SlideShare a Scribd company logo
1 of 43
Machinery Safety Analysis Meeting
Month of November-2015
O4th December- 2015
SEPCO HSE (Mechanical Dept.)
Agenda of the Meeting:
• Machinery management
• Monthly inspection procedure
• Violation /good practices photographs
• Inspection photographs
• Lifting/Hoisting requirements.
• Machineries situation in site.
• Machinery working condition
• New implementation and requirements.
MACHINERY MANAGEMENT:
Documents procedure:
• If any new machine comes to site then first inform to Mechanical
Dept. and submit the document in systematic manner given as
below:
1.INSURANCE PAPER
2.REGISTRATION CERTIFICATE
3.DRIVING LICENCE
4. Photocopy of third party certificate under C.G Government (for
Hydra ,Crane , Winch machine and lifting tools and tackles)
Gate-pass Procedure:
• When machine departure from our KMPCL site requested to all
subcontractors to take the photo copy of entry pass in KSK gate
before processing the gate pass procedure, and also that machine
will be registered in SEPCO Mechanical Department.
• First signature the execution department and then processing as
per gate pass format.
Cont.………
Circular bill signature Procedure:
• First take the signature of execution department and take the
approval form before come to signature the bill.
Machinery erection or dismantle procedure:
• Submit the erection and dismantle procedure of crawler, tower
and elevator before erection and dismantle.
Entry inspection Procedure:
• When new machine comes to our site ,check all the safety
devices,machinery condition ,documents as per inspection format
and fill the form then submit it to Mechanical Dept. ,after then
SEPCO issued admittance card which was six month validity.
Cont.………
On- site documentation Procedure:
• Must attach the valid TPI certificate on winch, Hydra, and all
types of crane.
• Operator must having driving license while operating
machine/vehicle in site.
• Attach the operating procedure of winch machine /crane etc.
on every machine.
• Attach the admittance card in front of machine / vehicles.
• Those machine are not in use attach the not in use tag
issued by Mechanical department.
TPI CERTIFICATE
ADMITTANCE CARD
NOT-IN-USE TAG
ON-SITE DOCUMENTATION:
Cont.………
OPERATING PROCEDURE DRIVING LICENSE
Inspection Procedure:
• Last week of every month SEPCO HSE and
Mechanical Department will check the machinery
safety device ,technical condition ,location etc.
• Every week on Tuesday/Wednesday check the lifting
tools tackles and color coding on different location.
• Special inspection will be organized as per
requirements.
• Chimney inspection together with HSE and Civil
Department.
• On every Saturday organize the tower crane foundation
inspection.
Violation /good practices
photographs
SIMPLEX: Winch M/C: all the required documents
must be attached on the front side of the machine
S.K.Const. : Limit switch broken, no tag line given while lifting
the load, and no color coding of wire ropes and d-shackles
SIMPLEX : Hydra : Limit switch broken.
TOWER CRANE VERTICALITYAND FOUNDATION
LEVEL CHECKED WITH CIVIL DEPT
FOUNDATION LEVEL OF TOWER CRANE CHECKED
FOUND SATISFACTORY
TOWER CRANE B#1 TOWER CRANE B#2
TOWER CRANE VERTICALITY CHECKED FOUND
SATISFACTORY
TOWER CRANE B#1 TOWER CRANE B#2 TOWER CRANE ESP
SEPCO MACHINERY INSPECTION
Lifting/Hoisting requirements
• It is requested to all the Sub-contractor’s submit the updated TPI certificate
for entire lifting/rigging equipment's to SEPCO Mechanical dept. as an
earliest. The color coding should be done accordingly which tools has valid
TPI certificate. From the month of December’-10th, It will be check by SEPCO
Mechanical and HSE dept.
Name of the months Types of color
JAN,FEB,MARCH
BLUE
APR,MAY,JUN
GREEN
JULY,AUG,SEPT
YELLOW
OCT.NOV,DEC
PINK
Pre-operational site activity and
inspection
• Review the site for possible hazards:
– Overhead lines
– Unstable soil
– High wind
conditions
– Other work
activities in
the area
1a
Pre-operational site activity and
inspection
• Characteristics of the load:
– Hazardous or toxic materials
– Weight
– Dimensions
– Center of gravity
• Rigging sketches and information:
– Lift points
– Methods of attachment
– Sling angles
– Load vectors
1b
Pre-operational site activity and
inspection
• Rigging sketches and information:
– Boom and swing angles
– Crane orientations
– Rated capacities
– Other factors affecting equipment operation
• Operating procedures:
– Step-by-step instructions
– Applicable rigging precautions
– Safety measures
– Emergency procedures
1d
