Breakout Session: Design, Fabrication and Testing of Cantilever Beams and Triangle Plates
Cantilever beams and triangle plates are valuable specialty rigging tools, but the engineering fundamentals behind their design and use are simpler than they may appear. This presentation will provide examples of commonly used rigging applications and will identify resources for design, fabrication, load testing and lift planning.
Speaker: Chad Fox, PE, Project Manager, ruby+associates
2. Introduction
ā¢ WhyTriangle PLās & Cantilever Beams?
ā¢ Started Eng. Dept w/ Limited Rigging Experience
ā¢ Mostly self taught ā research & trial/error
ā¢ Came to realize how valuable these tools were
ā¢ Salesmen were passing on jobs where these are needed
ā¢ Possibly under-utilized by smaller to mid size contractors
ā¢ Not so complicated ā share
?
9. Triangle Plates - Applications
Rotation of a Lifted Object:
This application allows a
object to be rotated by
two lines to the triangle
of which lengthens or
rotate the object.
17. Triangle Plates - Applications
3rd Leg Alignment
Adjustment: This
application allows
an adjustable third line to
for rotational variation of
lifted object.
20. Triangle Plates - Applications
Cascading System of Slings:
A triangle can be used to
rigging systems with
slings and avoid over-
a hook. This can help to
sling overlap or bunching.
23. Triangle Plates - Applications
Load Equalization Between Two
Hooks: In instances where multiple
hooks must be utilized due to
limitations of the lifting equipment
the triangle provides an efficient way
distribute the lifted loads relatively
to the two hooks.
28. Triangle Plates - Applications
Rigging System with Shifting
Center of Gravity: In this
case a triangle allows for
systems such as cantilever
with an adjustable line
center of gravity is shifted
throughout the lifting
32. Triangle Plates - Construction
ā¢ Resources:
ā¢ ASME B30.20
ā¢ Fabrication:
ā¢ Boss PLās
ā¢ Capacity and/or Limiting Shackles
ā¢ Drill after welding ā plies line up
ā¢ Local Steel Distribution may be
able to burn shape.
Photo Courtesy of ALL-LIFTS
34. Triangle PlatesāMarking
ā¢ ASME B30.20 Marking:
ā¢ Weight
ā¢ Rated Load
ā¢ Service Class
ā¢ Design Category
ā¢ Serial Number
ā¢ Manufacturer
35. Triangle Plates ā Inspection
ā¢ ASME B30.20 Inspection: (20-1.3)
ā¢ Designated Person
ā¢ Initial Inspection (New or Modified)
ā¢ Every Lift Inspection
ā¢ Frequent Inspection
ā¢ Periodic Inspection (recorded)
ā¢ Table 20-1.3.3-1 For Minimum
Frequency per Service (normal,
heavy, severe)
36.
37. Cantilever Beams ā Function
ā¢ Reach Objects without direct
overhead access
ā¢ Equipment installation through
sides of buildings/platforms
ā¢ Center of Gravity Over Hook
38. Cantilever Beams ā Function
ā¢ Shifting COG Depending on
Configuration.
ā¢ Beam Only
ā¢ Beam + CWT
ā¢ Beam + CWT + Object
39. Cantilever Beams ā Function
ā¢ Heavy Counterweight
ā¢ Light object Compared to CWT
ā¢ Watch Sloping of Beam
ā¢ Simplest Option if Possible
40. Cantilever Beams ā Function
ā¢ Sliding Counterweight or Hook
ā¢ Powered system to move the
counterweight in relation to the
pick point to counterbalance the
lifted load.
ā¢ Similar with sliding hook.
ā¢ Hydraulically Powered Common.
41. Cantilever Beams ā Function
ā¢ Adjustable Line to Lift Beam
ā¢ Winch Mounted to the Lift Beam
ā¢ Self Contained
ā¢ Need to Account forWinchWeight
ā¢ Mounting Space Needed
ā¢ Power
42. Cantilever Beams ā Function
ā¢ Adjustable Line to Lift Beam
ā¢ Using a Secondary Line From
Crane
ā¢ Similar toTripping Using Auxiliary
Line
ā¢ Run Second LineThrough Block
@Triangle
ā¢ Sheaves: Ch. 4 BTH-1
43. Cantilever Beams ā Function
ā¢ Adjustable Line to Lift Beam
ā¢ Hoist Line Above Hook
ā¢ Air
ā¢ Electric
ā¢ Hand (probably lots of work)
ā¢ Caution on Angle Loading of
Hoists:
ā¢ Contact Manufacturer on allowable
angles.
