SlideShare a Scribd company logo
1 of 29
INTEGRATING
CONSTRUCTABILITY
WITH LEAN
CONSTRUCTION &
WORK PLAN
helpdesk@construction-productivity.co.uk
htt://www.construction-productivity.co.uk
 Constructability is the integration of
construction expertise into all phases
of the project.
For Improving factors such as:
 cost
 schedule
 quality
 overall project objectives
 Constructability must be used at key
points in the project life cycle. This
includes:
 in the planning phase;
 early in the design phase;
 prior to the procurement phase;
 prior to the mobilization phase for
construction.
 Constructability process considers a
detailed review of:
 Design drawings;
 Models;
 Specifications;
 construction processes.
 This is carried out by one or more highly
experienced construction Engineers or
specialists.
 working closely with the project team
including cost engineering;
 this is carried out prior to construction
mobilization;
 before construction work is put for tender.
• The purpose of the
constructability review is to
identify the following items:
• Design errors (both material
selection or dimensions).
• Un clear specifications.
• Project features-difficult and very
costly to construct.
• Project complexity- that exceed the
knowledge and capability of industry
to properly build.
• Project features that are difficult to
interpret and will be hard to
accurately bid.
 Lean construction main objective is to
maximize value and reduce waste.
 It applies specific techniques in an
innovative project delivery approach.
 including:
1. supply chain management,
2. Just-In-Time techniques.
 As well as the open sharing of information
between all the parties involved in the
production process.
 Lean manufacturing is an outgrowth of the
Toyota Production system.
 Developed by Taichii Ohno in Toyota in
the 1950s.
 It is based on lean manufacturing,
of the Toyota Production system.
 Ohno learnt from mass production at Ford
Motor manufacturing facilities in the U.S.
and witnessed high level of waste during
production.
Ohno identified several wastes in mass
production systems in car industry
such as:
1. overproducing
2. waiting time
3. transporting
also, in other areas such as:
1. processing methods;
2. unnecessary stock on hand;
3. unnecessary motion;
4. defective goods;
5. failure to meet customers’ needs;
6. high waste through out the process. He
would be very disappointed by recent
failures in Toyota car performance.
 Womack and Jones (1996) suggested that
there are five key principles that need to be
monitored when lean construction systems
are applied in construction. Those are:
 Value-clarifying the customer’s needs;
 the supply chain involvement in all stages,
from inception to completion;
 By clarifying activities or products
that signify value.
Value stream: By mapping the
whole value stream
 establishing cooperation between all
parties involved;
 identifying and eliminating waste;
 From taking such steps the
construction process can be
improved.
Flow:
 Business flow includes project
information such as:
1. specifications
2. contracts
3. plans, etc.
 Job site flow involves the activities
and the way they have to be carried
out.
 Supply flow refers to the materials
used in a project.
Pull:
 The efforts of all participants provides
smooth pulls during the construction
process.
Perfection:
 Use of best methods of work
instructions and best procedures.
 Introduction of best quality control
methods.
 This well planned and systematic
approach helps the management
team to create quality work plans.
 They learn from any failure
 a good WorkPlan is a weekly work
plan
 based on lean construction
 production scheduling
 screening
 work package
 constraint
 percentage of planned completed (PPC)
 Scheduling of construction work is often
done with the help of computer tools
 It implement the critical-path method
(CPM)
 based on activities of given duration and
unit resources allocated to them
 as well as predecessor relationships
between activities
 for different parties involved in a
construction project to communicate with
one another whom should be doing what
work and when.
 The application of lean production techniques in
construction has been triggered by its success in
manufacturing (Womack and Jones 1996).
 Weekly work plans can be developed as valuable
tools for production planning and control.
 This is possible through the application of lean
construction techniques.
 In the application weekly work plans are generated
using a database (Choo, Tommelein
 Activity-on-Arrows Representation of a Nine
Activity Project
 Defining Precedence Relationships Among
Activities
Integrating Constructability & Lean for Improved Work Planning
Integrating Constructability & Lean for Improved Work Planning

More Related Content

What's hot

Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...Devendra Kachhi
 
Ops 571 riordan process design week 6 final paper
Ops 571 riordan process design week 6 final paperOps 571 riordan process design week 6 final paper
Ops 571 riordan process design week 6 final paperJoshua Kas-Osoka, MBA
 
Unit ii Process Planning
Unit ii Process PlanningUnit ii Process Planning
Unit ii Process PlanningAsha A
 
Computer integrated production planning
Computer integrated production planningComputer integrated production planning
Computer integrated production planningVenu Yadav
 
Production control presentation
Production control presentationProduction control presentation
Production control presentationkieran122
 
Om0017 advanced production planning and control
Om0017 advanced production planning and controlOm0017 advanced production planning and control
Om0017 advanced production planning and controlsmumbahelp
 
