Project Alpha
Process Improvement Plan – January,2016 Página 1
Process Improvement Plan
- Call Center Script –
Submitted by:
Agatha Maia Duarte de Assis, in
January, 29th, 2016.
Documents Attached:
1. Appendix I – Summary of Quality Management Plan
Project: Alpha
Prepared by: Agatha Assis
Approved by: Bob Smith
Document Version: V 1.2
Date prepared: 2016/01/29
Reference: January/2016
Project Alpha
Process Improvement Plan – January,2016 Página 2
1. Introduction
The Call Center Script is a guide that determines how each call must be treated in order to remedy all the questions asked. It
says step by step to answer the call efficiently and effectively. When our team has the proper training to end each call faster they
are able to answer a bigger number of calls during each shift. Our company has an understanding that the high efficiency of our call
center reflects to the popularity of our product.
The result of the tests showed that the current Process is taking 2 minutes more than the expected by the parameters detailed in
the Quality Assurance documents. Such parameters have as objective to ensure that our company complies with the Personal
Information Protection and Electronic Documents Acts – PIPEDA (Federal Legislation). The over time is due to conflicts between
existent accounts and the new product.
The results also showed that the questions asked by the call center to the customers in the beginning of the call don’t allow them
to reach their account within the expected time.
The Process Improvement Plan points the improvements that must be fit within the process configuration in order to reach those
parameters. According to the results the goal of this Plan is to reduce the Call in 2 minutes.
This document was developed by the Quality Team and Call Center Team. We believe that the improvement showed is going to
be enough to reach the goal of the process. However new tests must be accomplished in order to check the efficiency of the
process.
This process also implies in a change to previous documents, such as – Scope, Project Schedule and Project Budget. The
milestone content in this document must be follow effectively in order to align the changes in the project.
Project Alpha
Process Improvement Plan – January,2016 Página 3
2. Call Center Script Process Boundaries
The table below shows the purpose of each step within the Call Center Script Process:
Process Start End Inputs Outputs Improvement
Greeting
Process starts as
the call starts.
Process is
complete once the
standard greeting
is announced.
Call Center
Manual, OPA’s and
training.
The customer is
hosted and aware.
According to tests this step showed
efficiency and reached the objective.
Gathering
Data
Process starts
after listening to
the request by the
customer.
It is completed after
asking the account
information.
Computer System
data, data from the
customer and
knowledge about
the system.
Information about
the customer
account.
According to tests this step showed
inefficiency. The data introduced to the
System doesn’t show the information
necessary to answer the call.
Checking
Status
Starts after the
download of the
system.
Ends once all the
information are
showed on the
screen.
Computer System
data and
knowledge about
the product.
Information about
the customer
account.
According to tests this step showed
inefficiency. The information showed
converges to different accounts.
Answering
Request
Starts after
having the all the
account
information.
Process is
complete once the
question and
request are
answered.
Call Center
Manual, OPA’s,
knowledge about
the product and
training.
Customer
satisfaction.
According to tests this step showed
efficiency and reached the objective.
Closure of
Call
Process starts
after
understanding
that the customer
remedied his
request.
It is completed after
saying good bye.
Call Center
Manual, OPA’s and
training.
Customer
satisfaction and
product and brand
popularity.
According to tests this step showed
efficiency and reached the objective.
Project Alpha
Process Improvement Plan – January,2016 Página 4
3. Process Configuration
The graphic below describes the process and highlight the improvements to be done in each step of the process. It also shows
the interfaces to the Computer System (TI);
Greet the
customer: warn
them the call is being
recorded AND ask
them to carry the
Crredit Card, say the
name of the brand
and the product, ask
how he can be
helped.
Gather Data: listen
to the request, Ask
for the number of the
card, enter the data
into the System and
download the
account information.
Check Status:
ensure the screen is
showing the right
information –
account and
customer.
Answer Request:
according to the
account status,
answer the question
or do the procedures
to accomplish the
request. Explain to
the customer and
ask if they can be
helped with anything
else.
Close Call: inform
