SlideShare a Scribd company logo
Pueblo Chemical Agent-Destruction Pilot
Plant Explosive Destruction System
(PCAPP EDS)
Project Update
30 October 2013
“Distribution Statement A: Approved for
public release; Distribution is unlimited”
UNCLASSIFIED
Presented to:
Pueblo Chemical Depot (PCD) Citizens’ Advisory Commission (CAC)
Presented by:
Mr. Steven Bird
PCAPP EDS Project Lead
Joint Project Manager-Elimination (Provisional) (JPM-E (P))
Provide the Pueblo Chemical Depot (PCD) Citizens’ Advisory
Commission (CAC) with an update on the current status of
the construction contracting and planning effort supporting
Pueblo Chemical Agent-Destruction Pilot Plant Explosive
Destruction System (PCAPP EDS) Project
Objective
EDS Phase 2
Mission
To destroy an estimated 1,366 over packed leakers, DOT cylinders,
estimated rejects and leakers, and contaminated bursters identified
by the ACWA Program in a safe and efficient manner that is
protective of human health (workers and residents) and the
environment
Overview of PCAPP EDS
Operators place
the item in the
munition holder.
Linear-shaped charges are
attached along the munition body
and the item is placed in the
munition holder (up to 6 pack).
Operators slide the
munition holder into the
vessel.
Operators remotely detonate the
linear shaped charges to access
the munition body and destroy
explosives.
Once neutralization chemicals are
added, the vessel is heated with steam
and rotated to mix the contents. A
liquid sample is collected to verify
treatment goal ( less than 50 ppm) has
been met prior to draining.
The vessel is closed and
sealed.
Next water rinse is added, steam
heated, rotated, and drained. An air
sample is collected to verify treatment
goal has been met prior to opening
door and removing scrap metal.
PCAPP EDS Process Summary
Forecasted Items to be Destroyed
Overview of PCAPP EDS
Item Rejects Leakers
Known
Overpacks
Contaminated Total
155mm 59 114 197 0 370
105mm 391 58 264 0 713
4.2” Mortar 89 15 88 0 192
DOT
Cylinders
9 0 2 0 11
Bursters 0 0 0 80 80
Total 548 187 551 80 1,366
• Operations will be campaigned starting with over packed items and DOT cylinders,
followed by 155mm projectiles, 105 mm projectiles, and 4.2” mortars and
contaminated bursters
• A temporary closure of the PCAPP EDS site is planned between each campaign
Site Construction - Contractor
• Corps of Engineers (COE), Huntsville received approval from Small
Business Administration on 30 August 2013 to move forward with
8/(a)/Native American contractor
• The contractor, Komada LLC, based in Colorado Springs, CO, has a
strong local presence and a good relationship with state regulatory
bodies
• The design partner, Merrick & Company, based in Denver, CO, has
done chemical demilitarization work for Huntsville in the past
• Past performance ratings have been in the outstanding range
PCAPP EDS Contracting Status
Construction Schedule
• Initial proposal received: October 16, 2013
• Projected Contract Award Date: October 28, 2013
• Projected Design Start: November 2013
• Projected Design Complete: February 2014
• Projected Construction Start: February 2014
• Projected Construction Complete: July 2014
• Beneficial Occupancy Date (BOD): July 2014
• Projected Final As-Built Drawings/3rd Party Certification: August 8,
2014
Site Construction – Major Components
• EDS Trailers – P2R and P2A
• Environmental Enclosures – Each with support equipment
• Explosives Storage Magazines – Store donor explosives
• Air Monitoring Trailers – Hold air monitoring instruments
• Command Post Modular Facility (outside Chemical Limited Area (CLA))
• Treaty Trailer Modular Facility (outside CLA)
• Crew Change House Modular Facility
• Laboratory Facility
• Entry Control Facility (personnel and vehicular)
• Emergency site back up generator
• On-site munition storage (existing ammunition igloo)
• On-site warehouse (existing ammunition igloo)
• Connection to G-block CLA
Overview of PCAPP EDS
Site Location
Site Construction Concrete Pad Diagram
Site Construction Concrete Pad Close Up
Site Construction – Command Post
OFFICE
1
CP 3CP 2
REF REF
KITCHEN
BREAK ROOM
PROJECTION
SCREEN
WORK STATIONS
CONFERENCE
ROOM
CP 1
RECORDS
STORAGE
ROOM
JANITOR
MEN’S
ROOM
LADIES’
ROOM
ELEC/
SERVER ROOM
OFFICE
2
OFFICE
3
OFFICE
4
NSF
OFFICE
COMMAND POST
QUADRUPLE WIDE, 64’ X 64’
Scale
10’
64’
64’
Plan TableBook
Shelf
Book
Shelf
Plan TableBook
Shelf
Book
Shelf
Plan TableBook
Shelf
Book
Shelf
Site Construction – Change House
REF REFICE
MACH
SHWR
SHWR
SHWR
ELEC
BENCH
JANITOR’S
CLOSET
SHWR
SHWR
MEN’S
ROOM
MEN’S
LOCKERS
LADIES’
ROOM
PPE
DRESSOUT
ROOM
WOMEN’S
LOCKERS
LOCKERS
CHANGE HOUSE
TRIPLE WIDE, 64’ X 48’
Scale
10’
64’
48’
BENCH
BENCH
WORK STATIONS
Site Construction – Treaty Trailer
PCAPP EDS Chemical Laboratory
Mobile Chemical Laboratory Structure
PCAPP EDS Use of Existing Igloos
Igloo Refurbishment and Upgrade
• Igloos H1101, H1102, H1103 refurbished/upgraded to support PCAPP EDS
• Upgrades include:
‒ Apron extensions (H1102 and H1103)
‒ Igloo Containment System (Igloo H1102 only)
‒ Repair of magazine membrane
‒ Adding earthen cover
‒ Repairing Lightning Protection System
‒ Repairing vent system
‒ Installing fusible links
‒ Stenciling magazine numbers
‒ Epoxy coating (H1102 and H1103)
Questions?
For Information on the
Joint Project Manager for Elimination (Provisional)
Mr. Steven Bird
Operations Directorate
PCAPP EDS Project Lead, JPM-E (P)
Phone - 410.436.4577
steven.t.bird.civ@mail.mil

