SlideShare a Scribd company logo
1 of 48
Kiewit Crane &
Rigging Management
Bret Shields
• Corporate Crane Procedures Manual
• Corporate Rigging Manual
• Career Development
Corporate Crane Procedures Manual
Section 1 – Crane Procedures
Section 2 – Glossary Of Definitions
Section 3 – Crane Operations
Section 4 – Boom & Pendant Lines
Section 5 - Revisions
CCP Manual Section 1
• Section 1-A: Authorized Operator Program
• Section 1-E: Lift Planning
• Section 1-S: Site Specific Crane Management
Plan
• Section 1-Z: Incident Reporting
CCP Section 1-A: Authorized Operators
Detailed Incident Description:
The crane was being used as a concrete pile driving rig. When traveling to get the next pile, the operator lifted the
hammer in the leads about 4’ off of the ground and set his brake. Once the crane arrived at the next pile, the
crew began to rig it up with the #2 line. In the process of tightening up on the #2 line, the operator mistakenly
took the brake off of the hammer line, causing it to free fall 4’ to the ground. Upon striking the ground, the hammer
damaged three of the four lump guides and the pile gate bars. No one was within 25’ of the hammer and no one
was hurt.
Root Cause(s):
 Operator hit wrong brake release
Contributing Factors:
 Lack of concentration by the operator.
 Operator was not the daily operator on this machine. He was designated to operate the 4100 but had
been running a 999 since October 2009.
Corrective Measures/Maintenance:
 Operator was sent home for 3 days for equipment damage.
 Both pile driving crews were shut down in the morning and the incident was discussed.
 Operator will be re-designated by the jobsite Equipment Manager on the 4100 (15-3139)
 The operator will discuss the incident at the Jobsite Crane Operators meeting
 A change in crane operator will be identified on the Play of the Day. Operator shadowed the daily
operator for the day prior to running 4100.
CCP Section 1-A: Authorized Operators
CCP Section 1-A: Authorized Operators
CCP Section 1-A: Authorized Operators
CCP Section 1-A: Authorized Examiners
• Understand details of the Authorized Operator process
• Use good judgment to assess qualifications of operator
candidates
• Keep updated on procedures and regulations
• Be familiar with crane’s operator’s manuals and LMI systems
• Be consistent in applying assessment of operators; ask the
right questions
• Don’t be pressured in to not disqualifying an operator
• Don’t be afraid to ask questions; use your other resources
• Communicate to operators that they have the authority to stop
an operation if they feel it is not safe
• You are the company’s representative to decide whether a
person is qualified to operate our cranes
CCP Section 1-E: Lift Planning
Lift Planning Requirements
• Critical Lift Criteria
• Mobile Cranes
• Tower Cranes
• Overhead Cranes
CCP Section 1-E: Lift Planning
CCP Section 1-E: Lift Planning
CCP Section 1-E: Lift Planning
Planning/Approval Matrix
• Lift Types as Defined in CCP
• Planning Requirements
• Approval Requirements
CCP Section 1-E: Lift Planning
On the Spot Lift Plan Book
• Used for “General Lifts”
• Completed by Operator
• Reviewed with the Crew
• Page 1 – Under 75% of crane capacity
CCP Section 1-E: Lift Planning
On the Spot Lift Plan Book Page 2
• 75 – 85% of crane capacity
• Verification by Superintendent
• Address additional hazards
CCP Section 1-S: Site Specific Crane Management Plan
CCP Section 1-S: Site Specific Crane Management Plan
CCP Section 1-S: Site Specific Crane Management Plan
MAP Question # Risk Statement District/ Area Project
Fixed
Facility
Shared
Service
Regulatio
n
Policy Comments
Crane Safety -
Risk #1
All company owned and bare-
rented cranes are required to
have a documented daily
inspection performed by a
competent person prior to being
operated each shift. OSHA
1926.1412(d) & CCP Section 1D
   
Yes, Shift inspections are being performed for all
cranes. Project utilizing electronic DVI for cranes.
Crane Safety -
Risk #2
All company owned and bare-
rented in service cranes are
required to have a monthly
inspection performed by a
competent person. OSHA
1926.1412(e)
  
Yes, monthly inspections being scheduled and
performed.
Crane Safety -
Risk #3
Company owned and bare-
rented cranes are required to
have a current annual inspection
performed by a qualified
person. OSHA 1926.1412(f)
   
All Co. owned cranes on site have current annual
inspections.
Crane Safety -
Risk #4
Company owned and bare-
rented cranes must only be
operated by company-
authorized operators for the
type of crane assigned. CCP
Section 1A
  
All crane operators authorized for the type of crane
they are operating.
Crane Safety -
Risk #5
The company must ensure that
each signal person is qualified
prior to giving any signals, and
documentation of the signal
type qualification is available on-
site. This applies to the
Company, Subcontractors, and
3rd Parties. OSHA 1926.1428
  
Qualification documentation on site includes written
test and practical test. Needs to be more questions on
written test and more practical verification on voice
siganls. Documentation retained on project SharePoint
site. Need more visible recognition of qualified Signal
Person in the field
Crane Safety -
Risk #6
One person in the rigging
operation must be a qualified
rigger. This applies to the
Company, Subcontractors, and
3rd parties. CCP Section 1G and
Section 2H
  
