Individual Assignment: Construction Site Report
Name: Gan Jet Foong
StudentID: 0315998
Lecturer: Ms Ang Fuey Lin
MyzatulAishah Binti Kamarazaly
Azrina Binti Md Yaakob
2 | P a g e
Table of Content
TITLE No.
Cover Page 1
Table of Content 2
Introduction and Objectives of the Assignment 3
Content and Technical Observation 4-5
Photos and Descriptions 6-19
Learning Outcomes and Conclusion 20
3 | P a g e
Introduction
This is a report on a site visit to a construction site incorporating
the objectives of the site visit, the introduction of the site and
technical observations made on site including the learning
outcomes of the site visit.
The site visit is organized by our lecturers, Ms Ang, Ms Aishah
and Ms Azrina. We were divided into 2 groups, my group consists
of 23 members. The site visited is at SOHO in Bandar Sunway
beside Taylors University on Friday, 21st December 2014.
Objectives of the Assignment
 To prepare us for our future career as a Quantity Surveyor
 To give us exposure to construction site
 To expand our knowledge of construction site
 To understand the method and process of construction in
accordance to the sequence of work on site
 To recognize and understand the building materials used for
construction
 To give awareness and importance of safety in the
construction site
 To understand the importance of teamwork and
communication skills while working together on the site
4 | P a g e
Content and Technical Observation
The site visit was held on Friday, 21st
December 2014. The
location was at SOHO in Bandar Sunway near Taylors University.
Before that, Ms Ang, Ms Aishah and Ms Azrina briefed us about
the safety precautions and preparation for the site visit. Primary,
safety comes first, we have to prepare a safety helmet for head
protection in case of accidents such as dropping objects. We
were told to be always aware of our footsteps to avoid slipping or
fall into a hole. We were also required to wear bright long sleeves
shirt to avoid heat and sunlight. If we were hurt by rusty nails, a
tetanus shot is needed to prevent infection.
On the day of visit, some of us car pool or walked to the site
because it is very near to the campus. We were gathered at the
site at 9.45am and waited the lecturers and the safety officer to
organize the visit for us.
We were gathered by the safety officer to brief us about safety
precautions. We began our visit at 10am, everyone began to wear
their helmets and take pictures using phones and cameras. We
saw a few scaffolds attached to the building, those were
independent scaffolds because it is more easier to move, it was
used for temporary ladders and work place.
We went to the basement parking, it has cement package, PVC
pipes, reinforcement bars along the place. We saw how the
process of columns and beams were construct, it requires more
work and time than we imagine.
5 | P a g e
We were told that the formwork used was steel and timber. Steel
formworks are stronger and can be reuse many times, however it
is very heavy and requires more labour work. Timber formwork is
cheaper and lighter to carry so it get the small works done faster,
but it cannot be used many times.
The concrete used for the building was mostly grade 40, it is a
very strong concrete that has more aggregate, it does not crack
easily and can sustain more heavy loads. However, I would
recommend grade 30 for concrete works because the buildings
does not require to sustain heavy loads, it is also strong and
saves a lot of cost.
Our visit lasted one hour until 11am, it was a very fun experience
and we gained a lot of knowledge about construction of a building,
what does it requires and what is the process. We hope that we
could do another site visit in the future to gain new knowledge and
new technology used for construction.
6 | P a g e
Photos and Description
Figure 1.0 This is the Project Title and Details
7 | P a g e
Figure 2.0 We were gatheredandbrief forsafety
precautions
Figure 2.1 Warning signforhead
precaution
Figure 2.2 Penaltyfornot usingsafetyequipmentand
smoking
8 | P a g e
Figure 3.0 Shoe racks for shoes
Figure 3.1 Meetingroomfor staffs
9 | P a g e
Figure 4.0 We beganvisitingthe site wearingthe safetyhelmet
Figure 4.1 Outside viewof the constructionsite
10 | P a g e
Figure 5.0 Steel formwork
Figure 5.1 Workerscuttingthe steel bars
11 | P a g e
Figure 6.0 Blockedaccessarea
Figure 6.1 Materialsusedto constructscaffolding
12 | P a g e
Figure 7.0 Independentscaffoldingattachedtothe
building
Figure 7.1 Anotherindependent
scaffolding
Figure 7.2 Laddersfoundin scaffolding
13 | P a g e
Figure 8.0 Under-constructionScaffold
Figure 8.1 Bottom viewof the scaffold
14 | P a g e
Figure 9.0 High-tensile Steel usedfor
reinforcement
Figure 9.1 Mild-steel usedforstirrupsand
links
15 | P a g e
Figure 10.0 Vertical Reinforcement
bars
Figure 10.1 Horizontal Reinforcementbars
Figure 10.2 Timberformworkforbeam
16 | P a g e
Figure 11.0 Steel formworkontopfloor
Figure 11.1 Preparationforsteel formwork
17 | P a g e
Figure 12.0 columnsandbeamsinthe car park
basement
Figure 12.1 car park slop
Figure 12.2 Cementpowder
18 | P a g e
Figure 13.0 Concrete bricksusedforconstruction
Figure 13.1 Plasterfinish Figure 13.2 Fine Mortar (white)
19 | P a g e
Figure 14.1 Group photo
Figure 14.0 Temporarysheltersorhomesforworkers
20 | P a g e
Learning Outcomes
The site visit was a great experience for all of us, we have
gained a lot of knowledge about construction and understand
more of what we studied in class.
From the beginning of the site, we were told to always keep
our safety helmets on because safety always comes first, there
are many warning sign and rules along the site, heavy penalty
would be used if fail to follow instructions.
This site visit gives us a clearer understanding of a building
structure, such as the work and design of scaffolding,
reinforcement bars, concrete bars, formwork, columns, beams
and many others that we have learned in the construction
technology and building materials.
Besides that, we now know how difficult or complicated to
construct a building. It requires a lot of time, skills and teamwork
in order to finish it, workers also have to experience difficulties like
working under hot sun and may delay works on heavy rains.

