SlideShare a Scribd company logo
1 of 37
Construction Crane Safety
(new requirements 2010)
September 2, 2010
Why?
• Crane accidents killed an average of 78
people per year between 2003 and 2005
• The new standard is located at
http://www.federalregister.gov/articles/201
0/08/09/2010-17818/cranes-and-derricks-
in-construction#h-15
• OSHA expects the final standard to
prevent 22 fatalities and 175 non-fatal
injuries each year.
When?
• Intention to develop the rule in July 2002.
• Used negotiated rulemaking committee
consisting both industry and labor.
• The committee completed its work in 2004.
• Released – July 28, 2010
• Published – August 9, 2010
• Effective – November 8, 2010
• Phased in over four years – August 9, 2014
– Certification of operators phased in over four years.
No grandfathering of those past certification.
Key Hazards
• Four main causes of worker death and
injury:
• Electrocution,
• Crushed by parts of the equipment,
• Struck-by the equipment/load, and
• Falls. (See Subpart M 1926.500-503)
Largest Impact
• Mandatory crane operator certification -
qualification
• 200,000 construction crane operators in
the industry
• OSHA allowing four years to meet the
certification requirement.
• It will take time for certifying organizations
to gain enough capacity to cover so many
operators.
Other Significant Requirements
• Use of synthetic slings in accordance with
the manufacturer’s instructions during
assembly/disassembly work;
• Assessment of ground conditions;
• Procedures for working in the vicinity of
power lines.
• Pre-erection inspection of tower crane
parts;
OSHA – State - Local
• Employers must comply with local and
state operator licensing requirements
which meet the minimum criteria specified
in § 1926.1427.
• Some state had existing Crane standards
that exceeded the old standard. In state
plan states, please see the rules for that
state.
Who Pays?
• Employers must pay for certification or
qualification of their currently uncertified or
unqualified operators. 1926.1427 (a)(4)
• Reasonable that employees, who have already
been sufficiently trained in crane operation and
may have many years' experience, certainly
need no more than a short preparation to
successfully pass the crane operator certification
tests. – FR Preamble
Crane or Not Crane?
• Functional description
– Can hoist,
– Lower and
– Horizontally move a
suspended load
• Forklifts configured to hoist
and lower (by means of a
winch OR hook) and
horizontally move a suspended
load are covered
• Backhoes are excluded even if
used like a crane….1926.1400
(c)(2)
Forklift with attached
boom. 1926.1400 (c)(8)
See 1926.1441 if using
equipment with a rated
hoisting/lifting capacity of 2,000
pounds or less
10
• OPTION 1:
Accredited testing organization
• OPTION 2:
Employer qualification program
• OPTION 3:
U.S. military
• OPTION 4:
State/local gov’t license
Operator Qualifications and
Certifications - 4 Options
11
Operator Qualifications and
Certifications (cont’d)
Accredited testing
organization
YES * 5 years
Employer Qualification
Program
NO 5 years
US Military license NO * Set by issuing
entity
State/local license NO *
Valid only
in entity’s
jurisdiction
Set by issuing
entity, not > 5
years
Portable Valid
Written Certification Tests
• Administered in any language understood
by the operator candidate.
• Test must cover:
– Controls/performance characteristics
– Calculate capacity (w/ or w/out calculator)
– Preventing power line contact
– Ground support
– Read and locate info in operating manual
– Appendix Q subjects
Practical Examination
• Must be well designed and sufficiently
comprehensive
• Must have the demonstrated the skills and
knowledge needed to operate the equipment
safely.
• An operator's ability to handle unusual worksite
conditions, such as adverse weather or working
on crowded jobsites, are hazards that are not
commonly part of this exam.
14
1926.1408 Power Lines
• Step 1: Identify Work
Zone
– Work Zone = Marking
boundaries OR
– 360 degrees around
crane up to maximum
working radius
– Make the power line
hazard assessment