the number of the
call, wish the goods
and say good bye.
Interface to
the Computer
System.
Interface to
the Computer
System.
Request might bring forth a
internal HelpDesk.
Project Alpha
Process Improvement Plan – January,2016 Página 5
4. Targets for Improved Performance
The convergence between existent account and the new product just occurs to existent clients. The problem showed when the
download of the personal account information was gone. Instead of showing the both account, the system only showed the existent
credit card information. And then through this screen ask new question to download the information regarding to the product. To
avoid new questions and go straight to the product information it is necessary to enter into the system with the credit card number.
This way the data downloaded is exactly what is needed in one question. The goal of the improvement is to reduce in 2 minutes the
life cycle of the call.
The table below summarizes the improvement in the process and the goal expected:
Step to be
Improved
Process Detailed Failure Step Behavior to Improve Target
Greeting
The Call Center Analyst must
ensure that the customer is
carrying the Credit Card during
the call.
The customer wasn’t
ready to provide all
the information
needed to download
the right data.
Ask the client to carry
the Credit Card in
question.
To ensure that the information needed to
accomplish the call is in power.
Gathering
Data
The Call Center Analyst must
ask for the number of the card
in question and enter the
number into the System.
Entering the name or
ID bring the oldest
account information.
Enter into the System
with the Credit Card
Number.
To reduce time of download of the account
information and consequently to reduce the
Call in 2 minutes.
Project Alpha
Process Improvement Plan – January,2016 Página 6
5. Milestone
Milestone Responsible Owner Start Date Target Date Status
Plan the Improvement Plan.
Joseph
Underwood
Quality Team
and Call Center
Team
22/01/2016
27/01/2016
Approved and accomplished.
Do the changes according to the
plan.
Joseph
Underwood
Call Center
Team
27/01/2016 29/01/2016 In progress.
Do tests and Check the results.
Joseph
Underwood
Quality Team
and Call Center
Team
29/01/2016 02/02/2016 Scheduled and in progress.
**Upgrade the documents. Agatha Maia
Project
Management
Team.
03/02/2016 08/02/2016 Scheduled and in progress.
** Documents that must be updated include: Scope Baseline, Project Schedule, Training Plan and Process Documentation.
Reference
[1] Case study developed in semester 1 – 2015F.
[2] Quality Management Plan developed in semester 1 – 2015F.
Project Alpha
Process Improvement Plan – January,2016 Página 7
Summary of Quality Management Plan
- Quality Assurances -
Submitted by:
Agatha Maia Duarte de Assis, in
January, 29th, 2016.
Project: Alpha
Prepared by: Agatha Assis
Approved by: Bob Smith
Document Version: V 1.0
Date prepared: 2016/01/29
Reference: January/2016
Project Alpha
Process Improvement Plan – January,2016 Página 8
Roles and Resposibility:
Activity Responsible Notes and Tools
Quality Policy Project manager and Quality
Manager
Based on OPAs, portfolios and legislation.
Quality Assurance Project manager and Quality
Manager
Expert judgement, stakeholders expectations and specified parameters.
Quality Checklist Project Team and Quality Team The Team work has to fill the check list due each task accomplished.
Quality Control
Measurements
Project Team and Quality Team Expert judgement to analyse the data and report the results.
Control/Change Quality Project manager and Quality
Manager
Use Group Decision-Making to develop the Changing Plan and validate it.
Approve Quality Plan Sponsor Verify and validate the performance of the Quality Plan with the functional
manager.
Quality Policy and Quality Assurance:
Activity Deliverable Relationship Assurance Parameter Owner
Quality Product Credit Card External **ISO/IEC(International Electro-technical
Commission) 7810
VP Marketing – Sam Snead
Quality Process Credit Card External Code of Conduct for the Credit Card Industry of
Canada, according to financial Consumer
Agency of Canada.
VP Marketing – Sam Snead
Quality Process Call Center External Personal Information Protection and Electronic
Documents Acts – PIPEDA (Federal
Legislation)
VP Call Center – Joseph
Underwood
Quality Process Help Desk Internal OPA 1234 – Help Desk Answer VP IT – Mary Jones
Quality Process Back Office
Paper Work
Internal ISO(International Organisation for
Standardization) 9000
VP Call Center – Joseph
Underwood
Project Alpha
Process Improvement Plan – January,2016 Página 9
**The characteristics specified included in ISO/IEC 7810 are
• Physical dimensions.
• Resistance to bending, flame, chemicals, temperature and humidity.
• Toxicity.
• All bank cards should have thickness of 0.76mm.
85.60mm(or)3.370in
5 53.98mm
(or)
2.215in