More Related Content

What's hot

site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)Jia Hong Mui
 
Site visit report
Site visit reportSite visit report
Site visit reportJıa Yıı
 
bqs Site report
bqs Site reportbqs Site report
bqs Site reportFelix Vong
 
Site report for Measurement 1
Site report for Measurement 1Site report for Measurement 1
Site report for Measurement 1Yap Xin
 
CT site visit report
CT site visit report CT site visit report
CT site visit report Yap Xin
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1KhangWei Chin
 
Construction site
Construction siteConstruction site
Construction siteTimun Loh
 
Site visit report.
Site visit report.Site visit report.
Site visit report.Man Yee
 
Individual site report brief
Individual site report briefIndividual site report brief
Individual site report briefMomo Poyi
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1Zi Shan
 
Site Visit report- Measurement I, Building materials, Construction Technology I
Site Visit report- Measurement I, Building materials, Construction Technology ISite Visit report- Measurement I, Building materials, Construction Technology I
Site Visit report- Measurement I, Building materials, Construction Technology Ikaiwenyeo
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017bee_by
 
Site visit-report-nov2015
Site visit-report-nov2015Site visit-report-nov2015
Site visit-report-nov2015Joyce HweeMin
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORTWan Nee
 

What's hot (20)

site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)
 
Site visit report
Site visit reportSite visit report
Site visit report
 
bqs Site report
bqs Site reportbqs Site report
bqs Site report
 
Site report for Measurement 1
Site report for Measurement 1Site report for Measurement 1
Site report for Measurement 1
 
Site report
Site reportSite report
Site report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
CT site visit report
CT site visit report CT site visit report
CT site visit report
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1
 
Construction site
Construction siteConstruction site
Construction site
 
site report
site reportsite report
site report
 
Site visit report.
Site visit report.Site visit report.
Site visit report.
 
