SlideShare a Scribd company logo
1 of 5
Download to read offline
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 796
EFFECT OF PROJECT COST AND TIME MONITORING ON
PROGRESS OF CONSTRUCTION PROJCT
Shreyash Raut1
, S S Pimplikar2
, Karan Sawant3
1
Research Graduate ME Civil Construction & Management, Civil Engineering, Maharashtra Institute Of
Technology,Pune,Maharashtra,India,srraut16@gmail.com
2
Professor & Head Of Department, Civil Engineering, Maharashtra Institute Of Technology, Pune, Maharashtra,
India, sunil_pimplikar@rediffmail.com
3
ME Civil Construction & Management, Civil Engineering, Maharashtra Institute Of Technology, Pune,
Maharashtra, India
Abstract
During the construction phase it is the prime responsibility of project managers to monitor cost and avoid any overruns to
maintain the cost baseline. Project monitoring is an ongoing process and its importance cannot be undermined during the project
life cycle. It can be monitored by using traditional approach of direct reporting of actual cost against budget. However, the
comparison of budget versus actual spending does not indicate the worth of the work which is completed at any given time. This
approach does not portray the true cost performance of the project. In general Construction cost control consists of simply
monitoring actual performance against cost estimates and identifying variances. It has been usually seen there is a lack of
systematic and automated evaluation and monitoring system in construction project. Due to these limitations, this paper discusses
traditional project monitoring practices in construction industry and proposes some guideline for improving cost management in
fast, complex and uncertain construction projects. Such guideline involves the integrated application of Average Index formula
and S-curves. This study discusses the result of questionairre survey conducted on various construction sectors to show how cost
is compare as prime constraint in real estate sector.
Index Terms: Cost management, project monitoring, Average index formula.
--------------------------------------------------------------------***----------------------------------------------------------------------
1. INTRODUCTION
Effective cost monitoring and controlling has received much
attention in the construction industry due to excessive cost
escalation and woefull profit margin of some contractors.
The life cycle of construction projects comprise of different
phases including planning initiation, procurement contract
award and contract management phase. [6]. Government
construction client panel bench-marking study carried out in
1999 in UK shows that three quarter of the 66 projects
studies on the central government construction project
exceeded 50% of their contract price [4]. It is usually seen in
construction sector cost and time management is given more
importance.
1.1 Monitoring in construction
Project monitoring is the process where the construction
resources of project is managed through the best methods
and techniques so that the client does not suffer the losses
when carrying out the project activities. According to
Barnes, the main problem that accounts for poor cost
management by traditional methods is flaws in cost
estimates and cost control process , inadequate information
modeling , and lack of integration of cost management and
production management system[3].Project monitoring is
considered to be a managerial process, which aims to
generate information to support decision-making and to
stimulate cost reduction , value improvement and
continuous improvement in the organization. Cost
monitoring is understood as being composed of two main
processes: cost estimating processes and cost planning and
control processes. The objective of cost estimating process
is to estimate the cost of products and processes involved in
production. This requires a thorough understanding of the
design, contracts and production in order to properly model
the consumption of resources by transformation and flow
(non-value adding) activities. This process starts usually by
producing budget normally at early project phase. After cost
have been estimated, the financial performance must be
planned and controlled during the production phase by
means of a cycle composed by two sub-processes ,cost
planning and cost control. Cost planning involves refining
the initial cost estimate and generating a project cash flow,
based on additional information that is generated along the
project .The aim of the cost control sub-process is to
monitor actual cost performance and identify improvement
opportunities, which must be dealt by corrective actions.
According to Zubair Ahmed Memon, An integrated
simulation model ,named DCM (Digitalizing the
Construction Monitoring) is developed to integrate digital
images of construction scene with AutoCAD drawings and
it resolves the existing project progress reporting problems.
The DCM model improve the decision-making and
productivity of construction activity[8]
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 797
2. AIMS & OBJECTIVES
In construction almost all client are interested in obtaining
fully functional facilities completed in time, cost and
quality. A builder who is able to construct within the
estimated time and budget, to right standard and scope is an
excellent builder. The questionairre survey form was
designed to verify the time, cost and quality constraints. The
main aim of the paper is to reflect how cost is been consider
as a prime constraint in real estate sector. The focus of
