SlideShare a Scribd company logo
ConstructSim
Solutions
COMMUNICATION
S
BRIDGES BUILDINGS CAMPUSES
CADASTRE AND LAND
DEVELOPMENT
OIL AND GAS
ELECTRIC AND
GAS UTILITIES FACTORIES
METALS AND
MINING
POWER
GENERATION
ROADS
WATER AND
WASTEWATERRAIL AND TRANSIT
Introducing ConstructSim
Materials Management
Engineering Data Project Controls
Field Tracking
Virtual
Construction
Model
ConstructSim
Reporting & Simulation
Solves complex
planning and execution
problems for
For Who?
When?
• Owners
• Construction
Managers
• Direct Hire
• Early Planning
• Field Installation
• Turnover /
Commissioning
Addresses These Main Issues
Visibility into the planned and current project status
Material availability / engineering drawing production
Cost to complete
Information management / Aggregation
Reactive construction management
Productivity of field labor
ConstructSim AVI
Main Functionality
• Virtual Construction Model – dynamic updated daily with data from
engineering and construction
• Auto re-organize engr 3D data for construction tracking
– Spools (SpoolGen / IsoGen); Steel Piecemarks, etc …
• Provide construction views – area & systems (others)
• Work steps that relates to all small pieces (every pipe spool, steel
beam) – automatic
• Video game environment to build work packs (detailed planning
– Click, click, click -> print reports (spool list, field materials, checklist –
aka scorecard – for progressing … i.e. get paid)
• Status visualization …. See progress in 3D
– engineering production / Material availability / installation / testing
• Integration with schedule
– Visually produce schedule early in project
– During project … update schedule weekly with progress (summary
reports % complete per schedule )
–
Agile Construction Methodology
The
Quality
Gate
Develop
Construction Plan
Detailed
Engineering
Procurement
Field Installation
Testing & Inspection
Turnover & Commissioning
Offsite
Fabrication
Identify Key Requirement Dates,
Starting From Project Completion
and Define Schedule through
Backward Chaining of Activities
 Provide prioritization
requests / lists
 Monitor available work
Fronts
 Auto-trigger “Flags” and
expedite items that may
delay schedule
Agile Construction Methodology
Case Study – Off Shore Platform
Project Background
• Deepwater Offshore Platform - $150M
• Time and materials contract with Fab Yard
• ConstructSim Pipe purchased by Owner and
utilized by module Fab Yard contractor
Project Use-Case
• ConstructSim used to re-baseline schedule, prioritize by TO Systems
 Finish project on-time, under budget
• At “sail away”, only 7 Punch List items (compared to 1000’s )
• Development of crew-level work face plans with ConstructSim
Project Return-On-Investment
Investment
Software and Services $1M
Savings
Reduced project cost from labour efficiency $17M
Project completes ahead of schedule 3 mo.
Project Background
• New Refinery Unit - TIC $320M.
• Lump Sum Contract with Mechanical Sub
• ConstructSim Pipe purchased by Owner and
utilized by Construction Management firm
Project Use-Case
• Actual progress not in alignment with progress reported in field ... Switch
to progressing through ConstructSim
 Project recovers schedule losses to complete on time
• Excessive change order submitted by Mechanical Sub
 ConstructSim used to analyze change order and provide visibility to
impact on work
Project Benefits / Savings
Change order reduced from 2.5M to 500K $2M
Project recovered and completed on-time
Case Study – Diesel Refinery Unit
ConstructSim Users
ConstructSim Functionality
Data
Aggregation
Construction
Planning
Systems
Turnover
Progress
Reporting
Look-Ahead
Planning
Status
Visualization
Virtual Work
Packs
Quantity
Tracking
Streamline
Materials
Change
Management
Data Aggregation
Materials Management
Engineering Data Project Controls
Field Tracking
Virtual
Construction
Model
ConstructSim
Back
Data Aggregation – CAD Adaptors
PDS
PDMS AutoCAD AutoPlant PASCE
PwrTrax
CAD
ConvertersP4D DGN
CIS/2 VRML
Back
ConstructSim reads
digital ISO files and
correlates them with
the 3D CAD model …
Back
Data Aggregation – Digital ISO Input
ConstructSim represents
a manufacturing model
of „constructible‟ pipe
elements.
PIPE_SPOOL
PIPE_WELD
PIPE_SUPPORT
PIPE_BOLTUP
PIPE_LINEITEM
Back
Data Aggregation – ISO Components
ConstructSim
reads structural steel
detail drawings produced
for steel fabrication …
Back
Data Aggregation – Structural Details
ConstructSim
Take-Off
Line List
Digital Isometrics
3D CAD Model
Attributes for
ConstructSim
are derived from
multiple sources
Other Sources
ConstructSim
also infers
attributes
needed for
automated task
generation
Data Aggregation – Attributes
Back
Data Aggregation – CSIM Executive
Back
The Virtual Construction Model (VCM) is generated and updated by
the CSIM Executive data processing engine. The Executive
processes the Project Data as inputs and updates the VCM
throughout the course of a construction project.
Project Data
CSIM
Executive
VCM
Data Aggregation – VCM Templates
Back
Standard VCM Template
for
ConstructSim
Deployed VCM
for
Project ABC-123
VCM Template
for
Project ABC-123.
VCM Template
for
Company XYZ, Inc.
Virtual Construction Model
Virtual Construction Model
Virtual Construction Model
Virtual Construction Model
Data Aggregation – Project Data
Back
Typical Project Data input to ConstructSim on a project includes:
• 3D CAD
• Pipe Isometrics
• Structural Detailing Data
