Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
Free PMP® Exam Sample Question
1. PMP Exam
Sample Q & A
PMI®, PMP®, CAPM®, and PMBOK® Guide are trademarks of
the Project Management Institute, Inc.PMI® has not endorsed
and did not participate in the development of our products.
OSP International LLC has been reviewed and approved by the
PMI® Authorized Training Partner Program.Copyright 2020
OSP International LLC. All Rights Reserved.
2. The team has just reported to you that they have completed the
Plan Quality Management process. You review their work and
see that they have produced the quality management plan, and
made the necessary updates to the project management plan
and project documents.
QUESTION:
3. What did they forget?
A. Determine quality metrics
B. Define quality roles and responsibilities
C. Revise the lessons learned register
D. Update the requirements traceability matrix
HINT: An output of the Plan Quality Management process which
serves as an input to the Manage Quality and Control Quality
processes is missing.
QUESTION:
4. The correct answer is A.
A quality metric specifically describes a project or product
attribute and how the Manage Quality and Control Quality
processes will verify compliance with it. Quality metrics are an
output of the Plan Quality Management process and were not
stated as being completed. Therefore, the quality metrics are
what were most likely missed by the project team.
ANSWER:
5. The question suggests that the Plan Quality Management
process was performed, and an element of this process was
missed. Quality metrics are a project document that serves as
one of the outputs of the Plan Quality Management process.
This document was not mentioned in the scenario. All of the
other outputs are stated as being completed.
ANSWER:
6. A quality metric, an input to the Manage Quality and Control
Quality processes, specifically describes a project or product
attribute and how these processes will verify compliance with it.
Therefore, quality metrics are what we're most likely missed by
the project team.
ANSWER:
7. One may argue that quality metrics should be part of the
quality management plan just like the quality roles and
responsibilities. While this may sound counter-intuitive, the
<em>PMBOK<sup>®</sup> Guide</em> describes quality
metrics as a separate standalone document. The complete list
of the components of the project management plan vs. project
documents can be found on page 89, Table 4-1. Project
Management Plan and Project Documents.
ANSWER:
8. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.
OSP International LLC has been reviewed and approved by the PMI® Authorized Training Partner
Program.