Pre-operational site activity and
inspection
• Additions and modifications to
equipment:
– Tags, instruction plates, decals reflect to
modifications
– Ensure safety factor has not been
reduced by additions/modifications
1f
Types of inspections and
checks
• Frequent inspections
occur every day
• Periodic
inspections
occur monthly
• Depend upon
regulation and
equipment involved
2a
Frequent inspections
• Daily pre-operational walk-around or pre-startup check
• Exposed moving parts should be guarded/isolated
• High voltage warning signs are displayed
• Crane components
• Wire ropes
• Freedom of rotation of all swivels
• Tires
• Batteries
• Proper lubrication
• Fluid leaks
• Sheaves, drums, rigging, hardware, attachments
• Operating mechanisms
• Guardrails, handholds, steps
• Platforms/walkways
• Turntable connections
3a
Continued…..
• Boom and jib
– Look for straightness/damage
– Corrosion
– Cracking/peeling paint
– Bent lacing
• Outriggers
– Distortion/cracking
– Welds
– Extension/retraction of beams
– Floats
• Cab
– Cleanliness of cab
– Control labeling
– Function of gauges, lights, signals
– Service/parking brake
– Seat and cab door operation
– Inspection and maintenance records
3e
Pre-startup
• Field of vision
– Broken/cracked windows
– Adjustment/operation of brakes/clutches
– Operation/calibration of boom hoist lockout
– Gauges and warning lights
– Controls
• Inspection records must include the:
– date of the inspection
– signature of the inspector
– serial number of critical component
• Structural damage
• Cracks in welded connections
• Damage or defects of sheaves
• Main hoist and auxiliary drum damage/defects
• Even distribution of the wire rope on hoist drum
• Proper wire rope integrity 3i
Periodic inspections
• Performed monthly and/or annually
• Inspection varies depending on
crane use and site conditions
• Maintain records on:
– brakes
– crane hooks
– hoist chains
– ropes
4a
Periodic inspections - check
for:
• Excessive wear of brake and clutch
parts
• Worn, cracked, distorted parts
• Defects/damage to the main boom,
jib, boom extensions
4f
Hazard of overhead lines
• Maintain appropriate line clearance
• Direct contact
• Indirect contact
• Voltages 50 kv or less, the clearance
distance is 10 feet
• Voltages greater than 50kv, the
clearance is 10 feet plus 4 inches for
every 10 kv over 50 kv
• Use signalmen to assist in maintaining
proper clearances where vision is
obstructed
– Hand signals
– Chart of hand signals
6a
Prohibited actions
• Do not exceed load ratings
• Do not change the recommended counterweights
• Do not lift an unsecured/unbalanced load
• Do not lift two separately rigged loads at the same
time
• Do not wrap tag lines around one’s body
9a
Rigging And Lifting Safety
• The sling should be protected from the edges once the sling being
used for lifting.
• All the lifting machines, lifting tools and tackles should be with third
party inspection certificate.
• The overload of the lifting machines & tools and tackles is not
allowed.
• Hydra is only permitted for loading and unloading, it is prohibited for
transporting.
• No one is allowed to stay under the lifting objects. A full time person
should be arranged to supervise the lifting work.
• Limit switches, brakes and similar safety facilities in lifting
machineries should be effective.
1. Only qualified operators will be permitted to operate cranes. Operators
are responsible for the exercise of caution necessary for the safe
operation of their equipment.
2. Operators shall immediately report unsafe conditions, including defects
in the machine, to their supervisor.
3. Operators shall not permit anyone to ride the hook or load.
4. When the operator leaves his machine or repairs or being made, it is his
responsibility to set the brakes, secure the boom, take the machine out
of gear and turn off the engine.
5. When making a lift, the operator will take operational signals only from
the man authorized to give them. An emergency stop signal given by
anyone, will be acted upon by the operator.
6. It is the joint responsibility of the operator and the riggers to see that all
hitches are secure and that all loose material is removed before the
loads are lifted. Material should not be hoisted until it is ready to be
used/put into place.
7. Safety hooks, shall be used on all operations where loads are being
handled. Suspended loads shall be controlled by tag lines whenever
necessary.
CRANE TOOLBOX TALK:
8. Booms shall be equipped with a boom angle indicator and a device
designed and constructed to prevent the boom from falling over