• Line List / Equipment List
• Instrument Index / Electrical Lists
• L3 Project Schedule
• Unit Rates/ Rules of Progress
• Offsite Fabricator Status
• Material Availability
• Quantity Tracking (Progress)
• Weld Tracking / NDE
• TO Systems / Completions
Data Aggregation – Project Data
Back
Typical Progressing Options:
• Use ConstructSim reports and data entry forms to track progress
• Pipe
• Receive
• Fabricate
• Install
• Test
• Steel
• Receive
• Install
• Equipment
• Receive, Install, MC
Data Aggregation – Project Data
Back
Typical Progressing Options:
• Interface with other electronic system
• In-House / 3rd Party Commercial
• Progressing – QTY Tracking
• Material System
• Progressing XLS from sub-contractor
• Validate list is correct
• Use ConstructSim to produce XLS
sheet for sub-contractor, ask sub-
contractor to submit progress in XLS
format
• Reduces in-acuracies
Data Aggregation – Project Data
Back
Typical Progressing Options:
• FUTURE – State-of-the-art active
RFID hardware
• R&D Project
• Waseda University
• Partner - Intelliwave
Construction Planning – UD Groups
Back
Turnover Systems
Construction Areas
Unit 1, Level 3
Large Bore, CS
Construction Planning – 4D Playback
Back
Detailed Engineering
Procurement
Field Installation
Testing & Inspection
Turnover & Commissioning
Offsite Fabrication
Operations &
Maintenance
Direct
Labor
Conceptual Design
& Engineering
In-Direct
Labor
Constructability
Estimating
Planning & Scheduling
Site Supervision
Project Mgmt
Field Engineering - RFIs
Contract Mgmt
Doc Handover
Document Mgmt
Time Keeping & Payroll
Health, Safety & Environment Mgmt
Sub-Contractor Coordination
Materials Mgmt
Construction Planning – Activities
Streamline Materials
Back
Material Warehouse Status
Trial Allocation Priorities
Track Purchase Orders / ETAs
Materials Issue Request
Quantity Tracking
MTO
From CAD +
Isometric Documents
Work Steps
Labor Rates &
Rules of Progress
ConstructSimSchedule
Back
PaintFit-Up NDEPWHTWeldCut
Procure Fabricate Install Test
Turn-
over
Fabricate
Work
Steps
PIPE_SPOOL
Tasks grouped by “activity type” and “component type”
Quantity / Labor Tracking – Tasks
Back
Stage ConnectErect
Install
Work Steps
Procure Fabricate Install Test
Turn-
over
PIPE_SPOOL
Quantity / Labor Tracking – Tasks
Tasks grouped by “activity type” and “component type”
Back
Procure Fabricate Install Test
Turn-
over
PIPE_WELD
Tack Complete
Install
Work Steps
Quantity / Labor Tracking – Tasks
Tasks grouped by “activity type” and “component type”
Back
Levels of Planning & Scheduling
L3 - Schedule
Activity
Example – A/G Piping Field Installation – Area 3A
ConstructSim “Auto-links” Model Components to
L3 Activities By Attribute Matching Rules
ConstructSim “Auto-Generates” L5 Tasks
from Template “Rules of Progress”
Example – Spool 101-A Erect, Fit-Up, Connect
L5 - Tasks
L4 – Crew
Work Packs
Example – One “shift” of work (~1-2 weeks),
includes scope identified with associated L5 tasks
Work face planner “Builds” optimal path of
construction using ConstructSim
Virtual Work Packs
Back
Virtual Work Packs – 4 Views
Back
Virtual Work Packs - Reports
Back
Virtual Work Packs - Reports
Back
Virtual Work Packs - Reports
Back
Work Pack Stats displays a list of all the work packages, with
quantities and associated hours.
Status Visualization
Status information
from task progress
or from external
data sources
No Progress
Received
Staged
Erected
Final Complete
Punch Complete
Back
Status Visualization – Standard Modes
Back
• Spool fabrication
• Equipment installation
• ISO release status
• Pipe material availability
• Advance revision notices
• Work step tracking
• Test pack status
• QA/QC status
• Work package constraints
Project / user specific status
modes can also be created.
Status Visualization – Equip Delivery
Back
Area 15
Status Visualization – Pipe Fab
Back
Area 16
Status Visualization – Test Status
Back
Look-Ahead Planning
Back
Change Management
Back
45
ConstructSim keeps track of the changes in pipe isometrics and
propagates the changes throughout the Virtual Construction
Model
New
VCM
Existing
VCM
Document Linker
Progress Reports
Back
Progress Reports
Back
Systems Turnover
Back
Systems Turnover – Incomplete Work
Back
Work Process Topics
• Engineering Inputs
• Path of Construction
• Work Pack Development
• Sub-contractor coordination
• Lookahead Planning
• Equipment Planning & Tracking
• Shop Fabrication – Modular Construction
• Streamline Materials
• Progressing & Reporting
• Revision Management
• Turnover Systems
• Revision Analysis
Construction Driven Engineering
• Pull Driven Scheduling
– Prioritization / monitoring of engineering & fabrication
• Defining data requirements
– Engineering to construction handovers
– Specifications
– Contractual Terms
• Technology Approach
– Federated Information Workflows
Back
NASA Heritage
Back
Beta - Scaffold / Crane Resource Module
• Dynamic link to P3E
• Automated link to Tie-in List (XLS format)
• User specifies placement of
• Cranes
• Scaffold / Temp Work Platforms
• Crew workspaces
• Crew Density Analysis
• Equipment motion simulation
Back
Process FlowAcetylene
• Perform systems analysis and training
in a virtual model
• Drive the Virtual Model from
PowerPoint training slides
• Capture operator knowledge and
experience digitally in the virtual model
Enable a better trained
workforce in a safer
work environment.
OpSim Insight

