Most Projects do not Meet Their Expected
Goals
 Out of all projects that successfully met their
time, budget and requirements goals, many did
not deliver the expected business results to their
parent companies…
What’s the Problem?
My Observations
 Most project teams consider project strategy to be simply an
alignment of the project’s operational goals with the firm’s
strategy by ensuring that the project’s triple constraint (time,
budget, and performance goals) is in agreement with the
organizational goals.
 Strategic focus is generally not recognized, and usually there is no
strategic alignment in monitoring and controlling activities.
 The project management has focused primarily on the operational
aspects, namely on executing processes in the most efficient way.
Question to you
What is Effectiveness?
What is Efficiency?
Operational excellence is associated with efficiency
Focus Strategically
Strategic focus is the extent to which project management
activities focus on the expected business results from the
project outcome.
 The project’s strategic value is its contribution to long-term organizational goals.
 Strategic focus is associated with business success.
 Strategic focus is associated with customer satisfaction.
 Strategic focus is associated with future prospects.
 Inspired leadership is associated with teamwork effectiveness.
The Big Picture
Portfolio Management
Align portfolio with Strategy
Maintain portfolio balance
Maximize portfolio value
Enterprise Strategy
Investment decisions
Project
Management
€ (+24%)
€millions)
-800
400
1’500 5’600
4’500
20112010
Investment
Company Strategy
Resource supply and demand, by project and Department
Investment
Project Prioritization & Optimization
Value and Risk
Portfolio Value Change
Project Strategic Commercial Operational Costs
Project
score
Rank
A 90 70 50 60 68 1
B 65 65 50 75 64 2
C 85 85 30 50 63 3
D 75 80 30 65 63 4
E 55 45 55 90 61 5
-500
0
500
1'000
1'500
2'000
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Launch probability
NPV€millions
0
20
40
60
80
100
120
2012 2013 2014 2015
Resourceuse(%)
Dept A
Dept B
Dept C
Dept D
0
500
1'000
1'500
2'000
2'500
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
€millions
50%
25%
10%
75%
90%
1'000
1'500
2'000
2'500
3'000
Pipeline value change: + 1100 m
Pipelinevalue(
Pipeline-derived Sales
Are we doing the right things?
Are we doing them the right way?
Are we getting them done well?
Are we getting the benefits?
Strategic Portfolio
Management
Business Case Strategic Project
Management
Quantitative Risk and Performance Management
Activities Outputs Outcomes BenefitsResources
Strategic Planning Framework
Discussion
 Are we doing the right things?
 Addresses business direction and program alignment to that direction
 Are we doing them the right way?
 Addresses business processes & program integration to those processes
 Are we getting them done well?
 Addresses capabilities, resources, and supporting infrastructure
 Are we getting the benefits from them?
 Addresses the proactive management of benefits
Alignment of Project Outcomes to
Business Value
 Most projects focus on efficiency and
ignore the strategic aspects of the
business.
What went wrong here????
Questions Before Project Initiation -
 Do we really understand the problem?
 Are we making the right assumptions?
 Do we really have a business case?
 What is the value?
 What are the benefits?
What is a Business Case?
 A business case is a formal way of
asking: ‘‘Because we seek a particular
set of outcomes, we have to produce
and utilize a certain collection of
outputs. Producing those outputs will
require significant work and resources.
Are you willing to fund the project ?’’
Develop Project Roadmap
Strategic Project Planning Process
1. Develop Problem
Statement
2. Develop Value
Proposition
3. Develop Strategic
Project Roadmap
4. Develop
Performance
Measures
Develop Problem
Statement
Develop Value
Proposition & Value
Map
Develop Performance Measures
Strategize
MeasureAdjust
Roadmap
Exercise:
 During the morning and afternoon rush hours one of the greatest
disasters which can occur is for a car to stall or break down on the
San Francisco/Oakland Bridge. The Bay Bridge has four lanes of
traffic in each direction. If a car stalls this eliminates 25% of the
bridge’s capacity, backs up traffic for miles and causes people to
be 10 - 30 minutes late for work.
What is the problem and for whom?
Problem and Opportunity
 Define a Problem
 What is a problem?
 Who is affected by the
problem?
 How are they affected
by the problem?
 Why is it important to
solve this problem?
 Assess an Opportunity
 Who is currently addresses this
problem?
 How is the current solution
delivered?
 How effective is the current
solution?
 What can be improved?
 Alternative approach?
