You are in the process of developing an approximation of the monetary resources needed to complete project
work for a large-scale multinational project which will take at least seven years to complete. Your previous
projects have all been domestic with short timeframes.
As part of the process you are currently performing, what might you need to do differently compared with your
past projects?
A. Create a stakeholder engagement assessment matrix
B. Develop a more robust risk management plan
C. Consider additional enterprise environmental factors
D. Include additional organizational process assets
HINT: How might the Estimate Costs process differ with a large long-term multinational project?
Question
The correct answer is C.
Developing an approximation of the monetary resources needed to complete project work is the main
objective of the Estimate Costs process. Therefore, the question implies that you are conducting the
Estimate Costs process and asks how this process will be affected by a large long-term multinational
project.
Thus, the answer choices that relate to other project management processes can be eliminated as correct
responses. With the project lasting at least seven years, the impact of inflation over the course of the
project must be considered.
Additionally, since the project is international in scope, the project will likely be working with various
currencies that will be subject to fluctuations in relative values.
Answer
For large-scale projects that extend multiple years with multiple currencies, the fluctuations of currencies
and inflation need to be understood and built into the Estimate Costs process.
Exchange rates and inflation are considered enterprise environmental factors. Therefore, of the available
choices, considering additional enterprise environmental factors is the best response.
Answer
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.

More Related Content

Similar to PMP Exam Q & A

Tavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalTavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalSEKHAR KOMMURI
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentSiwawong Wuttipongprasert
 
LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2Jose Figueroa
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overviewcford1973
 
DAS PM RESPONSIBILITIES
DAS PM RESPONSIBILITIESDAS PM RESPONSIBILITIES
DAS PM RESPONSIBILITIESJoseph Hoffman
 
WRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docx
WRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docxWRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docx
WRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docxodiliagilby
 
What is the business value of my project?
What is the business value of my project?What is the business value of my project?
What is the business value of my project?Joe Raynus
 
Gokularani_Profile
Gokularani_ProfileGokularani_Profile
Gokularani_ProfileGokularani S
 
Sas Presentation
Sas PresentationSas Presentation
Sas Presentationpats384888
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfProject Cubicle
 

Similar to PMP Exam Q & A (20)

Tavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalTavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-Final
 
PMCourse businesscase
PMCourse businesscasePMCourse businesscase
PMCourse businesscase
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project Managment
 
U1 - S1 - Modern Project Management.pdf
U1 - S1 - Modern Project Management.pdfU1 - S1 - Modern Project Management.pdf
U1 - S1 - Modern Project Management.pdf
 
LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
DAS PM RESPONSIBILITIES
DAS PM RESPONSIBILITIESDAS PM RESPONSIBILITIES
DAS PM RESPONSIBILITIES
 
WRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docx
WRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docxWRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docx
WRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docx
 
Free PMP Exam Sample Question
Free PMP Exam Sample QuestionFree PMP Exam Sample Question
Free PMP Exam Sample Question
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
What is the business value of my project?
What is the business value of my project?What is the business value of my project?
What is the business value of my project?
 
Gokularani_Profile
Gokularani_ProfileGokularani_Profile
Gokularani_Profile
 
Sas Presentation
Sas PresentationSas Presentation
Sas Presentation
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
CSRA Havranek Hostetter Palisade 2012
CSRA Havranek Hostetter Palisade 2012CSRA Havranek Hostetter Palisade 2012
CSRA Havranek Hostetter Palisade 2012
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Project Management Process
Project Management ProcessProject Management Process
Project Management Process
 

More from OSP International LLC

Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!OSP International LLC
 
Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!OSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam SimulatorFree PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam SimulatorOSP International LLC
 
Free CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam SimulatorFree CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam SimulatorOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 

More from OSP International LLC (20)

Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!
 
Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam SimulatorFree PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam Simulator
 
Free CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam SimulatorFree CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam Simulator
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 

Recently uploaded

PUBLIC FINANCE AND TAXATION COURSE-1-4.pdf
PUBLIC FINANCE AND TAXATION COURSE-1-4.pdfPUBLIC FINANCE AND TAXATION COURSE-1-4.pdf
PUBLIC FINANCE AND TAXATION COURSE-1-4.pdfMinawBelay
 
Orientation Canvas Course Presentation.pdf
Orientation Canvas Course Presentation.pdfOrientation Canvas Course Presentation.pdf
Orientation Canvas Course Presentation.pdfElizabeth Walsh
 
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdfDiuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdfKartik Tiwari
 
Contoh Aksi Nyata Refleksi Diri ( NUR ).pdf
Contoh Aksi Nyata Refleksi Diri ( NUR ).pdfContoh Aksi Nyata Refleksi Diri ( NUR ).pdf
Contoh Aksi Nyata Refleksi Diri ( NUR ).pdfcupulin
 
dusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningdusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningMarc Dusseiller Dusjagr
 
Model Attribute _rec_name in the Odoo 17
Model Attribute _rec_name in the Odoo 17Model Attribute _rec_name in the Odoo 17
Model Attribute _rec_name in the Odoo 17Celine George
 