Production planning & control
Production planning & controlProduction planning & control
Production planning & controlAsadurzzaman nur
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and controlNikitaGidde
 
Functions of production planning and control 2
Functions of production planning and control 2Functions of production planning and control 2
Functions of production planning and control 2Vignesh Jayakumar
 
Production control
Production controlProduction control
Production controldeepu2000
 
Production Planning and Control
Production Planning and ControlProduction Planning and Control
Production Planning and ControlAijaz Aryan
 
production planning and control
production planning and controlproduction planning and control
production planning and controlParitosh Kasaudhan
 
Production control
Production controlProduction control
Production controlsadia saeed
 
Production planning
Production planningProduction planning
Production planningdeepu2000
 

What's hot (18)

015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
 
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
 
Ops 571 riordan process design week 6 final paper
Ops 571 riordan process design week 6 final paperOps 571 riordan process design week 6 final paper
Ops 571 riordan process design week 6 final paper
 
Analyn Nagpala_resume
Analyn Nagpala_resumeAnalyn Nagpala_resume
Analyn Nagpala_resume
 
Unit ii Process Planning
Unit ii Process PlanningUnit ii Process Planning
Unit ii Process Planning
 
Computer integrated production planning
Computer integrated production planningComputer integrated production planning
Computer integrated production planning
 
Production control presentation
Production control presentationProduction control presentation
Production control presentation
 
Om0017 advanced production planning and control
Om0017 advanced production planning and controlOm0017 advanced production planning and control
Om0017 advanced production planning and control
 
Production planning & control
Production planning & controlProduction planning & control
Production planning & control
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
Functions of production planning and control 2
Functions of production planning and control 2Functions of production planning and control 2
Functions of production planning and control 2
 
015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
 
Production control
Production controlProduction control
Production control
 
Production Planning and Control
Production Planning and ControlProduction Planning and Control
Production Planning and Control
 
production planning and control
production planning and controlproduction planning and control
production planning and control
 
Production control
Production controlProduction control
Production control
 
Production planning
Production planningProduction planning
Production planning
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 

Similar to Integrating Constructability & Lean for Improved Work Planning

041 Integrating Lean Construction (PART 2)
041 Integrating Lean Construction (PART 2)041 Integrating Lean Construction (PART 2)
041 Integrating Lean Construction (PART 2)Dr Fereidoun Dejahang
 
041 integrating lean construction (2)
041 integrating lean construction (2)041 integrating lean construction (2)
041 integrating lean construction (2)drdej19
 
046 INTERGRATING SCM WITH FEM & LEAN CONSTRUCTION
046 INTERGRATING SCM WITH FEM & LEAN CONSTRUCTION 046 INTERGRATING SCM WITH FEM & LEAN CONSTRUCTION
046 INTERGRATING SCM WITH FEM & LEAN CONSTRUCTION Dr Fereidoun Dejahang
 
058 Lean Construction (PART 2) Construction productivity
058 Lean Construction  (PART 2) Construction productivity 058 Lean Construction  (PART 2) Construction productivity
058 Lean Construction (PART 2) Construction productivity Dr Fereidoun Dejahang
 
058 lean construction (2)
058 lean construction (2)058 lean construction (2)
058 lean construction (2)drdej19
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
Essay On Stage Scheduling
Essay On Stage SchedulingEssay On Stage Scheduling
Essay On Stage SchedulingJessica Lopez
 
042 integrating lean construction
042 integrating lean construction042 integrating lean construction
042 integrating lean constructiondrdej19
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptpisal3
 
5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to considerOlivia Wilson
 
Design and production tools
Design and production toolsDesign and production tools
Design and production toolsyashikagupta48
 
IRJET- Construction Quality Management on Site
IRJET-  	  Construction Quality Management on SiteIRJET-  	  Construction Quality Management on Site
IRJET- Construction Quality Management on SiteIRJET Journal
 
Chapter 3. CON CURRENT ENGINEERING
Chapter 3. CON CURRENT ENGINEERINGChapter 3. CON CURRENT ENGINEERING
Chapter 3. CON CURRENT ENGINEERINGProf.Mayur Modi
 
Management of time uncertainty in agile
Management of time uncertainty in agileManagement of time uncertainty in agile
Management of time uncertainty in agileijseajournal
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 

Similar to Integrating Constructability & Lean for Improved Work Planning (20)

041 Integrating Lean Construction (PART 2)
041 Integrating Lean Construction (PART 2)041 Integrating Lean Construction (PART 2)
041 Integrating Lean Construction (PART 2)
 
041 integrating lean construction (2)
041 integrating lean construction (2)041 integrating lean construction (2)
041 integrating lean construction (2)
 