questionairre was to get information about monitoring from
four field of construction industry such as Road &
highways, Bridges & Stadium, Real estate and Oil & gas. It
also shows the relation between project control and
monitoring with progress of project.
3. QUATIONAIRRE SURVEY
A questionairre survey form was designed to collect data. It
consists of private and public sector projects such as Roads
& Highway , Bridges & stadiums, Real estate and oil & gas.
Data had been collected by face to face interview & by
getting draft of questionairre filled through e-mails.
Following table shows the number of respondent from each
sector.
Table -1: Total no. of respondent
Sector No of respondent
Roads & Highway 09
Bridges & Stadiums 08
Real Estate 09
Oil & Gas 10
The data was collected by using measurement on Likert
scale. Five scale rating was used to determine the influence.
The analysis was based on the qualitative measurement or
ranking system. Rating for the questionairre for each
parameter has been given separately as below. Average
Index Formula as given by Abd.Majid[1] has been used for
analysis-
∑ (β*n)
Average Index (A I ) =
N
‘n’ is the frequency of the respondents
‘N’ is the total number of respondents
3.1 To determine rating of time, cost & quality for
each sector
Weightage given is as follows-
Table -2: Weightage table to determine rating of time, cost
& quality
Ranking by Respondent Corresponding
weightage(β)
1 3
2 2
3 1
With the rating scale as below,
Less importance (1.00 < Average Index <1.5)
Average Importance (1.5 < Average Index < 2.5)
High Importance (2.5 < Average Index < 3.5)
Level of importance can be found by the formula,
Rating of parameter
Level of Importance (%) = *100
6
3.2 Data collection for each sector
Table -3: Data collection of Roads & Highways sector
Desc No of Respondent AI %
1 2 3 4 5 6 7 8 9
Time 1 2 2 1 2 1 3 2 1 2.3 38.8
Cost 2 1 3 2 1 3 2 1 3 2.0 33.3
Quality 3 3 1 3 3 2 1 3 2 1.6 27.7
Table -4: Data collection of Bridges & Stadiums sector
Desc No of Respondent AI %
1 2 3 4 5 6 7 8
Time 1 1 2 1 2 1 2 2 2.5 41.6
Cost 3 3 1 2 3 3 3 3 1.3 22.9
Quality 2 2 3 3 1 2 1 1 2.1 35.4
Table -5: Data collection of Real estate sector
Desc No of Respondent AI %
1 2 3 4 5 6 7 8 9
Time 2 1 3 2 1 3 3 1 3 1.8 31.4
Cost 1 2 2 1 2 1 2 2 1 2.4 40.7
Quality 3 3 1 3 3 2 1 3 2 1.6 27.7
Table -6: Data collection of oil & gas sector
Desc No of Respondent AI %
1 2 3 4 5 6 7 8 9 0
Time 2 1 3 2 1 3 2 1 3 2 2.0 33.3
Cost 3 3 1 3 3 2 1 3 2 3 1.6 26.6
Quality 1 2 2 1 2 1 3 2 1 1 2.4 40.0
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 798
A graph plotted from the calculation & results shown in 3.2,
summarizes the level of importance for monitoring time,
cost and quality in different sector of construction industry-
Table -7: Summary table
Sectors Time (%) Cost (%) Quality(%)
Roads &
Highways
38.88 33.33 27.77
Bridges &
Stadiums
41.66 22.92 35.42
Real estate 31.48 40.74 27.77
Oil & Gas 33.33 26.67 40
Chart -1: Monitoring status for cost, time & quality in
different sectors.
Key finding from above graph-
 It is seen that in roads & highways sector more
importance is given for time as compare to cost and
quality for monitoring.
 In case of bridges and stadium, time and quality are
more important to complete the project within time
frame and of desired quality.
 In Real estate sector as it is mostly commercial in
nature, more importance is given for cost
monitoring.
 Oil & gas which is only sector where quality has
been given more importance as compared to other
sectors. Importance has been given for time also for
monitoring purpose.
4. PROJECT MONITORING & CONTROLLING
As project grows in size and complexity, the ability to plan ,
monitor and control the project has become a key project
management function. Like any other business, builders,
contractors and developers have to plan and organize their
day to day activities in order to manage effectively. The task
of project monitoring and control is to give a fair indication
of the existence and the extent of problems associated with a
project. For monitoring and controlling purposes, the
original detailed cost estimate is typically converted to a
project budget, and the project budget is used subsequently
as a guide for management. According to Al-jibouri, within
construction, divergences from the original plan will occur ;
therefore project should have a control cycle as follows with
the aim of completing project within acceptable time and
budget[2].Monitoring and control cycle consists-
 Make a plan
 Implement the plan
 Monitor the actual output and record it.
 Report the actual, the planned parameters and their
variations.
 Take corrective action on the variation
Fig -1: Monitoring and control cycle
A project cost can be usually classified into direct, indirect
and overhead cost. During the budgeting process, all these
costs are summed up to develop a cost baseline A cost
baseline is defined as cumulative time-phased budget that
will be used to measure and monitor the current and future
project cost performance[7].It is graphically represented in
the form of S-curve and it is an important cost monitoring
tool. It allows the user to see the project cash flow over the
period of time and make it possible to forecast the trends of
future spending. The purpose of project monitoring and
controlling is to allow the project to be completed within the
approved budget and time.
4.1 Relation between project control , monitoring
and project progress
An effective project performance of the project control
cannot be achieved only by monitoring the actual physical