21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptxJoelynRubio1
 
How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17Celine George
 
Rich Dad Poor Dad ( PDFDrive.com )--.pdf
Rich Dad Poor Dad ( PDFDrive.com )--.pdfRich Dad Poor Dad ( PDFDrive.com )--.pdf
Rich Dad Poor Dad ( PDFDrive.com )--.pdfJerry Chew
 
Pharmaceutical Biotechnology VI semester.pdf
Pharmaceutical Biotechnology VI semester.pdfPharmaceutical Biotechnology VI semester.pdf
Pharmaceutical Biotechnology VI semester.pdfBALASUNDARESAN M
 
Ernest Hemingway's For Whom the Bell Tolls
Ernest Hemingway's For Whom the Bell TollsErnest Hemingway's For Whom the Bell Tolls
Ernest Hemingway's For Whom the Bell TollsPallavi Parmar
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonhttgc7rh9c
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfPondicherry University
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxAdelaideRefugio
 
Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...EduSkills OECD
 
UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024Borja Sotomayor
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
When Quality Assurance Meets Innovation in Higher Education - Report launch w...
When Quality Assurance Meets Innovation in Higher Education - Report launch w...When Quality Assurance Meets Innovation in Higher Education - Report launch w...
When Quality Assurance Meets Innovation in Higher Education - Report launch w...Gary Wood
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxCeline George
 

Recently uploaded (20)

PUBLIC FINANCE AND TAXATION COURSE-1-4.pdf
PUBLIC FINANCE AND TAXATION COURSE-1-4.pdfPUBLIC FINANCE AND TAXATION COURSE-1-4.pdf
PUBLIC FINANCE AND TAXATION COURSE-1-4.pdf
 
Orientation Canvas Course Presentation.pdf
Orientation Canvas Course Presentation.pdfOrientation Canvas Course Presentation.pdf
Orientation Canvas Course Presentation.pdf
 
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdfDiuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
 
Contoh Aksi Nyata Refleksi Diri ( NUR ).pdf
Contoh Aksi Nyata Refleksi Diri ( NUR ).pdfContoh Aksi Nyata Refleksi Diri ( NUR ).pdf
Contoh Aksi Nyata Refleksi Diri ( NUR ).pdf
 
dusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningdusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learning
 
Model Attribute _rec_name in the Odoo 17
Model Attribute _rec_name in the Odoo 17Model Attribute _rec_name in the Odoo 17
Model Attribute _rec_name in the Odoo 17
 
21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx
 
How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17
 
Rich Dad Poor Dad ( PDFDrive.com )--.pdf
Rich Dad Poor Dad ( PDFDrive.com )--.pdfRich Dad Poor Dad ( PDFDrive.com )--.pdf
Rich Dad Poor Dad ( PDFDrive.com )--.pdf
 
VAMOS CUIDAR DO NOSSO PLANETA! .
VAMOS CUIDAR DO NOSSO PLANETA!                    .VAMOS CUIDAR DO NOSSO PLANETA!                    .
VAMOS CUIDAR DO NOSSO PLANETA! .
 
Pharmaceutical Biotechnology VI semester.pdf
Pharmaceutical Biotechnology VI semester.pdfPharmaceutical Biotechnology VI semester.pdf
Pharmaceutical Biotechnology VI semester.pdf
 
Ernest Hemingway's For Whom the Bell Tolls
Ernest Hemingway's For Whom the Bell TollsErnest Hemingway's For Whom the Bell Tolls
Ernest Hemingway's For Whom the Bell Tolls
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptx
 
Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...
 
UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
When Quality Assurance Meets Innovation in Higher Education - Report launch w...
When Quality Assurance Meets Innovation in Higher Education - Report launch w...When Quality Assurance Meets Innovation in Higher Education - Report launch w...
When Quality Assurance Meets Innovation in Higher Education - Report launch w...
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptx
 

PMP Exam Q & A

  • 2. You are in the process of developing an approximation of the monetary resources needed to complete project work for a large-scale multinational project which will take at least seven years to complete. Your previous projects have all been domestic with short timeframes. As part of the process you are currently performing, what might you need to do differently compared with your past projects? A. Create a stakeholder engagement assessment matrix B. Develop a more robust risk management plan C. Consider additional enterprise environmental factors D. Include additional organizational process assets HINT: How might the Estimate Costs process differ with a large long-term multinational project? Question
  • 3. The correct answer is C. Developing an approximation of the monetary resources needed to complete project work is the main objective of the Estimate Costs process. Therefore, the question implies that you are conducting the Estimate Costs process and asks how this process will be affected by a large long-term multinational project. Thus, the answer choices that relate to other project management processes can be eliminated as correct responses. With the project lasting at least seven years, the impact of inflation over the course of the project must be considered. Additionally, since the project is international in scope, the project will likely be working with various currencies that will be subject to fluctuations in relative values. Answer
  • 4. For large-scale projects that extend multiple years with multiple currencies, the fluctuations of currencies and inflation need to be understood and built into the Estimate Costs process. Exchange rates and inflation are considered enterprise environmental factors. Therefore, of the available choices, considering additional enterprise environmental factors is the best response. Answer