I.m ii nd mid descriptive & objective [pls visit our blog sres11meches.blogspot.in]
1. 1 PLS VISIT OUR BLOG Sres11meches.blogspot.in
MECHANICAL ENGINEERING III YEAR – II SEMESTER
INDUSTRIAL MANAGEMENT
II MID - DESCRIPTIVE QUESTION PAPER
1. Write a short notes on
(A) Purchase Management (B) Stores Management
2. What is PERT and CPM? Write about difference between PERT & CPM
3. The various time estimates of activities involved in a project are given in table,
Determine:
(A) The expected completion time of the project
(B) The variance and standard deviation of the project
(C) The probability factor of completing the project within 23 days
Activities 1 – 2 1 - 3 2 - 4 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6
𝑡 𝑜 2 4 2 2 0 3 6 1
𝑡 𝑚 6 8 3 4 0 6 10 3
𝑡 𝑝 10 12 4 6 0 9 14 5
4. What is Inspection? Briefly explain about the methods of inspection
5. Briefly explain about
(A) Job Evaluation (B) Merit Rating
2. 2 PLS VISIT OUR BLOG Sres11meches.blogspot.in
MECHANICAL ENGINEERING II YEAR – II SEMESTER
INDUSTRIAL MANAGEMENT
II MID – OBJECTIVE PAPER
1. “It is a list of names, quantities and/or monetary values of all or any group of item [ A]
A) INVENTORY B)QUALITY CONTROL
C) INSPECTION D) PURCHASING
2. EOQ STANDS FOR [ A]
A) ECONOMIC ORDER QUANTITY B) ENTRY ORDER QUANTITY
C) EMERGING OFFICIAL QUANTITY D) EXIT OUT QUANTITY
3. IN ABC ANALYSIS ABC STANDS FOR [ D]
A) ALWAYS BETTER CHARACTER B) ALWAYS BEST COMPETITION
C) AUTOMATIC BEETER CONTROL D) ALWAYS BETTER CONTROL
4. THERE ARE HOW MANY ELEMENTS INVOLVE IN STORES MANAGEMENT [ C]
A) 1 B) 2 C) 3 D) 4
5. BIN CARD ALSO CALLED AS------- [ C]
A) GRAPH CARD B) SHEET CARD C) STOCK CARD D) SHARE CARD
6. WHICH TECHNIQUE STRESSES MORE ON EVENTS RATHER THAN ACTIVITIES? [ C]
A) EOQ B) SDE C) PERT D) CPM
7. ON WHICH PATH DO ALL EVENTS HAVE ZERO SLACK? [ B]
A) ZERO B) CRITICAL C) ALL PATHS D) NO PATH
8. THE TERM “FLOAT” IS ASSOCIATED WITH WHICH TECHNIQUE? [ B]
A) PERT B) CPM C) EOQ D) VED
9. WHAT IS THE START OR END AN ACTIVITY CALLED AS ? [ A]
A) EVENT B) ACTIVITY C) NETWORK D) FLOAT
10. WHICH COSTS ARE DIRECTLY PROPORTIONAL TO THE NUMBER OF
ACTIVITIES IN PROJECTS? [ A]
A) DIRECT COSTS B) INDIRECT COSTS C) FIXED COSTS D) DIFFERENTIAL COSTS
11. FLOOR INSPECTION IS THE PART OF [ A]
A) PROCESS INSPECTION B) VENDOR INSPECTION
3. 3 PLS VISIT OUR BLOG Sres11meches.blogspot.in
C) 100% INSPECTION D) FINAL INSPECTION
12. X CHART IS A [ C]
A) ATTRIBUTE CHART B)CONTROL CHART C)VARIABLE CHART D)NONE
13. IT IS USES STATISTICAL SAMPLING TO DETERMINE WHETHER TO ACCEPT OR REJECT A
PRODUCTION LOT OF MATERIAL. [ B]
A) ATTRIBUTE SAMPLING B) ACCEPTANCE SAMPLING
C) VARIABLE SAMPLING D) ZERO SAMPLING
14. HOW MANY SAMPLES ARE THERE IN ACCEPTANCE SAMPLING PLAN [ B]
A) 1 B) 2 C) 3 D) 4
15. THAT DEFINE, ESTABLISH, AND MAINTAIN AN EFFECTIVE QUALITY ASSURANCE SYSTEM
FOR MANUFACTURING AND SERVICE INDUSTRIES [ C]
A) ISO 14000 SERIES B) ISO 21000 SERIES C)ISO 9000 SERIES D)NONE
16.WHAT IS HUMAN RESOURCE MANAGEMENT MAINLY CONCERNED WITH? [ A]
A)HUMAN BEINGS AND THEIR NEEDS B)HUMAN PHYSIOLOGY
C)RESOURCE MANAGEMENT D)CAPITAL MANAGEMENT
17.WHICH OF THE FOLLOWING RELTAES TO TRAINING? [ A]
A) INCRESING PRODUCTIVITY B) ARRANGING FIELDS TRIPS
C) IDENTIFYING MANPOWER GAP D) ADJUSTMENT OF PRODUCTIVITY
18. OFF-THE-JOB TRAINING DOES NOT INCLUDES [ D]
A) MANAGEMENT GAMES B) CONFERENCES C) SEMINARS D) TASK FORCE
19. WHICH OF THE FOLLOWING IS NOT A PART OF JOB DESCRIPTION? [ C]
A) JOB IDENTIFICATION B) JOB SUMMARY C) JOB ANALYSIS D) JOB DUTIES
20.WHAT IS REMUNERATION TO EMPLOYEES ON DIALY BASIS?
[ C]
A) SALARY B) BONUS C) WAGES D) COMENSATION