backward. Boom heads, load blocks and hooks shall be painted with
high visibility paint.
9. Where necessary to increase stability, cranes, except crawler cranes
and boom type excavators, shall be equipped with outriggers of a
design and strength suitable for the work being performed.
10. Hooks, wire rope, bearings, gears, friction clutches, chain drives and
other parts subject to wear must be inspected at regular intervals and
repaired or replaced as required. Records of such inspections and
resultant action taken shall be maintained by the contractor.
11. Crawler, truck and locomotive cranes must be inspected monthly. A
certification of performance of these inspections is required.
12. When loads are being hoisted, avoid walking under the lift or
permitting an employee to be exposed to the swing of the lift.
Daily before operating:
– Check battery
– Check all controls
– Visually inspect
– Wire rope for kinks or
damage
– Sheaves, drums for
damage
– Upper and lower limit
switches.
Inspection and Maintenance
• Loads should be well secured.
• Slings should be adequate to the task.
• Slings should be unlinked and load balanced and
secured.
• No sudden stops.
• No obstructions while lifting or traveling.
• No loose items on load or crane before lift.
• Bumping into runway stops is prohibited.
• Hoist line must be vertical prior to the lift (remove
slack in the hoist slowly).
• No crane load should pass overhead of personnel,
clear the area before making the lift.
• No one is to ride the crane without permission.
RIGGING:
Crane and Rigging Safety Rules:
• Check limit switches before rigging the load.
• Make sure the load does not exceed rated capacity.
• Know the center of gravity of the load.
• Attach load above the center of gravity for stability.
• Select hitch that will control the load.
• Know the rated capacities of rigging and slinging.
• Inspect all rigging before use.
• Protect the sling from sharp corners.
• Allow for increased tension due to sling angle.
• Equalize loading on multiple leg slings.
• Allow for load reductions when using choker hitches.
• Attach tag line prior to lift.
Continued…….
• Keep personnel clear of lift area.
• Wear hard hats when making overhead lifts.
• Lift load a few inches and verify rigging.
• Check for any loose items.
• Know limitations of hoisting device.
• Start and stop SLOWLY! Watch for obstructions (not
only hook and load but outboard end of the bridge).
• Check pathway is clear before making a lift (use a
spotter for blind spots).
• Verify hook completely closes.
• Use appropriate hand signals.
• Maintain load control at all times.
• Never leave load unattended.
Machineries situation in site.
 Establishing a high effective machinery management network。
 At present total 18 subcontractors have confirmed a special
mechanical engineer to attend mechanical meeting and all kinds of
inspection organized by Mechanical Dept. ,these mechanical
engineers are responsible for regularly submitting and updating
machinery accounts and documents to SEPCO Mechanical
Department.
 Machinery resource situation:till the end of November 2015,
there are 149 set big—middle—sized machines 、 149 set
machines submitted the documents 、149 set machines gotten
《machinery admittance card》 issued by SEPCO
*New implementation and
requirements.
 Requested to each subcontractor must organize a especial inspection of machine once in a week.
 Use firmer ,large steel plate to distribute the load and reduce the weight on the soil.
 Keeping a safe distance from a power line is the key to preventing power line accidents.
 All agencies who are responsible for operation & maintenance of tower crane must remove water
from tower crane foundation after each raining continuously .
 Provide suitable earthling for lightning protection of silo of batching plant and tower crane where
the earthling resistance is less than 10 ohm.
 Provide proper rain protection covers to all electric equipment’s like electric motors, electric
cables, electric panel’s etc.
 At no work condition, take both hooks (small & big) up to hoist limit switch position.
 Hydra shall be prohibited to transport equipment and material for long distance.
 For work completion Do not force on operator for wrong operation.
 Tandem lifting by using hydra is strictly prohibited in our site.
HIGHLIGHTS:
SEPCO will organize the ANNUAL meeting
in the first week of January 2016.Request to
all subcontractors concerned engineer
and Project managers kind attend the meeting.
THANK YOU