046 INTERGRATING SCM WITH FEM & LEAN CONSTRUCTION
046 INTERGRATING SCM WITH FEM & LEAN CONSTRUCTION 046 INTERGRATING SCM WITH FEM & LEAN CONSTRUCTION
046 INTERGRATING SCM WITH FEM & LEAN CONSTRUCTION
 
concurrent engineering.pdf
concurrent engineering.pdfconcurrent engineering.pdf
concurrent engineering.pdf
 
058 Lean Construction (PART 2) Construction productivity
058 Lean Construction  (PART 2) Construction productivity 058 Lean Construction  (PART 2) Construction productivity
058 Lean Construction (PART 2) Construction productivity
 
058 lean construction (2)
058 lean construction (2)058 lean construction (2)
058 lean construction (2)
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Essay On Stage Scheduling
Essay On Stage SchedulingEssay On Stage Scheduling
Essay On Stage Scheduling
 
042 integrating lean construction
042 integrating lean construction042 integrating lean construction
042 integrating lean construction
 
042 iIntegrating Lean Construction
042 iIntegrating Lean Construction042 iIntegrating Lean Construction
042 iIntegrating Lean Construction
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
Ce seminar
Ce seminarCe seminar
Ce seminar
 
5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider
 
Design and production tools
Design and production toolsDesign and production tools
Design and production tools
 
IRJET- Construction Quality Management on Site
IRJET-  	  Construction Quality Management on SiteIRJET-  	  Construction Quality Management on Site
IRJET- Construction Quality Management on Site
 
Chapter 3. CON CURRENT ENGINEERING
Chapter 3. CON CURRENT ENGINEERINGChapter 3. CON CURRENT ENGINEERING
Chapter 3. CON CURRENT ENGINEERING
 
Management of time uncertainty in agile
Management of time uncertainty in agileManagement of time uncertainty in agile
Management of time uncertainty in agile
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 

More from drdej19

069 managing people
069 managing people069 managing people
069 managing peopledrdej19
 
070 material management
070 material management070 material management
070 material managementdrdej19
 
068 managing fundamentals
068 managing fundamentals068 managing fundamentals
068 managing fundamentalsdrdej19
 
067 management
067 management067 management
067 managementdrdej19
 
066 management structure-the design
066 management structure-the design066 management structure-the design
066 management structure-the designdrdej19
 
062 logistics and productivity
062 logistics and productivity062 logistics and productivity
062 logistics and productivitydrdej19
 
065 management information system
065 management information system065 management information system
065 management information systemdrdej19
 
064 management accounting
064 management accounting064 management accounting
064 management accountingdrdej19
 
063 management theory
063 management theory063 management theory
063 management theorydrdej19
 
061 logistics and productivity
061 logistics and productivity061 logistics and productivity
061 logistics and productivitydrdej19
 
059 lean construction
059 lean construction059 lean construction
059 lean constructiondrdej19
 
060 lean supply chain
060 lean supply chain060 lean supply chain
060 lean supply chaindrdej19
 
055 kpi's-success factor
055 kpi's-success factor055 kpi's-success factor
055 kpi's-success factordrdej19
 
057 lean and environment
057 lean and environment057 lean and environment
057 lean and environmentdrdej19
 
056 labour productivity
056 labour productivity056 labour productivity
056 labour productivitydrdej19
 
054 jit and quality management system
054 jit and quality management system054 jit and quality management system
054 jit and quality management systemdrdej19
 
049 integration of constructability
049 integration of constructability049 integration of constructability
049 integration of constructabilitydrdej19
 
048 integrating workers motivation
048 integrating workers motivation048 integrating workers motivation
048 integrating workers motivationdrdej19
 
047 integrating tqm-cons-ve
047 integrating tqm-cons-ve047 integrating tqm-cons-ve
047 integrating tqm-cons-vedrdej19
 
045 integrating scm with jit and tqm
045 integrating scm with jit and tqm045 integrating scm with jit and tqm
045 integrating scm with jit and tqmdrdej19
 

More from drdej19 (20)

069 managing people
069 managing people069 managing people
069 managing people
 
070 material management
070 material management070 material management
070 material management
 
068 managing fundamentals
068 managing fundamentals068 managing fundamentals
068 managing fundamentals
 
067 management
067 management067 management
067 management
 
066 management structure-the design
066 management structure-the design066 management structure-the design
066 management structure-the design
 
062 logistics and productivity
062 logistics and productivity062 logistics and productivity
062 logistics and productivity
 
065 management information system
065 management information system065 management information system
065 management information system
 
064 management accounting
064 management accounting064 management accounting
064 management accounting
 
063 management theory
063 management theory063 management theory
063 management theory
 
061 logistics and productivity
061 logistics and productivity061 logistics and productivity
061 logistics and productivity
 
059 lean construction
059 lean construction059 lean construction
059 lean construction
 
060 lean supply chain
060 lean supply chain060 lean supply chain
060 lean supply chain
 