More Related Content

What's hot

Tracking Single-Use & Scale-Up Best Practices
Tracking Single-Use & Scale-Up Best PracticesTracking Single-Use & Scale-Up Best Practices
Tracking Single-Use & Scale-Up Best PracticesWPICPE
 
APMP Foundation: Managing Time, Cost and Quality
APMP Foundation: Managing Time, Cost and QualityAPMP Foundation: Managing Time, Cost and Quality
APMP Foundation: Managing Time, Cost and QualityBid to Win Ltd
 
Project Status Report With Highlights And Key Takeaways Printable Presentatio...
Project Status Report With Highlights And Key Takeaways Printable Presentatio...Project Status Report With Highlights And Key Takeaways Printable Presentatio...
Project Status Report With Highlights And Key Takeaways Printable Presentatio...SlideTeam
 
Demystifying the APMP Foundation Certification
Demystifying the APMP  Foundation Certification Demystifying the APMP  Foundation Certification
Demystifying the APMP Foundation Certification Abhijit Majumdar CP.APMP
 
Reckitt Benckiser Case Study | Campus winners
Reckitt Benckiser Case Study | Campus winnersReckitt Benckiser Case Study | Campus winners
Reckitt Benckiser Case Study | Campus winnersTarun Gupta
 
AP Automation for EBS or PeopleSoft with Oracle WebCenter
AP Automation for EBS or PeopleSoft with Oracle WebCenterAP Automation for EBS or PeopleSoft with Oracle WebCenter
AP Automation for EBS or PeopleSoft with Oracle WebCenterBrian Huff
 
Kickoff Meeting PowerPoint Presentation Slides
Kickoff Meeting PowerPoint Presentation SlidesKickoff Meeting PowerPoint Presentation Slides
Kickoff Meeting PowerPoint Presentation SlidesSlideTeam
 
Computer System Validation - The Validation Master Plan
Computer System Validation - The Validation Master PlanComputer System Validation - The Validation Master Plan
Computer System Validation - The Validation Master PlanWolfgang Kuchinke
 
The bose corporation: JIT II case solution
The bose corporation: JIT II case solutionThe bose corporation: JIT II case solution
The bose corporation: JIT II case solutionShubham Gupta
 
Agile Testing – embedding testing into agile software development lifecycle
Agile Testing – embedding testing into agile software development lifecycle Agile Testing – embedding testing into agile software development lifecycle
Agile Testing – embedding testing into agile software development lifecycle Kari Kakkonen
 
Gamp Riskbased Approch To Validation
Gamp Riskbased Approch To ValidationGamp Riskbased Approch To Validation
Gamp Riskbased Approch To ValidationRajendra Sadare
 
SOP for printing production
SOP for printing productionSOP for printing production
SOP for printing productionStewart Ngan
 

What's hot (20)

Skan ebeam System - Handout
Skan ebeam System - HandoutSkan ebeam System - Handout
Skan ebeam System - Handout
 
Ispe sf ch_gamp
Ispe sf ch_gampIspe sf ch_gamp
Ispe sf ch_gamp
 
Tracking Single-Use & Scale-Up Best Practices
Tracking Single-Use & Scale-Up Best PracticesTracking Single-Use & Scale-Up Best Practices
Tracking Single-Use & Scale-Up Best Practices
 
Caterpilar
CaterpilarCaterpilar
Caterpilar
 
APMP Foundation: Managing Time, Cost and Quality
APMP Foundation: Managing Time, Cost and QualityAPMP Foundation: Managing Time, Cost and Quality
APMP Foundation: Managing Time, Cost and Quality
 
Correlation of FDA-EU-PICS-WHO Requirement for Computer System Validation
Correlation  of  FDA-EU-PICS-WHO Requirement for Computer System Validation Correlation  of  FDA-EU-PICS-WHO Requirement for Computer System Validation
Correlation of FDA-EU-PICS-WHO Requirement for Computer System Validation
 
Project Status Report With Highlights And Key Takeaways Printable Presentatio...
Project Status Report With Highlights And Key Takeaways Printable Presentatio...Project Status Report With Highlights And Key Takeaways Printable Presentatio...
Project Status Report With Highlights And Key Takeaways Printable Presentatio...
 
PMP certification
PMP certificationPMP certification
PMP certification
 
Demystifying the APMP Foundation Certification
Demystifying the APMP  Foundation Certification Demystifying the APMP  Foundation Certification
Demystifying the APMP Foundation Certification
 
Reckitt Benckiser Case Study | Campus winners
Reckitt Benckiser Case Study | Campus winnersReckitt Benckiser Case Study | Campus winners
Reckitt Benckiser Case Study | Campus winners
 
Spend & Contract Management
Spend & Contract ManagementSpend & Contract Management
Spend & Contract Management
 
AP Automation for EBS or PeopleSoft with Oracle WebCenter
AP Automation for EBS or PeopleSoft with Oracle WebCenterAP Automation for EBS or PeopleSoft with Oracle WebCenter
AP Automation for EBS or PeopleSoft with Oracle WebCenter
 