More Related Content

What's hot

Overhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&IOverhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&IAtlantic Training, LLC.
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchHaGun Gunawan
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sitesPrastowo Priyatmoko
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting OperationsJames McCann
 
Change- out P119 Pulley-2
Change- out P119 Pulley-2Change- out P119 Pulley-2
Change- out P119 Pulley-2Scott Jarrold
 
SAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEASAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEAANA ISABEL R.R.
 
450 series rail installation instructions rev
450 series rail installation instructions rev450 series rail installation instructions rev
450 series rail installation instructions revYover Rodriguez
 
Lifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesLifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesSimon Faulkner-Duke
 
Lifting plan
Lifting planLifting plan
Lifting plantnsv22
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at workPaul Smith
 

What's hot (20)

Overhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&IOverhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&I
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
Overhead Crane Safety Course
Overhead Crane Safety CourseOverhead Crane Safety Course
Overhead Crane Safety Course
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
Aerial Lift Training by EHSDB
Aerial Lift Training by EHSDBAerial Lift Training by EHSDB
Aerial Lift Training by EHSDB
 
Change- out P119 Pulley-2
Change- out P119 Pulley-2Change- out P119 Pulley-2
Change- out P119 Pulley-2
 
SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
Standards Regulations
Standards RegulationsStandards Regulations
Standards Regulations
 
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
 
2016 CRW - Hands-on Crane Inspection
2016 CRW - Hands-on Crane Inspection2016 CRW - Hands-on Crane Inspection
2016 CRW - Hands-on Crane Inspection
 
Failure analysis mtn526
Failure analysis mtn526Failure analysis mtn526
Failure analysis mtn526
 
SAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEASAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEA
 
450 series rail installation instructions rev
450 series rail installation instructions rev450 series rail installation instructions rev
450 series rail installation instructions rev
 
Lifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesLifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sites
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at work
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
 
Cranes ppt
Cranes pptCranes ppt
Cranes ppt
 

Similar to HSE

Hse new microsoft power point presentation
Hse new microsoft power point presentationHse new microsoft power point presentation
Hse new microsoft power point presentationSamip Nathani nathani
 
HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...AhmedAliKhan38
 
Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekRoseGaming1
 
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industryCrane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industryRamana Reddy G
 
BOCW my Version.pptx
BOCW my Version.pptxBOCW my Version.pptx
BOCW my Version.pptxSuresh459496
 
