SlideShare a Scribd company logo
1 of 7
DEVRY PROJ 586 Final Exam Set 3 NEW
Check this A+ tutorial guideline at
http://www.uopassignments.com/proj-586-devry/proj-
586-final-exam-set-3-recent
For more classes visit
http://www.uopassignments.com/
1. (TCO A) The most common types of organization structures
are _____.
2. (TCO H) This first phase of the project life cycle involves the
_____.
3. (TCO B) The lowest level item of any one branch of the WBS is
called a(n) _____.
4. (TCO D) All of the following are risk response types except
_____.
5. (TCO F) The two most common types of project reports are
_____.
6. (TCO C) The _____ time is the latest time by which a particular
activity must be finished in order for the entire project to be
completed by its required completion time.
7. (TCO G) Which of the following is not a criterion for selecting
project
8. (TCO A) Which of the following is not an example of a
project?
9. (TCO C) Why are activities drawn in a serial relationship on a
network diagram?
10. (TCO F) The budget for each work package is _____.
11. (TCO F) The _____ is the amount that was budgeted to
accomplish the work scheduled to be performed up to that
point in time.
12. (TCO C) Calculate the earliest start for Task D if one of its
predecessors, Task A, finishes on day 3, its other predecessor,
Task C, finishes on day 4, and the duration of Task D is 2 days.
13. (TCO B) Describe what each of the following means in
project planning: what, how, who, how long, and how much.
14. (TCO E) Part 1: What are some common barriers to team
effectiveness?
Part 2: Describe an example of a team project that would
include barriers to success.
15. (TCO C) A project to remodel an office area has the
following activities. (Hint: You will need to build an AIB
diagram, perform a forward pass, and perform a backward pass
to answer this question.)
Activity Duration Predecessors
A 2 months ---
B 4 months ---
C 4 months ---
D 1 month A
E 5 months B
F 2 months B, C
G 1 month C
H 3 months E, F, G
I 2 months D, E
J 2 months G, H
a) What are the critical path activities?
b) What is the project's scheduled completion time?
c) What is the slack or float for Activity A? Show your
calculations.
d) What is the slack or float for Activity E? Show your
calculations.
e) What is the slack or float for Activity F? Show your
calculations.
f) What is the slack or float for Activity G? Show your
calculations.
Activity Duration Predecessors ES EF LS LF
Slack
A 3 months --- 0 3 7 9 7
B 2 months --- 0 2 0 4 0
C 4 months --- 0 4 3 7 3
D 1 month A 2 3 9 12 9
E 5 months B 4 9 4 9 0
F 2 months B, C 4 6 7 9 3
G 1 month C 4 5 8 9 4
H 3 months E, F, G 9 12 9 12 0
I 2 months D, E 9 11 12 14 3
J 2 months G, H 12 14 12 14 0
a) What are the critical path activities? – B-E-H-J
b) What is the project's scheduled completion time?
c) What is the slack or float for Activity A? Show your
calculations
d) What is the slack or float for Activity E? Show your
calculations.
e) What is the slack or float for Activity F? Show your
calculations.
f) What is the slack or float for Activity G? Show your
calculations.
16. (TCO A) Part 1: Compare and contrast the responsibilities of
a functional manager and a project manager in a pure project-
type organization.
Part 2: A company builds state-of-the-art barges for riverboat
companies. Which organization structure is the most suitable?
Why?
Part 3: An organization builds custom greenhouses for desert-
climate cities. Which organization structure is the most
suitable? Why?
17. (TCO D) A firm stores data for other organizations. The
company stores data across many states, providing backup data
storage for state, municipal governments, and large
corporations. The firm is deploying a new set of storage devices
that are faster, denser, and more energy efficient.
Part 1: List and discuss the major risk-management functions
from a project-management perspective for the new data
storage project.
Part 2: Describe a risk event, the related consequences, and the
risk response plan for the new data storage project.
18. (TCO F) Analyze and compare the performance of the
following two projects in terms of cost, schedule, and efficiency.
Make sure to show your calculations and analyze and explain
the results. (Note: Providing just numbers will receive only
partial credit.)
Project A: The budgeted cost of work performed is $92,000, and
the actual cost of work performed is $175,000. The budgeted
cost of work scheduled is $173,000.
Project B: The budgeted cost of work performed is $68,000, and
the actual cost of work performed is $69,000. The budgeted
cost of work scheduled is $71,000.
19. (TCO B) An environmental consulting firm has been hired to
clean up contaminated ground water beneath the site of a
former chemical factory. The cleanup design process consists of
evaluating several alternatives; preparing a conceptual design
for the most appropriate alternative; evaluating the conceptual
design by performing a small-scale pilot test on site; and, based
on the results of the pilot test, preparing a final design.
Installation of the cleanup system will be performed by
subcontractors under the supervision of the consultant. Prior
to installation, the consultant will work on setting up the
subcontracts by preparing specifications, prequalifying
installation contractors, reviewing all bids, and executing the
contracts. The installation will consist of the following phases:
recovery wells, piping, treatment equipment, and start up.
The consultant will also be responsible for system-performance
monitoring, which consists of sampling the groundwater,
monitoring wells on a quarterly basis, and sampling the
groundwater treatment-system discharge.
Prepare a work breakdown structure (WBS) for this project
with activities corresponding to a two-level task and subtask
hierarchy. Number the WBS codes so that the level of each
activity is clearly identified. Do not worry about indentation.
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 new