Case study Boots
Case study BootsCase study Boots
Case study Boots
 
Kickoff Meeting PowerPoint Presentation Slides
Kickoff Meeting PowerPoint Presentation SlidesKickoff Meeting PowerPoint Presentation Slides
Kickoff Meeting PowerPoint Presentation Slides
 
Computer System Validation - The Validation Master Plan
Computer System Validation - The Validation Master PlanComputer System Validation - The Validation Master Plan
Computer System Validation - The Validation Master Plan
 
The bose corporation: JIT II case solution
The bose corporation: JIT II case solutionThe bose corporation: JIT II case solution
The bose corporation: JIT II case solution
 
Agile Testing – embedding testing into agile software development lifecycle
Agile Testing – embedding testing into agile software development lifecycle Agile Testing – embedding testing into agile software development lifecycle
Agile Testing – embedding testing into agile software development lifecycle
 
Gamp Riskbased Approch To Validation
Gamp Riskbased Approch To ValidationGamp Riskbased Approch To Validation
Gamp Riskbased Approch To Validation
 
Training for quality
Training for qualityTraining for quality
Training for quality
 
SOP for printing production
SOP for printing productionSOP for printing production
SOP for printing production
 

Viewers also liked

Process Improvement Plan by Barry Botha
Process Improvement Plan by Barry BothaProcess Improvement Plan by Barry Botha
Process Improvement Plan by Barry BothaBarry Botha, CSM
 
Senior Capstone Presentation: Process Improvement Plan
Senior Capstone Presentation: Process Improvement PlanSenior Capstone Presentation: Process Improvement Plan
Senior Capstone Presentation: Process Improvement Planaldenknibbs
 
Process improvement proposal for site plan and appearance 9.5.12
Process improvement proposal for site plan and appearance 9.5.12Process improvement proposal for site plan and appearance 9.5.12
Process improvement proposal for site plan and appearance 9.5.12cityofevanston
 
Project on Productivity Improvement.
Project on Productivity Improvement.Project on Productivity Improvement.
Project on Productivity Improvement.Ankit Kumar
 
Business Process Improvement plan - SQL
Business Process Improvement plan - SQLBusiness Process Improvement plan - SQL
Business Process Improvement plan - SQLrubylu818
 
Mortgage Bank Business Process Improvement Case Study
Mortgage Bank Business Process Improvement Case StudyMortgage Bank Business Process Improvement Case Study
Mortgage Bank Business Process Improvement Case StudyDATAMARK
 
Diane Turton Realtors Agent Recruiting Drip Email Campaign
Diane Turton Realtors Agent Recruiting Drip Email CampaignDiane Turton Realtors Agent Recruiting Drip Email Campaign
Diane Turton Realtors Agent Recruiting Drip Email CampaignJennifer Pricci
 
Call Center Operation
Call Center OperationCall Center Operation
Call Center OperationTaaham
 
Increasing Call Center Effectiveness with First Call Resolution
Increasing Call Center Effectiveness with First Call ResolutionIncreasing Call Center Effectiveness with First Call Resolution
Increasing Call Center Effectiveness with First Call ResolutionUpstream Works
 
Software Process Improvement
Software Process ImprovementSoftware Process Improvement
Software Process ImprovementBilal Shah
 
Lean Transformation ~ A Journey
Lean Transformation ~ A JourneyLean Transformation ~ A Journey
Lean Transformation ~ A JourneyAnand Subramaniam
 
Supply Chain Process Improvement Methodology V1
Supply Chain Process Improvement Methodology V1Supply Chain Process Improvement Methodology V1
Supply Chain Process Improvement Methodology V1John Paulson
 
Continuous process improvement
Continuous process improvementContinuous process improvement
Continuous process improvementNaeem Hassan
 
Merchandising process in the apparel industry
Merchandising process in the apparel industryMerchandising process in the apparel industry
Merchandising process in the apparel industryMuhundhan Muhu
 
Free Call Center Training | Call Center Best Practices
Free Call Center Training | Call Center Best PracticesFree Call Center Training | Call Center Best Practices
Free Call Center Training | Call Center Best PracticesMetricNet
 

Viewers also liked (20)

Process Improvement Plan by Barry Botha
Process Improvement Plan by Barry BothaProcess Improvement Plan by Barry Botha
Process Improvement Plan by Barry Botha
 
Senior Capstone Presentation: Process Improvement Plan
Senior Capstone Presentation: Process Improvement PlanSenior Capstone Presentation: Process Improvement Plan
Senior Capstone Presentation: Process Improvement Plan
 
Process improvement proposal for site plan and appearance 9.5.12
Process improvement proposal for site plan and appearance 9.5.12Process improvement proposal for site plan and appearance 9.5.12
Process improvement proposal for site plan and appearance 9.5.12
 
Project on Productivity Improvement.
Project on Productivity Improvement.Project on Productivity Improvement.
Project on Productivity Improvement.
 