Rigger qualification documentation (training sign up
sheet) maintained on project SharePoint site. Need
more visible recognition of qualified Rigger in the field.
Crane Safety -
Risk #7
Subcontractor-operated cranes
require documented daily
inspections. CCP Section 4L
  
No direct subcontractors working for the project.
Crane Safety -
Risk #8
Subcontractor-operated cranes
require documented monthly
inspections. OSHA 1926.1412(e)
  
NA
Crane Safety -
Risk #9
3rd party fully-operated cranes
require documented monthly
inspections. OSHA 1926.1412(e)
  
NA - no 3rd party fully operated cranes being used on
project.
Compliance Topic: Crane Safety - Orlando South Terminal Structures Project
Mitigation Action Plan
• Site Specific ID of risk
• Reviewed during Crane
Operation Assessments
CCP Section 1-S: Site Specific Crane Management Plan
Project Crane Operation Assessment
• Senior Personnel – Crane “experts”
• Study operations and evaluate risk areas
• Improvement suggestions to job
• 20-24 Projects per Year
Assessors:
Project:
Project Manager:
DEM:
CCM:
Crane Supervisor:
Total cranes on site
Cranes Assessed
Yes No N/A
Signalman/Rigger Documentation:
Training / qualification process in place
Does operator know who the Identified
signalman/riggers are?
Crane Condition:
Overall appearance / condition of the cranes
Copy of current physical exam
Authorization for specific crane type / manufacturer
Personnel hoisting procedure
FAA compliant - Form: 7460.1
Critical lift planning
Anti collision program In place - I.E. tower cranes
On the spot lift plan
Lift director identified
Crane set-up
Operators knowledge of CCP Manual
Lift Planning:
Crane moves (planned?)
Have all crane incidents been reported?
Assembly / disassembly director
Operators manual / load charts / CCP manual in cab
Crane Operations:
Cranes leveled and on firm ground
Machine Files (Random Check):
On-hire reports completed
Daily/monthly / annual inspection reports
Repair records / backlog current / PM
Wire rope certification available
Cab cleanliness
Visual rope condition
Crane Operator Files (Random Checks)
Authorized operator
Indoctrinated in job site safety or escorted
Job hosts:
Categories
Site Crane Manager:
Project Crane Operations Assessment
Time:
Job Location:
Date:
Proper signals being used I.E. radio communication
CCP Section 1-Z: Incident Reporting
CCP Section 1-Z: Incident Reporting
Corporate Rigging Manual
SECTION I
PERSONNEL
A. Rigger I
B. Rigger II
C. Lift Director
D. Lift Planner
E. Master Rigger
F. Engineer
G. Signal Person
H. Chain of Command / Sequence of Events
People
The knowledge, skills and abilities of persons who perform rigging tasks can enhance
the safety and efficiency of our load handling activities while also reducing the associated risks.
The capability of the person who performs rigging tasks originates with training, experience,
hands-on practice and attention to detail. The following titles are often used in the load handling
field, with the same individuals having additional craft or trade designations as pipefitters,
boilermakers, iron workers, carpenters, millwrights, mechanics and the like. For Kiewit
employees and other contract personnel who perform rigging tasks it is expected that they will
have at least one of the qualification titles below as relates to their work assignments.
Corporate Rigging Manual
Qual.
Level
NCCCO NCCER CIC
Other
Trained/Qualified
Kiewit Qualified
Rig I Approved Approved Approved Approved after
successful KQ exam
Written exam
required
Rig II Approved Approved Approved
Approved after
successful KQ
exams
Written exam,
supervision
observe work
performance
Lift
Director
Approved
Not
Available
Not
Available
Kiewit supervision
observes LD
performance
Kiewit
supervision
observes work
performance
Signal
Person
Approved Approved Approved
Approved after
successful KQ exam
Oral or written
exam,
performance test
required
Corporate Rigging Manual
Corporate Rigging Manual
Corporate Rigging Manual
SECTION II
EQUIPMENT AND ITS USE
A. Slings
B. Rigging Hardware
C. Below-the-Hook Lifting Devices
D. Hoists and Winches
E. Jacks and Industrial Rollers
F. Personnel Lifting Systems
Introduction
The following section provides information concerning the care, use and inspection
of rigging equipment. The rigger should become familiar with the manufacturers’ guidelines and
requirements as relate to usage and inspection. Repairs to any equipment should be performed
by the manufacturer, their approved repair entity or a qualified person.
Those performing rigging activities should select the rigging that best suits the application. The
rigging shall have sufficient capacity to withstand the forces imposed as created by all or a
portion of the load’s weight, its center-of-gravity and the angle of the rigging to the load. Rigging
shall be protected as applicable during its use and re-inspected before its return to a storage
location.
Corporate Rigging Manual
SECTION III
RIGGING PRACTICES
A. Load Weights
B. Center of Gravity
C. Hitch Types
D. Rigging Considerations
E. Rigging Selection and Protection
F. Rigging Capacities Using Data Charts
G. Rigging Selection Using a Tape Measure
H. Rigging from Cranes
I. Rigging with Chain Hoists
J. Rigging with Winches
K. Rigging with Jacks and Rollers
L. Crib Piles and Blocking
M. Load Turning
N. Load Uprighting
Introduction
Every rigging task should be approached by initially addressing the following three
items:
 load weight
 CG (center of gravity)
 rigging method (type, capacity, configuration and load control)
If those three elements are thoroughly evaluated, then the execution of the activity should be
fairly simple and straightforward.
Besides the ultimate rigging selection, the weight of the load often dictates which type of
machine or LHE (load handling equipment) is needed to provide the lifting, pushing or pulling
of the load during the load handling activity.
Corporate Rigging Manual
SECTION IV
PLANNING
A. Lift Considerations
B. Lift Categorization
C. General Load Handling Activities
D. Critical Load Handling Activities
Introduction
Planning is an important and integral part of the load handling process. Plans shall
be detailed enough to give the impression that the load has been moved ‘on paper’ and that
during the process, no stone was left unturned in regard to all facets of the operation. Risks
shall be identified and mitigated to allow for the safest load handling activity possible.
Corporate Rigging Manual
SECTION V
DATAAND FORMULAS
A. Capacities: Beams, Channel and Pipes
B. Pad Eyes
C. Load Angle Factors
D. Rigging Block Load Factors
E. Weights of Materials
F. Center of Gravity and Load Distribution
G. Rigging Tensions: Length / Height / Run
H. D/d Ratios
I. A2 + B2 = C2, Level & Incline Planes, Friction
J. Geometry
K. General Equations
L. Section Properties
M. Work and Energy, Temperatures and Unit Conversions
N. Sling and Rigging Hardware Capacities
O. Rigging Planning Form – 584RP
Introduction
From a planning or performing standpoint, nearly every rigging task requires some
form of calculation. Often rigging equipment can be selected based on known angles along with
the load’s weight and center of gravity. At other times, we need to closely estimate the
anticipated tension that the rigging will experience prior to the load handling activity.
Career Development - 2015
Career Development - 2015
Career Development - 2016
• Riggers
• Signal Persons
• Authorized Operators
• Front Line Supervisors
• E-Learning
• Skills/ Knowledge Verification
Career Development
• Strategic Partnerships
– Industrial Training International
• Rigging Manual
• E-Learning Modules
• Online Skills Verification
• Continuing Education Model
• Rigging Train the Trainer
– Crosby
• Online Knowledge Verification
• Live Training
• E-Learning Modules
Career Development
3 ea. Simulators
• Manitowoc
• Liebherr
• Tower
• Signal Person Integration
& Training
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System