More Related Content

What's hot

Containment Filtered Venting - A new approach
Containment Filtered Venting - A new approachContainment Filtered Venting - A new approach
Containment Filtered Venting - A new approach
Alexander Wolski
 
Iso 14001 aspect impact management
Iso 14001 aspect impact managementIso 14001 aspect impact management
Iso 14001 aspect impact management
Hpm India
 
ReactIR as a Diagnostic Tool for Developing Robust, Scalable Synthetic Processes
ReactIR as a Diagnostic Tool for Developing Robust, Scalable Synthetic ProcessesReactIR as a Diagnostic Tool for Developing Robust, Scalable Synthetic Processes
ReactIR as a Diagnostic Tool for Developing Robust, Scalable Synthetic Processes
placed1
 
HAZCON / HAZDEM
HAZCON / HAZDEMHAZCON / HAZDEM
HAZCON / HAZDEM
Gerard B. Hawkins
 
The 411 on secondary spill containment and spcc regulations
The 411 on secondary spill containment and spcc regulationsThe 411 on secondary spill containment and spcc regulations
The 411 on secondary spill containment and spcc regulations
C.I.Agent Solutions
 
PRE-SULFIDING & ON-LINE SULFIDING of VULCAN Series CoMo and NiMo Catalyst in...
PRE-SULFIDING & ON-LINE SULFIDING of  VULCAN Series CoMo and NiMo Catalyst in...PRE-SULFIDING & ON-LINE SULFIDING of  VULCAN Series CoMo and NiMo Catalyst in...
PRE-SULFIDING & ON-LINE SULFIDING of VULCAN Series CoMo and NiMo Catalyst in...
Gerard B. Hawkins
 