Mohamed_Nabil_CV1 (1)
Mohamed_Nabil_CV1 (1)Mohamed_Nabil_CV1 (1)
Mohamed_Nabil_CV1 (1)
 
Adding virtual agent & live chat to help desk and service desk 1.5
Adding virtual agent & live chat to help desk and service desk 1.5Adding virtual agent & live chat to help desk and service desk 1.5
Adding virtual agent & live chat to help desk and service desk 1.5
 
Business Process Improvement plan - SQL
Business Process Improvement plan - SQLBusiness Process Improvement plan - SQL
Business Process Improvement plan - SQL
 
Alpha Case Study - Work Authorization - Sample
Alpha Case Study - Work Authorization - SampleAlpha Case Study - Work Authorization - Sample
Alpha Case Study - Work Authorization - Sample
 
Mortgage Bank Business Process Improvement Case Study
Mortgage Bank Business Process Improvement Case StudyMortgage Bank Business Process Improvement Case Study
Mortgage Bank Business Process Improvement Case Study
 
Diane Turton Realtors Agent Recruiting Drip Email Campaign
Diane Turton Realtors Agent Recruiting Drip Email CampaignDiane Turton Realtors Agent Recruiting Drip Email Campaign
Diane Turton Realtors Agent Recruiting Drip Email Campaign
 
Call Center Operation
Call Center OperationCall Center Operation
Call Center Operation
 
Increasing Call Center Effectiveness with First Call Resolution
Increasing Call Center Effectiveness with First Call ResolutionIncreasing Call Center Effectiveness with First Call Resolution
Increasing Call Center Effectiveness with First Call Resolution
 
Call center Management
Call center ManagementCall center Management
Call center Management
 
Software Process Improvement
Software Process ImprovementSoftware Process Improvement
Software Process Improvement
 
Lean Transformation ~ A Journey
Lean Transformation ~ A JourneyLean Transformation ~ A Journey
Lean Transformation ~ A Journey
 
Supply Chain Process Improvement Methodology V1
Supply Chain Process Improvement Methodology V1Supply Chain Process Improvement Methodology V1
Supply Chain Process Improvement Methodology V1
 
Continuous process improvement
Continuous process improvementContinuous process improvement
Continuous process improvement
 
Merchandising process in the apparel industry
Merchandising process in the apparel industryMerchandising process in the apparel industry
Merchandising process in the apparel industry
 
Lean Manufacturing
Lean ManufacturingLean Manufacturing
Lean Manufacturing
 
Free Call Center Training | Call Center Best Practices
Free Call Center Training | Call Center Best PracticesFree Call Center Training | Call Center Best Practices
Free Call Center Training | Call Center Best Practices
 

Similar to Alpha Case Study - Process Improvement Plan_Sample

Puneet Green Belt(13th feb).pptx
Puneet Green Belt(13th feb).pptxPuneet Green Belt(13th feb).pptx
Puneet Green Belt(13th feb).pptxPuneet Gupta
 
Advanced process analysis project report
Advanced process analysis project reportAdvanced process analysis project report
Advanced process analysis project reportShruti Anil Narkhede
 
Feature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMFeature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMProduct School
 
4 Steps to Drive Process Innovation
4 Steps to Drive Process Innovation4 Steps to Drive Process Innovation
4 Steps to Drive Process InnovationJuran Global
 
D team weekly powerpoint presentation spqm
D team weekly powerpoint presentation spqmD team weekly powerpoint presentation spqm
D team weekly powerpoint presentation spqmMiraj Mhaisuria
 
Moving Health Insurance into the Digital World
Moving Health Insurance into the Digital WorldMoving Health Insurance into the Digital World
Moving Health Insurance into the Digital WorldIIBA UK Chapter
 
Resume -pd 241020106 (2)
Resume -pd 241020106 (2)Resume -pd 241020106 (2)
Resume -pd 241020106 (2)Pankaj Dass
 
Legrand crm diagnostics readout v25
Legrand crm diagnostics readout  v25Legrand crm diagnostics readout  v25
Legrand crm diagnostics readout v25Ankit Mune
 
