. On the other hand, it must be drafted in a way that incorporates elements of other project contracts. In other words, the force majeure clause should include such things as a terminated concession rights, delays in construction, etc. 51 G., Vinter, supra note 5, p. 63. 52 Ibid., p. 65 53 Baker & McKenzie, supra note 13, p. 65. 54 Ibid., pp. 60-61.
  • 17. Matriculation Number 00 99 43 036 16 Ideally, the supplier should take full responsibility for compensating the project company for revenues lost or liabilities incurred due to supply failure. In practice, however, suppliers will only accept responsibility for the additional cost of replacement fuel.55 4.3 Output Agreements The output agreement, or the offtake agreement is key to the success of any BOT project. Every BOT project has a good or service produced that needs to be sold. The negotiated price must be enough to pay for the entire project. It must also give the adequate rate of return sought. As the Electronic Construction Law Journal (ECLJ) notes: “The viability of the project and in particular its bankability will depend upon the reliability of the cashflow under the offtake agreement, and the government agency and sponsor performing their respective obligations.”56 It must be reminded that the product or service can be either sold on a spot basis or can be sold to an individual offtaker. If it is sold in a spot market, then the contract will be dependent on the rules of the spot market in question and might vary on a case-by-case basis. This paper will rather analyse the long-term offtake agreement, which usually is negotiated with a government agency. Certainly, the offtaker must be creditworthy and must have the capacity to pay. The aim of the sponsors and of the banks is to minimise market risks in order to guarantee the profitability of the project. The practice has shown that for this purpose the cashflow must be structured in two parts, an availability fee and a usage fee.57 The availability fee must cover all or a substantial part of the fixed costs. On the other hand, the usage fee will be mainly composed of variable costs.58 55 Ibid., p. 63. 56 Electronic Construction Law Journal (ECLJ), supra note 32. 57 Ibid. 58 Ibid.
  • 18. Matriculation Number 00 99 43 036 17 The higher the negotiated availability fee, the lower the market risks. The fixed costs in the calculation of availability are re-estimated every year. These are, as a general rule, composed of such thing as:59 - the amount of the banks’ loan due to be repaid in that year including the interests; - the non-variable operating costs for that year; - taxes payable by the project company for that year; - insurance premiums payable in that year; - the project company’s overheads for that year; - the equity return for that year. On the other hand, variable costs are mainly composed of such things as the cost of fuel and other input elements. It must be stressed that all costs, fixed and variable must be passed through to the offtaker. Moreover, take-or-pay provisions should definitely be included.60 The tariff charged to the final offtaker must be adjusted in the case of unforeseen circumstances. If, for example, a new environmental legislation imposes higher costs then, these must be passed through to the offtaker. It is not the occurrence of any event that justifies an adjustment. Obviously, this is left to negotiation of course. However, such things as tax changes are not usually included in the list of events.61 As for the force majeure clause, it must be negotiated in a way that the offtaker carries as much of the risk as possible. Basically, the sponsors’ negotiation plan must be aimed at the payment of tariffs whether or not the project is producing. 5. Conclusion As Philip Wood remarks, 59 G., Vinter, supra note 5, p. 73. 60 Electronic Construction Law Journal (ECLJ), supra note 32. 61 Ibid.
  • 19. Matriculation Number 00 99 43 036 18 “Banks lending to a BOT project will ensure that both the performance and financial obligations of the project company to the grantor are matched by corresponding obligations on the part of the sub-contractors owed to the project company and that the relevant sub-contracts impose no greater liability on the project company to the sub- contractor than that owed by the grantor to the project company under the concession agreement.”62 The project company should not be over-burdened with obligations and should not carry an unreasonable amount of risks. If this is the case, the banks’ security on the project company is likely to be reduced. It must be reminded that BOT arrangements are a form of project finance. Banks want to make sure that the cashflow is adequate for the reimbursement of the loan along with the interests. The sponsors must negotiate BOT arrangements in accordance with the terms of the banks. Otherwise, these will just find the whole deal unattractive. 62 P. R., Wood, supra note 17, pp. 11-12.