More Related Content

What's hot

LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1Sreenath Pokkadavath
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting OperationsJames McCann
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templatesDwarika Bhushan Sharma
 
Rigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh RajputRigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh RajputGaurav Singh Rajput
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputGaurav Singh Rajput
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchHaGun Gunawan
 
SAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEASAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEAANA ISABEL R.R.
 
Lorry crane operator_handbook_1st_revision_2019
Lorry crane operator_handbook_1st_revision_2019Lorry crane operator_handbook_1st_revision_2019
Lorry crane operator_handbook_1st_revision_2019Cuong Manh Nguyen
 
CONCRETE PUMP & EXTENSION PIPELINE Form # HSEQ - CPC Rev 2.docx
CONCRETE PUMP & EXTENSION PIPELINE Form # HSEQ - CPC Rev 2.docxCONCRETE PUMP & EXTENSION PIPELINE Form # HSEQ - CPC Rev 2.docx
CONCRETE PUMP & EXTENSION PIPELINE Form # HSEQ - CPC Rev 2.docxDwarika Bhushan Sharma
 

What's hot (20)

Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
Lifting tools
Lifting toolsLifting tools
Lifting tools
 
Duties lifting supervisors
Duties lifting supervisorsDuties lifting supervisors
Duties lifting supervisors
 
Loler
LolerLoler
Loler
 
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
 
Mobile crane
Mobile craneMobile crane
Mobile crane
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
Scaffolding2. CO3.ppt
Scaffolding2. CO3.pptScaffolding2. CO3.ppt
Scaffolding2. CO3.ppt
 
Crane Rigging Safety by HF & C
Crane Rigging Safety by HF & CCrane Rigging Safety by HF & C
Crane Rigging Safety by HF & C
 
Man and machine interface
Man and machine interfaceMan and machine interface
Man and machine interface
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates
 
Rigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh RajputRigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh Rajput
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
 
Lifting practices for engineers
Lifting practices for engineersLifting practices for engineers
Lifting practices for engineers
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
SAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEASAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEA
 
Lorry crane operator_handbook_1st_revision_2019
Lorry crane operator_handbook_1st_revision_2019Lorry crane operator_handbook_1st_revision_2019
Lorry crane operator_handbook_1st_revision_2019
 
CONCRETE PUMP & EXTENSION PIPELINE Form # HSEQ - CPC Rev 2.docx
CONCRETE PUMP & EXTENSION PIPELINE Form # HSEQ - CPC Rev 2.docxCONCRETE PUMP & EXTENSION PIPELINE Form # HSEQ - CPC Rev 2.docx
CONCRETE PUMP & EXTENSION PIPELINE Form # HSEQ - CPC Rev 2.docx
 

Viewers also liked

DDS01 v.1 clr manual book
DDS01 v.1   clr manual bookDDS01 v.1   clr manual book
DDS01 v.1 clr manual bookarwicaksono
 
General Workplace Safety
General Workplace Safety General Workplace Safety
General Workplace Safety AlphaStaff
 
Safety manual.bfp a8006f
Safety manual.bfp a8006fSafety manual.bfp a8006f
Safety manual.bfp a8006fAbe Paih
 
