1. SHABEER AHMAD
AGE: 22 Years
Job Experience: 3.6Years
Post Applied: Process Plant Operator
:: Urea plant CCR-1, Fatima Fertilizer company,Sadiqabad.Urea plant CCR-1, Fatima Fertilizer company,Sadiqabad.
:: (+92-3067722471),(+92-3360020122)(+92-3067722471),(+92-3360020122)
:: 03067722471shab@gmail.com03067722471shab@gmail.com
: shabeer.ahmad2471: shabeer.ahmad2471
Objective My goal is to become associated with a company where I can utilize my skills and gain
further experience while enhancing the company’s productivity and reputation with
the best use of my dedication, determination and resourcefulness.
Personal
Information
Father’s Name Muhammad Ashiq
Date of Birth 17-12-1993
Religion Islam
Marital Status Single
Domicile Multan(Punjab)
Nationality Pakistani
C.N.I.C. Number 36303-2354051-7
Permanent
address
Urea plant Fatima Fertilizer company, Sadiqabad.
Course Title Particular Year of Passing Percentage/ Marks Marks Board
D.A.E
(Chemical)
2011 75.67%
2573/3400 P.B.T.E Lahore
Metric (Science) 2008
82% 697/850 BISE Multan
Professional Experience
Technical skills
Worked at following
equipments &
machinery.
Centrifugal
Compressors
P D Pumps
Centrifugal
FATIMA FERTILIZER,UREA UNIT:
Enhancing personal professional experience at ever expanding
Petro-Chemical industry, Fatima fertilizers. Working as plant operator in a challenging
environment handling emergency situations along with obtaining thorough knowledge
about STAMICARBON Technology used for UREA Production for 1.5 years (from 10-
10-12 to till date).
Steam Turbine:
15 stages Steam Turbine of Impulse & Reaction Induction, Condensing and
Extraction type made by Siemens.
2. Pumps
P D Compressors
Surfaces
Condenser
Electronic
Governors
Condensing
Turbines
Safety & skill
improvement
courses
Fire fighting
Rescue
training
Work permit
procedure
Process
control
Centrifugal
pump &
compressor
Steam &
steam turbine
Heat and heat
exchangers
Safety
standards
IMS
ISO:9001
Environment
al
Management
System(EMS
)
ISO:14001
Quality
control
Management
System(QM
S)
ISO: 18001
8.1M.W power having latest electronic governor System (WOODWARD 505E).
CO2 Compressor:
Compressor is steam turbine Driven.
04 stages CO2 compressor (centrifugal type) made by HITACHI Japan
02 casing one horizontal split and second vertical split
H2 converter is also introduced b/w two stages to remove Hydrogen
Operating pressure 147 Kg/Cm2
and flow 47 Ton/Hr having latest surge control
system.
Synthesis and High Pressure Decomposition Section:
Pool Reactor
It consists of two parts (cooling part, adiabatic part) with operating conditions
145 kg/cm2
and 174-184 o
C.
High pressure stripper
Design CO2 stripping {falling film evaporator).
Operating condition,145 kg/cm2
and 175-190 o
C
High pressure scrubber
Spherical scrubber having capacity of 9m3
.Having ability to scrubs of the off
gasses of the pool reactor by fresh ammonia and carbamate.
High Pressure Pumps
High pressure Ammonia Pump (EBARA)
Multi stage centrifugal Pump (10 Stage) Motor Driven, 0.6 MW, 6526 Rpm
Operating Pressure 180 kg/cm2
.
High pressure Carbamate Pump (EBARA)
Multi stage centrifugal Pump (08 Stage) Motor Driven, 0.35 MW, 7249 Rpm
Operating Pressure 170 kg/cm2
.
High Pressure Flush pump (150 Kg/cm2
).
N/C analyzer & N/C metering system.
Vacuum type leakage Detection system.
Low pressure (lP) and Vacuum Section.
To purify and achieve 99 % urea solution concentration, following equipments
are used in Low pressure and Vacuum sections with operating conditons:
Rectifying column 4.5 kg/cm2
(a) & 135o
C
Low pressure carbonate condenser 3.5 kg/cm2
(a) & 50o
C
Pre evaporator 0.45kg/cm2
(a) & 85o
C
Double Evaporator 0.25kg/cm2
(a) & 130o
C ,
0.02kg/cm2
(a) & 140C.
Evaporator condenser 0.27kg/cm2
(a) & 50o
C
Waste water & process condensate treatment section (PCT):
Double desorber€€ [3.8-4.0 kg/cm2
(a)] having 41 sieve trays to avoid back
mixing and solution down comers.
3. Occupational
Health &
Safety
assessment
series(OHSA
S)
PSM
Process
Safety
Management
System
having 22
elements
divided into
two parts.
1st
Risk base
consists on
10 elements
2nd
Behavior
base
elements
consists on
12 elements.
A hydrolyser to break urea to its reactants (NH3 + CO2) by using 21 kg/cm2
steam also provided with 16 sieve trays and down comers.
Job Responsibilities:
Reporting to “In-Charge Department” according to my responsibilities include:
Understand the control logic and its valid reasoning.
Smooth operation of plant by adjusting the process control variable according
to SOP.
Maintaining the record of plant operating parameters for best communication.
To handle the start up & shut down activities.
To control plant maintenance under the safety environment.
Strictly application of personal & equipment safety.
Execution of “Permit to work” system for safely handling over jobs.
Deep understanding with the equipment details & routine behavior.
Suggest the suitable modification in working procedures to eliminate the
hazard &to improve the performance of various equipment,
Monitoring of process plant parameters.
Sound knowledge of the safety precautions & standard used during
the time of catastrophic conditions.
Skill &
Competences
Effectively handled emergencies like compressor, turbine tripping
Coordinating thirty days (injury/fire free) shutdown for major repair &
modification two times.
Handling of emergencies in case of fire & ammonia leakages
Commanding in language (Urdu, English)
Safety Trainings:
Toxic gas release & its handling.
Fire fighting & use of fire extinguisher.
Explosive gas release.
Working at height.
Electric short circuit prevention
Working at Confined space & validation of vessel entry permits.
Importance of PPE’s (Personal Protection Equipments).
Permit to work system.
SBM (stand by man) training.
4. Achievements Successfully handling of the following emergencies
Cooling water failure
Power failure
Instrument Air failure
Steam failure