progress with the planned progress and actual spending with
the budgeted values. Harris and McCaffer describe
monitoring as the act of checking actual progress and actual
resource usage against planned and the act of taking
0
5
10
15
20
25
30
35
40
45
Levelofimportance(%)
Sectors
Time (%)
Cost (%)
Quality(%)
Make a plan
Implement the
plan
Monitor the
actual output
and record it
Report the
actual, the
planned
parameters and
their variations.
Take corrective
action on the
variation
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 799
decision to alter the likely future outcome and bring the
project back on the planned schedule is control [5].The data
is collected from the questionairres by respondent at several
stages of project showing the weightage for project control
and project progress. The questionairre was prepared in
order to determine whether project progress control and
monitoring affects the progress of project. Therefore a close
end questionairre was designed for this study; to identify the
current practice. A typical S-curve was used. Weightage
given to find out the relation between project control &
monitoring and project progress were as follow,
Table -8: Weightage table to find relation between project
control & monitoring and project progress
Ranking given by
respondent
Weightage Range
(%)
Average
Weightage (%)
1 75 to 100 87.5
2 50 to 75 62.5
3 25 to 50 37.5
4 0 to 25 12.5
Weightage given by the respondent from various
constructions sector (Roads & highways, Bridges &
stadiums, Real estate and Oil & gas) for the progress
monitoring and control into stages of project i.e. Award of
project, start of project, middle of project and closure of
project. Following were the data collection and calculation
showing average rating given to each parameter in all four
field of construction industry-
Table -9: Data collection for project stage in different
sectors
Project
stage
Sector
Average
Index
Roads &
Highways
Bridges
&
Stadiums
Real
Estate
Oil
&
Gas
Award 1 1 2 1 81.25 %
Start 2 2 1 2 68.75 %
Middle 4 3 3 3 31.25 %
Closure 3 4 4 4 18.75 %
Assuming that project progress at Award stage is 5%, at
Start stage is 30%, at Middle stage is 60% and at closure
stage is 100%.A S-curve is been plotted to show the relation
between project control & monitoring and project progress
as shown below in chart2.
Table -10: Summary table
Project Stage Project
Monitoring &
control
Project Progress
Award 81.25 % 5%
Start 68.75 % 30%
Middle 31.25 % 60%
Closure 18.75 % 100%
Chart -2: S-curve showing relation between project control
and project progress.
From the above plotted graph some findings interpreted
were,
 It is seen that overall project monitoring and
control process goes on decreasing as project
progresses.
 Project monitoring & control process is maximum
from award stage to start stage of project but it is
less from middle stage to closure stage of project.
 For any project start stage to middle stage is very
important hence it is necessary to monitor and
control the project but from above plotted graph it
is seen that monitoring and controlling process
goes decreasing which can be a major cause for
delays.
CONCLUSIONS
This research has identified that the weightage given for
time, cost and quality in different sector is not the same. The
main finding can be said that in real estate more weightage
is given for cost rather than time and quality. Successful
implementation of average index can result in the relation
between project monitoring and progress of project .Graph
clearly shows that project monitoring decreases as the
project progresses. Thus can be a major reason for project
delays, cost and time overruns.
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
Award
Start
Middle
Closure
Precentage
Project Stages Project
Monitor…
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 800
REFERENCES
[1]. Adb.Majid, M.Z. Non-Excusable Delays in
construction. Department of civil and Building Engineering,
Laughborough University Loughborough, Leicestershire,
UK (1997):Ph.D. Thesis.
[2]. Al-jibouri,S. H (2003):Monitoring system and their
effectiveness for project cost control in constructions.
International Journal of Project Management 21:145-154.
[3].Barnes, N.M. cost modeling - "An integrated approach
to planning and cost control Engineering and process
Economics". n.2,p 24-51,1977.
[4]. Benchmarking the Government Client Stage,1999,2
study.
[5]. Harris,F. and McCaffer. R.,2001. Modern Construction
Management, 5th Edition Black well Science Ltd, Malden
USA.
[6]. Mohd Faris Khamidi and Waris Ali Khan, "The cost
monitoring of construction projects through earned value
analysis", International conference on economics and
finance research,Singapore,2011.
[7]. PMI Project Management Book Of Knowledge,(2004)
3rd Edition.
[8]. Zubair Ahmed Memon, Mudh. Zaimi Abd. Majidand
Mushairry Mustaffar, 'A Systematic approach for
monitoring and Evaluating the construction project
progress' Journal-The Institution of Engineers, Malaysia
(vol. 67,No. 3, September 2006).
BIOGRAPHIES
Shreyash R Raut doing research
gradute persuing Master in
Engineering Construction &
Management from Maharashtra
Institute of Technology, Pune.
Prof.Dr.Sunil S.Pimplikar is
currently working as Professor and
Head of Civil Engineering
Department at Maharashtra Institute
of Technology, Pune. He is the co-
ordinator and faculty of the Post
Graduate Program in Construction
and Management. His research
interests are Accident Studies, Total
Quality Management, Contracts
Management and Human Resource
Management .