1Ascon Banksman and flagman Presentation-RO.ppt
1Ascon Banksman and flagman Presentation-RO.ppt1Ascon Banksman and flagman Presentation-RO.ppt
1Ascon Banksman and flagman Presentation-RO.pptFarhanMalik434232
 
apm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
apm-et13e-chapter-16-hoisting-and-conveying-equipment.pptapm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
apm-et13e-chapter-16-hoisting-and-conveying-equipment.pptLeandroGonzlezDeCecc
 
www.scanrent.com.au
www.scanrent.com.au www.scanrent.com.au
www.scanrent.com.au Ghazanfar Ali
 
Rigger_ENG.PPTX dddd dvgfr rr ergre gerg er gerg erger g ergr
Rigger_ENG.PPTX dddd dvgfr rr ergre gerg er gerg erger  g ergrRigger_ENG.PPTX dddd dvgfr rr ergre gerg er gerg erger  g ergr
Rigger_ENG.PPTX dddd dvgfr rr ergre gerg er gerg erger g ergrLuisValente37
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedureAbdul Shukur
 
Rig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docRig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docYasserAbdulkareem1
 
const_cranes_090310 (1).ppt
const_cranes_090310 (1).pptconst_cranes_090310 (1).ppt
const_cranes_090310 (1).pptRonald Aranha
 
Safe Material Handling
Safe Material Handling Safe Material Handling
Safe Material Handling Reliance
 

Similar to HSE (20)

Rigger safety .pdf
Rigger safety                        .pdfRigger safety                        .pdf
Rigger safety .pdf
 
Rigging Course .pdf
Rigging Course                       .pdfRigging Course                       .pdf
Rigging Course .pdf
 
Hse new microsoft power point presentation
Hse new microsoft power point presentationHse new microsoft power point presentation
Hse new microsoft power point presentation
 
HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...
 
Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhek
 
Man and machine interface
Man and machine interfaceMan and machine interface
Man and machine interface
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industryCrane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
 
Man and machine interface
Man and machine interfaceMan and machine interface
Man and machine interface
 
BOCW my Version.pptx
BOCW my Version.pptxBOCW my Version.pptx
BOCW my Version.pptx
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
Construction safety VI
Construction safety VIConstruction safety VI
Construction safety VI
 
1Ascon Banksman and flagman Presentation-RO.ppt
1Ascon Banksman and flagman Presentation-RO.ppt1Ascon Banksman and flagman Presentation-RO.ppt
1Ascon Banksman and flagman Presentation-RO.ppt
 
apm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
apm-et13e-chapter-16-hoisting-and-conveying-equipment.pptapm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
apm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
 
www.scanrent.com.au
www.scanrent.com.au www.scanrent.com.au
www.scanrent.com.au
 
Rigger_ENG.PPTX dddd dvgfr rr ergre gerg er gerg erger g ergr
Rigger_ENG.PPTX dddd dvgfr rr ergre gerg er gerg erger  g ergrRigger_ENG.PPTX dddd dvgfr rr ergre gerg er gerg erger  g ergr
Rigger_ENG.PPTX dddd dvgfr rr ergre gerg er gerg erger g ergr
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedure
 
Rig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docRig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.doc
 
const_cranes_090310 (1).ppt
const_cranes_090310 (1).pptconst_cranes_090310 (1).ppt
const_cranes_090310 (1).ppt
 
Safe Material Handling
Safe Material Handling Safe Material Handling
Safe Material Handling
 

Recently uploaded

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 

Recently uploaded (20)