Marks, Julie, Barr Engineering, How to Treat Hazardous Waste Without Permit, ...
Marks, Julie, Barr Engineering, How to Treat Hazardous Waste Without Permit, ...Marks, Julie, Barr Engineering, How to Treat Hazardous Waste Without Permit, ...
Marks, Julie, Barr Engineering, How to Treat Hazardous Waste Without Permit, ...
Kevin Perry
 
Ohio Dept. of Health Guidelines for Analyzing Samples of Oil & Gas Wastes for...
Ohio Dept. of Health Guidelines for Analyzing Samples of Oil & Gas Wastes for...Ohio Dept. of Health Guidelines for Analyzing Samples of Oil & Gas Wastes for...
Ohio Dept. of Health Guidelines for Analyzing Samples of Oil & Gas Wastes for...
Marcellus Drilling News
 
DEACTIVATION OF METHANOL SYNTHESIS CATALYSTS
DEACTIVATION OF METHANOL SYNTHESIS CATALYSTSDEACTIVATION OF METHANOL SYNTHESIS CATALYSTS
DEACTIVATION OF METHANOL SYNTHESIS CATALYSTS
Gerard B. Hawkins
 
Chato liquid acquisition strategies for exploration missions current status 2010
Chato liquid acquisition strategies for exploration missions current status 2010Chato liquid acquisition strategies for exploration missions current status 2010
Chato liquid acquisition strategies for exploration missions current status 2010
David Chato
 
245TCP - Perspectives on PCDD/Fs from a Review of Industrial Processes and Hi...
245TCP - Perspectives on PCDD/Fs from a Review of Industrial Processes and Hi...245TCP - Perspectives on PCDD/Fs from a Review of Industrial Processes and Hi...
245TCP - Perspectives on PCDD/Fs from a Review of Industrial Processes and Hi...
Chemistry Matters Inc.
 
Shift Conversion Catalysts - Operating Manual
Shift Conversion Catalysts - Operating ManualShift Conversion Catalysts - Operating Manual
Shift Conversion Catalysts - Operating Manual
Gerard B. Hawkins
 
Naphtha Steam Reforming Catalyst Reduction with Methanol
Naphtha Steam Reforming Catalyst Reduction with MethanolNaphtha Steam Reforming Catalyst Reduction with Methanol
Naphtha Steam Reforming Catalyst Reduction with Methanol
Gerard B. Hawkins
 
Volume check 100 overview
Volume check 100 overviewVolume check 100 overview
Volume check 100 overview
simmonslm
 
Dilip Shah_Resume
Dilip Shah_ResumeDilip Shah_Resume
Dilip Shah_ResumeDilip Shah
 
Determination of Oxygen in Anhydrous Ammonia
Determination of Oxygen in Anhydrous AmmoniaDetermination of Oxygen in Anhydrous Ammonia
Determination of Oxygen in Anhydrous Ammonia
Gerard B. Hawkins
 
UL Certificate of Compliance (FFT) for Listed Systems
UL Certificate of Compliance (FFT) for Listed SystemsUL Certificate of Compliance (FFT) for Listed Systems
UL Certificate of Compliance (FFT) for Listed SystemsFire Fluid Technologies - MEA
 

What's hot (20)

Containment Filtered Venting - A new approach
Containment Filtered Venting - A new approachContainment Filtered Venting - A new approach
Containment Filtered Venting - A new approach
 
Iso 14001 aspect impact management
Iso 14001 aspect impact managementIso 14001 aspect impact management
Iso 14001 aspect impact management
 
ReactIR as a Diagnostic Tool for Developing Robust, Scalable Synthetic Processes
ReactIR as a Diagnostic Tool for Developing Robust, Scalable Synthetic ProcessesReactIR as a Diagnostic Tool for Developing Robust, Scalable Synthetic Processes
ReactIR as a Diagnostic Tool for Developing Robust, Scalable Synthetic Processes
 