More Related Content

What's hot

Finns Using FME Like Crazy
Finns Using FME Like CrazyFinns Using FME Like Crazy
Finns Using FME Like Crazy
Safe Software
 
Winter Maintenance Management System Bavaria
Winter Maintenance Management System BavariaWinter Maintenance Management System Bavaria
Winter Maintenance Management System Bavaria
Safe Software
 
bim & energy analysis
bim & energy analysisbim & energy analysis
bim & energy analysis
EVERSENDAI ENGINEERING (L.L.C.)
 
Office Lean
Office LeanOffice Lean
Office Lean
flevko
 
LMS Imagine.Lab Amesim/STAR-CCM+ co-simulation: solid stress analysis of a ge...
LMS Imagine.Lab Amesim/STAR-CCM+ co-simulation: solid stress analysis of a ge...LMS Imagine.Lab Amesim/STAR-CCM+ co-simulation: solid stress analysis of a ge...
LMS Imagine.Lab Amesim/STAR-CCM+ co-simulation: solid stress analysis of a ge...
Siemens PLM Software
 
MEP Coordination Shop Drawing Service USA - MEPF, Mechanical, Electrical & Pl...
MEP Coordination Shop Drawing Service USA - MEPF, Mechanical, Electrical & Pl...MEP Coordination Shop Drawing Service USA - MEPF, Mechanical, Electrical & Pl...
MEP Coordination Shop Drawing Service USA - MEPF, Mechanical, Electrical & Pl...
siliconllc
 
The use of BIM to analyse the energy performance of a retrofitted educational...
The use of BIM to analyse the energy performance of a retrofitted educational...The use of BIM to analyse the energy performance of a retrofitted educational...
The use of BIM to analyse the energy performance of a retrofitted educational...
Mark Thornton
 
IBM Maximo Performance Tuning
IBM Maximo Performance TuningIBM Maximo Performance Tuning
IBM Maximo Performance Tuning
FMMUG
 
IES Faculty - Intelligent Big Data: Opportunities for Real Estate Asset Manag...
IES Faculty - Intelligent Big Data: Opportunities for Real Estate Asset Manag...IES Faculty - Intelligent Big Data: Opportunities for Real Estate Asset Manag...
IES Faculty - Intelligent Big Data: Opportunities for Real Estate Asset Manag...
IES VE
 
Imagin presentation
Imagin presentationImagin presentation
Imagin presentation
Timothy Michael
 
Femap Version 11.4 Whats New Presentation
Femap Version 11.4 Whats New PresentationFemap Version 11.4 Whats New Presentation
Femap Version 11.4 Whats New Presentation
Siemens PLM Software
 
Earned Value Management FAR 34.2 and DFARS 252.234-7001
Earned Value Management  FAR 34.2  and  DFARS 252.234-7001Earned Value Management  FAR 34.2  and  DFARS 252.234-7001
Earned Value Management FAR 34.2 and DFARS 252.234-7001
Glen Alleman
 
Building Energy parametric optimization / collaboration
Building Energy parametric optimization / collaborationBuilding Energy parametric optimization / collaboration
Building Energy parametric optimization / collaboration
Tero Järvinen
 
Innovations in program controls integrating primavera and cost systems
Innovations in program controls   integrating primavera and cost systemsInnovations in program controls   integrating primavera and cost systems
Innovations in program controls integrating primavera and cost systems
p6academy
 

What's hot (14)

Finns Using FME Like Crazy
Finns Using FME Like CrazyFinns Using FME Like Crazy
Finns Using FME Like Crazy
 
Winter Maintenance Management System Bavaria
Winter Maintenance Management System BavariaWinter Maintenance Management System Bavaria
Winter Maintenance Management System Bavaria
 
bim & energy analysis
bim & energy analysisbim & energy analysis
bim & energy analysis
 
Office Lean
Office LeanOffice Lean
Office Lean
 
LMS Imagine.Lab Amesim/STAR-CCM+ co-simulation: solid stress analysis of a ge...
LMS Imagine.Lab Amesim/STAR-CCM+ co-simulation: solid stress analysis of a ge...LMS Imagine.Lab Amesim/STAR-CCM+ co-simulation: solid stress analysis of a ge...
LMS Imagine.Lab Amesim/STAR-CCM+ co-simulation: solid stress analysis of a ge...
 
MEP Coordination Shop Drawing Service USA - MEPF, Mechanical, Electrical & Pl...
MEP Coordination Shop Drawing Service USA - MEPF, Mechanical, Electrical & Pl...MEP Coordination Shop Drawing Service USA - MEPF, Mechanical, Electrical & Pl...
MEP Coordination Shop Drawing Service USA - MEPF, Mechanical, Electrical & Pl...
 
The use of BIM to analyse the energy performance of a retrofitted educational...
The use of BIM to analyse the energy performance of a retrofitted educational...The use of BIM to analyse the energy performance of a retrofitted educational...
The use of BIM to analyse the energy performance of a retrofitted educational...
 