15
Could you get within 20
feet of power line?
YES NO
Option #1
Deenergize &
Ground
Encroachment
Prevention measures
Option #3
Ask Utility for
Voltage and
Use Table A
(with minimum
clearance distance)
Option #2
20 foot
clearance
No further
action
• Planning meeting
• If tag lines used Non-conductive
• Elevated warning lines, barricade
or line of signs
•PLUS (Choose one):
• Proximity alarm, spotter, warning
device, range limiter, or insulating link
16
Table A – Minimum Clearance Distances
Voltage (nominal, kV,
alternating current)
Minimum clearance
distance (feet)
up to 50 10
over 50 to 200 15
over 200 to 350 20
over 350 to 500 25
over 500 to 750 35
over 750 to 1000 45
over 1000 (as established by the power line
owner/operator or registered
professional engineer who is a
qualified person with respect to
electrical power transmission and
distribution)
Intentionally Working Closer
Than Table A Zone 1910.1410
• Paragraph (b) requires the employer to consult
with the utility owner/operator before deciding
that it infeasible to deenergize and ground the
lines or relocate them.
• Employer can establish this distance by either
having the utility owner/operator determine
the minimum clearance distance that must be
maintained or by having a registered
professional engineer who is a qualified
person with respect to electrical transmission
and distribution determine the minimum
clearance distance that must be maintained.
18
Must show:
• Staying outside zone
is infeasible
• Infeasible to
deenergize and
ground
Intentionally Working Closer Than Table A Zone
All of the following are required:
1. PL owner – sets minimum approach
distance
2. Planning meeting – procedures
3. Dedicated spotter
4. Elevated warning line or barricade
5. Insulating link/device
6. Non-conductive rigging
7. Range limiter (if equipped)
8. Non-conductive tag line (if used)
9. Barricades - 10 feet from equipment
10. Limit access to essential employees
11. Ground crane
12. Deactivate automatic re-energizer
1926.1410
Assembly Disassembly
• Employers must use a qualified rigger for
rigging operations during assembly &
disassembly
• Two options:
– Manufacturer procedures or
– Employer procedures (criteria requirements)
Assembly/Disassembly Supervisor
• Must understand procedures
• Review procedures (unless they’ve used
them before)
• Check that crew members understand
their tasks, hazards
• Follow manufacturer’s prohibitions
• When using outriggers - fully extended or
deployed per the load chart
21
• A/D supervisor addresses 12 key hazards,
including:
– Adequate site and ground conditions
– Sufficient blocking for load and stability
– Suitable boom and jib pick points
– Identify center of gravity
– Stability for pin removal
– Consider wind speed and weather
Assembly/Disassembly (cont’d)
22
• The suitability of blocking material
• Verification of the loads for assist cranes
• Snagging of cables or components
• Struck by counter weights
• Boom hoist brake failure
• Loss of backwards stability
Assembly/Disassembly (cont’d)
Qualified Rigger
• 1926.1404 (r)
• Meets the criteria for a qualified person
• Possession of a recognized degree,
certificate, or professional standing, or
extensive (rigging) knowledge, training
and experience
• Successfully demonstrated the ability to
solve/resolve problems (relating to rigging)
Tower Cranes
• Employers must perform a pre-erection
inspection of tower cranes.
• Extensive requirements under 1926.1435
and other sections.
• Beyond scope of this presentation
• Numerous accidents such as Seattle in
85, San Francisco in 89, Manhattan in 08,
Hong Kong in 08, New York in 06,
Ground Conditions
• 1926.1402 (b)
• Ground conditions must be firm, drained,
and graded
• Use supporting materials,
• Use equipment manufacturer's
specifications for adequate support
• Use equipment manufacturer's
specifications for degree of level of the
equipment
Controlling Entity
• 1926.1402 (c)(3)
• Must ensure that ground preparations are safe
• Must inform the user of the equipment and the
operator of the location of known hazards