More Related Content

What's hot

An Automated Input Data Management Approach for Discrete Event Simulation App...
An Automated Input Data Management Approach for Discrete Event Simulation App...An Automated Input Data Management Approach for Discrete Event Simulation App...
An Automated Input Data Management Approach for Discrete Event Simulation App...
IJERA Editor
 

What's hot (17)

The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
 
A survey on modeling guidelines for quantity takeoff-oriented BIM-based design
A survey on modeling guidelines for quantity takeoff-oriented BIM-based designA survey on modeling guidelines for quantity takeoff-oriented BIM-based design
A survey on modeling guidelines for quantity takeoff-oriented BIM-based design
 
T o p i c 3
T o p i c  3T o p i c  3
T o p i c 3
 
Duration
DurationDuration
Duration
 
Software presentation
Software presentationSoftware presentation
Software presentation
 
RME-085 TQM Unit-5 part 5
RME-085 TQM Unit-5  part 5RME-085 TQM Unit-5  part 5
RME-085 TQM Unit-5 part 5
 
_4D_quality_.pdf
_4D_quality_.pdf_4D_quality_.pdf
_4D_quality_.pdf
 
F013143840
F013143840F013143840
F013143840
 
An Automated Input Data Management Approach for Discrete Event Simulation App...
An Automated Input Data Management Approach for Discrete Event Simulation App...An Automated Input Data Management Approach for Discrete Event Simulation App...
An Automated Input Data Management Approach for Discrete Event Simulation App...
 
Software Report
Software ReportSoftware Report
Software Report
 
Rme 085 tqm unit-3 part 2
Rme 085 tqm unit-3  part 2Rme 085 tqm unit-3  part 2
Rme 085 tqm unit-3 part 2
 
Estimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential BuildingEstimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential Building
 
IRJET- Analysis and Design of G+3 Storey and G+25 Storey RC Frame Building St...
IRJET- Analysis and Design of G+3 Storey and G+25 Storey RC Frame Building St...IRJET- Analysis and Design of G+3 Storey and G+25 Storey RC Frame Building St...
IRJET- Analysis and Design of G+3 Storey and G+25 Storey RC Frame Building St...
 
cost estimation techniques
cost estimation techniquescost estimation techniques
cost estimation techniques
 
Bl26411418
Bl26411418Bl26411418
Bl26411418
 
Jce 64 2012_8_3_1036_en
Jce 64 2012_8_3_1036_enJce 64 2012_8_3_1036_en
Jce 64 2012_8_3_1036_en
 
ME6501 Unit 1 introduction to cad
ME6501 Unit 1 introduction to cadME6501 Unit 1 introduction to cad
ME6501 Unit 1 introduction to cad
 

Viewers also liked

사이버컴과 네트워크분석 6주차 2
사이버컴과 네트워크분석 6주차 2사이버컴과 네트워크분석 6주차 2
사이버컴과 네트워크분석 6주차 2
Han Woo PARK
 
Post colonial perspectives
Post colonial perspectivesPost colonial perspectives
Post colonial perspectives
Simon Gummer
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Francis Ho
 

Viewers also liked (18)

Keynote slides: Creating the Future of Arab Media
Keynote slides: Creating the Future of Arab MediaKeynote slides: Creating the Future of Arab Media
Keynote slides: Creating the Future of Arab Media
 
Keg.io
Keg.ioKeg.io
Keg.io
 
The New Advertising: a primer for brands
The New Advertising: a primer for brandsThe New Advertising: a primer for brands
The New Advertising: a primer for brands
 
07 arts-312-359-h.pen
07 arts-312-359-h.pen07 arts-312-359-h.pen
07 arts-312-359-h.pen
 