IBM Maximo Performance Tuning
IBM Maximo Performance TuningIBM Maximo Performance Tuning
IBM Maximo Performance Tuning
 
IES Faculty - Intelligent Big Data: Opportunities for Real Estate Asset Manag...
IES Faculty - Intelligent Big Data: Opportunities for Real Estate Asset Manag...IES Faculty - Intelligent Big Data: Opportunities for Real Estate Asset Manag...
IES Faculty - Intelligent Big Data: Opportunities for Real Estate Asset Manag...
 
Imagin presentation
Imagin presentationImagin presentation
Imagin presentation
 
Femap Version 11.4 Whats New Presentation
Femap Version 11.4 Whats New PresentationFemap Version 11.4 Whats New Presentation
Femap Version 11.4 Whats New Presentation
 
Earned Value Management FAR 34.2 and DFARS 252.234-7001
Earned Value Management  FAR 34.2  and  DFARS 252.234-7001Earned Value Management  FAR 34.2  and  DFARS 252.234-7001
Earned Value Management FAR 34.2 and DFARS 252.234-7001
 
Building Energy parametric optimization / collaboration
Building Energy parametric optimization / collaborationBuilding Energy parametric optimization / collaboration
Building Energy parametric optimization / collaboration
 
Innovations in program controls integrating primavera and cost systems
Innovations in program controls   integrating primavera and cost systemsInnovations in program controls   integrating primavera and cost systems
Innovations in program controls integrating primavera and cost systems
 

Viewers also liked

Instalacja edukacyjnego oprogramowania Autodesk
Instalacja edukacyjnego oprogramowania AutodeskInstalacja edukacyjnego oprogramowania Autodesk
Instalacja edukacyjnego oprogramowania Autodesk
bim.edu.pl
 
Pl wp finanse i księgowość
Pl wp finanse i księgowośćPl wp finanse i księgowość
Pl wp finanse i księgowośćProfiData
 
Bank on traffic prezentacja
Bank on traffic prezentacjaBank on traffic prezentacja
Bank on traffic prezentacjaKrzysztof Dziuba
 
2015_11_Goldbach_Media_DOOH_SHOPPING_CENTER_Screens
2015_11_Goldbach_Media_DOOH_SHOPPING_CENTER_Screens2015_11_Goldbach_Media_DOOH_SHOPPING_CENTER_Screens
2015_11_Goldbach_Media_DOOH_SHOPPING_CENTER_Screens
Goldbach Group AG
 
Goldbach Multichannel - nowy kanał w mediaplanie digital | Goldbach Audience ...
Goldbach Multichannel - nowy kanał w mediaplanie digital | Goldbach Audience ...Goldbach Multichannel - nowy kanał w mediaplanie digital | Goldbach Audience ...
Goldbach Multichannel - nowy kanał w mediaplanie digital | Goldbach Audience ...Goldbach Group AG
 
Typologia klienta
Typologia klientaTypologia klienta
Typologia klienta
NoweKompetencje
 
10 niewielkich rzeczy, które możesz robić codziennie, aby stawać się mądrzejszym
10 niewielkich rzeczy, które możesz robić codziennie, aby stawać się mądrzejszym10 niewielkich rzeczy, które możesz robić codziennie, aby stawać się mądrzejszym
10 niewielkich rzeczy, które możesz robić codziennie, aby stawać się mądrzejszym
NoweKompetencje
 
Techniki aktywnego słuchania
Techniki aktywnego słuchaniaTechniki aktywnego słuchania
Techniki aktywnego słuchania
NoweKompetencje
 
Bądź jak wykrywacz kłamstw! Jak czytać mowę ciała i wychwytywać sygnały niewe...
Bądź jak wykrywacz kłamstw! Jak czytać mowę ciała i wychwytywać sygnały niewe...Bądź jak wykrywacz kłamstw! Jak czytać mowę ciała i wychwytywać sygnały niewe...
Bądź jak wykrywacz kłamstw! Jak czytać mowę ciała i wychwytywać sygnały niewe...
NoweKompetencje
 
11 sposobów na motywowanie produktywności pracownika
11 sposobów na motywowanie produktywności pracownika11 sposobów na motywowanie produktywności pracownika
11 sposobów na motywowanie produktywności pracownika
NoweKompetencje
 
Jak umiejętnie sterować rozmową?
Jak umiejętnie sterować rozmową?Jak umiejętnie sterować rozmową?
Jak umiejętnie sterować rozmową?
Zielona Linia
 
ADONIS - funkcjonalnosci i scenariusze zastosowania
ADONIS - funkcjonalnosci i scenariusze zastosowaniaADONIS - funkcjonalnosci i scenariusze zastosowania
ADONIS - funkcjonalnosci i scenariusze zastosowania
Zbigniew Misiak
 
ADONIS 4.0 - prezentacja nowych funkcji
ADONIS 4.0 - prezentacja nowych funkcjiADONIS 4.0 - prezentacja nowych funkcji
ADONIS 4.0 - prezentacja nowych funkcji
Zbigniew Misiak
 
BPMN 2.0 Poster EN
BPMN 2.0 Poster ENBPMN 2.0 Poster EN
BPMN 2.0 Poster EN
bpmworldconvention
 
System ADONIS - prezentacja
System ADONIS - prezentacjaSystem ADONIS - prezentacja
System ADONIS - prezentacja
Zbigniew Misiak
 
Creative brief. melting pot.
Creative brief. melting pot.Creative brief. melting pot.
Creative brief. melting pot.
Melting Pot. Strategic Collective.
 