055 kpi's-success factor
055 kpi's-success factor055 kpi's-success factor
055 kpi's-success factor
 
057 lean and environment
057 lean and environment057 lean and environment
057 lean and environment
 
056 labour productivity
056 labour productivity056 labour productivity
056 labour productivity
 
054 jit and quality management system
054 jit and quality management system054 jit and quality management system
054 jit and quality management system
 
049 integration of constructability
049 integration of constructability049 integration of constructability
049 integration of constructability
 
048 integrating workers motivation
048 integrating workers motivation048 integrating workers motivation
048 integrating workers motivation
 
047 integrating tqm-cons-ve
047 integrating tqm-cons-ve047 integrating tqm-cons-ve
047 integrating tqm-cons-ve
 
045 integrating scm with jit and tqm
045 integrating scm with jit and tqm045 integrating scm with jit and tqm
045 integrating scm with jit and tqm
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 

Integrating Constructability & Lean for Improved Work Planning

  • 1. INTEGRATING CONSTRUCTABILITY WITH LEAN CONSTRUCTION & WORK PLAN helpdesk@construction-productivity.co.uk htt://www.construction-productivity.co.uk
  • 2.  Constructability is the integration of construction expertise into all phases of the project. For Improving factors such as:  cost  schedule  quality  overall project objectives
  • 3.  Constructability must be used at key points in the project life cycle. This includes:  in the planning phase;  early in the design phase;  prior to the procurement phase;  prior to the mobilization phase for construction.
  • 4.  Constructability process considers a detailed review of:  Design drawings;  Models;  Specifications;  construction processes.
  • 5.  This is carried out by one or more highly experienced construction Engineers or specialists.  working closely with the project team including cost engineering;  this is carried out prior to construction mobilization;  before construction work is put for tender.
  • 6. • The purpose of the constructability review is to identify the following items: • Design errors (both material selection or dimensions). • Un clear specifications.
  • 7. • Project features-difficult and very costly to construct. • Project complexity- that exceed the knowledge and capability of industry to properly build. • Project features that are difficult to interpret and will be hard to accurately bid.
  • 8.
  • 9.
  • 10.  Lean construction main objective is to maximize value and reduce waste.  It applies specific techniques in an innovative project delivery approach.  including: 1. supply chain management, 2. Just-In-Time techniques.
  • 11.
  • 12.  As well as the open sharing of information between all the parties involved in the production process.  Lean manufacturing is an outgrowth of the Toyota Production system.  Developed by Taichii Ohno in Toyota in the 1950s.
  • 13.  It is based on lean manufacturing, of the Toyota Production system.  Ohno learnt from mass production at Ford Motor manufacturing facilities in the U.S. and witnessed high level of waste during production.
  • 14. Ohno identified several wastes in mass production systems in car industry such as: 1. overproducing 2. waiting time 3. transporting
  • 15. also, in other areas such as: 1. processing methods; 2. unnecessary stock on hand; 3. unnecessary motion; 4. defective goods; 5. failure to meet customers’ needs; 6. high waste through out the process. He would be very disappointed by recent failures in Toyota car performance.
  • 16.  Womack and Jones (1996) suggested that there are five key principles that need to be monitored when lean construction systems are applied in construction. Those are:  Value-clarifying the customer’s needs;  the supply chain involvement in all stages, from inception to completion;  By clarifying activities or products that signify value.
  • 17. Value stream: By mapping the whole value stream  establishing cooperation between all parties involved;  identifying and eliminating waste;  From taking such steps the construction process can be improved.
  • 18. Flow:  Business flow includes project information such as: 1. specifications 2. contracts 3. plans, etc.  Job site flow involves the activities and the way they have to be carried out.  Supply flow refers to the materials used in a project.
  • 19. Pull:  The efforts of all participants provides smooth pulls during the construction process. Perfection:  Use of best methods of work instructions and best procedures.  Introduction of best quality control methods.
  • 20.
  • 21.  This well planned and systematic approach helps the management team to create quality work plans.  They learn from any failure  a good WorkPlan is a weekly work plan  based on lean construction  production scheduling
  • 22.  screening  work package  constraint  percentage of planned completed (PPC)  Scheduling of construction work is often done with the help of computer tools  It implement the critical-path method (CPM)
  • 23.  based on activities of given duration and unit resources allocated to them  as well as predecessor relationships between activities  for different parties involved in a construction project to communicate with one another whom should be doing what work and when.
  • 24.  The application of lean production techniques in construction has been triggered by its success in manufacturing (Womack and Jones 1996).  Weekly work plans can be developed as valuable tools for production planning and control.  This is possible through the application of lean construction techniques.  In the application weekly work plans are generated using a database (Choo, Tommelein
  • 25.
  • 26.  Activity-on-Arrows Representation of a Nine Activity Project
  • 27.  Defining Precedence Relationships Among Activities