2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS (Mike M...
2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS (Mike M...2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS (Mike M...
2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS (Mike M...Specialized Carriers & Rigging Association
 
2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS ( Randy...
2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS ( Randy...2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS ( Randy...
2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS ( Randy...Specialized Carriers & Rigging Association
 
Safety And Health Leg & Reg 2011 Asse Pdc Iv
Safety And Health Leg & Reg 2011   Asse Pdc IvSafety And Health Leg & Reg 2011   Asse Pdc Iv
Safety And Health Leg & Reg 2011 Asse Pdc IvMuhammad Akhlaq Khan
 
Fire safety and emergency evac warden manual
Fire safety and emergency evac warden manualFire safety and emergency evac warden manual
Fire safety and emergency evac warden manualbenmary07
 
Crane signal-person-training-slides
Crane signal-person-training-slidesCrane signal-person-training-slides
Crane signal-person-training-slidesAlfatih Mattar
 
Health and safety manual (last updated 11.12.15)
Health and safety manual (last updated 11.12.15)Health and safety manual (last updated 11.12.15)
Health and safety manual (last updated 11.12.15)JCurragh
 

Viewers also liked (20)

2016 CRW - Hands-on Crane Inspection
2016 CRW - Hands-on Crane Inspection2016 CRW - Hands-on Crane Inspection
2016 CRW - Hands-on Crane Inspection
 
DDS01 v.1 clr manual book
DDS01 v.1   clr manual bookDDS01 v.1   clr manual book
DDS01 v.1 clr manual book
 
Xd Manual
Xd ManualXd Manual
Xd Manual
 
General Workplace Safety
General Workplace Safety General Workplace Safety
General Workplace Safety
 
Safety manual.bfp a8006f
Safety manual.bfp a8006fSafety manual.bfp a8006f
Safety manual.bfp a8006f
 
2017 STS - COMMUNICATIONS WINS WITH STATE OFFICIALS (Danny Wells)
2017 STS - COMMUNICATIONS WINS WITH STATE OFFICIALS (Danny Wells)2017 STS - COMMUNICATIONS WINS WITH STATE OFFICIALS (Danny Wells)
2017 STS - COMMUNICATIONS WINS WITH STATE OFFICIALS (Danny Wells)
 
2017 STS - GREAT DRIVER TALENT REQUIRES GREAT DRIVER MANAGEMENT
2017 STS - GREAT DRIVER TALENT REQUIRES GREAT DRIVER MANAGEMENT2017 STS - GREAT DRIVER TALENT REQUIRES GREAT DRIVER MANAGEMENT
2017 STS - GREAT DRIVER TALENT REQUIRES GREAT DRIVER MANAGEMENT
 
2017 STS - COMMUNICATIONS WINS WITH STATE OFFICIALS (Joanna Jungels)
2017 STS - COMMUNICATIONS WINS WITH STATE OFFICIALS (Joanna Jungels)2017 STS - COMMUNICATIONS WINS WITH STATE OFFICIALS (Joanna Jungels)
2017 STS - COMMUNICATIONS WINS WITH STATE OFFICIALS (Joanna Jungels)
 
2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS (Mike M...
2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS (Mike M...2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS (Mike M...
2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS (Mike M...
 
STS 2017 - THE MITIGATION OF LITIGATION
STS 2017 - THE MITIGATION OF LITIGATION STS 2017 - THE MITIGATION OF LITIGATION
STS 2017 - THE MITIGATION OF LITIGATION
 
2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS ( Randy...
2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS ( Randy...2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS ( Randy...
2017 STS - PERFECTING THE PARTNERSHIP BETWEEN PILOT CARS AND CARRIERS ( Randy...
 
2017 STS - THE “HOW-TO” OF HARMONIZATION
2017 STS - THE “HOW-TO” OF HARMONIZATION 2017 STS - THE “HOW-TO” OF HARMONIZATION
2017 STS - THE “HOW-TO” OF HARMONIZATION
 
2017 STS - OPENING SESSION: CAPITOL CONERNS: WHAT’S BREWING IN WASHINGTON?
2017 STS - OPENING SESSION: CAPITOL CONERNS: WHAT’S BREWING IN WASHINGTON? 2017 STS - OPENING SESSION: CAPITOL CONERNS: WHAT’S BREWING IN WASHINGTON?
2017 STS - OPENING SESSION: CAPITOL CONERNS: WHAT’S BREWING IN WASHINGTON?
 
2017 STS - INSURANCE FOR AN UNCERTAIN FUTURE
2017 STS - INSURANCE FOR AN UNCERTAIN FUTURE2017 STS - INSURANCE FOR AN UNCERTAIN FUTURE
2017 STS - INSURANCE FOR AN UNCERTAIN FUTURE
 
2016 CRW - The ELD Mandate: The Time has Come
2016 CRW - The ELD Mandate: The Time has Come2016 CRW - The ELD Mandate: The Time has Come
2016 CRW - The ELD Mandate: The Time has Come
 
Safety And Health Leg & Reg 2011 Asse Pdc Iv
Safety And Health Leg & Reg 2011   Asse Pdc IvSafety And Health Leg & Reg 2011   Asse Pdc Iv
Safety And Health Leg & Reg 2011 Asse Pdc Iv
 