Zarządzanie procesami-projekt-mapowanie-procesu
Zarządzanie procesami-projekt-mapowanie-procesuZarządzanie procesami-projekt-mapowanie-procesu
Zarządzanie procesami-projekt-mapowanie-procesu
Lukasz Kaszuba P2, MSPP
 
Brief kreatywny. Insight. melting-pot
Brief kreatywny. Insight. melting-potBrief kreatywny. Insight. melting-pot
Brief kreatywny. Insight. melting-pot
Melting Pot. Strategic Collective.
 

Viewers also liked (20)

Instalacja edukacyjnego oprogramowania Autodesk
Instalacja edukacyjnego oprogramowania AutodeskInstalacja edukacyjnego oprogramowania Autodesk
Instalacja edukacyjnego oprogramowania Autodesk
 
Pl wp finanse i księgowość
Pl wp finanse i księgowośćPl wp finanse i księgowość
Pl wp finanse i księgowość
 
Bank on traffic prezentacja
Bank on traffic prezentacjaBank on traffic prezentacja
Bank on traffic prezentacja
 
AdCarousel
AdCarouselAdCarousel
AdCarousel
 
2015_11_Goldbach_Media_DOOH_SHOPPING_CENTER_Screens
2015_11_Goldbach_Media_DOOH_SHOPPING_CENTER_Screens2015_11_Goldbach_Media_DOOH_SHOPPING_CENTER_Screens
2015_11_Goldbach_Media_DOOH_SHOPPING_CENTER_Screens
 
Goldbach Multichannel - nowy kanał w mediaplanie digital | Goldbach Audience ...
Goldbach Multichannel - nowy kanał w mediaplanie digital | Goldbach Audience ...Goldbach Multichannel - nowy kanał w mediaplanie digital | Goldbach Audience ...
Goldbach Multichannel - nowy kanał w mediaplanie digital | Goldbach Audience ...
 
Typologia klienta
Typologia klientaTypologia klienta
Typologia klienta
 
10 niewielkich rzeczy, które możesz robić codziennie, aby stawać się mądrzejszym
10 niewielkich rzeczy, które możesz robić codziennie, aby stawać się mądrzejszym10 niewielkich rzeczy, które możesz robić codziennie, aby stawać się mądrzejszym
10 niewielkich rzeczy, które możesz robić codziennie, aby stawać się mądrzejszym
 
Techniki aktywnego słuchania
Techniki aktywnego słuchaniaTechniki aktywnego słuchania
Techniki aktywnego słuchania
 
Bądź jak wykrywacz kłamstw! Jak czytać mowę ciała i wychwytywać sygnały niewe...
Bądź jak wykrywacz kłamstw! Jak czytać mowę ciała i wychwytywać sygnały niewe...Bądź jak wykrywacz kłamstw! Jak czytać mowę ciała i wychwytywać sygnały niewe...
Bądź jak wykrywacz kłamstw! Jak czytać mowę ciała i wychwytywać sygnały niewe...
 
11 sposobów na motywowanie produktywności pracownika
11 sposobów na motywowanie produktywności pracownika11 sposobów na motywowanie produktywności pracownika
11 sposobów na motywowanie produktywności pracownika
 
Jak umiejętnie sterować rozmową?
Jak umiejętnie sterować rozmową?Jak umiejętnie sterować rozmową?
Jak umiejętnie sterować rozmową?
 
ADONIS - funkcjonalnosci i scenariusze zastosowania
ADONIS - funkcjonalnosci i scenariusze zastosowaniaADONIS - funkcjonalnosci i scenariusze zastosowania
ADONIS - funkcjonalnosci i scenariusze zastosowania
 
ADONIS 4.0 - prezentacja nowych funkcji
ADONIS 4.0 - prezentacja nowych funkcjiADONIS 4.0 - prezentacja nowych funkcji
ADONIS 4.0 - prezentacja nowych funkcji
 
BPMN 2.0 Poster EN
BPMN 2.0 Poster ENBPMN 2.0 Poster EN
BPMN 2.0 Poster EN
 
System ADONIS - prezentacja
System ADONIS - prezentacjaSystem ADONIS - prezentacja
System ADONIS - prezentacja
 
Creative brief. melting pot.
Creative brief. melting pot.Creative brief. melting pot.
Creative brief. melting pot.
 
Zarządzanie procesami-projekt-mapowanie-procesu
Zarządzanie procesami-projekt-mapowanie-procesuZarządzanie procesami-projekt-mapowanie-procesu
Zarządzanie procesami-projekt-mapowanie-procesu
 
Brief kreatywny. Insight. melting-pot
Brief kreatywny. Insight. melting-potBrief kreatywny. Insight. melting-pot
Brief kreatywny. Insight. melting-pot
 
Strategia w praktyce. melting-pot
Strategia w praktyce. melting-potStrategia w praktyce. melting-pot
Strategia w praktyce. melting-pot
 

Similar to agile constructsim overview

Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
raghunathan janarthanan
 
Wastewater networks modeling using info works cs
Wastewater networks modeling using info works csWastewater networks modeling using info works cs
Wastewater networks modeling using info works cs
AHMED NADIM JILANI
 