More Related Content

Similar to Devry proj 586 final exam set 3 new

PROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comPROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comvenkat60045
 
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.comPROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.comRoelofMerwe131
 
PROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.comPROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.comagathachristie149
 
Devry proj 586 final exam set 1 new
Devry proj 586 final exam set 1 newDevry proj 586 final exam set 1 new
Devry proj 586 final exam set 1 newuopassignment
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxalfred4lewis58146
 
1.1. Provide the definitions for resource loading and resource.docx
1.1. Provide the definitions for resource loading and resource.docx1.1. Provide the definitions for resource loading and resource.docx
1.1. Provide the definitions for resource loading and resource.docxjackiewalcutt
 
Examination paper of project management certification
Examination paper of project management certificationExamination paper of project management certification
Examination paper of project management certificationNMIMS ASSIGNMENTS HELP
 
Iibm examination paper of project management
Iibm examination paper of project managementIibm examination paper of project management
Iibm examination paper of project managementNMIMS ASSIGNMENTS HELP
 
Examination paper of project management
Examination paper of project managementExamination paper of project management
Examination paper of project managementNMIMS ASSIGNMENTS HELP
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxIRESH3
 
Devry proj 595 final exam set 2 new
Devry proj 595 final exam set 2 newDevry proj 595 final exam set 2 new
Devry proj 595 final exam set 2 newuopassignment
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bankBaskar El
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docxjackiewalcutt
 
ACC 251 Intro to Managerial AccountingChapters 9 through 12 .docx
ACC 251 Intro to Managerial AccountingChapters 9 through 12 .docxACC 251 Intro to Managerial AccountingChapters 9 through 12 .docx
ACC 251 Intro to Managerial AccountingChapters 9 through 12 .docxnettletondevon
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfMoncefMakni1
 

Similar to Devry proj 586 final exam set 3 new (20)

PROJ 586 Entire Course NEW
PROJ 586 Entire Course NEWPROJ 586 Entire Course NEW
PROJ 586 Entire Course NEW
 
PROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comPROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.com
 
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.comPROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
 
PROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.comPROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.com
 
Devry proj 586 final exam set 1 new
Devry proj 586 final exam set 1 newDevry proj 586 final exam set 1 new
Devry proj 586 final exam set 1 new
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
 
1.1. Provide the definitions for resource loading and resource.docx
1.1. Provide the definitions for resource loading and resource.docx1.1. Provide the definitions for resource loading and resource.docx
1.1. Provide the definitions for resource loading and resource.docx
 
Examination paper of project management certification
Examination paper of project management certificationExamination paper of project management certification
Examination paper of project management certification
 
Iibm examination paper of project management
Iibm examination paper of project managementIibm examination paper of project management
Iibm examination paper of project management
 
Examination paper of project management
Examination paper of project managementExamination paper of project management
Examination paper of project management
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
 
Devry proj 595 final exam set 2 new
Devry proj 595 final exam set 2 newDevry proj 595 final exam set 2 new
Devry proj 595 final exam set 2 new
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
Project Management
Project Management Project Management
Project Management
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 
ACC 251 Intro to Managerial AccountingChapters 9 through 12 .docx
ACC 251 Intro to Managerial AccountingChapters 9 through 12 .docxACC 251 Intro to Managerial AccountingChapters 9 through 12 .docx
ACC 251 Intro to Managerial AccountingChapters 9 through 12 .docx
 
150 PMP Questions
150 PMP Questions 150 PMP Questions
150 PMP Questions
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 

More from uopassignment

Uop cis 349 final exam guide set 1 new
Uop cis 349 final exam guide set 1 newUop cis 349 final exam guide set 1 new
Uop cis 349 final exam guide set 1 newuopassignment
 