2016 CRW - Keynote Session: Driving Best Practices in Business Development
2016 CRW - Keynote Session: Driving Best Practices in Business Development2016 CRW - Keynote Session: Driving Best Practices in Business Development
2016 CRW - Keynote Session: Driving Best Practices in Business Development
 
Fire safety and emergency evac warden manual
Fire safety and emergency evac warden manualFire safety and emergency evac warden manual
Fire safety and emergency evac warden manual
 
Crane signal-person-training-slides
Crane signal-person-training-slidesCrane signal-person-training-slides
Crane signal-person-training-slides
 
Health and safety manual (last updated 11.12.15)
Health and safety manual (last updated 11.12.15)Health and safety manual (last updated 11.12.15)
Health and safety manual (last updated 11.12.15)
 

Similar to 2016 CRW - An inside look at Kiewit's Crane & Rigging Management System

10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2Sergio Augusto Esteves
 
Rigging Requirements Training by L&I Washington
Rigging Requirements Training by L&I WashingtonRigging Requirements Training by L&I Washington
Rigging Requirements Training by L&I WashingtonAtlantic Training, LLC.
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sitesPrastowo Priyatmoko
 
const_cranes_090310 (1).ppt
const_cranes_090310 (1).pptconst_cranes_090310 (1).ppt
const_cranes_090310 (1).pptRonald Aranha
 
Pr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning executionPr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning executionSergio Augusto Esteves
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templatesDwarika Bhushan Sharma
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdfdinesh622857
 
22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templatesDwarika Bhushan Sharma
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docxDwarika Bhushan Sharma
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Dnyaneshwar_Sonawane CV
Dnyaneshwar_Sonawane CVDnyaneshwar_Sonawane CV
Dnyaneshwar_Sonawane CVNANDLAL PRASAD
 
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetySafe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetyAtlantic Training, LLC.
 

Similar to 2016 CRW - An inside look at Kiewit's Crane & Rigging Management System (20)

10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2
 
HSE
HSEHSE
HSE
 
Rigging Requirements Training by L&I Washington
Rigging Requirements Training by L&I WashingtonRigging Requirements Training by L&I Washington
Rigging Requirements Training by L&I Washington
 
Rigger safety .pdf
Rigger safety                        .pdfRigger safety                        .pdf
Rigger safety .pdf
 
Rigging Course .pdf
Rigging Course                       .pdfRigging Course                       .pdf
Rigging Course .pdf
 
Eswaran-CV
Eswaran-CVEswaran-CV
Eswaran-CV
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites
 
const_cranes_090310 (1).ppt
const_cranes_090310 (1).pptconst_cranes_090310 (1).ppt
const_cranes_090310 (1).ppt
 
Pr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning executionPr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning execution
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdf
 
22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates
 
2018 CRW: Engineered Lift Plans From A to Z
2018 CRW: Engineered Lift Plans From A to Z2018 CRW: Engineered Lift Plans From A to Z
2018 CRW: Engineered Lift Plans From A to Z
 
2015 CRW - New Crane Rules = New Compliance Directives
 2015 CRW - New Crane Rules = New Compliance Directives 2015 CRW - New Crane Rules = New Compliance Directives
2015 CRW - New Crane Rules = New Compliance Directives
 
Dustin L. Marshall's Resume
Dustin L. Marshall's ResumeDustin L. Marshall's Resume
Dustin L. Marshall's Resume
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
Dnyaneshwar_Sonawane CV
Dnyaneshwar_Sonawane CVDnyaneshwar_Sonawane CV
Dnyaneshwar_Sonawane CV
 
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetySafe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
 

More from Specialized Carriers & Rigging Association

2019 CRW - Inside Scoop: How Crane Operator Certification and Evaluation is R...
2019 CRW - Inside Scoop: How Crane Operator Certification and Evaluation is R...2019 CRW - Inside Scoop: How Crane Operator Certification and Evaluation is R...
2019 CRW - Inside Scoop: How Crane Operator Certification and Evaluation is R...Specialized Carriers & Rigging Association
 
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...Specialized Carriers & Rigging Association
 
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...Specialized Carriers & Rigging Association
 
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...Specialized Carriers & Rigging Association
 
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...Specialized Carriers & Rigging Association
 

More from Specialized Carriers & Rigging Association (20)

2019 CRW: How the Latest Regulations Impact Your Business
2019 CRW: How the Latest Regulations Impact Your Business2019 CRW: How the Latest Regulations Impact Your Business
2019 CRW: How the Latest Regulations Impact Your Business
 
2019 CRW - Understanding Ground Bearing Capacities (Mike Walsh presentation)
2019 CRW - Understanding Ground Bearing Capacities (Mike Walsh presentation)2019 CRW - Understanding Ground Bearing Capacities (Mike Walsh presentation)
2019 CRW - Understanding Ground Bearing Capacities (Mike Walsh presentation)
 
2019 CRW - Insurance Q&A: Ask the Industry Expert
2019 CRW - Insurance Q&A: Ask the Industry Expert2019 CRW - Insurance Q&A: Ask the Industry Expert
2019 CRW - Insurance Q&A: Ask the Industry Expert
 
2019 CRW - How to Use Data to Revitalize Your Marketing
2019 CRW - How to Use Data to Revitalize Your Marketing2019 CRW - How to Use Data to Revitalize Your Marketing
2019 CRW - How to Use Data to Revitalize Your Marketing
 