Integration of Analytical Software and 3D Platform in Plant Design and Engine...
Integration of Analytical Software and 3D Platform in Plant Design and Engine...Integration of Analytical Software and 3D Platform in Plant Design and Engine...
Integration of Analytical Software and 3D Platform in Plant Design and Engine...
Anirban Datta, CEng
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
SAJJAD KHUDHUR ABBAS
 
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanFiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
CCT International
 
AB114-5 BIM-based Collaboration-PPT.pdf
AB114-5 BIM-based Collaboration-PPT.pdfAB114-5 BIM-based Collaboration-PPT.pdf
AB114-5 BIM-based Collaboration-PPT.pdf
RavenousSolos
 
Session T4 - Deliverables Management - A strategic Opportunity
Session T4 - Deliverables Management - A strategic OpportunitySession T4 - Deliverables Management - A strategic Opportunity
Session T4 - Deliverables Management - A strategic Opportunity
Project Controls Expo
 
Building Information Modelling (BIM) for Handover and Facilities Management
Building Information Modelling (BIM) for Handover and Facilities ManagementBuilding Information Modelling (BIM) for Handover and Facilities Management
Building Information Modelling (BIM) for Handover and Facilities Management
The Hong Kong Institute of Building Information Modelling (HKIBIM)
 
Construct Sim V8i 5 19 2011
Construct Sim V8i 5 19 2011Construct Sim V8i 5 19 2011
Construct Sim V8i 5 19 2011
Rob_Skeleton
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.ppt
yashchotaliyael21
 
Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction Industry
CCT International
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & Monitoring
CCT International
 
Epc projects and cad tools
Epc projects and cad toolsEpc projects and cad tools
Epc projects and cad tools
Morteza Shahmoradi
 
Resume +Tahir 2016
Resume +Tahir 2016Resume +Tahir 2016
Resume +Tahir 2016
Tahir Khan
 
AES_Capabilities_09012016
AES_Capabilities_09012016AES_Capabilities_09012016
AES_Capabilities_09012016
Svetlana Vasey
 
Adco presentation june 4 2013
Adco presentation june 4 2013Adco presentation june 4 2013
Adco presentation june 4 2013
shivendragautam21
 
6.0 CURT CII - Digital Transformation of Construction Industry
6.0 CURT CII  - Digital Transformation of Construction Industry6.0 CURT CII  - Digital Transformation of Construction Industry
6.0 CURT CII - Digital Transformation of Construction Industry
CCT International
 
Mainframe Application Testing both With and Without Live Data
Mainframe Application Testing both With and Without Live DataMainframe Application Testing both With and Without Live Data
Mainframe Application Testing both With and Without Live Data
DevOps for Enterprise Systems
 
Gi oss offering top cell_partnership (1)
Gi oss offering top cell_partnership (1)Gi oss offering top cell_partnership (1)
Gi oss offering top cell_partnership (1)
Emerson Eduardo Rodrigues Von Staffen
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution Teams
CCT International
 

Similar to agile constructsim overview (20)

Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Wastewater networks modeling using info works cs
Wastewater networks modeling using info works csWastewater networks modeling using info works cs
Wastewater networks modeling using info works cs
 
Integration of Analytical Software and 3D Platform in Plant Design and Engine...
Integration of Analytical Software and 3D Platform in Plant Design and Engine...Integration of Analytical Software and 3D Platform in Plant Design and Engine...
Integration of Analytical Software and 3D Platform in Plant Design and Engine...
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanFiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
 
AB114-5 BIM-based Collaboration-PPT.pdf
AB114-5 BIM-based Collaboration-PPT.pdfAB114-5 BIM-based Collaboration-PPT.pdf
AB114-5 BIM-based Collaboration-PPT.pdf
 
Session T4 - Deliverables Management - A strategic Opportunity
Session T4 - Deliverables Management - A strategic OpportunitySession T4 - Deliverables Management - A strategic Opportunity
Session T4 - Deliverables Management - A strategic Opportunity
 
Building Information Modelling (BIM) for Handover and Facilities Management
Building Information Modelling (BIM) for Handover and Facilities ManagementBuilding Information Modelling (BIM) for Handover and Facilities Management
Building Information Modelling (BIM) for Handover and Facilities Management
 
Construct Sim V8i 5 19 2011
Construct Sim V8i 5 19 2011Construct Sim V8i 5 19 2011
Construct Sim V8i 5 19 2011
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.ppt
 
Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction Industry
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & Monitoring
 
Epc projects and cad tools
Epc projects and cad toolsEpc projects and cad tools
Epc projects and cad tools
 
Resume +Tahir 2016
Resume +Tahir 2016Resume +Tahir 2016
Resume +Tahir 2016
 
AES_Capabilities_09012016
AES_Capabilities_09012016AES_Capabilities_09012016
AES_Capabilities_09012016
 
Adco presentation june 4 2013
Adco presentation june 4 2013Adco presentation june 4 2013
Adco presentation june 4 2013
 
6.0 CURT CII - Digital Transformation of Construction Industry
6.0 CURT CII  - Digital Transformation of Construction Industry6.0 CURT CII  - Digital Transformation of Construction Industry
6.0 CURT CII - Digital Transformation of Construction Industry
 
Mainframe Application Testing both With and Without Live Data
Mainframe Application Testing both With and Without Live DataMainframe Application Testing both With and Without Live Data
Mainframe Application Testing both With and Without Live Data
 