  • 20. Matriculation Number 00 99 43 036 19 Annex A The Typical Structure of a BOT Project (Reproduced from C., Walker, and A. J., Smith, eds., Privatized Infrastructure: the BOT Approach, p. 5)
  • 21. Matriculation Number 00 99 43 036 20 Bibliography 1. Secondary Sources 1.1 Books Baker & McKenzie, Project Finance: The Guide to Financing Power Projects, (England: Euromoney Publications, 1996). Bodie, Z., and, Merton, R. C., Finance, Preliminary Edition, (Upper Saddle River, New Jersey: Prentice-Hall Inc., 1998). Brealey, R. A., and Myers, S., C., Principles of Corporate Finance, Sixth Edition, (London, England: McGraw-Hill Companies, 2000). Milbank, Twees, Hadley & McCloy, Project Finance:The Guide to Financing International Oil and Gas Projects, (England: Euromoney Publications, 1996). Vinter, G., Project Finance: A Legal Guide, Second Edition, (London, England: Sweet & Maxwell, 1998). Walker, C., and Smith, A. J., eds., Privatized Infrastructure: the BOT Approach, (London, England: Thomas Telford Publications, 1995). Wood, P. R., Project Finance, Subordinated Debt and State Loans, (London, England: Sweet & Maxwell, 1995). 1.2 Articles Beardsworth, J. Jr., Negotiating Power Purchase Agreements: Fundamentals for Risk Allocation and Dispute Resolution, [1995] 707 PLI/Comm 27. Berry, C., Criteria for Successful Project Financing, 1991/1992 PFY 15. Brown, T., et al., The Shandong PRC Milestonem [1999] 165 PFI 52. Davidson, P., Political Risk Insurance – Commercial, 1991/1992 PFY 43. Dow, S., and Andrews-Speed, P., Considerations for Foreign Investors in China’s Electricity Sector, [1998] OGLTR Ingham, R., Risk Management, 1991/1992 PFY 35. Issen, R., et al., Malaysia’s Johor Water Privatisation Project: A BOT Success Story, 1991/1992 PFY 23
  • 22. Matriculation Number 00 99 43 036 21 Keeley, P., J., Project Financing for International Independent Power Facilities: Management of Risks, [1996] 14:4 JENRL 445. Mauel, J. G., Common Contractual Risk Allocations in International Power Projects, [1996] 1996 CLMBLR 37. McCormick, R. S., Legal Issues in Project Finance, Moroney, G., J., Project Financing in Emerging Markets: Success Factors in Volatile Markets, IOGFR 29. Peppiatt, S., Introduction to Power Station Project Financing, [1995] 13 INTXBL 46. Pritchard, R., Downstream Energy Financing and the Limitations of BOT Projects, [1997] 5 OGLTR 149. Prowse, N., and Rowson, M., Project Finance in Turkey: The BOT Model, [1999] 1 OGLTR 29. Roberts, P., Bankable Gas Sales Agreements in the Project Financing of Offshore Gas Production Projects, [1998] 16:2 JENRL 200. Siegl, C. F. J., How to Get the Best Out of Your Bank, 1991/1992 PFY 75. Syrett, S., The Future of Project Finance, 1991/1992 PFY 11. Townsend, D., Powering Ahead, April 2000 PE 14. Vinoski & Associates, Revenue Collection Experiences and Insight, [1999] 165 PFI 82. Wallin, S., and, Fairfull, H., Financing Power Generation Projects in Central and Eastern Europe, 1991/1992 PFY 46. 1.3 Internet Sources Adefulu, A., Downstream Energy Financing in Developing Countries: Are BOTs the Answer?, [1999] 3 CAR, http://www.dundee.ac.uk/cepmlp/main/html/car_article1.html Electronic Construction Law Journal (ECLJ), Build Own Operate Transfer (BOOT) Projects, http://www.mcmullan.net/eclj/BOT.html UNCITRAL, Possible Future Work: Build-Operate-Transfer Projects, Twenty-Ninth Session, A/CN.9/424, April 19, 1996, http://www.uncitral.org/english/sessions/unc/unc- 29/acn9-424.htm
  • 23. Matriculation Number 00 99 43 036 22 Watanabe, H., On the Road to Independent Power Producer (IPP), http://www.cosapi.com.pe/instituciones/cepeja/cepeja4/watanabe.html