Legrand CRM diagnostics_Readout_ v25.pptx
Legrand CRM diagnostics_Readout_ v25.pptxLegrand CRM diagnostics_Readout_ v25.pptx
Legrand CRM diagnostics_Readout_ v25.pptxMonzerrathRoque
 
Aces 405 - Team that actually saved the most money..!!
Aces 405 - Team that actually saved the most money..!!Aces 405 - Team that actually saved the most money..!!
Aces 405 - Team that actually saved the most money..!!Satwinder Singh
 
aces405upload-091211003244-phpapp01 (1)
aces405upload-091211003244-phpapp01 (1)aces405upload-091211003244-phpapp01 (1)
aces405upload-091211003244-phpapp01 (1)Satwinder Singh
 
Chapter 10 Tools and Techniques for Quality Management.ppt
Chapter 10 Tools and Techniques for Quality Management.pptChapter 10 Tools and Techniques for Quality Management.ppt
Chapter 10 Tools and Techniques for Quality Management.pptDr. Nazrul Islam
 

Similar to Alpha Case Study - Process Improvement Plan_Sample (20)

Puneet Green Belt(13th feb).pptx
Puneet Green Belt(13th feb).pptxPuneet Green Belt(13th feb).pptx
Puneet Green Belt(13th feb).pptx
 
Project Alpha - Summary of the Project
Project Alpha - Summary of the ProjectProject Alpha - Summary of the Project
Project Alpha - Summary of the Project
 
Advanced process analysis project report
Advanced process analysis project reportAdvanced process analysis project report
Advanced process analysis project report
 
Company project kick off
Company project kick off Company project kick off
Company project kick off
 
6 Sigma
6 Sigma6 Sigma
6 Sigma
 
Six Sigma DMAIC Case Study
Six Sigma DMAIC Case StudySix Sigma DMAIC Case Study
Six Sigma DMAIC Case Study
 
Six sigma define - v1.0
Six sigma   define - v1.0Six sigma   define - v1.0
Six sigma define - v1.0
 
Feature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMFeature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PM
 
4 Steps to Drive Process Innovation
4 Steps to Drive Process Innovation4 Steps to Drive Process Innovation
4 Steps to Drive Process Innovation
 
D team weekly powerpoint presentation spqm
D team weekly powerpoint presentation spqmD team weekly powerpoint presentation spqm
D team weekly powerpoint presentation spqm
 
Moving Health Insurance into the Digital World
Moving Health Insurance into the Digital WorldMoving Health Insurance into the Digital World
Moving Health Insurance into the Digital World
 
Resume -pd 241020106 (2)
Resume -pd 241020106 (2)Resume -pd 241020106 (2)
Resume -pd 241020106 (2)
 
Salesforce PPT.pptx
Salesforce PPT.pptxSalesforce PPT.pptx
Salesforce PPT.pptx
 
Legrand crm diagnostics readout v25
Legrand crm diagnostics readout  v25Legrand crm diagnostics readout  v25
Legrand crm diagnostics readout v25
 
Legrand CRM diagnostics_Readout_ v25.pptx
Legrand CRM diagnostics_Readout_ v25.pptxLegrand CRM diagnostics_Readout_ v25.pptx
Legrand CRM diagnostics_Readout_ v25.pptx
 
Aces 405 - Team that actually saved the most money..!!
Aces 405 - Team that actually saved the most money..!!Aces 405 - Team that actually saved the most money..!!
Aces 405 - Team that actually saved the most money..!!
 
aces405upload-091211003244-phpapp01 (1)
aces405upload-091211003244-phpapp01 (1)aces405upload-091211003244-phpapp01 (1)
aces405upload-091211003244-phpapp01 (1)
 
Queenie Barrettoo
Queenie Barrettoo Queenie Barrettoo
Queenie Barrettoo
 
CV_BIJU.A
CV_BIJU.ACV_BIJU.A
CV_BIJU.A
 
Chapter 10 Tools and Techniques for Quality Management.ppt
Chapter 10 Tools and Techniques for Quality Management.pptChapter 10 Tools and Techniques for Quality Management.ppt
Chapter 10 Tools and Techniques for Quality Management.ppt
 

More from Agatha Maia Duarte de Assis

More from Agatha Maia Duarte de Assis (8)

VILA DA ALEGRIA_TCC
VILA DA ALEGRIA_TCCVILA DA ALEGRIA_TCC
VILA DA ALEGRIA_TCC
 
BC_Three-StoreyHouse
BC_Three-StoreyHouseBC_Three-StoreyHouse
BC_Three-StoreyHouse
 