Gi oss offering top cell_partnership (1)
Gi oss offering top cell_partnership (1)Gi oss offering top cell_partnership (1)
Gi oss offering top cell_partnership (1)
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution Teams
 

Recently uploaded

原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
Seminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptxSeminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptx
Madan Karki
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
RamonNovais6
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
PKavitha10
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
GauravCar
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
ramrag33
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
riddhimaagrawal986
 

Recently uploaded (20)

原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
Seminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptxSeminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptx
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
 

agile constructsim overview

  • 2. Solutions COMMUNICATION S BRIDGES BUILDINGS CAMPUSES CADASTRE AND LAND DEVELOPMENT OIL AND GAS ELECTRIC AND GAS UTILITIES FACTORIES METALS AND MINING POWER GENERATION ROADS WATER AND WASTEWATERRAIL AND TRANSIT
  • 3. Introducing ConstructSim Materials Management Engineering Data Project Controls Field Tracking Virtual Construction Model ConstructSim Reporting & Simulation Solves complex planning and execution problems for For Who? When? • Owners • Construction Managers • Direct Hire • Early Planning • Field Installation • Turnover / Commissioning
  • 4. Addresses These Main Issues Visibility into the planned and current project status Material availability / engineering drawing production Cost to complete Information management / Aggregation Reactive construction management Productivity of field labor
  • 6. Main Functionality • Virtual Construction Model – dynamic updated daily with data from engineering and construction • Auto re-organize engr 3D data for construction tracking – Spools (SpoolGen / IsoGen); Steel Piecemarks, etc … • Provide construction views – area & systems (others) • Work steps that relates to all small pieces (every pipe spool, steel beam) – automatic • Video game environment to build work packs (detailed planning – Click, click, click -> print reports (spool list, field materials, checklist – aka scorecard – for progressing … i.e. get paid) • Status visualization …. See progress in 3D – engineering production / Material availability / installation / testing • Integration with schedule – Visually produce schedule early in project – During project … update schedule weekly with progress (summary reports % complete per schedule ) –
  • 8. Detailed Engineering Procurement Field Installation Testing & Inspection Turnover & Commissioning Offsite Fabrication Identify Key Requirement Dates, Starting From Project Completion and Define Schedule through Backward Chaining of Activities  Provide prioritization requests / lists  Monitor available work Fronts  Auto-trigger “Flags” and expedite items that may delay schedule Agile Construction Methodology
  • 9. Case Study – Off Shore Platform Project Background • Deepwater Offshore Platform - $150M • Time and materials contract with Fab Yard • ConstructSim Pipe purchased by Owner and utilized by module Fab Yard contractor Project Use-Case • ConstructSim used to re-baseline schedule, prioritize by TO Systems  Finish project on-time, under budget • At “sail away”, only 7 Punch List items (compared to 1000’s ) • Development of crew-level work face plans with ConstructSim Project Return-On-Investment Investment Software and Services $1M Savings Reduced project cost from labour efficiency $17M Project completes ahead of schedule 3 mo.
  • 10. Project Background • New Refinery Unit - TIC $320M. • Lump Sum Contract with Mechanical Sub • ConstructSim Pipe purchased by Owner and utilized by Construction Management firm Project Use-Case • Actual progress not in alignment with progress reported in field ... Switch to progressing through ConstructSim  Project recovers schedule losses to complete on time • Excessive change order submitted by Mechanical Sub  ConstructSim used to analyze change order and provide visibility to impact on work Project Benefits / Savings Change order reduced from 2.5M to 500K $2M Project recovered and completed on-time Case Study – Diesel Refinery Unit
  • 13. Data Aggregation Materials Management Engineering Data Project Controls Field Tracking Virtual Construction Model ConstructSim Back
  • 14. Data Aggregation – CAD Adaptors PDS PDMS AutoCAD AutoPlant PASCE PwrTrax CAD ConvertersP4D DGN CIS/2 VRML Back
  • 15. ConstructSim reads digital ISO files and correlates them with the 3D CAD model … Back Data Aggregation – Digital ISO Input
  • 16. ConstructSim represents a manufacturing model of „constructible‟ pipe elements. PIPE_SPOOL PIPE_WELD PIPE_SUPPORT PIPE_BOLTUP PIPE_LINEITEM Back Data Aggregation – ISO Components
  • 17. ConstructSim reads structural steel detail drawings produced for steel fabrication … Back Data Aggregation – Structural Details
  • 18. ConstructSim Take-Off Line List Digital Isometrics 3D CAD Model Attributes for ConstructSim are derived from multiple sources Other Sources ConstructSim also infers attributes needed for automated task generation Data Aggregation – Attributes Back
  • 19. Data Aggregation – CSIM Executive Back The Virtual Construction Model (VCM) is generated and updated by the CSIM Executive data processing engine. The Executive processes the Project Data as inputs and updates the VCM throughout the course of a construction project. Project Data CSIM Executive VCM