2019 CRW - Tech Trends in Crane & Rigging (David Thorton presentation)
2019 CRW - Tech Trends in Crane & Rigging (David Thorton presentation)2019 CRW - Tech Trends in Crane & Rigging (David Thorton presentation)
2019 CRW - Tech Trends in Crane & Rigging (David Thorton presentation)
 
2019 CRW - Tech Trends in Crane & Rigging (Ted Blanton presentation)
2019 CRW - Tech Trends in Crane & Rigging (Ted Blanton presentation)2019 CRW - Tech Trends in Crane & Rigging (Ted Blanton presentation)
2019 CRW - Tech Trends in Crane & Rigging (Ted Blanton presentation)
 
2019 CRW - Tech Trends in Crane & Rigging (Tawnia Weiss presentation)
2019 CRW - Tech Trends in Crane & Rigging (Tawnia Weiss presentation)2019 CRW - Tech Trends in Crane & Rigging (Tawnia Weiss presentation)
2019 CRW - Tech Trends in Crane & Rigging (Tawnia Weiss presentation)
 
2019 CRW - Inside Scoop: How Crane Operator Certification and Evaluation is R...
2019 CRW - Inside Scoop: How Crane Operator Certification and Evaluation is R...2019 CRW - Inside Scoop: How Crane Operator Certification and Evaluation is R...
2019 CRW - Inside Scoop: How Crane Operator Certification and Evaluation is R...
 
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
 
2019 CRW - Understanding Ground Bearing Capacities (Jeff Steiner presentation)
2019 CRW - Understanding Ground Bearing Capacities (Jeff Steiner presentation)2019 CRW - Understanding Ground Bearing Capacities (Jeff Steiner presentation)
2019 CRW - Understanding Ground Bearing Capacities (Jeff Steiner presentation)
 
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
 
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
 
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
2019 CRW - Navigating the Haze of Legalized Marijuana in the Construction Ind...
 
2019 CRW: Sample ELD Policy (Dave Osiecki session)
2019 CRW: Sample ELD Policy (Dave Osiecki session)2019 CRW: Sample ELD Policy (Dave Osiecki session)
2019 CRW: Sample ELD Policy (Dave Osiecki session)
 
2019 CRW: PC Guidance Article (Dave Osiecki session)
2019 CRW: PC Guidance Article (Dave Osiecki session)2019 CRW: PC Guidance Article (Dave Osiecki session)
2019 CRW: PC Guidance Article (Dave Osiecki session)
 
2019 CRW: Clearinghouse Policy Update (Dave Osiecki session)
2019 CRW: Clearinghouse Policy Update (Dave Osiecki session)2019 CRW: Clearinghouse Policy Update (Dave Osiecki session)
2019 CRW: Clearinghouse Policy Update (Dave Osiecki session)
 
2019 CRW Tower Crane Committee Meeting
2019 CRW Tower Crane Committee Meeting2019 CRW Tower Crane Committee Meeting
2019 CRW Tower Crane Committee Meeting
 
2019 CRW Safety Education & Training Committee Meeting
2019 CRW Safety Education & Training Committee Meeting2019 CRW Safety Education & Training Committee Meeting
2019 CRW Safety Education & Training Committee Meeting
 
2019 CRW Labor Committee Meeting
2019 CRW Labor Committee Meeting2019 CRW Labor Committee Meeting
2019 CRW Labor Committee Meeting
 
2019 CRW Governing Committee Meeting
2019 CRW Governing Committee Meeting2019 CRW Governing Committee Meeting
2019 CRW Governing Committee Meeting
 

Recently uploaded

Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 

Recently uploaded (20)

Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 

2016 CRW - An inside look at Kiewit's Crane & Rigging Management System

  • 1. Kiewit Crane & Rigging Management Bret Shields
  • 2.
  • 3.
  • 4.
  • 5.
  • 6.
  • 7. • Corporate Crane Procedures Manual • Corporate Rigging Manual • Career Development
  • 8. Corporate Crane Procedures Manual Section 1 – Crane Procedures Section 2 – Glossary Of Definitions Section 3 – Crane Operations Section 4 – Boom & Pendant Lines Section 5 - Revisions
  • 9. CCP Manual Section 1 • Section 1-A: Authorized Operator Program • Section 1-E: Lift Planning • Section 1-S: Site Specific Crane Management Plan • Section 1-Z: Incident Reporting
  • 10. CCP Section 1-A: Authorized Operators
  • 11. Detailed Incident Description: The crane was being used as a concrete pile driving rig. When traveling to get the next pile, the operator lifted the hammer in the leads about 4’ off of the ground and set his brake. Once the crane arrived at the next pile, the crew began to rig it up with the #2 line. In the process of tightening up on the #2 line, the operator mistakenly took the brake off of the hammer line, causing it to free fall 4’ to the ground. Upon striking the ground, the hammer damaged three of the four lump guides and the pile gate bars. No one was within 25’ of the hammer and no one was hurt. Root Cause(s):  Operator hit wrong brake release Contributing Factors:  Lack of concentration by the operator.  Operator was not the daily operator on this machine. He was designated to operate the 4100 but had been running a 999 since October 2009. Corrective Measures/Maintenance:  Operator was sent home for 3 days for equipment damage.  Both pile driving crews were shut down in the morning and the incident was discussed.  Operator will be re-designated by the jobsite Equipment Manager on the 4100 (15-3139)  The operator will discuss the incident at the Jobsite Crane Operators meeting  A change in crane operator will be identified on the Play of the Day. Operator shadowed the daily operator for the day prior to running 4100.
  • 12.
  • 13. CCP Section 1-A: Authorized Operators
  • 14. CCP Section 1-A: Authorized Operators
  • 15. CCP Section 1-A: Authorized Operators
  • 16. CCP Section 1-A: Authorized Examiners • Understand details of the Authorized Operator process • Use good judgment to assess qualifications of operator candidates • Keep updated on procedures and regulations • Be familiar with crane’s operator’s manuals and LMI systems • Be consistent in applying assessment of operators; ask the right questions • Don’t be pressured in to not disqualifying an operator • Don’t be afraid to ask questions; use your other resources • Communicate to operators that they have the authority to stop an operation if they feel it is not safe • You are the company’s representative to decide whether a person is qualified to operate our cranes
  • 17. CCP Section 1-E: Lift Planning Lift Planning Requirements • Critical Lift Criteria • Mobile Cranes • Tower Cranes • Overhead Cranes
  • 18. CCP Section 1-E: Lift Planning
  • 19. CCP Section 1-E: Lift Planning
  • 20. CCP Section 1-E: Lift Planning Planning/Approval Matrix • Lift Types as Defined in CCP • Planning Requirements • Approval Requirements
  • 21. CCP Section 1-E: Lift Planning On the Spot Lift Plan Book • Used for “General Lifts” • Completed by Operator • Reviewed with the Crew • Page 1 – Under 75% of crane capacity
  • 22. CCP Section 1-E: Lift Planning On the Spot Lift Plan Book Page 2 • 75 – 85% of crane capacity • Verification by Superintendent • Address additional hazards
  • 23. CCP Section 1-S: Site Specific Crane Management Plan
  • 24. CCP Section 1-S: Site Specific Crane Management Plan
  • 25. CCP Section 1-S: Site Specific Crane Management Plan MAP Question # Risk Statement District/ Area Project Fixed Facility Shared Service Regulatio n Policy Comments Crane Safety - Risk #1 All company owned and bare- rented cranes are required to have a documented daily inspection performed by a competent person prior to being operated each shift. OSHA 1926.1412(d) & CCP Section 1D     Yes, Shift inspections are being performed for all cranes. Project utilizing electronic DVI for cranes. Crane Safety - Risk #2 All company owned and bare- rented in service cranes are required to have a monthly inspection performed by a competent person. OSHA 1926.1412(e)    Yes, monthly inspections being scheduled and performed. Crane Safety - Risk #3 Company owned and bare- rented cranes are required to have a current annual inspection performed by a qualified person. OSHA 1926.1412(f)     All Co. owned cranes on site have current annual inspections. Crane Safety - Risk #4 Company owned and bare- rented cranes must only be operated by company- authorized operators for the type of crane assigned. CCP Section 1A    All crane operators authorized for the type of crane they are operating. Crane Safety - Risk #5 The company must ensure that each signal person is qualified prior to giving any signals, and documentation of the signal type qualification is available on- site. This applies to the Company, Subcontractors, and 3rd Parties. OSHA 1926.1428    Qualification documentation on site includes written test and practical test. Needs to be more questions on written test and more practical verification on voice siganls. Documentation retained on project SharePoint site. Need more visible recognition of qualified Signal Person in the field Crane Safety - Risk #6 One person in the rigging operation must be a qualified rigger. This applies to the Company, Subcontractors, and 3rd parties. CCP Section 1G and Section 2H    Rigger qualification documentation (training sign up sheet) maintained on project SharePoint site. Need more visible recognition of qualified Rigger in the field. Crane Safety - Risk #7 Subcontractor-operated cranes require documented daily inspections. CCP Section 4L    No direct subcontractors working for the project. Crane Safety - Risk #8 Subcontractor-operated cranes require documented monthly inspections. OSHA 1926.1412(e)    NA Crane Safety - Risk #9 3rd party fully-operated cranes require documented monthly inspections. OSHA 1926.1412(e)    NA - no 3rd party fully operated cranes being used on project. Compliance Topic: Crane Safety - Orlando South Terminal Structures Project Mitigation Action Plan • Site Specific ID of risk • Reviewed during Crane Operation Assessments