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

HSE

  • 1. Machinery Safety Analysis Meeting Month of November-2015 O4th December- 2015 SEPCO HSE (Mechanical Dept.)
  • 2. Agenda of the Meeting: • Machinery management • Monthly inspection procedure • Violation /good practices photographs • Inspection photographs • Lifting/Hoisting requirements. • Machineries situation in site. • Machinery working condition • New implementation and requirements.
  • 3. MACHINERY MANAGEMENT: Documents procedure: • If any new machine comes to site then first inform to Mechanical Dept. and submit the document in systematic manner given as below: 1.INSURANCE PAPER 2.REGISTRATION CERTIFICATE 3.DRIVING LICENCE 4. Photocopy of third party certificate under C.G Government (for Hydra ,Crane , Winch machine and lifting tools and tackles) Gate-pass Procedure: • When machine departure from our KMPCL site requested to all subcontractors to take the photo copy of entry pass in KSK gate before processing the gate pass procedure, and also that machine will be registered in SEPCO Mechanical Department. • First signature the execution department and then processing as per gate pass format.
  • 4. Cont.……… Circular bill signature Procedure: • First take the signature of execution department and take the approval form before come to signature the bill. Machinery erection or dismantle procedure: • Submit the erection and dismantle procedure of crawler, tower and elevator before erection and dismantle. Entry inspection Procedure: • When new machine comes to our site ,check all the safety devices,machinery condition ,documents as per inspection format and fill the form then submit it to Mechanical Dept. ,after then SEPCO issued admittance card which was six month validity.
  • 5. Cont.……… On- site documentation Procedure: • Must attach the valid TPI certificate on winch, Hydra, and all types of crane. • Operator must having driving license while operating machine/vehicle in site. • Attach the operating procedure of winch machine /crane etc. on every machine. • Attach the admittance card in front of machine / vehicles. • Those machine are not in use attach the not in use tag issued by Mechanical department.
  • 6. TPI CERTIFICATE ADMITTANCE CARD NOT-IN-USE TAG ON-SITE DOCUMENTATION:
  • 8. Inspection Procedure: • Last week of every month SEPCO HSE and Mechanical Department will check the machinery safety device ,technical condition ,location etc. • Every week on Tuesday/Wednesday check the lifting tools tackles and color coding on different location. • Special inspection will be organized as per requirements. • Chimney inspection together with HSE and Civil Department. • On every Saturday organize the tower crane foundation inspection.
  • 10. SIMPLEX: Winch M/C: all the required documents must be attached on the front side of the machine
  • 11. S.K.Const. : Limit switch broken, no tag line given while lifting the load, and no color coding of wire ropes and d-shackles
  • 12. SIMPLEX : Hydra : Limit switch broken.
  • 13.
  • 14. TOWER CRANE VERTICALITYAND FOUNDATION LEVEL CHECKED WITH CIVIL DEPT
  • 15. FOUNDATION LEVEL OF TOWER CRANE CHECKED FOUND SATISFACTORY TOWER CRANE B#1 TOWER CRANE B#2
  • 16. TOWER CRANE VERTICALITY CHECKED FOUND SATISFACTORY TOWER CRANE B#1 TOWER CRANE B#2 TOWER CRANE ESP
  • 19. • It is requested to all the Sub-contractor’s submit the updated TPI certificate for entire lifting/rigging equipment's to SEPCO Mechanical dept. as an earliest. The color coding should be done accordingly which tools has valid TPI certificate. From the month of December’-10th, It will be check by SEPCO Mechanical and HSE dept. Name of the months Types of color JAN,FEB,MARCH BLUE APR,MAY,JUN GREEN JULY,AUG,SEPT YELLOW OCT.NOV,DEC PINK
  • 20.
  • 21. Pre-operational site activity and inspection • Review the site for possible hazards: – Overhead lines – Unstable soil – High wind conditions – Other work activities in the area 1a
  • 22. Pre-operational site activity and inspection • Characteristics of the load: – Hazardous or toxic materials – Weight – Dimensions – Center of gravity • Rigging sketches and information: – Lift points – Methods of attachment – Sling angles – Load vectors 1b
  • 23. Pre-operational site activity and inspection • Rigging sketches and information: – Boom and swing angles – Crane orientations – Rated capacities – Other factors affecting equipment operation • Operating procedures: – Step-by-step instructions – Applicable rigging precautions – Safety measures – Emergency procedures 1d