MBA_ELBA
MBA_ELBAMBA_ELBA
MBA_ELBA
 
Learn more about
Learn more aboutLearn more about
Learn more about
 
사이버컴과 네트워크분석 6주차 2
사이버컴과 네트워크분석 6주차 2사이버컴과 네트워크분석 6주차 2
사이버컴과 네트워크분석 6주차 2
 
M2Mobi Airport Solution
M2Mobi Airport SolutionM2Mobi Airport Solution
M2Mobi Airport Solution
 
Grupo conico
Grupo conicoGrupo conico
Grupo conico
 
Assessment of hygienic practices among pig slaughterhouses and markets in Chi...
Assessment of hygienic practices among pig slaughterhouses and markets in Chi...Assessment of hygienic practices among pig slaughterhouses and markets in Chi...
Assessment of hygienic practices among pig slaughterhouses and markets in Chi...
 
Eye Tracking, Journal of Marketing Research
Eye Tracking, Journal of Marketing ResearchEye Tracking, Journal of Marketing Research
Eye Tracking, Journal of Marketing Research
 
Post colonial perspectives
Post colonial perspectivesPost colonial perspectives
Post colonial perspectives
 
Microbrewery in india- raw materials
Microbrewery in india- raw materialsMicrobrewery in india- raw materials
Microbrewery in india- raw materials
 
Beer
BeerBeer
Beer
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
 
Ventes en ligne cross-border en Europe : Pourquoi la logistique est-elle impo...
Ventes en ligne cross-border en Europe : Pourquoi la logistique est-elle impo...Ventes en ligne cross-border en Europe : Pourquoi la logistique est-elle impo...
Ventes en ligne cross-border en Europe : Pourquoi la logistique est-elle impo...
 
Tender
TenderTender
Tender
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 

Similar to Effect of project cost and time monitoring on progress of construction projct

Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
IAEME Publication
 
Performance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsPerformance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projects
iaemedu
 

Similar to Effect of project cost and time monitoring on progress of construction projct (20)

Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
Value stream mapping a case study of automotive
Value stream mapping a case study of automotiveValue stream mapping a case study of automotive
Value stream mapping a case study of automotive
 
Value stream mapping
Value stream mappingValue stream mapping
Value stream mapping
 
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONREWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
 
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
 
RURAL ROAD DESIGN ENHANCEMENT USING CIVIL 3D
RURAL ROAD DESIGN ENHANCEMENT USING CIVIL 3DRURAL ROAD DESIGN ENHANCEMENT USING CIVIL 3D
RURAL ROAD DESIGN ENHANCEMENT USING CIVIL 3D
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projects
 
Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
 
Performance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsPerformance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projects
 
Quality – cost trade off (qct) for contractor selection
Quality – cost trade off (qct) for contractor selectionQuality – cost trade off (qct) for contractor selection
Quality – cost trade off (qct) for contractor selection
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
 
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
 
Predicting construction project duration with support vector machine
Predicting construction project duration with support vector machinePredicting construction project duration with support vector machine
Predicting construction project duration with support vector machine
 
A Review of _Urban Water Networks Management Using GIS
A Review of _Urban Water Networks Management Using GISA Review of _Urban Water Networks Management Using GIS
A Review of _Urban Water Networks Management Using GIS
 

More from eSAT Journals

Material management in construction – a case study
Material management in construction – a case studyMaterial management in construction – a case study
Material management in construction – a case study
eSAT Journals
 
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialsLaboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
eSAT Journals
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources management
eSAT Journals
 
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodEstimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn method
eSAT Journals
 
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...
eSAT Journals
 

More from eSAT Journals (20)

Mechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementsMechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavements
 
Material management in construction – a case study
Material management in construction – a case studyMaterial management in construction – a case study
Material management in construction – a case study
 
Managing drought short term strategies in semi arid regions a case study
Managing drought    short term strategies in semi arid regions  a case studyManaging drought    short term strategies in semi arid regions  a case study
Managing drought short term strategies in semi arid regions a case study
 
Life cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreLife cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangalore
 
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialsLaboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
 
Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...
 
Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...
 
Influence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizerInfluence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizer
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources management
 
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
 
Factors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteFactors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concrete
 
Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...
 
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
 
Evaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabsEvaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabs
 
Evaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaEvaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in india
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...
 
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodEstimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn method
 
Estimation of morphometric parameters and runoff using rs &amp; gis techniques
Estimation of morphometric parameters and runoff using rs &amp; gis techniquesEstimation of morphometric parameters and runoff using rs &amp; gis techniques
Estimation of morphometric parameters and runoff using rs &amp; gis techniques
 
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...
 
Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...
 