HAZCON / HAZDEM
HAZCON / HAZDEMHAZCON / HAZDEM
HAZCON / HAZDEM
 
GG Nigeria Profile 2016
GG Nigeria Profile 2016GG Nigeria Profile 2016
GG Nigeria Profile 2016
 
The 411 on secondary spill containment and spcc regulations
The 411 on secondary spill containment and spcc regulationsThe 411 on secondary spill containment and spcc regulations
The 411 on secondary spill containment and spcc regulations
 
PRE-SULFIDING & ON-LINE SULFIDING of VULCAN Series CoMo and NiMo Catalyst in...
PRE-SULFIDING & ON-LINE SULFIDING of  VULCAN Series CoMo and NiMo Catalyst in...PRE-SULFIDING & ON-LINE SULFIDING of  VULCAN Series CoMo and NiMo Catalyst in...
PRE-SULFIDING & ON-LINE SULFIDING of VULCAN Series CoMo and NiMo Catalyst in...
 
Marks, Julie, Barr Engineering, How to Treat Hazardous Waste Without Permit, ...
Marks, Julie, Barr Engineering, How to Treat Hazardous Waste Without Permit, ...Marks, Julie, Barr Engineering, How to Treat Hazardous Waste Without Permit, ...
Marks, Julie, Barr Engineering, How to Treat Hazardous Waste Without Permit, ...
 
Ohio Dept. of Health Guidelines for Analyzing Samples of Oil & Gas Wastes for...
Ohio Dept. of Health Guidelines for Analyzing Samples of Oil & Gas Wastes for...Ohio Dept. of Health Guidelines for Analyzing Samples of Oil & Gas Wastes for...
Ohio Dept. of Health Guidelines for Analyzing Samples of Oil & Gas Wastes for...
 
DEACTIVATION OF METHANOL SYNTHESIS CATALYSTS
DEACTIVATION OF METHANOL SYNTHESIS CATALYSTSDEACTIVATION OF METHANOL SYNTHESIS CATALYSTS
DEACTIVATION OF METHANOL SYNTHESIS CATALYSTS
 
Chato liquid acquisition strategies for exploration missions current status 2010
Chato liquid acquisition strategies for exploration missions current status 2010Chato liquid acquisition strategies for exploration missions current status 2010
Chato liquid acquisition strategies for exploration missions current status 2010
 
245TCP - Perspectives on PCDD/Fs from a Review of Industrial Processes and Hi...
245TCP - Perspectives on PCDD/Fs from a Review of Industrial Processes and Hi...245TCP - Perspectives on PCDD/Fs from a Review of Industrial Processes and Hi...
245TCP - Perspectives on PCDD/Fs from a Review of Industrial Processes and Hi...
 
Shift Conversion Catalysts - Operating Manual
Shift Conversion Catalysts - Operating ManualShift Conversion Catalysts - Operating Manual
Shift Conversion Catalysts - Operating Manual
 
Naphtha Steam Reforming Catalyst Reduction with Methanol
Naphtha Steam Reforming Catalyst Reduction with MethanolNaphtha Steam Reforming Catalyst Reduction with Methanol
Naphtha Steam Reforming Catalyst Reduction with Methanol
 
Virupaksh group presentation
Virupaksh group presentationVirupaksh group presentation
Virupaksh group presentation
 
WP4_Work&Future
WP4_Work&FutureWP4_Work&Future
WP4_Work&Future
 
Volume check 100 overview
Volume check 100 overviewVolume check 100 overview
Volume check 100 overview
 
Dilip Shah_Resume
Dilip Shah_ResumeDilip Shah_Resume
Dilip Shah_Resume
 
Determination of Oxygen in Anhydrous Ammonia
Determination of Oxygen in Anhydrous AmmoniaDetermination of Oxygen in Anhydrous Ammonia
Determination of Oxygen in Anhydrous Ammonia
 