ā¢ Height Limitations Due to
Power/Air/Access Needs
45. Cantilever Beams ā Example
ā¢ Beam Construction
ā¢ Steel Shapes Most Efficient:
ā¢ Box Sections
ā¢ Tubes
ā¢ StoutWide Flange
ā¢ Slender Shapes More Prone to
Failure by Buckling of the
Compression Flange (Twisting of
the Shape)
46. Cantilever Beams ā Example
ā¢ Beam Construction
ā¢ Shackle/Sling attachment lugs
ā¢ Welded Single Lugs (one-time use)
ā¢ Welded Continuous (heavy)
ā¢ Bolted (removable)
47. Cantilever Beams ā Example
ā¢ Bolted Lift Lug
ā¢ Can Be Re-Used
ā¢ Locations Easily Adjusted
ā¢ Transferred to Other Beams
48. Cantilever Beams ā Example
ā¢ Bolted Lift Lug
ā¢ If Pretensioned:
ā¢ DTIWashers helpful
ā¢ Not All Bolts Can Be re-used
(A490, Galvanized)
ā¢ Typically Spec A325
49. Cantilever Beams ā Example
ā¢ End Plates
ā¢ Allow For Extensions
ā¢ End Fixtures
ā¢ Allow Join (2)Together
50. Cantilever Beams ā Lift Planning
ā¢ Lift Plans Important For Use
ā¢ Clearances
ā¢ Lengths
ā¢ Line Adjustment Needed
ā¢ Forces (change)
ā¢ Stability Verification
60. Cantilever Beams- Construction
ā¢ Resources:
ā¢ ASME B30.20
ā¢ AWS D14.1
ā¢ Fabrication:
ā¢ Local Steel Distribution may have
drill line.
61. Cantileverā Load Testing
ā¢ Resources:
ā¢ ASME B30.20 (should)
ā¢ OSHA, 29 CFR 1926.251 (shall)
ā¢ 125% Design Capacity
ā¢ Recommend full Simulation
ā¢ Could also use forTraining
ā¢ Be aware overloading Shackles
& Hoist
ā¢ Bolt-on Lugs ā AlsoTested
62. Lift Beams ā Marking
ā¢ ASME B30.20 Marking:
ā¢ Weight
ā¢ Rated Load(Difficultā¦multiple)
ā¢ Service Class
ā¢ Design Category
ā¢ Serial Number
ā¢ Manufacturer
63. Cantileverā Inspection
ā¢ ASME B30.20 Inspection: (20-1.3)
ā¢ Designated Person
ā¢ Initial Inspection (New or
Modified)
ā¢ Every Lift Inspection
ā¢ Frequent Inspection
ā¢ Periodic Inspection (recorded)
ā¢ Table 20-1.3.3-1 For Minimum
Frequency per Service (normal,
heavy, severe)
68. Thank You
David Duerr PE
Bruce Burt PE
Ericksonās Inc
Alberici/Hillsdale
All-Lifts
Triangle Plates & Cantilever Beams:
Applications, Design, Construction &Testing
Editor's Notes
-Send in Presentation Samples
-Non-technical preferred
Triangle orientations depend up each apex(corner) loading
-Moment balance determines rotation, Basic Statics
-Corner hardware attachments allow rotation so points of Zero moment
-This may be of particular value when installing or removing equipment from a structure with a permanent or temporary monorail system that extends outside of the boundaries of the structure, or applications where setting down of the lifted object is not feasible prior to transfer.
-Gantry handoffs
Made up project:
-Monorail that extends outside of a building.
-Stairway directly Below
-Load handoff between mobile crane & monorail hoist.
-Floor rating
-Piping interference
-2nd Trolley
Additional handoff around obstruction (piping/duct) internally along monorail.
This may be of particular value during uprighting and/or tilting procedures from a single hook.(no aux or assist crane, working off overhead)
Nuclear Example
Animation
-Load testing requirement ā Nureg 612
-Nuclear Example ā Load Testing & Training
-2014 First test, presented SCRA ā15
-Witnessed other load tests ā similar thing
-Travelling from the loading bay to staging location along spent fuel pool.
-Works in horizontal position, maximum rotation
-Too much rotation ā block contact
-Installation of new
-Saddle beams on floor
-Kind of a mess with all the chain, air hoses, tag lines
The triangle can be helpful to achieve high accuracy alignment for certain installation or erection procedures.
Example: Syracuse University Carrier Dome
-New dome on top of the existing inflatable dome
-Compression ring comprised of box sections
-All different slopes and skews
-Try to find a way to minimize rigging (and costs) but adjustable enough to build
Example: Syracuse University Carrier Dome
-2 triangles with a hand hoist
-Bolts ā Standard holes 1/8ā
-1 degree off = 1 Ā½ā off corner to corner
-Electronic level to monitor
-Structurally flexible objects requiring multiple pick points to maintain integrity during lift.
Digester Cover Example
-12 trusses
-Engage 10 for integrity
-triangles both avoid too many slings in the hook and also allow for better load distribution
-Sling lengths, adjustment, never get everything equal
-5 Triangles down to 10 slings
-Triangle rotation along with adjustable chain ā engage all 10 locations
-Rigging & structural work together
-Avoid large load variations between crane hooks.
-This application may also allow for greater horizontal clearances between crane hooks and/or booms by spacing out hook attachment points.
Project example: Sun Life Stadium Canopy
-4 trusses, one along each sideline & end zone
-Erection trussesā build ground or air on towers
-Strand Jacks, crane capacity
-Trade off between more equipment but safer/faster working conditions
-4 Cranes: MLC 650
-2 Triangles (triangle trusses)
-Designed to allow safe spacing between crane hooks/booms
-Problems with load transfer between hooks if connecting directly to truss. Stiffness causes problems.
Load testing
-Anchored & use 2 OH
-Inspection following load testing
Project example: Transformer Lift
-Lift beam, really functioning as a 3-pt triangle
-Adjust to get percentage of load to each crane ā maximize efficiency & crane chart utilization
Triangle rotates rather than hook, or slings moving in hook
Design standards to help with design
Design standards to help with design
BTH-1 Section 3-3.3
Fairly easy to build a spreadsheet if youāre using frequently - example