PM and The Customer
Question Customer 1____ Customer N____
How is your customer currently
dealing with this task/problem?
What do they need to accomplish?
What are desired outcomes?
What approach are they
attempting?
What are the interfering factors?
What are the economic
consequences? – Costs?
PM Needs Assessment
Question Customer 1_______ Customer n_______
What is your approach to
help your customer?
What are enabling factors?
Economic rewards?
Is our cost consistent with
budget?
Now Let’s Talk Value
 What is Value?
 What is Value Proposition?
Key
Activities
Key
Partners
Key
Resources
Value
Proposition
Customer
Relationships
Channels
Customer
Segments
Revenue Stream
Cost Structure
Value Proposition and Customer Fit
18
Dynamically Interdependent
Strategic Roadmap
Activities Outputs Outcomes BenefitsResources
Tactical
Strategic
The Roadmap: Alignment of Targets
Project
Initialization
Benefits
Realization
Project
Planning
Project
Execution
Business
Case Outputs Outcomes
Project
Activities
Project
Deliverables
Business case is driven by target outcomes. Target outcomes determine
the outputs to be produced.
Strategic Planning Phase
Execution Phase
What is the Worth of My Project?
 Benefits generated by the project: relate to the value
of desirable outcomes as perceived by the funder.
 Dis-benefits arising from the project: relate to the
value of undesirable outcomes as perceived by the
funder.
 Project cost: relate to the cost of developing and
(later) maintaining the project’s outputs.
Worth of my project? = Fn (Benefits; Dis-benefits; Costs)
Challenges We Discussed
 What is the “Big Picture”?
 What is the problem you are trying to solve?
 What value do you deliver to the customer?
 What are the benefits to your company?
Summary
 Project teams need to focus on strategic aspects of the project.
 Projects are a part of the strategic business planning.
 Project success is aligned to overall business strategy.
 Project managers are accountable for achieving planned
benefits and not just the triple constraint.
 Project outcomes are defined up-front in a business case.
 Projects are selected according to their contribution to the
company’s strategy and expected benefits.
23
Build an agile organization to solve problems & provide value to
customers over time
Final Thoughts
Your Questions??
Joseph Raynus
joer@sharedynamics.com
(781) 863-9633
Thank you!!!

What is the business value of my project?

  • 1.
    LOOKING BEYOND DELIVERABLES: WHATIS THE BUSINESS VALUE OF MY PROJECT? Presented at PMI Mass Bay Chapter Professional Development Day Conference 06.19.2015 By Joseph Raynus
  • 2.
    Most Projects donot Meet Their Expected Goals  Out of all projects that successfully met their time, budget and requirements goals, many did not deliver the expected business results to their parent companies… What’s the Problem?
  • 3.
    My Observations  Mostproject teams consider project strategy to be simply an alignment of the project’s operational goals with the firm’s strategy by ensuring that the project’s triple constraint (time, budget, and performance goals) is in agreement with the organizational goals.  Strategic focus is generally not recognized, and usually there is no strategic alignment in monitoring and controlling activities.  The project management has focused primarily on the operational aspects, namely on executing processes in the most efficient way.
  • 4.
    Question to you Whatis Effectiveness? What is Efficiency? Operational excellence is associated with efficiency
  • 5.
    Focus Strategically Strategic focusis the extent to which project management activities focus on the expected business results from the project outcome.  The project’s strategic value is its contribution to long-term organizational goals.  Strategic focus is associated with business success.  Strategic focus is associated with customer satisfaction.  Strategic focus is associated with future prospects.  Inspired leadership is associated with teamwork effectiveness.
  • 6.
    The Big Picture PortfolioManagement Align portfolio with Strategy Maintain portfolio balance Maximize portfolio value Enterprise Strategy Investment decisions Project Management € (+24%) €millions) -800 400 1’500 5’600 4’500 20112010 Investment Company Strategy Resource supply and demand, by project and Department Investment Project Prioritization & Optimization Value and Risk Portfolio Value Change Project Strategic Commercial Operational Costs Project score Rank A 90 70 50 60 68 1 B 65 65 50 75 64 2 C 85 85 30 50 63 3 D 75 80 30 65 63 4 E 55 45 55 90 61 5 -500 0 500 1'000 1'500 2'000 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Launch probability NPV€millions 0 20 40 60 80 100 120 2012 2013 2014 2015 Resourceuse(%) Dept A Dept B Dept C Dept D 0 500 1'000 1'500 2'000 2'500 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 €millions 50% 25% 10% 75% 90% 1'000 1'500 2'000 2'500 3'000 Pipeline value change: + 1100 m Pipelinevalue( Pipeline-derived Sales
  • 7.