UL Certificate of Compliance (FFT) for Listed Systems
UL Certificate of Compliance (FFT) for Listed SystemsUL Certificate of Compliance (FFT) for Listed Systems
UL Certificate of Compliance (FFT) for Listed Systems
 

Viewers also liked

Pueblo Chemical Depot Explosive Destruction System (PCD EDS) May 2013
Pueblo Chemical Depot Explosive Destruction System (PCD EDS) May 2013Pueblo Chemical Depot Explosive Destruction System (PCD EDS) May 2013
Pueblo Chemical Depot Explosive Destruction System (PCD EDS) May 2013
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Bomb explosion death a case report
Bomb explosion death a case reportBomb explosion death a case report
Bomb explosion death a case report
pharmaindexing
 
Explosive Violence: The Problem of Explosive Weapons
Explosive Violence: The Problem of Explosive WeaponsExplosive Violence: The Problem of Explosive Weapons
Explosive Violence: The Problem of Explosive WeaponsInsecurity Insight
 
LOTTO Explosive presentation-v11-en
LOTTO Explosive presentation-v11-enLOTTO Explosive presentation-v11-en
LOTTO Explosive presentation-v11-en
Heiworld
 
Defining the Boundaries of Addiction: A Biological Perspective
Defining the Boundaries of Addiction: A Biological PerspectiveDefining the Boundaries of Addiction: A Biological Perspective
Defining the Boundaries of Addiction: A Biological Perspective
ovalaz
 
Brameld IV (1984 - 2006)
Brameld IV (1984 - 2006)Brameld IV (1984 - 2006)
Brameld IV (1984 - 2006)
Joelyn K Foy
 

Viewers also liked (6)

Pueblo Chemical Depot Explosive Destruction System (PCD EDS) May 2013
Pueblo Chemical Depot Explosive Destruction System (PCD EDS) May 2013Pueblo Chemical Depot Explosive Destruction System (PCD EDS) May 2013
Pueblo Chemical Depot Explosive Destruction System (PCD EDS) May 2013
 
Bomb explosion death a case report
Bomb explosion death a case reportBomb explosion death a case report
Bomb explosion death a case report
 
Explosive Violence: The Problem of Explosive Weapons
Explosive Violence: The Problem of Explosive WeaponsExplosive Violence: The Problem of Explosive Weapons
Explosive Violence: The Problem of Explosive Weapons
 
LOTTO Explosive presentation-v11-en
LOTTO Explosive presentation-v11-enLOTTO Explosive presentation-v11-en
LOTTO Explosive presentation-v11-en
 
Defining the Boundaries of Addiction: A Biological Perspective
Defining the Boundaries of Addiction: A Biological PerspectiveDefining the Boundaries of Addiction: A Biological Perspective
Defining the Boundaries of Addiction: A Biological Perspective
 
Brameld IV (1984 - 2006)
Brameld IV (1984 - 2006)Brameld IV (1984 - 2006)
Brameld IV (1984 - 2006)
 

Similar to Pueblo Chemical Agent-Destruction Pilot Plant Explosive Destruction System (PCAPP EDS) Project Update 30 October 2013

General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015Arun Jothilingam
 
BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...
BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...
BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...
BlueScape
 
Hard Rock Literature and Information
Hard Rock Literature and InformationHard Rock Literature and Information
Hard Rock Literature and Informationjacob Burkett
 
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanFiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
CCT International
 
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
BlueScape
 
SVResume -Lead Mch Enginer June16
SVResume -Lead Mch Enginer June16SVResume -Lead Mch Enginer June16
SVResume -Lead Mch Enginer June16Sudhakar Vallala
 
CV - Philip Turner [Photo] - Nov 2015
CV - Philip Turner [Photo] - Nov 2015CV - Philip Turner [Photo] - Nov 2015
CV - Philip Turner [Photo] - Nov 2015Philip Turner
 
EZ Relief Systems Consulting Capabilities with Selected Bibliography
EZ Relief Systems Consulting Capabilities with Selected BibliographyEZ Relief Systems Consulting Capabilities with Selected Bibliography
EZ Relief Systems Consulting Capabilities with Selected BibliographyEd Zamejc
 