RC_Three-StoreyHouse
RC_Three-StoreyHouseRC_Three-StoreyHouse
RC_Three-StoreyHouse
 
Study_Three-StoreyHouse
Study_Three-StoreyHouseStudy_Three-StoreyHouse
Study_Three-StoreyHouse
 
Alpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan SampleAlpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan Sample
 
Project Management Plan - Group Presentation
Project Management Plan - Group PresentationProject Management Plan - Group Presentation
Project Management Plan - Group Presentation
 
Alpha Case Study - Lessons Learned Assigment Sample
Alpha Case Study - Lessons Learned Assigment SampleAlpha Case Study - Lessons Learned Assigment Sample
Alpha Case Study - Lessons Learned Assigment Sample
 
Alpha Case Study - Contract Administration Sample
Alpha Case Study - Contract Administration SampleAlpha Case Study - Contract Administration Sample
Alpha Case Study - Contract Administration Sample
 

Alpha Case Study - Process Improvement Plan_Sample

  • 1. Project Alpha Process Improvement Plan – January,2016 Página 1 Process Improvement Plan - Call Center Script – Submitted by: Agatha Maia Duarte de Assis, in January, 29th, 2016. Documents Attached: 1. Appendix I – Summary of Quality Management Plan Project: Alpha Prepared by: Agatha Assis Approved by: Bob Smith Document Version: V 1.2 Date prepared: 2016/01/29 Reference: January/2016
  • 2. Project Alpha Process Improvement Plan – January,2016 Página 2 1. Introduction The Call Center Script is a guide that determines how each call must be treated in order to remedy all the questions asked. It says step by step to answer the call efficiently and effectively. When our team has the proper training to end each call faster they are able to answer a bigger number of calls during each shift. Our company has an understanding that the high efficiency of our call center reflects to the popularity of our product. The result of the tests showed that the current Process is taking 2 minutes more than the expected by the parameters detailed in the Quality Assurance documents. Such parameters have as objective to ensure that our company complies with the Personal Information Protection and Electronic Documents Acts – PIPEDA (Federal Legislation). The over time is due to conflicts between existent accounts and the new product. The results also showed that the questions asked by the call center to the customers in the beginning of the call don’t allow them to reach their account within the expected time. The Process Improvement Plan points the improvements that must be fit within the process configuration in order to reach those parameters. According to the results the goal of this Plan is to reduce the Call in 2 minutes. This document was developed by the Quality Team and Call Center Team. We believe that the improvement showed is going to be enough to reach the goal of the process. However new tests must be accomplished in order to check the efficiency of the process. This process also implies in a change to previous documents, such as – Scope, Project Schedule and Project Budget. The milestone content in this document must be follow effectively in order to align the changes in the project.
  • 3. Project Alpha Process Improvement Plan – January,2016 Página 3 2. Call Center Script Process Boundaries The table below shows the purpose of each step within the Call Center Script Process: Process Start End Inputs Outputs Improvement Greeting Process starts as the call starts. Process is complete once the standard greeting is announced. Call Center Manual, OPA’s and training. The customer is hosted and aware. According to tests this step showed efficiency and reached the objective. Gathering Data Process starts after listening to the request by the customer. It is completed after asking the account information. Computer System data, data from the customer and knowledge about the system. Information about the customer account. According to tests this step showed inefficiency. The data introduced to the System doesn’t show the information necessary to answer the call. Checking Status Starts after the download of the system. Ends once all the information are showed on the screen. Computer System data and knowledge about the product. Information about the customer account. According to tests this step showed inefficiency. The information showed converges to different accounts. Answering Request Starts after having the all the account information. Process is complete once the question and request are answered. Call Center Manual, OPA’s, knowledge about the product and training. Customer satisfaction. According to tests this step showed efficiency and reached the objective. Closure of Call Process starts after understanding that the customer remedied his request. It is completed after saying good bye. Call Center Manual, OPA’s and training. Customer satisfaction and product and brand popularity. According to tests this step showed efficiency and reached the objective.