beneath the equipment set-up area (such as
voids, tanks, utilities)
• If there is no controlling entity then the employer
that has authority at the site to make or arrange
for ground preparations must do so.
27
Signals
• Signal person –
when required:
– Point of operation not
in full view of operator
– View of direction of
travel is obstructed
– Site specific safety
concerns
– 1926.1428 Signal
person qualifications
• Signal Types:
– Hand, voice, audible
or “new”
– Only time an operator
can use a cell phone is
while lifting as part of a
planned procedure
28
Signals (cont’d.)
• Signal person qualifications
3rd party qualified
evaluator
Yes Yes
Employer Qualified
Evaluator
Yes No
Qualified how Documentation Portable
29
• Qualification
Requirements:
– Know & understand signals
– Competent in using signals
– Basic understanding of crane
operation
– Verbal or written test +
practical test
Signals (cont’d.)
30
1926.1412 Inspections
Modified or Repaired/
adjusted
Qualified
Post-assembly Qualified
Shift Competent
Monthly Competent
Annual Qualified
Type of Inspection: Who Inspects:
31
Inspections (cont’d)
• Shift = visual inspection for apparent
deficiencies
• Monthly = documented shift inspection
• Annual = comprehensive, every 12 months
Each Shift Inspection
• 1926.1412 (d)
• Apparent deficiencies
• Control and Drive
mechanisms
• Hydraulics
• Hooks
• Wire Rope
• Electrical
• Ground Conditions
• Levelness of the
crane
• Operator view
• All Safety Devices
• Operational Aids are
working
Operators
• 1926.1417 has many requirements. Some highlights are:
• Must not engage in any activity that diverts his/her
attention while operating the equipment,
• No cell phones (other than when used for signal
communications)
• Must not leave the controls while the load is
suspended, (four exceptions)
• Must verify that the load is within the rated capacity of
the equipment (2 methods)
• Must obey a stop (or emergency stop) signal,
irrespective of who gives it.
• Told of any employee entering the crane work area
1926.1424(a)(3)
Employer Training
• 1926.1430 Employee
Training Issues
• Powerline safety
• Signal persons
• Operators
• Competent Person
• Qualified Persons
• Crush Pinch point
hazards
• Tagout for repair
• Must confirm that the
employee understands
the information provided
in the training
• Provide the training at no
cost to the employee
Work Area Control
• 1926.1424
• Train each employee assigned to work on
or near the equipment
• Erect and maintain control lines, warning
lines, railings or similar barriers to mark
the boundaries of the hazard area (1
Exception)
36
Resources
• Cranes and Derricks in Construction Final Rule
– http://www.osha.gov/cranes-derricks/index.html
• Associated Training Service Network
– http://www.operator-school.com/
• National Commission for the Certification of Crane Operators
– http://www.nccco.org/
• National Association of Heavy Equipment Training Schools
– http://www.heavy-equipment-school.com/
• North American Crane Bureau Group
– http://www.cranesafe.com/history.htm
• California Crane School
– http://www.californiacraneschool.com/
Further
• This ppt was prepared by John Newquist as a preliminary aid for the new
standard. Please check the OSHA website for Crane Outreach Material that
will be developed in the coming months.
• This is not an official OSHA publication. Those will be on the OSHA.gov
website.
• Newquist.john@dol.gov is my email if you see any errors
• 312-353-5977
• Brian Sturtecky is our Region V Certified Crane Inspector and has provided
key assistance on this standard. He can be reached at 312-353-2220.
• Several slides were obtained from the OSHA Training Institute from their
Webinar August 30, 2010.
• Every aspect from inspecting, repairing, operating, rigging and signaling
these cranes require extensive training. Please take classes with hands on
training if you are expected to perform any of these activities.
• I want to thank Brian, Lisa, Tom, Bill, Cathy for all their assistance in
answering questions and providing issues that are coming from the public.