Ankur Singh 7 years exp. oil & gas
Ankur Singh 7 years exp. oil & gasAnkur Singh 7 years exp. oil & gas
Ankur Singh 7 years exp. oil & gasAnkur Singh
 
Aims presentation on Western Region NACE Conference at Victoria 2013
Aims presentation on Western Region NACE Conference at Victoria 2013Aims presentation on Western Region NACE Conference at Victoria 2013
Aims presentation on Western Region NACE Conference at Victoria 2013
gobindkhiani
 
BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013BGCAPP Year in Review Dec. 11, 2013
01 Design of chemical processes Week 1.pptx
01 Design of chemical processes  Week 1.pptx01 Design of chemical processes  Week 1.pptx
01 Design of chemical processes Week 1.pptx
Dr. Rashmi Walvekar
 
Overview of Experience Presentation
Overview of Experience PresentationOverview of Experience Presentation
Overview of Experience PresentationJerry Rodgers
 
Overview of Experience Presentation
Overview of Experience PresentationOverview of Experience Presentation
Overview of Experience PresentationJerry Rodgers
 
LLW challenges and developments FINAL pptx
LLW challenges and developments FINAL pptxLLW challenges and developments FINAL pptx
LLW challenges and developments FINAL pptxPeter ORMAI
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
Comit Projects Ltd
 

Similar to Pueblo Chemical Agent-Destruction Pilot Plant Explosive Destruction System (PCAPP EDS) Project Update 30 October 2013 (20)

General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015
 
Austin Okwordu CV PDF
Austin Okwordu CV PDFAustin Okwordu CV PDF
Austin Okwordu CV PDF
 
BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...
BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...
BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...
 
Hard Rock Literature and Information
Hard Rock Literature and InformationHard Rock Literature and Information
Hard Rock Literature and Information
 
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanFiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
 
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
 
SVResume -Lead Mch Enginer June16
SVResume -Lead Mch Enginer June16SVResume -Lead Mch Enginer June16
SVResume -Lead Mch Enginer June16
 
Mg Innovation Flng Cn 2010 R1
Mg Innovation Flng Cn 2010 R1Mg Innovation Flng Cn 2010 R1
Mg Innovation Flng Cn 2010 R1
 
CV - Philip Turner [Photo] - Nov 2015
CV - Philip Turner [Photo] - Nov 2015CV - Philip Turner [Photo] - Nov 2015
CV - Philip Turner [Photo] - Nov 2015
 
EZ Relief Systems Consulting Capabilities with Selected Bibliography
EZ Relief Systems Consulting Capabilities with Selected BibliographyEZ Relief Systems Consulting Capabilities with Selected Bibliography
EZ Relief Systems Consulting Capabilities with Selected Bibliography
 
Ankur Singh 7 years exp. oil & gas
Ankur Singh 7 years exp. oil & gasAnkur Singh 7 years exp. oil & gas
Ankur Singh 7 years exp. oil & gas
 
Aims presentation on Western Region NACE Conference at Victoria 2013
Aims presentation on Western Region NACE Conference at Victoria 2013Aims presentation on Western Region NACE Conference at Victoria 2013
Aims presentation on Western Region NACE Conference at Victoria 2013
 
BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013
 
CV_ak_2015EN
CV_ak_2015ENCV_ak_2015EN
CV_ak_2015EN
 
01 Design of chemical processes Week 1.pptx
01 Design of chemical processes  Week 1.pptx01 Design of chemical processes  Week 1.pptx
01 Design of chemical processes Week 1.pptx
 
Overview of Experience Presentation
Overview of Experience PresentationOverview of Experience Presentation
Overview of Experience Presentation
 
Overview of Experience Presentation
Overview of Experience PresentationOverview of Experience Presentation
Overview of Experience Presentation
 