Recently uploaded

Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 

Recently uploaded (20)

Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICSUNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 

Effect of project cost and time monitoring on progress of construction projct

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 796 EFFECT OF PROJECT COST AND TIME MONITORING ON PROGRESS OF CONSTRUCTION PROJCT Shreyash Raut1 , S S Pimplikar2 , Karan Sawant3 1 Research Graduate ME Civil Construction & Management, Civil Engineering, Maharashtra Institute Of Technology,Pune,Maharashtra,India,srraut16@gmail.com 2 Professor & Head Of Department, Civil Engineering, Maharashtra Institute Of Technology, Pune, Maharashtra, India, sunil_pimplikar@rediffmail.com 3 ME Civil Construction & Management, Civil Engineering, Maharashtra Institute Of Technology, Pune, Maharashtra, India Abstract During the construction phase it is the prime responsibility of project managers to monitor cost and avoid any overruns to maintain the cost baseline. Project monitoring is an ongoing process and its importance cannot be undermined during the project life cycle. It can be monitored by using traditional approach of direct reporting of actual cost against budget. However, the comparison of budget versus actual spending does not indicate the worth of the work which is completed at any given time. This approach does not portray the true cost performance of the project. In general Construction cost control consists of simply monitoring actual performance against cost estimates and identifying variances. It has been usually seen there is a lack of systematic and automated evaluation and monitoring system in construction project. Due to these limitations, this paper discusses traditional project monitoring practices in construction industry and proposes some guideline for improving cost management in fast, complex and uncertain construction projects. Such guideline involves the integrated application of Average Index formula and S-curves. This study discusses the result of questionairre survey conducted on various construction sectors to show how cost is compare as prime constraint in real estate sector. Index Terms: Cost management, project monitoring, Average index formula. --------------------------------------------------------------------***---------------------------------------------------------------------- 1. INTRODUCTION Effective cost monitoring and controlling has received much attention in the construction industry due to excessive cost escalation and woefull profit margin of some contractors. The life cycle of construction projects comprise of different phases including planning initiation, procurement contract award and contract management phase. [6]. Government construction client panel bench-marking study carried out in 1999 in UK shows that three quarter of the 66 projects studies on the central government construction project exceeded 50% of their contract price [4]. It is usually seen in construction sector cost and time management is given more importance. 1.1 Monitoring in construction Project monitoring is the process where the construction resources of project is managed through the best methods and techniques so that the client does not suffer the losses when carrying out the project activities. According to Barnes, the main problem that accounts for poor cost management by traditional methods is flaws in cost estimates and cost control process , inadequate information modeling , and lack of integration of cost management and production management system[3].Project monitoring is considered to be a managerial process, which aims to generate information to support decision-making and to stimulate cost reduction , value improvement and continuous improvement in the organization. Cost monitoring is understood as being composed of two main processes: cost estimating processes and cost planning and control processes. The objective of cost estimating process is to estimate the cost of products and processes involved in production. This requires a thorough understanding of the design, contracts and production in order to properly model the consumption of resources by transformation and flow (non-value adding) activities. This process starts usually by producing budget normally at early project phase. After cost have been estimated, the financial performance must be planned and controlled during the production phase by means of a cycle composed by two sub-processes ,cost planning and cost control. Cost planning involves refining the initial cost estimate and generating a project cash flow, based on additional information that is generated along the project .The aim of the cost control sub-process is to monitor actual cost performance and identify improvement opportunities, which must be dealt by corrective actions. According to Zubair Ahmed Memon, An integrated simulation model ,named DCM (Digitalizing the Construction Monitoring) is developed to integrate digital images of construction scene with AutoCAD drawings and it resolves the existing project progress reporting problems. The DCM model improve the decision-making and productivity of construction activity[8]