More Related Content

Similar to const_cranes_090310 (1).ppt

Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptxAizazFarhat3
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdfdinesh622857
 
Crane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxCrane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxVikasMore37
 
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLift Events
 
HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...AhmedAliKhan38
 
Nimonik Expert EHS Series: Rack Safety and Compliance
Nimonik Expert EHS Series: Rack Safety and ComplianceNimonik Expert EHS Series: Rack Safety and Compliance
Nimonik Expert EHS Series: Rack Safety and ComplianceNimonik
 
Change- out P119 Pulley-2
Change- out P119 Pulley-2Change- out P119 Pulley-2
Change- out P119 Pulley-2Scott Jarrold
 
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetySafe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetyAtlantic Training, LLC.
 
Lockout tagout
Lockout tagoutLockout tagout
Lockout tagoutMary Helen
 
BOCW my Version.pptx
BOCW my Version.pptxBOCW my Version.pptx
BOCW my Version.pptxSuresh459496
 
loto.ppt
loto.pptloto.ppt
loto.pptmurrtex
 
Crane_&_Sling_baysrgrys wyruyv egeryuey1.ppt
Crane_&_Sling_baysrgrys wyruyv egeryuey1.pptCrane_&_Sling_baysrgrys wyruyv egeryuey1.ppt
Crane_&_Sling_baysrgrys wyruyv egeryuey1.pptSurajAmbekar7
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2Sergio Augusto Esteves
 
Plant & Machinery Training
Plant & Machinery TrainingPlant & Machinery Training
Plant & Machinery TrainingMJ Conroy Group
 

Similar to const_cranes_090310 (1).ppt (20)

Chapter 08
Chapter 08Chapter 08
Chapter 08
 
ADO-A Chapter 08
ADO-A Chapter 08ADO-A Chapter 08
ADO-A Chapter 08
 
Lifting Operation.ppt
Lifting Operation.pptLifting Operation.ppt
Lifting Operation.ppt
 
Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptx
 
2015 CRW - New Crane Rules = New Compliance Directives
 2015 CRW - New Crane Rules = New Compliance Directives 2015 CRW - New Crane Rules = New Compliance Directives
2015 CRW - New Crane Rules = New Compliance Directives
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdf
 
Crane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxCrane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptx
 
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
 
HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...
 
Nimonik Expert EHS Series: Rack Safety and Compliance
Nimonik Expert EHS Series: Rack Safety and ComplianceNimonik Expert EHS Series: Rack Safety and Compliance
Nimonik Expert EHS Series: Rack Safety and Compliance
 
Darren Johnson CV
Darren Johnson CVDarren Johnson CV
Darren Johnson CV
 
HSE
HSEHSE
HSE
 
Change- out P119 Pulley-2
Change- out P119 Pulley-2Change- out P119 Pulley-2
Change- out P119 Pulley-2
 
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetySafe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
 
Lockout tagout
Lockout tagoutLockout tagout
Lockout tagout
 
BOCW my Version.pptx
BOCW my Version.pptxBOCW my Version.pptx
BOCW my Version.pptx
 
loto.ppt
loto.pptloto.ppt
loto.ppt
 
Crane_&_Sling_baysrgrys wyruyv egeryuey1.ppt
Crane_&_Sling_baysrgrys wyruyv egeryuey1.pptCrane_&_Sling_baysrgrys wyruyv egeryuey1.ppt
Crane_&_Sling_baysrgrys wyruyv egeryuey1.ppt
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2
 
Plant & Machinery Training
Plant & Machinery TrainingPlant & Machinery Training
Plant & Machinery Training
 

More from Ronald Aranha

Chapter 17 Technical Instructions.ppt
Chapter 17  Technical Instructions.pptChapter 17  Technical Instructions.ppt
Chapter 17 Technical Instructions.pptRonald Aranha
 
Chapter 16 Email and Instant Messaging.ppt
Chapter 16 Email and Instant Messaging.pptChapter 16 Email and Instant Messaging.ppt
Chapter 16 Email and Instant Messaging.pptRonald Aranha
 
RCA-Guidebook-Accompanying-SlideDeck_Feb_2021.pptx
RCA-Guidebook-Accompanying-SlideDeck_Feb_2021.pptxRCA-Guidebook-Accompanying-SlideDeck_Feb_2021.pptx
RCA-Guidebook-Accompanying-SlideDeck_Feb_2021.pptxRonald Aranha
 
fy11_sh-22297-11_HeavyEquipmentSafety.pptx
fy11_sh-22297-11_HeavyEquipmentSafety.pptxfy11_sh-22297-11_HeavyEquipmentSafety.pptx
fy11_sh-22297-11_HeavyEquipmentSafety.pptxRonald Aranha
 