LLW challenges and developments FINAL pptx
LLW challenges and developments FINAL pptxLLW challenges and developments FINAL pptx
LLW challenges and developments FINAL pptx
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
 
COMPL OF WORKS1
COMPL OF WORKS1COMPL OF WORKS1
COMPL OF WORKS1
 

More from Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)

CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013CAC/CDCAB Vent Recommendation 5 March 2013
Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014Secondary Waste Working Group 12 March 2014
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013M55 Rocket Separation Operation 11 Dec 2013
2015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 20142015 ACWA Funding 11 June 2014
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012BGCAPP Year in Review Dec. 11, 2012
Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012Chemical Weapons Convention Update 13 June 2012
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons ConventionOPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012CDCAB Working Group Updates 11 December 2012
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Economic Development Working Group Update
Economic Development Working Group UpdateEconomic Development Working Group Update

More from Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA) (20)

CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013
 
Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
 
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
 
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
 
June '13 cdcab
June '13 cdcabJune '13 cdcab
June '13 cdcab
 
M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013
 
2015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 20142015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 2014
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
 
Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014
 
BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012
 
Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013
 
Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012
 
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons ConventionOPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
 
CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012
 
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
 
Economic Development Working Group Update
Economic Development Working Group UpdateEconomic Development Working Group Update
Economic Development Working Group Update
 

Recently uploaded

NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
AjayVejendla3
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
SERUDS INDIA
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
GrantManagementInsti
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
Get Government Grants
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
ARCResearch
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
JSchaus & Associates
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
ahcitycouncil
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
ClaudioTebaldi2
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
ILC- UK
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
ahcitycouncil
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Congressional Budget Office
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
ahcitycouncil
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
850fcj96
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
JSchaus & Associates
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
Mohammed325561
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
SERUDS INDIA
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
850fcj96
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
Saeed Al Dhaheri
 

Recently uploaded (20)

NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
 

Pueblo Chemical Agent-Destruction Pilot Plant Explosive Destruction System (PCAPP EDS) Project Update 30 October 2013