Individual site report brief
Individual site report briefIndividual site report brief
Individual site report brief
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Construction Site Report
Construction Site ReportConstruction Site Report
Construction Site Report
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1
 
Site Visit report- Measurement I, Building materials, Construction Technology I
Site Visit report- Measurement I, Building materials, Construction Technology ISite Visit report- Measurement I, Building materials, Construction Technology I
Site Visit report- Measurement I, Building materials, Construction Technology I
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site visit-report-nov2015
Site visit-report-nov2015Site visit-report-nov2015
Site visit-report-nov2015
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
 

Viewers also liked

Viewers also liked (7)

Ct report
Ct reportCt report
Ct report
 
Ojt report final2
Ojt report final2Ojt report final2
Ojt report final2
 
Building technology in construction intro
Building technology in construction introBuilding technology in construction intro
Building technology in construction intro
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction site
 
videocon Telecom Project Report
videocon Telecom Project Reportvideocon Telecom Project Report
videocon Telecom Project Report
 
Building methods and construction technology 1
Building methods and construction technology 1Building methods and construction technology 1
Building methods and construction technology 1
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 

Similar to Site report

Site report algel
Site report algelSite report algel
Site report algelAlgel Yee
 
Project SlideShare
Project SlideShareProject SlideShare
Project SlideShareYung Kai
 
Site report
Site reportSite report
Site reportvaylu
 
Site visit report
Site visit reportSite visit report
Site visit reportJordon Wong
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visitPui San
 
site report
site reportsite report
site reportszelun
 
CT, BM & MEASUREMENT Report
CT, BM & MEASUREMENT ReportCT, BM & MEASUREMENT Report
CT, BM & MEASUREMENT Reporttianji96
 
Site visit report
Site visit reportSite visit report
Site visit reportwleying
 
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorAssignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorKai Yun Pang
 
SUMMER TRAINING REPORT BY VIJAY VERMA
SUMMER TRAINING REPORT BY VIJAY VERMASUMMER TRAINING REPORT BY VIJAY VERMA
SUMMER TRAINING REPORT BY VIJAY VERMAvjverma123
 
Integrated site vite report
Integrated site vite reportIntegrated site vite report
Integrated site vite reportxennechau
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit reportMomo Poyi
 
Site visit report
Site visit reportSite visit report
Site visit reportDoreen Yeo
 
Site Visit Report - Chin Kian Hon & Chong Gia Xao
Site Visit Report - Chin Kian Hon & Chong Gia XaoSite Visit Report - Chin Kian Hon & Chong Gia Xao
Site Visit Report - Chin Kian Hon & Chong Gia XaoChin Kian Hon
 

Similar to Site report (20)

Site report algel
Site report algelSite report algel
Site report algel
 
Site report
Site reportSite report
Site report
 
Project SlideShare
Project SlideShareProject SlideShare
Project SlideShare
 
Site report
Site reportSite report
Site report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visit
 
site report
site reportsite report
site report
 
Site report
Site reportSite report
Site report
 
CT, BM & MEASUREMENT Report
CT, BM & MEASUREMENT ReportCT, BM & MEASUREMENT Report
CT, BM & MEASUREMENT Report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorAssignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
 
SUMMER TRAINING REPORT BY VIJAY VERMA
SUMMER TRAINING REPORT BY VIJAY VERMASUMMER TRAINING REPORT BY VIJAY VERMA
SUMMER TRAINING REPORT BY VIJAY VERMA
 
Integrated site vite report
Integrated site vite reportIntegrated site vite report
Integrated site vite report
 
Final report
Final reportFinal report
Final report
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site Visit Report - Chin Kian Hon & Chong Gia Xao
Site Visit Report - Chin Kian Hon & Chong Gia XaoSite Visit Report - Chin Kian Hon & Chong Gia Xao
Site Visit Report - Chin Kian Hon & Chong Gia Xao
 
Ez
EzEz
Ez
 
Site report
Site reportSite report
Site report
 
MCB Final report
MCB Final reportMCB Final report
MCB Final report
 

More from Gan Jet Foong

Customers & false advertising
Customers & false advertisingCustomers & false advertising
Customers & false advertisingGan Jet Foong
 
Psychoreport 140609090547-phpapp01
Psychoreport 140609090547-phpapp01Psychoreport 140609090547-phpapp01
Psychoreport 140609090547-phpapp01Gan Jet Foong
 
Mathematics survey assignment
Mathematics survey assignmentMathematics survey assignment
Mathematics survey assignmentGan Jet Foong
 
Presentation of researh assignment
Presentation of researh assignmentPresentation of researh assignment
Presentation of researh assignmentGan Jet Foong
 
Research Presentation
Research PresentationResearch Presentation
Research PresentationGan Jet Foong
 