Ash hcs 334 week 5 discussion 2 fitness resources and exercise behavior
Ash hcs 334 week 5 discussion 2 fitness resources and exercise behaviorAsh hcs 334 week 5 discussion 2 fitness resources and exercise behavior
Ash hcs 334 week 5 discussion 2 fitness resources and exercise behavioruopassignment
 
Ash hcs 334 week 2 quiz
Ash hcs 334 week 2 quizAsh hcs 334 week 2 quiz
Ash hcs 334 week 2 quizuopassignment
 
Ash hcs 334 week 2 assignment cardiorespiratory assessment and prescription new
Ash hcs 334 week 2 assignment cardiorespiratory assessment and prescription newAsh hcs 334 week 2 assignment cardiorespiratory assessment and prescription new
Ash hcs 334 week 2 assignment cardiorespiratory assessment and prescription newuopassignment
 
Mktg 320 week 4 dq 2 making surveys work
Mktg 320 week 4 dq 2 making surveys workMktg 320 week 4 dq 2 making surveys work
Mktg 320 week 4 dq 2 making surveys workuopassignment
 
Ash mgt 601 week 3 quiz
Ash mgt 601 week 3 quizAsh mgt 601 week 3 quiz
Ash mgt 601 week 3 quizuopassignment
 
Devry ecet 380 week 5 lab code division multiple access a 3 g cellular multip...
Devry ecet 380 week 5 lab code division multiple access a 3 g cellular multip...Devry ecet 380 week 5 lab code division multiple access a 3 g cellular multip...
Devry ecet 380 week 5 lab code division multiple access a 3 g cellular multip...uopassignment
 
Devry ecet 375 week 6 homework new
Devry ecet 375 week 6 homework newDevry ecet 375 week 6 homework new
Devry ecet 375 week 6 homework newuopassignment
 
Devry ecet 375 week 1
Devry ecet 375 week 1Devry ecet 375 week 1
Devry ecet 375 week 1uopassignment
 
Uop ecet 370 week 7 ilab collections framework new
Uop ecet 370 week 7 ilab collections framework newUop ecet 370 week 7 ilab collections framework new
Uop ecet 370 week 7 ilab collections framework newuopassignment
 
Devry ecet 370 week 6 ilab binary trees new
Devry ecet 370 week 6 ilab binary trees newDevry ecet 370 week 6 ilab binary trees new
Devry ecet 370 week 6 ilab binary trees newuopassignment
 
Devry ecet 370 week 5 ilab search techniques and hashing new
Devry ecet 370 week 5 ilab search techniques and hashing newDevry ecet 370 week 5 ilab search techniques and hashing new
Devry ecet 370 week 5 ilab search techniques and hashing newuopassignment
 
Devry ecet 370 week 4 ilab the efficiency of algorithms and sorting new
Devry ecet 370 week 4 ilab the efficiency of algorithms and sorting newDevry ecet 370 week 4 ilab the efficiency of algorithms and sorting new
Devry ecet 370 week 4 ilab the efficiency of algorithms and sorting newuopassignment
 
Devry ecet 370 week 3 ilab the stack and the queue ad ts new
Devry ecet 370 week 3 ilab the stack and the queue ad ts newDevry ecet 370 week 3 ilab the stack and the queue ad ts new
Devry ecet 370 week 3 ilab the stack and the queue ad ts newuopassignment
 
Devry ecet 370 week 2 ilab linked lists new
Devry ecet 370 week 2 ilab linked lists newDevry ecet 370 week 2 ilab linked lists new
Devry ecet 370 week 2 ilab linked lists newuopassignment
 
Devry ecet 370 week 1 i lab array
Devry ecet 370 week 1 i lab arrayDevry ecet 370 week 1 i lab array
Devry ecet 370 week 1 i lab arrayuopassignment
 
Xeco 212 week 5 check point a new house
Xeco 212 week 5 check point a new houseXeco 212 week 5 check point a new house
Xeco 212 week 5 check point a new houseuopassignment
 
Uop acc 543 week 3 exam new syllabus
Uop acc 543 week 3 exam new syllabusUop acc 543 week 3 exam new syllabus
Uop acc 543 week 3 exam new syllabusuopassignment
 

More from uopassignment (20)

Uop cis 349 final exam guide set 1 new
Uop cis 349 final exam guide set 1 newUop cis 349 final exam guide set 1 new
Uop cis 349 final exam guide set 1 new
 