    Are we doingthe right things? Are we doing them the right way? Are we getting them done well? Are we getting the benefits? Strategic Portfolio Management Business Case Strategic Project Management Quantitative Risk and Performance Management Activities Outputs Outcomes BenefitsResources Strategic Planning Framework
  • 8.
    Discussion  Are wedoing the right things?  Addresses business direction and program alignment to that direction  Are we doing them the right way?  Addresses business processes & program integration to those processes  Are we getting them done well?  Addresses capabilities, resources, and supporting infrastructure  Are we getting the benefits from them?  Addresses the proactive management of benefits
  • 9.
    Alignment of ProjectOutcomes to Business Value  Most projects focus on efficiency and ignore the strategic aspects of the business. What went wrong here????
  • 10.
    Questions Before ProjectInitiation -  Do we really understand the problem?  Are we making the right assumptions?  Do we really have a business case?  What is the value?  What are the benefits?
  • 11.
    What is aBusiness Case?  A business case is a formal way of asking: ‘‘Because we seek a particular set of outcomes, we have to produce and utilize a certain collection of outputs. Producing those outputs will require significant work and resources. Are you willing to fund the project ?’’
  • 12.
    Develop Project Roadmap StrategicProject Planning Process 1. Develop Problem Statement 2. Develop Value Proposition 3. Develop Strategic Project Roadmap 4. Develop Performance Measures Develop Problem Statement Develop Value Proposition & Value Map Develop Performance Measures Strategize MeasureAdjust Roadmap
  • 13.
    Exercise:  During themorning and afternoon rush hours one of the greatest disasters which can occur is for a car to stall or break down on the San Francisco/Oakland Bridge. The Bay Bridge has four lanes of traffic in each direction. If a car stalls this eliminates 25% of the bridge’s capacity, backs up traffic for miles and causes people to be 10 - 30 minutes late for work. What is the problem and for whom?
  • 14.
    Problem and Opportunity Define a Problem  What is a problem?  Who is affected by the problem?  How are they affected by the problem?  Why is it important to solve this problem?  Assess an Opportunity  Who is currently addresses this problem?  How is the current solution delivered?  How effective is the current solution?  What can be improved?  Alternative approach?
  • 15.
    PM and TheCustomer Question Customer 1____ Customer N____ How is your customer currently dealing with this task/problem? What do they need to accomplish? What are desired outcomes? What approach are they attempting? What are the interfering factors? What are the economic consequences? – Costs?
  • 16.
    PM Needs Assessment QuestionCustomer 1_______ Customer n_______ What is your approach to help your customer? What are enabling factors? Economic rewards? Is our cost consistent with budget?
  • 17.
    Now Let’s TalkValue  What is Value?  What is Value Proposition?
  • 18.
  • 19.
    Strategic Roadmap Activities OutputsOutcomes BenefitsResources Tactical Strategic
  • 20.
    The Roadmap: Alignmentof Targets Project Initialization Benefits Realization Project Planning Project Execution Business Case Outputs Outcomes Project Activities Project Deliverables Business case is driven by target outcomes. Target outcomes determine the outputs to be produced. Strategic Planning Phase Execution Phase
  • 21.
    What is theWorth of My Project?  Benefits generated by the project: relate to the value of desirable outcomes as perceived by the funder.  Dis-benefits arising from the project: relate to the value of undesirable outcomes as perceived by the funder.  Project cost: relate to the cost of developing and (later) maintaining the project’s outputs. Worth of my project? = Fn (Benefits; Dis-benefits; Costs)
  • 22.
    Challenges We Discussed What is the “Big Picture”?  What is the problem you are trying to solve?  What value do you deliver to the customer?  What are the benefits to your company?
  • 23.
    Summary  Project teamsneed to focus on strategic aspects of the project.  Projects are a part of the strategic business planning.  Project success is aligned to overall business strategy.  Project managers are accountable for achieving planned benefits and not just the triple constraint.  Project outcomes are defined up-front in a business case.  Projects are selected according to their contribution to the company’s strategy and expected benefits. 23 Build an agile organization to solve problems & provide value to customers over time
  • 24.
  • 25.
  • 26.