Presentation of epc mural arts
Presentation of epc mural artsPresentation of epc mural arts
Presentation of epc mural artsGan Jet Foong
 
English Assignment 1 - essay
English Assignment 1 -  essayEnglish Assignment 1 -  essay
English Assignment 1 - essayGan Jet Foong
 
Social Psychology - Assignment 1 Journal
Social Psychology -  Assignment 1 JournalSocial Psychology -  Assignment 1 Journal
Social Psychology - Assignment 1 JournalGan Jet Foong
 
Economics Assignment
Economics AssignmentEconomics Assignment
Economics AssignmentGan Jet Foong
 
Accounting assignment
Accounting assignmentAccounting assignment
Accounting assignmentGan Jet Foong
 

More from Gan Jet Foong (13)

Bs assignment
Bs assignmentBs assignment
Bs assignment
 
Customers & false advertising
Customers & false advertisingCustomers & false advertising
Customers & false advertising
 
Business report
Business  reportBusiness  report
Business report
 
Psychoreport 140609090547-phpapp01
Psychoreport 140609090547-phpapp01Psychoreport 140609090547-phpapp01
Psychoreport 140609090547-phpapp01
 
Threesome love
Threesome loveThreesome love
Threesome love
 
Mathematics survey assignment
Mathematics survey assignmentMathematics survey assignment
Mathematics survey assignment
 
Presentation of researh assignment
Presentation of researh assignmentPresentation of researh assignment
Presentation of researh assignment
 
Research Presentation
Research PresentationResearch Presentation
Research Presentation
 
Presentation of epc mural arts
Presentation of epc mural artsPresentation of epc mural arts
Presentation of epc mural arts
 
English Assignment 1 - essay
English Assignment 1 -  essayEnglish Assignment 1 -  essay
English Assignment 1 - essay
 
Social Psychology - Assignment 1 Journal
Social Psychology -  Assignment 1 JournalSocial Psychology -  Assignment 1 Journal
Social Psychology - Assignment 1 Journal
 
Economics Assignment
Economics AssignmentEconomics Assignment
Economics Assignment
 
Accounting assignment
Accounting assignmentAccounting assignment
Accounting assignment
 