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 797 2. AIMS & OBJECTIVES In construction almost all client are interested in obtaining fully functional facilities completed in time, cost and quality. A builder who is able to construct within the estimated time and budget, to right standard and scope is an excellent builder. The questionairre survey form was designed to verify the time, cost and quality constraints. The main aim of the paper is to reflect how cost is been consider as a prime constraint in real estate sector. The focus of questionairre was to get information about monitoring from four field of construction industry such as Road & highways, Bridges & Stadium, Real estate and Oil & gas. It also shows the relation between project control and monitoring with progress of project. 3. QUATIONAIRRE SURVEY A questionairre survey form was designed to collect data. It consists of private and public sector projects such as Roads & Highway , Bridges & stadiums, Real estate and oil & gas. Data had been collected by face to face interview & by getting draft of questionairre filled through e-mails. Following table shows the number of respondent from each sector. Table -1: Total no. of respondent Sector No of respondent Roads & Highway 09 Bridges & Stadiums 08 Real Estate 09 Oil & Gas 10 The data was collected by using measurement on Likert scale. Five scale rating was used to determine the influence. The analysis was based on the qualitative measurement or ranking system. Rating for the questionairre for each parameter has been given separately as below. Average Index Formula as given by Abd.Majid[1] has been used for analysis- ∑ (β*n) Average Index (A I ) = N ‘n’ is the frequency of the respondents ‘N’ is the total number of respondents 3.1 To determine rating of time, cost & quality for each sector Weightage given is as follows- Table -2: Weightage table to determine rating of time, cost & quality Ranking by Respondent Corresponding weightage(β) 1 3 2 2 3 1 With the rating scale as below, Less importance (1.00 < Average Index <1.5) Average Importance (1.5 < Average Index < 2.5) High Importance (2.5 < Average Index < 3.5) Level of importance can be found by the formula, Rating of parameter Level of Importance (%) = *100 6 3.2 Data collection for each sector Table -3: Data collection of Roads & Highways sector Desc No of Respondent AI % 1 2 3 4 5 6 7 8 9 Time 1 2 2 1 2 1 3 2 1 2.3 38.8 Cost 2 1 3 2 1 3 2 1 3 2.0 33.3 Quality 3 3 1 3 3 2 1 3 2 1.6 27.7 Table -4: Data collection of Bridges & Stadiums sector Desc No of Respondent AI % 1 2 3 4 5 6 7 8 Time 1 1 2 1 2 1 2 2 2.5 41.6 Cost 3 3 1 2 3 3 3 3 1.3 22.9 Quality 2 2 3 3 1 2 1 1 2.1 35.4 Table -5: Data collection of Real estate sector Desc No of Respondent AI % 1 2 3 4 5 6 7 8 9 Time 2 1 3 2 1 3 3 1 3 1.8 31.4 Cost 1 2 2 1 2 1 2 2 1 2.4 40.7 Quality 3 3 1 3 3 2 1 3 2 1.6 27.7 Table -6: Data collection of oil & gas sector Desc No of Respondent AI % 1 2 3 4 5 6 7 8 9 0 Time 2 1 3 2 1 3 2 1 3 2 2.0 33.3 Cost 3 3 1 3 3 2 1 3 2 3 1.6 26.6 Quality 1 2 2 1 2 1 3 2 1 1 2.4 40.0
  • 3. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 798 A graph plotted from the calculation & results shown in 3.2, summarizes the level of importance for monitoring time, cost and quality in different sector of construction industry- Table -7: Summary table Sectors Time (%) Cost (%) Quality(%) Roads & Highways 38.88 33.33 27.77 Bridges & Stadiums 41.66 22.92 35.42 Real estate 31.48 40.74 27.77 Oil & Gas 33.33 26.67 40 Chart -1: Monitoring status for cost, time & quality in different sectors. Key finding from above graph-  It is seen that in roads & highways sector more importance is given for time as compare to cost and quality for monitoring.  In case of bridges and stadium, time and quality are more important to complete the project within time frame and of desired quality.  In Real estate sector as it is mostly commercial in nature, more importance is given for cost monitoring.  Oil & gas which is only sector where quality has been given more importance as compared to other sectors. Importance has been given for time also for monitoring purpose. 4. PROJECT MONITORING & CONTROLLING As project grows in size and complexity, the ability to plan , monitor and control the project has become a key project management function. Like any other business, builders, contractors and developers have to plan and organize their day to day activities in order to manage effectively. The task of project monitoring and control is to give a fair indication of the existence and the extent of problems associated with a project. For monitoring and controlling purposes, the original detailed cost estimate is typically converted to a project budget, and the project budget is used subsequently as a guide for management. According to Al-jibouri, within construction, divergences from the original plan will occur ; therefore project should have a control cycle as follows with the aim of completing project within acceptable time and budget[2].Monitoring and control cycle consists-  Make a plan  Implement the plan  Monitor the actual output and record it.  Report the actual, the planned parameters and their variations.  Take corrective action on the variation Fig -1: Monitoring and control cycle A project cost can be usually classified into direct, indirect and overhead cost. During the budgeting process, all these costs are summed up to develop a cost baseline A cost baseline is defined as cumulative time-phased budget that will be used to measure and monitor the current and future project cost performance[7].It is graphically represented in the form of S-curve and it is an important cost monitoring tool. It allows the user to see the project cash flow over the period of time and make it possible to forecast the trends of future spending. The purpose of project monitoring and controlling is to allow the project to be completed within the approved budget and time. 4.1 Relation between project control , monitoring and project progress An effective project performance of the project control cannot be achieved only by monitoring the actual physical progress with the planned progress and actual spending with the budgeted values. Harris and McCaffer describe monitoring as the act of checking actual progress and actual resource usage against planned and the act of taking 0 5 10 15 20 25 30 35 40 45 Levelofimportance(%) Sectors Time (%) Cost (%) Quality(%) Make a plan Implement the plan Monitor the actual output and record it Report the actual, the planned parameters and their variations. Take corrective action on the variation