Defensive_Driving.ppt
Defensive_Driving.pptDefensive_Driving.ppt
Defensive_Driving.pptRonald Aranha
 
Entrepreneurship-PPT.pptx
Entrepreneurship-PPT.pptxEntrepreneurship-PPT.pptx
Entrepreneurship-PPT.pptxRonald Aranha
 
jobhazardanalysis-220818061315-e3aa6739.pptx
jobhazardanalysis-220818061315-e3aa6739.pptxjobhazardanalysis-220818061315-e3aa6739.pptx
jobhazardanalysis-220818061315-e3aa6739.pptxRonald Aranha
 
job_hazard_analysis.ppt
job_hazard_analysis.pptjob_hazard_analysis.ppt
job_hazard_analysis.pptRonald Aranha
 
job-safety-training.ppt
job-safety-training.pptjob-safety-training.ppt
job-safety-training.pptRonald Aranha
 
fy14_sh-26301-sh4_Aerial_Lift_Safety.pptx
fy14_sh-26301-sh4_Aerial_Lift_Safety.pptxfy14_sh-26301-sh4_Aerial_Lift_Safety.pptx
fy14_sh-26301-sh4_Aerial_Lift_Safety.pptxRonald Aranha
 

More from Ronald Aranha (20)

Chapter 17 Technical Instructions.ppt
Chapter 17  Technical Instructions.pptChapter 17  Technical Instructions.ppt
Chapter 17 Technical Instructions.ppt
 
Chapter 16 Email and Instant Messaging.ppt
Chapter 16 Email and Instant Messaging.pptChapter 16 Email and Instant Messaging.ppt
Chapter 16 Email and Instant Messaging.ppt
 
TechnicalReport.ppt
TechnicalReport.pptTechnicalReport.ppt
TechnicalReport.ppt
 
Cryogenics.ppt
Cryogenics.pptCryogenics.ppt
Cryogenics.ppt
 
Driving_1.ppt
Driving_1.pptDriving_1.ppt
Driving_1.ppt
 
RCA-Guidebook-Accompanying-SlideDeck_Feb_2021.pptx
RCA-Guidebook-Accompanying-SlideDeck_Feb_2021.pptxRCA-Guidebook-Accompanying-SlideDeck_Feb_2021.pptx
RCA-Guidebook-Accompanying-SlideDeck_Feb_2021.pptx
 
fy11_sh-22297-11_HeavyEquipmentSafety.pptx
fy11_sh-22297-11_HeavyEquipmentSafety.pptxfy11_sh-22297-11_HeavyEquipmentSafety.pptx
fy11_sh-22297-11_HeavyEquipmentSafety.pptx
 
Defensive_Driving.ppt
Defensive_Driving.pptDefensive_Driving.ppt
Defensive_Driving.ppt
 
Entrepreneurship-PPT.pptx
Entrepreneurship-PPT.pptxEntrepreneurship-PPT.pptx
Entrepreneurship-PPT.pptx
 
jobhazardanalysis-220818061315-e3aa6739.pptx
jobhazardanalysis-220818061315-e3aa6739.pptxjobhazardanalysis-220818061315-e3aa6739.pptx
jobhazardanalysis-220818061315-e3aa6739.pptx
 
job_hazard_analysis.ppt
job_hazard_analysis.pptjob_hazard_analysis.ppt
job_hazard_analysis.ppt
 
job-safety-training.ppt
job-safety-training.pptjob-safety-training.ppt
job-safety-training.ppt
 