Site report

  • 1. 1 | P a g e SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) AUGUST INTAKE 2014 SEMESTER 1 [QSB 60104] MEASUREMENT I [BLD60104] CONSTRUCTION TECHNOLOGY l [BLD 62003] BUILDING MATERIALS Individual Assignment: Construction Site Report Name: Gan Jet Foong StudentID: 0315998 Lecturer: Ms Ang Fuey Lin MyzatulAishah Binti Kamarazaly Azrina Binti Md Yaakob
  • 2. 2 | P a g e Table of Content TITLE No. Cover Page 1 Table of Content 2 Introduction and Objectives of the Assignment 3 Content and Technical Observation 4-5 Photos and Descriptions 6-19 Learning Outcomes and Conclusion 20
  • 3. 3 | P a g e Introduction This is a report on a site visit to a construction site incorporating the objectives of the site visit, the introduction of the site and technical observations made on site including the learning outcomes of the site visit. The site visit is organized by our lecturers, Ms Ang, Ms Aishah and Ms Azrina. We were divided into 2 groups, my group consists of 23 members. The site visited is at SOHO in Bandar Sunway beside Taylors University on Friday, 21st December 2014. Objectives of the Assignment  To prepare us for our future career as a Quantity Surveyor  To give us exposure to construction site  To expand our knowledge of construction site  To understand the method and process of construction in accordance to the sequence of work on site  To recognize and understand the building materials used for construction  To give awareness and importance of safety in the construction site  To understand the importance of teamwork and communication skills while working together on the site
  • 4. 4 | P a g e Content and Technical Observation The site visit was held on Friday, 21st December 2014. The location was at SOHO in Bandar Sunway near Taylors University. Before that, Ms Ang, Ms Aishah and Ms Azrina briefed us about the safety precautions and preparation for the site visit. Primary, safety comes first, we have to prepare a safety helmet for head protection in case of accidents such as dropping objects. We were told to be always aware of our footsteps to avoid slipping or fall into a hole. We were also required to wear bright long sleeves shirt to avoid heat and sunlight. If we were hurt by rusty nails, a tetanus shot is needed to prevent infection. On the day of visit, some of us car pool or walked to the site because it is very near to the campus. We were gathered at the site at 9.45am and waited the lecturers and the safety officer to organize the visit for us. We were gathered by the safety officer to brief us about safety precautions. We began our visit at 10am, everyone began to wear their helmets and take pictures using phones and cameras. We saw a few scaffolds attached to the building, those were independent scaffolds because it is more easier to move, it was used for temporary ladders and work place. We went to the basement parking, it has cement package, PVC pipes, reinforcement bars along the place. We saw how the process of columns and beams were construct, it requires more work and time than we imagine.
  • 5. 5 | P a g e We were told that the formwork used was steel and timber. Steel formworks are stronger and can be reuse many times, however it is very heavy and requires more labour work. Timber formwork is cheaper and lighter to carry so it get the small works done faster, but it cannot be used many times. The concrete used for the building was mostly grade 40, it is a very strong concrete that has more aggregate, it does not crack easily and can sustain more heavy loads. However, I would recommend grade 30 for concrete works because the buildings does not require to sustain heavy loads, it is also strong and saves a lot of cost. Our visit lasted one hour until 11am, it was a very fun experience and we gained a lot of knowledge about construction of a building, what does it requires and what is the process. We hope that we could do another site visit in the future to gain new knowledge and new technology used for construction.
  • 6. 6 | P a g e Photos and Description Figure 1.0 This is the Project Title and Details
  • 7. 7 | P a g e Figure 2.0 We were gatheredandbrief forsafety precautions Figure 2.1 Warning signforhead precaution Figure 2.2 Penaltyfornot usingsafetyequipmentand smoking
  • 8. 8 | P a g e Figure 3.0 Shoe racks for shoes Figure 3.1 Meetingroomfor staffs
  • 9. 9 | P a g e Figure 4.0 We beganvisitingthe site wearingthe safetyhelmet Figure 4.1 Outside viewof the constructionsite
  • 10. 10 | P a g e Figure 5.0 Steel formwork Figure 5.1 Workerscuttingthe steel bars
  • 11. 11 | P a g e Figure 6.0 Blockedaccessarea Figure 6.1 Materialsusedto constructscaffolding
  • 12. 12 | P a g e Figure 7.0 Independentscaffoldingattachedtothe building Figure 7.1 Anotherindependent scaffolding Figure 7.2 Laddersfoundin scaffolding
  • 13. 13 | P a g e Figure 8.0 Under-constructionScaffold Figure 8.1 Bottom viewof the scaffold
  • 14. 14 | P a g e Figure 9.0 High-tensile Steel usedfor reinforcement Figure 9.1 Mild-steel usedforstirrupsand links
  • 15. 15 | P a g e Figure 10.0 Vertical Reinforcement bars Figure 10.1 Horizontal Reinforcementbars Figure 10.2 Timberformworkforbeam
  • 16. 16 | P a g e Figure 11.0 Steel formworkontopfloor Figure 11.1 Preparationforsteel formwork
  • 17. 17 | P a g e Figure 12.0 columnsandbeamsinthe car park basement Figure 12.1 car park slop Figure 12.2 Cementpowder
  • 18. 18 | P a g e Figure 13.0 Concrete bricksusedforconstruction Figure 13.1 Plasterfinish Figure 13.2 Fine Mortar (white)
  • 19. 19 | P a g e Figure 14.1 Group photo Figure 14.0 Temporarysheltersorhomesforworkers
  • 20. 20 | P a g e Learning Outcomes The site visit was a great experience for all of us, we have gained a lot of knowledge about construction and understand more of what we studied in class. From the beginning of the site, we were told to always keep our safety helmets on because safety always comes first, there are many warning sign and rules along the site, heavy penalty would be used if fail to follow instructions. This site visit gives us a clearer understanding of a building structure, such as the work and design of scaffolding, reinforcement bars, concrete bars, formwork, columns, beams and many others that we have learned in the construction technology and building materials. Besides that, we now know how difficult or complicated to construct a building. It requires a lot of time, skills and teamwork in order to finish it, workers also have to experience difficulties like working under hot sun and may delay works on heavy rains.