  • 26. CCP Section 1-S: Site Specific Crane Management Plan Project Crane Operation Assessment • Senior Personnel – Crane “experts” • Study operations and evaluate risk areas • Improvement suggestions to job • 20-24 Projects per Year Assessors: Project: Project Manager: DEM: CCM: Crane Supervisor: Total cranes on site Cranes Assessed Yes No N/A Signalman/Rigger Documentation: Training / qualification process in place Does operator know who the Identified signalman/riggers are? Crane Condition: Overall appearance / condition of the cranes Copy of current physical exam Authorization for specific crane type / manufacturer Personnel hoisting procedure FAA compliant - Form: 7460.1 Critical lift planning Anti collision program In place - I.E. tower cranes On the spot lift plan Lift director identified Crane set-up Operators knowledge of CCP Manual Lift Planning: Crane moves (planned?) Have all crane incidents been reported? Assembly / disassembly director Operators manual / load charts / CCP manual in cab Crane Operations: Cranes leveled and on firm ground Machine Files (Random Check): On-hire reports completed Daily/monthly / annual inspection reports Repair records / backlog current / PM Wire rope certification available Cab cleanliness Visual rope condition Crane Operator Files (Random Checks) Authorized operator Indoctrinated in job site safety or escorted Job hosts: Categories Site Crane Manager: Project Crane Operations Assessment Time: Job Location: Date: Proper signals being used I.E. radio communication
  • 27. CCP Section 1-Z: Incident Reporting
  • 28. CCP Section 1-Z: Incident Reporting
  • 29.
  • 30. Corporate Rigging Manual SECTION I PERSONNEL A. Rigger I B. Rigger II C. Lift Director D. Lift Planner E. Master Rigger F. Engineer G. Signal Person H. Chain of Command / Sequence of Events People The knowledge, skills and abilities of persons who perform rigging tasks can enhance the safety and efficiency of our load handling activities while also reducing the associated risks. The capability of the person who performs rigging tasks originates with training, experience, hands-on practice and attention to detail. The following titles are often used in the load handling field, with the same individuals having additional craft or trade designations as pipefitters, boilermakers, iron workers, carpenters, millwrights, mechanics and the like. For Kiewit employees and other contract personnel who perform rigging tasks it is expected that they will have at least one of the qualification titles below as relates to their work assignments.
  • 31. Corporate Rigging Manual Qual. Level NCCCO NCCER CIC Other Trained/Qualified Kiewit Qualified Rig I Approved Approved Approved Approved after successful KQ exam Written exam required Rig II Approved Approved Approved Approved after successful KQ exams Written exam, supervision observe work performance Lift Director Approved Not Available Not Available Kiewit supervision observes LD performance Kiewit supervision observes work performance Signal Person Approved Approved Approved Approved after successful KQ exam Oral or written exam, performance test required
  • 34. Corporate Rigging Manual SECTION II EQUIPMENT AND ITS USE A. Slings B. Rigging Hardware C. Below-the-Hook Lifting Devices D. Hoists and Winches E. Jacks and Industrial Rollers F. Personnel Lifting Systems Introduction The following section provides information concerning the care, use and inspection of rigging equipment. The rigger should become familiar with the manufacturers’ guidelines and requirements as relate to usage and inspection. Repairs to any equipment should be performed by the manufacturer, their approved repair entity or a qualified person. Those performing rigging activities should select the rigging that best suits the application. The rigging shall have sufficient capacity to withstand the forces imposed as created by all or a portion of the load’s weight, its center-of-gravity and the angle of the rigging to the load. Rigging shall be protected as applicable during its use and re-inspected before its return to a storage location.
  • 35. Corporate Rigging Manual SECTION III RIGGING PRACTICES A. Load Weights B. Center of Gravity C. Hitch Types D. Rigging Considerations E. Rigging Selection and Protection F. Rigging Capacities Using Data Charts G. Rigging Selection Using a Tape Measure H. Rigging from Cranes I. Rigging with Chain Hoists J. Rigging with Winches K. Rigging with Jacks and Rollers L. Crib Piles and Blocking M. Load Turning N. Load Uprighting Introduction Every rigging task should be approached by initially addressing the following three items:  load weight  CG (center of gravity)  rigging method (type, capacity, configuration and load control) If those three elements are thoroughly evaluated, then the execution of the activity should be fairly simple and straightforward. Besides the ultimate rigging selection, the weight of the load often dictates which type of machine or LHE (load handling equipment) is needed to provide the lifting, pushing or pulling of the load during the load handling activity.
  • 36. Corporate Rigging Manual SECTION IV PLANNING A. Lift Considerations B. Lift Categorization C. General Load Handling Activities D. Critical Load Handling Activities Introduction Planning is an important and integral part of the load handling process. Plans shall be detailed enough to give the impression that the load has been moved ‘on paper’ and that during the process, no stone was left unturned in regard to all facets of the operation. Risks shall be identified and mitigated to allow for the safest load handling activity possible.
  • 37. Corporate Rigging Manual SECTION V DATAAND FORMULAS A. Capacities: Beams, Channel and Pipes B. Pad Eyes C. Load Angle Factors D. Rigging Block Load Factors E. Weights of Materials F. Center of Gravity and Load Distribution G. Rigging Tensions: Length / Height / Run H. D/d Ratios I. A2 + B2 = C2, Level & Incline Planes, Friction J. Geometry K. General Equations L. Section Properties M. Work and Energy, Temperatures and Unit Conversions N. Sling and Rigging Hardware Capacities O. Rigging Planning Form – 584RP Introduction From a planning or performing standpoint, nearly every rigging task requires some form of calculation. Often rigging equipment can be selected based on known angles along with the load’s weight and center of gravity. At other times, we need to closely estimate the anticipated tension that the rigging will experience prior to the load handling activity.
  • 38.
  • 41. Career Development - 2016 • Riggers • Signal Persons • Authorized Operators • Front Line Supervisors • E-Learning • Skills/ Knowledge Verification
  • 42. Career Development • Strategic Partnerships – Industrial Training International • Rigging Manual • E-Learning Modules • Online Skills Verification • Continuing Education Model • Rigging Train the Trainer – Crosby • Online Knowledge Verification • Live Training • E-Learning Modules
  • 43. Career Development 3 ea. Simulators • Manitowoc • Liebherr • Tower • Signal Person Integration & Training