Ash hcs 334 week 5 discussion 2 fitness resources and exercise behavior
Ash hcs 334 week 5 discussion 2 fitness resources and exercise behaviorAsh hcs 334 week 5 discussion 2 fitness resources and exercise behavior
Ash hcs 334 week 5 discussion 2 fitness resources and exercise behavior
 
Ash hcs 334 week 2 quiz
Ash hcs 334 week 2 quizAsh hcs 334 week 2 quiz
Ash hcs 334 week 2 quiz
 
Ash hcs 334 week 2 assignment cardiorespiratory assessment and prescription new
Ash hcs 334 week 2 assignment cardiorespiratory assessment and prescription newAsh hcs 334 week 2 assignment cardiorespiratory assessment and prescription new
Ash hcs 334 week 2 assignment cardiorespiratory assessment and prescription new
 
Mktg 320 week 4 dq 2 making surveys work
Mktg 320 week 4 dq 2 making surveys workMktg 320 week 4 dq 2 making surveys work
Mktg 320 week 4 dq 2 making surveys work
 
Ash mgt 601 week 3 quiz
Ash mgt 601 week 3 quizAsh mgt 601 week 3 quiz
Ash mgt 601 week 3 quiz
 
Devry ecet 380 week 5 lab code division multiple access a 3 g cellular multip...
Devry ecet 380 week 5 lab code division multiple access a 3 g cellular multip...Devry ecet 380 week 5 lab code division multiple access a 3 g cellular multip...
Devry ecet 380 week 5 lab code division multiple access a 3 g cellular multip...
 
Devry ecet 375 week 6 homework new
Devry ecet 375 week 6 homework newDevry ecet 375 week 6 homework new
Devry ecet 375 week 6 homework new
 
Devry ecet 375 week 1
Devry ecet 375 week 1Devry ecet 375 week 1
Devry ecet 375 week 1
 
Uop ecet 370 week 7 ilab collections framework new
Uop ecet 370 week 7 ilab collections framework newUop ecet 370 week 7 ilab collections framework new
Uop ecet 370 week 7 ilab collections framework new
 
Devry ecet 370 week 6 ilab binary trees new
Devry ecet 370 week 6 ilab binary trees newDevry ecet 370 week 6 ilab binary trees new
Devry ecet 370 week 6 ilab binary trees new
 
Devry ecet 370 week 5 ilab search techniques and hashing new
Devry ecet 370 week 5 ilab search techniques and hashing newDevry ecet 370 week 5 ilab search techniques and hashing new
Devry ecet 370 week 5 ilab search techniques and hashing new
 
Devry ecet 370 week 4 ilab the efficiency of algorithms and sorting new
Devry ecet 370 week 4 ilab the efficiency of algorithms and sorting newDevry ecet 370 week 4 ilab the efficiency of algorithms and sorting new
Devry ecet 370 week 4 ilab the efficiency of algorithms and sorting new
 
Devry ecet 370 week 3 ilab the stack and the queue ad ts new
Devry ecet 370 week 3 ilab the stack and the queue ad ts newDevry ecet 370 week 3 ilab the stack and the queue ad ts new
Devry ecet 370 week 3 ilab the stack and the queue ad ts new
 
Devry ecet 370 week 2 ilab linked lists new
Devry ecet 370 week 2 ilab linked lists newDevry ecet 370 week 2 ilab linked lists new
Devry ecet 370 week 2 ilab linked lists new
 
Devry ecet 370 week 1 i lab array
Devry ecet 370 week 1 i lab arrayDevry ecet 370 week 1 i lab array
Devry ecet 370 week 1 i lab array
 
Ethc 445 final exam
Ethc 445 final examEthc 445 final exam
Ethc 445 final exam
 
Ethc 445 final exam
Ethc 445 final examEthc 445 final exam
Ethc 445 final exam
 
Xeco 212 week 5 check point a new house
Xeco 212 week 5 check point a new houseXeco 212 week 5 check point a new house
Xeco 212 week 5 check point a new house
 
Uop acc 543 week 3 exam new syllabus
Uop acc 543 week 3 exam new syllabusUop acc 543 week 3 exam new syllabus
Uop acc 543 week 3 exam new syllabus
 

Recently uploaded

SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...PsychoTech Services
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 

Recently uploaded (20)

SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 

Devry proj 586 final exam set 3 new

  • 1. DEVRY PROJ 586 Final Exam Set 3 NEW Check this A+ tutorial guideline at http://www.uopassignments.com/proj-586-devry/proj- 586-final-exam-set-3-recent For more classes visit http://www.uopassignments.com/ 1. (TCO A) The most common types of organization structures are _____. 2. (TCO H) This first phase of the project life cycle involves the _____. 3. (TCO B) The lowest level item of any one branch of the WBS is called a(n) _____. 4. (TCO D) All of the following are risk response types except _____. 5. (TCO F) The two most common types of project reports are _____. 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. 7. (TCO G) Which of the following is not a criterion for selecting project 8. (TCO A) Which of the following is not an example of a project?
  • 2. 9. (TCO C) Why are activities drawn in a serial relationship on a network diagram? 10. (TCO F) The budget for each work package is _____. 11. (TCO F) The _____ is the amount that was budgeted to accomplish the work scheduled to be performed up to that point in time. 12. (TCO C) Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days. 13. (TCO B) Describe what each of the following means in project planning: what, how, who, how long, and how much. 14. (TCO E) Part 1: What are some common barriers to team effectiveness? Part 2: Describe an example of a team project that would include barriers to success. 15. (TCO C) A project to remodel an office area has the following activities. (Hint: You will need to build an AIB diagram, perform a forward pass, and perform a backward pass to answer this question.) Activity Duration Predecessors A 2 months --- B 4 months --- C 4 months --- D 1 month A E 5 months B F 2 months B, C G 1 month C
  • 3. H 3 months E, F, G I 2 months D, E J 2 months G, H a) What are the critical path activities? b) What is the project's scheduled completion time? c) What is the slack or float for Activity A? Show your calculations. d) What is the slack or float for Activity E? Show your calculations. e) What is the slack or float for Activity F? Show your calculations. f) What is the slack or float for Activity G? Show your calculations. Activity Duration Predecessors ES EF LS LF Slack A 3 months --- 0 3 7 9 7 B 2 months --- 0 2 0 4 0 C 4 months --- 0 4 3 7 3 D 1 month A 2 3 9 12 9 E 5 months B 4 9 4 9 0 F 2 months B, C 4 6 7 9 3 G 1 month C 4 5 8 9 4 H 3 months E, F, G 9 12 9 12 0 I 2 months D, E 9 11 12 14 3 J 2 months G, H 12 14 12 14 0 a) What are the critical path activities? – B-E-H-J b) What is the project's scheduled completion time? c) What is the slack or float for Activity A? Show your
  • 4. calculations d) What is the slack or float for Activity E? Show your calculations. e) What is the slack or float for Activity F? Show your calculations. f) What is the slack or float for Activity G? Show your calculations. 16. (TCO A) Part 1: Compare and contrast the responsibilities of a functional manager and a project manager in a pure project- type organization. Part 2: A company builds state-of-the-art barges for riverboat companies. Which organization structure is the most suitable? Why? Part 3: An organization builds custom greenhouses for desert- climate cities. Which organization structure is the most suitable? Why? 17. (TCO D) A firm stores data for other organizations. The company stores data across many states, providing backup data storage for state, municipal governments, and large corporations. The firm is deploying a new set of storage devices that are faster, denser, and more energy efficient. Part 1: List and discuss the major risk-management functions from a project-management perspective for the new data storage project. Part 2: Describe a risk event, the related consequences, and the risk response plan for the new data storage project.
  • 5. 18. (TCO F) Analyze and compare the performance of the following two projects in terms of cost, schedule, and efficiency. Make sure to show your calculations and analyze and explain the results. (Note: Providing just numbers will receive only partial credit.) Project A: The budgeted cost of work performed is $92,000, and the actual cost of work performed is $175,000. The budgeted cost of work scheduled is $173,000. Project B: The budgeted cost of work performed is $68,000, and the actual cost of work performed is $69,000. The budgeted cost of work scheduled is $71,000. 19. (TCO B) An environmental consulting firm has been hired to clean up contaminated ground water beneath the site of a former chemical factory. The cleanup design process consists of evaluating several alternatives; preparing a conceptual design for the most appropriate alternative; evaluating the conceptual design by performing a small-scale pilot test on site; and, based on the results of the pilot test, preparing a final design. Installation of the cleanup system will be performed by subcontractors under the supervision of the consultant. Prior to installation, the consultant will work on setting up the subcontracts by preparing specifications, prequalifying installation contractors, reviewing all bids, and executing the contracts. The installation will consist of the following phases: recovery wells, piping, treatment equipment, and start up. The consultant will also be responsible for system-performance monitoring, which consists of sampling the groundwater, monitoring wells on a quarterly basis, and sampling the groundwater treatment-system discharge. Prepare a work breakdown structure (WBS) for this project with activities corresponding to a two-level task and subtask hierarchy. Number the WBS codes so that the level of each activity is clearly identified. Do not worry about indentation.