  • 1. Pueblo Chemical Agent-Destruction Pilot Plant Explosive Destruction System (PCAPP EDS) Project Update 30 October 2013 “Distribution Statement A: Approved for public release; Distribution is unlimited” UNCLASSIFIED Presented to: Pueblo Chemical Depot (PCD) Citizens’ Advisory Commission (CAC) Presented by: Mr. Steven Bird PCAPP EDS Project Lead Joint Project Manager-Elimination (Provisional) (JPM-E (P))
  • 2. Provide the Pueblo Chemical Depot (PCD) Citizens’ Advisory Commission (CAC) with an update on the current status of the construction contracting and planning effort supporting Pueblo Chemical Agent-Destruction Pilot Plant Explosive Destruction System (PCAPP EDS) Project Objective
  • 3. EDS Phase 2 Mission To destroy an estimated 1,366 over packed leakers, DOT cylinders, estimated rejects and leakers, and contaminated bursters identified by the ACWA Program in a safe and efficient manner that is protective of human health (workers and residents) and the environment Overview of PCAPP EDS
  • 4. Operators place the item in the munition holder. Linear-shaped charges are attached along the munition body and the item is placed in the munition holder (up to 6 pack). Operators slide the munition holder into the vessel. Operators remotely detonate the linear shaped charges to access the munition body and destroy explosives. Once neutralization chemicals are added, the vessel is heated with steam and rotated to mix the contents. A liquid sample is collected to verify treatment goal ( less than 50 ppm) has been met prior to draining. The vessel is closed and sealed. Next water rinse is added, steam heated, rotated, and drained. An air sample is collected to verify treatment goal has been met prior to opening door and removing scrap metal. PCAPP EDS Process Summary
  • 5. Forecasted Items to be Destroyed Overview of PCAPP EDS Item Rejects Leakers Known Overpacks Contaminated Total 155mm 59 114 197 0 370 105mm 391 58 264 0 713 4.2” Mortar 89 15 88 0 192 DOT Cylinders 9 0 2 0 11 Bursters 0 0 0 80 80 Total 548 187 551 80 1,366 • Operations will be campaigned starting with over packed items and DOT cylinders, followed by 155mm projectiles, 105 mm projectiles, and 4.2” mortars and contaminated bursters • A temporary closure of the PCAPP EDS site is planned between each campaign
  • 6. Site Construction - Contractor • Corps of Engineers (COE), Huntsville received approval from Small Business Administration on 30 August 2013 to move forward with 8/(a)/Native American contractor • The contractor, Komada LLC, based in Colorado Springs, CO, has a strong local presence and a good relationship with state regulatory bodies • The design partner, Merrick & Company, based in Denver, CO, has done chemical demilitarization work for Huntsville in the past • Past performance ratings have been in the outstanding range
  • 7. PCAPP EDS Contracting Status Construction Schedule • Initial proposal received: October 16, 2013 • Projected Contract Award Date: October 28, 2013 • Projected Design Start: November 2013 • Projected Design Complete: February 2014 • Projected Construction Start: February 2014 • Projected Construction Complete: July 2014 • Beneficial Occupancy Date (BOD): July 2014 • Projected Final As-Built Drawings/3rd Party Certification: August 8, 2014
  • 8. Site Construction – Major Components • EDS Trailers – P2R and P2A • Environmental Enclosures – Each with support equipment • Explosives Storage Magazines – Store donor explosives • Air Monitoring Trailers – Hold air monitoring instruments • Command Post Modular Facility (outside Chemical Limited Area (CLA)) • Treaty Trailer Modular Facility (outside CLA) • Crew Change House Modular Facility • Laboratory Facility • Entry Control Facility (personnel and vehicular) • Emergency site back up generator • On-site munition storage (existing ammunition igloo) • On-site warehouse (existing ammunition igloo) • Connection to G-block CLA
  • 9. Overview of PCAPP EDS Site Location
  • 12. Site Construction – Command Post OFFICE 1 CP 3CP 2 REF REF KITCHEN BREAK ROOM PROJECTION SCREEN WORK STATIONS CONFERENCE ROOM CP 1 RECORDS STORAGE ROOM JANITOR MEN’S ROOM LADIES’ ROOM ELEC/ SERVER ROOM OFFICE 2 OFFICE 3 OFFICE 4 NSF OFFICE COMMAND POST QUADRUPLE WIDE, 64’ X 64’ Scale 10’ 64’ 64’ Plan TableBook Shelf Book Shelf Plan TableBook Shelf Book Shelf Plan TableBook Shelf Book Shelf
  • 13. Site Construction – Change House REF REFICE MACH SHWR SHWR SHWR ELEC BENCH JANITOR’S CLOSET SHWR SHWR MEN’S ROOM MEN’S LOCKERS LADIES’ ROOM PPE DRESSOUT ROOM WOMEN’S LOCKERS LOCKERS CHANGE HOUSE TRIPLE WIDE, 64’ X 48’ Scale 10’ 64’ 48’ BENCH BENCH WORK STATIONS
  • 14. Site Construction – Treaty Trailer
  • 15. PCAPP EDS Chemical Laboratory Mobile Chemical Laboratory Structure
  • 16. PCAPP EDS Use of Existing Igloos Igloo Refurbishment and Upgrade • Igloos H1101, H1102, H1103 refurbished/upgraded to support PCAPP EDS • Upgrades include: ‒ Apron extensions (H1102 and H1103) ‒ Igloo Containment System (Igloo H1102 only) ‒ Repair of magazine membrane ‒ Adding earthen cover ‒ Repairing Lightning Protection System ‒ Repairing vent system ‒ Installing fusible links ‒ Stenciling magazine numbers ‒ Epoxy coating (H1102 and H1103)
  • 18. For Information on the Joint Project Manager for Elimination (Provisional) Mr. Steven Bird Operations Directorate PCAPP EDS Project Lead, JPM-E (P) Phone - 410.436.4577 steven.t.bird.civ@mail.mil