4215962.ppt
4215962.ppt4215962.ppt
4215962.ppt
 
7637655.ppt
7637655.ppt7637655.ppt
7637655.ppt
 
6725743.ppt
6725743.ppt6725743.ppt
6725743.ppt
 
coldweather1.ppt
coldweather1.pptcoldweather1.ppt
coldweather1.ppt
 
Hypothemia10.ppt
Hypothemia10.pptHypothemia10.ppt
Hypothemia10.ppt
 
MOHSIN RAZA.pdf
MOHSIN RAZA.pdfMOHSIN RAZA.pdf
MOHSIN RAZA.pdf
 
Bosiet.pptx
Bosiet.pptxBosiet.pptx
Bosiet.pptx
 
fy14_sh-26301-sh4_Aerial_Lift_Safety.pptx
fy14_sh-26301-sh4_Aerial_Lift_Safety.pptxfy14_sh-26301-sh4_Aerial_Lift_Safety.pptx
fy14_sh-26301-sh4_Aerial_Lift_Safety.pptx
 

Recently uploaded

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 

Recently uploaded (20)

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 

const_cranes_090310 (1).ppt

  • 1. Construction Crane Safety (new requirements 2010) September 2, 2010
  • 2. Why? • Crane accidents killed an average of 78 people per year between 2003 and 2005 • The new standard is located at http://www.federalregister.gov/articles/201 0/08/09/2010-17818/cranes-and-derricks- in-construction#h-15 • OSHA expects the final standard to prevent 22 fatalities and 175 non-fatal injuries each year.
  • 3. When? • Intention to develop the rule in July 2002. • Used negotiated rulemaking committee consisting both industry and labor. • The committee completed its work in 2004. • Released – July 28, 2010 • Published – August 9, 2010 • Effective – November 8, 2010 • Phased in over four years – August 9, 2014 – Certification of operators phased in over four years. No grandfathering of those past certification.
  • 4. Key Hazards • Four main causes of worker death and injury: • Electrocution, • Crushed by parts of the equipment, • Struck-by the equipment/load, and • Falls. (See Subpart M 1926.500-503)
  • 5. Largest Impact • Mandatory crane operator certification - qualification • 200,000 construction crane operators in the industry • OSHA allowing four years to meet the certification requirement. • It will take time for certifying organizations to gain enough capacity to cover so many operators.
  • 6. Other Significant Requirements • Use of synthetic slings in accordance with the manufacturer’s instructions during assembly/disassembly work; • Assessment of ground conditions; • Procedures for working in the vicinity of power lines. • Pre-erection inspection of tower crane parts;
  • 7. OSHA – State - Local • Employers must comply with local and state operator licensing requirements which meet the minimum criteria specified in § 1926.1427. • Some state had existing Crane standards that exceeded the old standard. In state plan states, please see the rules for that state.
  • 8. Who Pays? • Employers must pay for certification or qualification of their currently uncertified or unqualified operators. 1926.1427 (a)(4) • Reasonable that employees, who have already been sufficiently trained in crane operation and may have many years' experience, certainly need no more than a short preparation to successfully pass the crane operator certification tests. – FR Preamble
  • 9. Crane or Not Crane? • Functional description – Can hoist, – Lower and – Horizontally move a suspended load • Forklifts configured to hoist and lower (by means of a winch OR hook) and horizontally move a suspended load are covered • Backhoes are excluded even if used like a crane….1926.1400 (c)(2) Forklift with attached boom. 1926.1400 (c)(8) See 1926.1441 if using equipment with a rated hoisting/lifting capacity of 2,000 pounds or less
  • 10. 10 • OPTION 1: Accredited testing organization • OPTION 2: Employer qualification program • OPTION 3: U.S. military • OPTION 4: State/local gov’t license Operator Qualifications and Certifications - 4 Options
  • 11. 11 Operator Qualifications and Certifications (cont’d) Accredited testing organization YES * 5 years Employer Qualification Program NO 5 years US Military license NO * Set by issuing entity State/local license NO * Valid only in entity’s jurisdiction Set by issuing entity, not > 5 years Portable Valid
  • 12. Written Certification Tests • Administered in any language understood by the operator candidate. • Test must cover: – Controls/performance characteristics – Calculate capacity (w/ or w/out calculator) – Preventing power line contact – Ground support – Read and locate info in operating manual – Appendix Q subjects