  • 4. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 799 decision to alter the likely future outcome and bring the project back on the planned schedule is control [5].The data is collected from the questionairres by respondent at several stages of project showing the weightage for project control and project progress. The questionairre was prepared in order to determine whether project progress control and monitoring affects the progress of project. Therefore a close end questionairre was designed for this study; to identify the current practice. A typical S-curve was used. Weightage given to find out the relation between project control & monitoring and project progress were as follow, Table -8: Weightage table to find relation between project control & monitoring and project progress Ranking given by respondent Weightage Range (%) Average Weightage (%) 1 75 to 100 87.5 2 50 to 75 62.5 3 25 to 50 37.5 4 0 to 25 12.5 Weightage given by the respondent from various constructions sector (Roads & highways, Bridges & stadiums, Real estate and Oil & gas) for the progress monitoring and control into stages of project i.e. Award of project, start of project, middle of project and closure of project. Following were the data collection and calculation showing average rating given to each parameter in all four field of construction industry- Table -9: Data collection for project stage in different sectors Project stage Sector Average Index Roads & Highways Bridges & Stadiums Real Estate Oil & Gas Award 1 1 2 1 81.25 % Start 2 2 1 2 68.75 % Middle 4 3 3 3 31.25 % Closure 3 4 4 4 18.75 % Assuming that project progress at Award stage is 5%, at Start stage is 30%, at Middle stage is 60% and at closure stage is 100%.A S-curve is been plotted to show the relation between project control & monitoring and project progress as shown below in chart2. Table -10: Summary table Project Stage Project Monitoring & control Project Progress Award 81.25 % 5% Start 68.75 % 30% Middle 31.25 % 60% Closure 18.75 % 100% Chart -2: S-curve showing relation between project control and project progress. From the above plotted graph some findings interpreted were,  It is seen that overall project monitoring and control process goes on decreasing as project progresses.  Project monitoring & control process is maximum from award stage to start stage of project but it is less from middle stage to closure stage of project.  For any project start stage to middle stage is very important hence it is necessary to monitor and control the project but from above plotted graph it is seen that monitoring and controlling process goes decreasing which can be a major cause for delays. CONCLUSIONS This research has identified that the weightage given for time, cost and quality in different sector is not the same. The main finding can be said that in real estate more weightage is given for cost rather than time and quality. Successful implementation of average index can result in the relation between project monitoring and progress of project .Graph clearly shows that project monitoring decreases as the project progresses. Thus can be a major reason for project delays, cost and time overruns. 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 120.00% Award Start Middle Closure Precentage Project Stages Project Monitor…
  • 5. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 800 REFERENCES [1]. Adb.Majid, M.Z. Non-Excusable Delays in construction. Department of civil and Building Engineering, Laughborough University Loughborough, Leicestershire, UK (1997):Ph.D. Thesis. [2]. Al-jibouri,S. H (2003):Monitoring system and their effectiveness for project cost control in constructions. International Journal of Project Management 21:145-154. [3].Barnes, N.M. cost modeling - "An integrated approach to planning and cost control Engineering and process Economics". n.2,p 24-51,1977. [4]. Benchmarking the Government Client Stage,1999,2 study. [5]. Harris,F. and McCaffer. R.,2001. Modern Construction Management, 5th Edition Black well Science Ltd, Malden USA. [6]. Mohd Faris Khamidi and Waris Ali Khan, "The cost monitoring of construction projects through earned value analysis", International conference on economics and finance research,Singapore,2011. [7]. PMI Project Management Book Of Knowledge,(2004) 3rd Edition. [8]. Zubair Ahmed Memon, Mudh. Zaimi Abd. Majidand Mushairry Mustaffar, 'A Systematic approach for monitoring and Evaluating the construction project progress' Journal-The Institution of Engineers, Malaysia (vol. 67,No. 3, September 2006). BIOGRAPHIES Shreyash R Raut doing research gradute persuing Master in Engineering Construction & Management from Maharashtra Institute of Technology, Pune. Prof.Dr.Sunil S.Pimplikar is currently working as Professor and Head of Civil Engineering Department at Maharashtra Institute of Technology, Pune. He is the co- ordinator and faculty of the Post Graduate Program in Construction and Management. His research interests are Accident Studies, Total Quality Management, Contracts Management and Human Resource Management .