  • 4. Project Alpha Process Improvement Plan – January,2016 Página 4 3. Process Configuration The graphic below describes the process and highlight the improvements to be done in each step of the process. It also shows the interfaces to the Computer System (TI); Greet the customer: warn them the call is being recorded AND ask them to carry the Crredit Card, say the name of the brand and the product, ask how he can be helped. Gather Data: listen to the request, Ask for the number of the card, enter the data into the System and download the account information. Check Status: ensure the screen is showing the right information – account and customer. Answer Request: according to the account status, answer the question or do the procedures to accomplish the request. Explain to the customer and ask if they can be helped with anything else. Close Call: inform the number of the call, wish the goods and say good bye. Interface to the Computer System. Interface to the Computer System. Request might bring forth a internal HelpDesk.
  • 5. Project Alpha Process Improvement Plan – January,2016 Página 5 4. Targets for Improved Performance The convergence between existent account and the new product just occurs to existent clients. The problem showed when the download of the personal account information was gone. Instead of showing the both account, the system only showed the existent credit card information. And then through this screen ask new question to download the information regarding to the product. To avoid new questions and go straight to the product information it is necessary to enter into the system with the credit card number. This way the data downloaded is exactly what is needed in one question. The goal of the improvement is to reduce in 2 minutes the life cycle of the call. The table below summarizes the improvement in the process and the goal expected: Step to be Improved Process Detailed Failure Step Behavior to Improve Target Greeting The Call Center Analyst must ensure that the customer is carrying the Credit Card during the call. The customer wasn’t ready to provide all the information needed to download the right data. Ask the client to carry the Credit Card in question. To ensure that the information needed to accomplish the call is in power. Gathering Data The Call Center Analyst must ask for the number of the card in question and enter the number into the System. Entering the name or ID bring the oldest account information. Enter into the System with the Credit Card Number. To reduce time of download of the account information and consequently to reduce the Call in 2 minutes.
  • 6. Project Alpha Process Improvement Plan – January,2016 Página 6 5. Milestone Milestone Responsible Owner Start Date Target Date Status Plan the Improvement Plan. Joseph Underwood Quality Team and Call Center Team 22/01/2016 27/01/2016 Approved and accomplished. Do the changes according to the plan. Joseph Underwood Call Center Team 27/01/2016 29/01/2016 In progress. Do tests and Check the results. Joseph Underwood Quality Team and Call Center Team 29/01/2016 02/02/2016 Scheduled and in progress. **Upgrade the documents. Agatha Maia Project Management Team. 03/02/2016 08/02/2016 Scheduled and in progress. ** Documents that must be updated include: Scope Baseline, Project Schedule, Training Plan and Process Documentation. Reference [1] Case study developed in semester 1 – 2015F. [2] Quality Management Plan developed in semester 1 – 2015F.
  • 7. Project Alpha Process Improvement Plan – January,2016 Página 7 Summary of Quality Management Plan - Quality Assurances - Submitted by: Agatha Maia Duarte de Assis, in January, 29th, 2016. Project: Alpha Prepared by: Agatha Assis Approved by: Bob Smith Document Version: V 1.0 Date prepared: 2016/01/29 Reference: January/2016
  • 8. Project Alpha Process Improvement Plan – January,2016 Página 8 Roles and Resposibility: Activity Responsible Notes and Tools Quality Policy Project manager and Quality Manager Based on OPAs, portfolios and legislation. Quality Assurance Project manager and Quality Manager Expert judgement, stakeholders expectations and specified parameters. Quality Checklist Project Team and Quality Team The Team work has to fill the check list due each task accomplished. Quality Control Measurements Project Team and Quality Team Expert judgement to analyse the data and report the results. Control/Change Quality Project manager and Quality Manager Use Group Decision-Making to develop the Changing Plan and validate it. Approve Quality Plan Sponsor Verify and validate the performance of the Quality Plan with the functional manager. Quality Policy and Quality Assurance: Activity Deliverable Relationship Assurance Parameter Owner Quality Product Credit Card External **ISO/IEC(International Electro-technical Commission) 7810 VP Marketing – Sam Snead Quality Process Credit Card External Code of Conduct for the Credit Card Industry of Canada, according to financial Consumer Agency of Canada. VP Marketing – Sam Snead Quality Process Call Center External Personal Information Protection and Electronic Documents Acts – PIPEDA (Federal Legislation) VP Call Center – Joseph Underwood Quality Process Help Desk Internal OPA 1234 – Help Desk Answer VP IT – Mary Jones Quality Process Back Office Paper Work Internal ISO(International Organisation for Standardization) 9000 VP Call Center – Joseph Underwood
  • 9. Project Alpha Process Improvement Plan – January,2016 Página 9 **The characteristics specified included in ISO/IEC 7810 are • Physical dimensions. • Resistance to bending, flame, chemicals, temperature and humidity. • Toxicity. • All bank cards should have thickness of 0.76mm. 85.60mm(or)3.370in 5 53.98mm (or) 2.215in