  • 13. Practical Examination • Must be well designed and sufficiently comprehensive • Must have the demonstrated the skills and knowledge needed to operate the equipment safely. • An operator's ability to handle unusual worksite conditions, such as adverse weather or working on crowded jobsites, are hazards that are not commonly part of this exam.
  • 14. 14 1926.1408 Power Lines • Step 1: Identify Work Zone – Work Zone = Marking boundaries OR – 360 degrees around crane up to maximum working radius – Make the power line hazard assessment
  • 15. 15 Could you get within 20 feet of power line? YES NO Option #1 Deenergize & Ground Encroachment Prevention measures Option #3 Ask Utility for Voltage and Use Table A (with minimum clearance distance) Option #2 20 foot clearance No further action • Planning meeting • If tag lines used Non-conductive • Elevated warning lines, barricade or line of signs •PLUS (Choose one): • Proximity alarm, spotter, warning device, range limiter, or insulating link
  • 16. 16 Table A – Minimum Clearance Distances Voltage (nominal, kV, alternating current) Minimum clearance distance (feet) up to 50 10 over 50 to 200 15 over 200 to 350 20 over 350 to 500 25 over 500 to 750 35 over 750 to 1000 45 over 1000 (as established by the power line owner/operator or registered professional engineer who is a qualified person with respect to electrical power transmission and distribution)
  • 17. Intentionally Working Closer Than Table A Zone 1910.1410 • Paragraph (b) requires the employer to consult with the utility owner/operator before deciding that it infeasible to deenergize and ground the lines or relocate them. • Employer can establish this distance by either having the utility owner/operator determine the minimum clearance distance that must be maintained or by having a registered professional engineer who is a qualified person with respect to electrical transmission and distribution determine the minimum clearance distance that must be maintained.
  • 18. 18 Must show: • Staying outside zone is infeasible • Infeasible to deenergize and ground Intentionally Working Closer Than Table A Zone All of the following are required: 1. PL owner – sets minimum approach distance 2. Planning meeting – procedures 3. Dedicated spotter 4. Elevated warning line or barricade 5. Insulating link/device 6. Non-conductive rigging 7. Range limiter (if equipped) 8. Non-conductive tag line (if used) 9. Barricades - 10 feet from equipment 10. Limit access to essential employees 11. Ground crane 12. Deactivate automatic re-energizer 1926.1410
  • 19. Assembly Disassembly • Employers must use a qualified rigger for rigging operations during assembly & disassembly • Two options: – Manufacturer procedures or – Employer procedures (criteria requirements)
  • 20. Assembly/Disassembly Supervisor • Must understand procedures • Review procedures (unless they’ve used them before) • Check that crew members understand their tasks, hazards • Follow manufacturer’s prohibitions • When using outriggers - fully extended or deployed per the load chart
  • 21. 21 • A/D supervisor addresses 12 key hazards, including: – Adequate site and ground conditions – Sufficient blocking for load and stability – Suitable boom and jib pick points – Identify center of gravity – Stability for pin removal – Consider wind speed and weather Assembly/Disassembly (cont’d)
  • 22. 22 • The suitability of blocking material • Verification of the loads for assist cranes • Snagging of cables or components • Struck by counter weights • Boom hoist brake failure • Loss of backwards stability Assembly/Disassembly (cont’d)
  • 23. Qualified Rigger • 1926.1404 (r) • Meets the criteria for a qualified person • Possession of a recognized degree, certificate, or professional standing, or extensive (rigging) knowledge, training and experience • Successfully demonstrated the ability to solve/resolve problems (relating to rigging)
  • 24. Tower Cranes • Employers must perform a pre-erection inspection of tower cranes. • Extensive requirements under 1926.1435 and other sections. • Beyond scope of this presentation • Numerous accidents such as Seattle in 85, San Francisco in 89, Manhattan in 08, Hong Kong in 08, New York in 06,
  • 25. Ground Conditions • 1926.1402 (b) • Ground conditions must be firm, drained, and graded • Use supporting materials, • Use equipment manufacturer's specifications for adequate support • Use equipment manufacturer's specifications for degree of level of the equipment