  • 24. Pre-operational site activity and inspection • Additions and modifications to equipment: – Tags, instruction plates, decals reflect to modifications – Ensure safety factor has not been reduced by additions/modifications 1f
  • 25. Types of inspections and checks • Frequent inspections occur every day • Periodic inspections occur monthly • Depend upon regulation and equipment involved 2a
  • 26. Frequent inspections • Daily pre-operational walk-around or pre-startup check • Exposed moving parts should be guarded/isolated • High voltage warning signs are displayed • Crane components • Wire ropes • Freedom of rotation of all swivels • Tires • Batteries • Proper lubrication • Fluid leaks • Sheaves, drums, rigging, hardware, attachments • Operating mechanisms • Guardrails, handholds, steps • Platforms/walkways • Turntable connections 3a
  • 27. Continued….. • Boom and jib – Look for straightness/damage – Corrosion – Cracking/peeling paint – Bent lacing • Outriggers – Distortion/cracking – Welds – Extension/retraction of beams – Floats • Cab – Cleanliness of cab – Control labeling – Function of gauges, lights, signals – Service/parking brake – Seat and cab door operation – Inspection and maintenance records 3e
  • 28. Pre-startup • Field of vision – Broken/cracked windows – Adjustment/operation of brakes/clutches – Operation/calibration of boom hoist lockout – Gauges and warning lights – Controls • Inspection records must include the: – date of the inspection – signature of the inspector – serial number of critical component • Structural damage • Cracks in welded connections • Damage or defects of sheaves • Main hoist and auxiliary drum damage/defects • Even distribution of the wire rope on hoist drum • Proper wire rope integrity 3i
  • 29. Periodic inspections • Performed monthly and/or annually • Inspection varies depending on crane use and site conditions • Maintain records on: – brakes – crane hooks – hoist chains – ropes 4a
  • 30. Periodic inspections - check for: • Excessive wear of brake and clutch parts • Worn, cracked, distorted parts • Defects/damage to the main boom, jib, boom extensions 4f
  • 31. Hazard of overhead lines • Maintain appropriate line clearance • Direct contact • Indirect contact • Voltages 50 kv or less, the clearance distance is 10 feet • Voltages greater than 50kv, the clearance is 10 feet plus 4 inches for every 10 kv over 50 kv • Use signalmen to assist in maintaining proper clearances where vision is obstructed – Hand signals – Chart of hand signals 6a
  • 32. Prohibited actions • Do not exceed load ratings • Do not change the recommended counterweights • Do not lift an unsecured/unbalanced load • Do not lift two separately rigged loads at the same time • Do not wrap tag lines around one’s body 9a
  • 33. Rigging And Lifting Safety • The sling should be protected from the edges once the sling being used for lifting. • All the lifting machines, lifting tools and tackles should be with third party inspection certificate. • The overload of the lifting machines & tools and tackles is not allowed. • Hydra is only permitted for loading and unloading, it is prohibited for transporting. • No one is allowed to stay under the lifting objects. A full time person should be arranged to supervise the lifting work. • Limit switches, brakes and similar safety facilities in lifting machineries should be effective.
  • 34. 1. Only qualified operators will be permitted to operate cranes. Operators are responsible for the exercise of caution necessary for the safe operation of their equipment. 2. Operators shall immediately report unsafe conditions, including defects in the machine, to their supervisor. 3. Operators shall not permit anyone to ride the hook or load. 4. When the operator leaves his machine or repairs or being made, it is his responsibility to set the brakes, secure the boom, take the machine out of gear and turn off the engine. 5. When making a lift, the operator will take operational signals only from the man authorized to give them. An emergency stop signal given by anyone, will be acted upon by the operator. 6. It is the joint responsibility of the operator and the riggers to see that all hitches are secure and that all loose material is removed before the loads are lifted. Material should not be hoisted until it is ready to be used/put into place. 7. Safety hooks, shall be used on all operations where loads are being handled. Suspended loads shall be controlled by tag lines whenever necessary. CRANE TOOLBOX TALK:
  • 35. 8. Booms shall be equipped with a boom angle indicator and a device designed and constructed to prevent the boom from falling over backward. Boom heads, load blocks and hooks shall be painted with high visibility paint. 9. Where necessary to increase stability, cranes, except crawler cranes and boom type excavators, shall be equipped with outriggers of a design and strength suitable for the work being performed. 10. Hooks, wire rope, bearings, gears, friction clutches, chain drives and other parts subject to wear must be inspected at regular intervals and repaired or replaced as required. Records of such inspections and resultant action taken shall be maintained by the contractor. 11. Crawler, truck and locomotive cranes must be inspected monthly. A certification of performance of these inspections is required. 12. When loads are being hoisted, avoid walking under the lift or permitting an employee to be exposed to the swing of the lift.
  • 36. Daily before operating: – Check battery – Check all controls – Visually inspect – Wire rope for kinks or damage – Sheaves, drums for damage – Upper and lower limit switches. Inspection and Maintenance
  • 37. • Loads should be well secured. • Slings should be adequate to the task. • Slings should be unlinked and load balanced and secured. • No sudden stops. • No obstructions while lifting or traveling. • No loose items on load or crane before lift. • Bumping into runway stops is prohibited. • Hoist line must be vertical prior to the lift (remove slack in the hoist slowly). • No crane load should pass overhead of personnel, clear the area before making the lift. • No one is to ride the crane without permission. RIGGING:
  • 38. Crane and Rigging Safety Rules: • Check limit switches before rigging the load. • Make sure the load does not exceed rated capacity. • Know the center of gravity of the load. • Attach load above the center of gravity for stability. • Select hitch that will control the load. • Know the rated capacities of rigging and slinging. • Inspect all rigging before use. • Protect the sling from sharp corners. • Allow for increased tension due to sling angle. • Equalize loading on multiple leg slings. • Allow for load reductions when using choker hitches. • Attach tag line prior to lift.
  • 39. Continued……. • Keep personnel clear of lift area. • Wear hard hats when making overhead lifts. • Lift load a few inches and verify rigging. • Check for any loose items. • Know limitations of hoisting device. • Start and stop SLOWLY! Watch for obstructions (not only hook and load but outboard end of the bridge). • Check pathway is clear before making a lift (use a spotter for blind spots). • Verify hook completely closes. • Use appropriate hand signals. • Maintain load control at all times. • Never leave load unattended.
  • 40. Machineries situation in site.  Establishing a high effective machinery management network。  At present total 18 subcontractors have confirmed a special mechanical engineer to attend mechanical meeting and all kinds of inspection organized by Mechanical Dept. ,these mechanical engineers are responsible for regularly submitting and updating machinery accounts and documents to SEPCO Mechanical Department.  Machinery resource situation:till the end of November 2015, there are 149 set big—middle—sized machines 、 149 set machines submitted the documents 、149 set machines gotten 《machinery admittance card》 issued by SEPCO
  • 41. *New implementation and requirements.  Requested to each subcontractor must organize a especial inspection of machine once in a week.  Use firmer ,large steel plate to distribute the load and reduce the weight on the soil.  Keeping a safe distance from a power line is the key to preventing power line accidents.  All agencies who are responsible for operation & maintenance of tower crane must remove water from tower crane foundation after each raining continuously .  Provide suitable earthling for lightning protection of silo of batching plant and tower crane where the earthling resistance is less than 10 ohm.  Provide proper rain protection covers to all electric equipment’s like electric motors, electric cables, electric panel’s etc.  At no work condition, take both hooks (small & big) up to hoist limit switch position.  Hydra shall be prohibited to transport equipment and material for long distance.  For work completion Do not force on operator for wrong operation.  Tandem lifting by using hydra is strictly prohibited in our site.
  • 42. HIGHLIGHTS: SEPCO will organize the ANNUAL meeting in the first week of January 2016.Request to all subcontractors concerned engineer and Project managers kind attend the meeting.