  • 20. Data Aggregation – VCM Templates Back Standard VCM Template for ConstructSim Deployed VCM for Project ABC-123 VCM Template for Project ABC-123. VCM Template for Company XYZ, Inc. Virtual Construction Model Virtual Construction Model Virtual Construction Model Virtual Construction Model
  • 21. Data Aggregation – Project Data Back Typical Project Data input to ConstructSim on a project includes: • 3D CAD • Pipe Isometrics • Structural Detailing Data • Line List / Equipment List • Instrument Index / Electrical Lists • L3 Project Schedule • Unit Rates/ Rules of Progress • Offsite Fabricator Status • Material Availability • Quantity Tracking (Progress) • Weld Tracking / NDE • TO Systems / Completions
  • 22. Data Aggregation – Project Data Back Typical Progressing Options: • Use ConstructSim reports and data entry forms to track progress • Pipe • Receive • Fabricate • Install • Test • Steel • Receive • Install • Equipment • Receive, Install, MC
  • 23. Data Aggregation – Project Data Back Typical Progressing Options: • Interface with other electronic system • In-House / 3rd Party Commercial • Progressing – QTY Tracking • Material System • Progressing XLS from sub-contractor • Validate list is correct • Use ConstructSim to produce XLS sheet for sub-contractor, ask sub- contractor to submit progress in XLS format • Reduces in-acuracies
  • 24. Data Aggregation – Project Data Back Typical Progressing Options: • FUTURE – State-of-the-art active RFID hardware • R&D Project • Waseda University • Partner - Intelliwave
  • 25. Construction Planning – UD Groups Back Turnover Systems Construction Areas Unit 1, Level 3 Large Bore, CS
  • 26. Construction Planning – 4D Playback Back
  • 27. Detailed Engineering Procurement Field Installation Testing & Inspection Turnover & Commissioning Offsite Fabrication Operations & Maintenance Direct Labor Conceptual Design & Engineering In-Direct Labor Constructability Estimating Planning & Scheduling Site Supervision Project Mgmt Field Engineering - RFIs Contract Mgmt Doc Handover Document Mgmt Time Keeping & Payroll Health, Safety & Environment Mgmt Sub-Contractor Coordination Materials Mgmt Construction Planning – Activities
  • 28. Streamline Materials Back Material Warehouse Status Trial Allocation Priorities Track Purchase Orders / ETAs Materials Issue Request
  • 29. Quantity Tracking MTO From CAD + Isometric Documents Work Steps Labor Rates & Rules of Progress ConstructSimSchedule Back
  • 30. PaintFit-Up NDEPWHTWeldCut Procure Fabricate Install Test Turn- over Fabricate Work Steps PIPE_SPOOL Tasks grouped by “activity type” and “component type” Quantity / Labor Tracking – Tasks Back
  • 31. Stage ConnectErect Install Work Steps Procure Fabricate Install Test Turn- over PIPE_SPOOL Quantity / Labor Tracking – Tasks Tasks grouped by “activity type” and “component type” Back
  • 32. Procure Fabricate Install Test Turn- over PIPE_WELD Tack Complete Install Work Steps Quantity / Labor Tracking – Tasks Tasks grouped by “activity type” and “component type” Back
  • 33. Levels of Planning & Scheduling L3 - Schedule Activity Example – A/G Piping Field Installation – Area 3A ConstructSim “Auto-links” Model Components to L3 Activities By Attribute Matching Rules ConstructSim “Auto-Generates” L5 Tasks from Template “Rules of Progress” Example – Spool 101-A Erect, Fit-Up, Connect L5 - Tasks L4 – Crew Work Packs Example – One “shift” of work (~1-2 weeks), includes scope identified with associated L5 tasks Work face planner “Builds” optimal path of construction using ConstructSim
  • 35. Virtual Work Packs – 4 Views Back
  • 36. Virtual Work Packs - Reports Back
  • 37. Virtual Work Packs - Reports Back
  • 38. Virtual Work Packs - Reports Back Work Pack Stats displays a list of all the work packages, with quantities and associated hours.
  • 39. Status Visualization Status information from task progress or from external data sources No Progress Received Staged Erected Final Complete Punch Complete Back
  • 40. Status Visualization – Standard Modes Back • Spool fabrication • Equipment installation • ISO release status • Pipe material availability • Advance revision notices • Work step tracking • Test pack status • QA/QC status • Work package constraints Project / user specific status modes can also be created.
  • 41. Status Visualization – Equip Delivery Back
  • 42. Area 15 Status Visualization – Pipe Fab Back
  • 43. Area 16 Status Visualization – Test Status Back
  • 45. Change Management Back 45 ConstructSim keeps track of the changes in pipe isometrics and propagates the changes throughout the Virtual Construction Model New VCM Existing VCM
  • 50. Systems Turnover – Incomplete Work Back
  • 51. Work Process Topics • Engineering Inputs • Path of Construction • Work Pack Development • Sub-contractor coordination • Lookahead Planning • Equipment Planning & Tracking • Shop Fabrication – Modular Construction • Streamline Materials • Progressing & Reporting • Revision Management • Turnover Systems • Revision Analysis
  • 52. Construction Driven Engineering • Pull Driven Scheduling – Prioritization / monitoring of engineering & fabrication • Defining data requirements – Engineering to construction handovers – Specifications – Contractual Terms • Technology Approach – Federated Information Workflows
  • 54. Back Beta - Scaffold / Crane Resource Module • Dynamic link to P3E • Automated link to Tie-in List (XLS format) • User specifies placement of • Cranes • Scaffold / Temp Work Platforms • Crew workspaces • Crew Density Analysis • Equipment motion simulation
  • 55. Back Process FlowAcetylene • Perform systems analysis and training in a virtual model • Drive the Virtual Model from PowerPoint training slides • Capture operator knowledge and experience digitally in the virtual model Enable a better trained workforce in a safer work environment. OpSim Insight