  • 26. Controlling Entity • 1926.1402 (c)(3) • Must ensure that ground preparations are safe • Must inform the user of the equipment and the operator of the location of known hazards beneath the equipment set-up area (such as voids, tanks, utilities) • If there is no controlling entity then the employer that has authority at the site to make or arrange for ground preparations must do so.
  • 27. 27 Signals • Signal person – when required: – Point of operation not in full view of operator – View of direction of travel is obstructed – Site specific safety concerns – 1926.1428 Signal person qualifications • Signal Types: – Hand, voice, audible or “new” – Only time an operator can use a cell phone is while lifting as part of a planned procedure
  • 28. 28 Signals (cont’d.) • Signal person qualifications 3rd party qualified evaluator Yes Yes Employer Qualified Evaluator Yes No Qualified how Documentation Portable
  • 29. 29 • Qualification Requirements: – Know & understand signals – Competent in using signals – Basic understanding of crane operation – Verbal or written test + practical test Signals (cont’d.)
  • 30. 30 1926.1412 Inspections Modified or Repaired/ adjusted Qualified Post-assembly Qualified Shift Competent Monthly Competent Annual Qualified Type of Inspection: Who Inspects:
  • 31. 31 Inspections (cont’d) • Shift = visual inspection for apparent deficiencies • Monthly = documented shift inspection • Annual = comprehensive, every 12 months
  • 32. Each Shift Inspection • 1926.1412 (d) • Apparent deficiencies • Control and Drive mechanisms • Hydraulics • Hooks • Wire Rope • Electrical • Ground Conditions • Levelness of the crane • Operator view • All Safety Devices • Operational Aids are working
  • 33. Operators • 1926.1417 has many requirements. Some highlights are: • Must not engage in any activity that diverts his/her attention while operating the equipment, • No cell phones (other than when used for signal communications) • Must not leave the controls while the load is suspended, (four exceptions) • Must verify that the load is within the rated capacity of the equipment (2 methods) • Must obey a stop (or emergency stop) signal, irrespective of who gives it. • Told of any employee entering the crane work area 1926.1424(a)(3)
  • 34. Employer Training • 1926.1430 Employee Training Issues • Powerline safety • Signal persons • Operators • Competent Person • Qualified Persons • Crush Pinch point hazards • Tagout for repair • Must confirm that the employee understands the information provided in the training • Provide the training at no cost to the employee
  • 35. Work Area Control • 1926.1424 • Train each employee assigned to work on or near the equipment • Erect and maintain control lines, warning lines, railings or similar barriers to mark the boundaries of the hazard area (1 Exception)
  • 36. 36 Resources • Cranes and Derricks in Construction Final Rule – http://www.osha.gov/cranes-derricks/index.html • Associated Training Service Network – http://www.operator-school.com/ • National Commission for the Certification of Crane Operators – http://www.nccco.org/ • National Association of Heavy Equipment Training Schools – http://www.heavy-equipment-school.com/ • North American Crane Bureau Group – http://www.cranesafe.com/history.htm • California Crane School – http://www.californiacraneschool.com/
  • 37. Further • This ppt was prepared by John Newquist as a preliminary aid for the new standard. Please check the OSHA website for Crane Outreach Material that will be developed in the coming months. • This is not an official OSHA publication. Those will be on the OSHA.gov website. • Newquist.john@dol.gov is my email if you see any errors • 312-353-5977 • Brian Sturtecky is our Region V Certified Crane Inspector and has provided key assistance on this standard. He can be reached at 312-353-2220. • Several slides were obtained from the OSHA Training Institute from their Webinar August 30, 2010. • Every aspect from inspecting, repairing, operating, rigging and signaling these cranes require extensive training. Please take classes with hands on training if you are expected to perform any of these activities. • I want to thank Brian, Lisa, Tom, Bill, Cathy for all their assistance in answering questions and providing issues that are coming from the public.