This document discusses integrating constructability reviews with lean construction and work planning. It describes how constructability must be considered early in the project life cycle during planning, design, procurement, and mobilization phases. Conducting detailed reviews of designs, models, specifications, and construction processes allows constructability specialists to identify issues like errors, unclear specifications, complex features, and risks to cost and schedule. The document also outlines key aspects of lean construction including maximizing value and reducing waste. Developing well-planned weekly work schedules using lean techniques allows for production scheduling, work packaging, and monitoring percentage of planned work completed.
2. Constructability is the integration of
construction expertise into all phases
of the project.
For Improving factors such as:
cost
schedule
quality
overall project objectives
3. Constructability must be used at key
points in the project life cycle. This
includes:
in the planning phase;
early in the design phase;
prior to the procurement phase;
prior to the mobilization phase for
construction.
4. Constructability process considers a
detailed review of:
Design drawings;
Models;
Specifications;
construction processes.
5. This is carried out by one or more highly
experienced construction Engineers or
specialists.
working closely with the project team
including cost engineering;
this is carried out prior to construction
mobilization;
before construction work is put for tender.
6. • The purpose of the
constructability review is to
identify the following items:
• Design errors (both material
selection or dimensions).
• Un clear specifications.
7. • Project features-difficult and very
costly to construct.
• Project complexity- that exceed the
knowledge and capability of industry
to properly build.
• Project features that are difficult to
interpret and will be hard to
accurately bid.
8.
9.
10. Lean construction main objective is to
maximize value and reduce waste.
It applies specific techniques in an
innovative project delivery approach.
including:
1. supply chain management,
2. Just-In-Time techniques.
11.
12. As well as the open sharing of information
between all the parties involved in the
production process.
Lean manufacturing is an outgrowth of the
Toyota Production system.
Developed by Taichii Ohno in Toyota in
the 1950s.
13. It is based on lean manufacturing,
of the Toyota Production system.
Ohno learnt from mass production at Ford
Motor manufacturing facilities in the U.S.
and witnessed high level of waste during
production.
14. Ohno identified several wastes in mass
production systems in car industry
such as:
1. overproducing
2. waiting time
3. transporting
15. also, in other areas such as:
1. processing methods;
2. unnecessary stock on hand;
3. unnecessary motion;
4. defective goods;
5. failure to meet customers’ needs;
6. high waste through out the process. He
would be very disappointed by recent
failures in Toyota car performance.
16. Womack and Jones (1996) suggested that
there are five key principles that need to be
monitored when lean construction systems
are applied in construction. Those are:
Value-clarifying the customer’s needs;
the supply chain involvement in all stages,
from inception to completion;
By clarifying activities or products
that signify value.
17. Value stream: By mapping the
whole value stream
establishing cooperation between all
parties involved;
identifying and eliminating waste;
From taking such steps the
construction process can be
improved.
18. Flow:
Business flow includes project
information such as:
1. specifications
2. contracts
3. plans, etc.
Job site flow involves the activities
and the way they have to be carried
out.
Supply flow refers to the materials
used in a project.
19. Pull:
The efforts of all participants provides
smooth pulls during the construction
process.
Perfection:
Use of best methods of work
instructions and best procedures.
Introduction of best quality control
methods.
20.
21. This well planned and systematic
approach helps the management
team to create quality work plans.
They learn from any failure
a good WorkPlan is a weekly work
plan
based on lean construction
production scheduling
22. screening
work package
constraint
percentage of planned completed (PPC)
Scheduling of construction work is often
done with the help of computer tools
It implement the critical-path method
(CPM)
23. based on activities of given duration and
unit resources allocated to them
as well as predecessor relationships
between activities
for different parties involved in a
construction project to communicate with
one another whom should be doing what
work and when.
24. The application of lean production techniques in
construction has been triggered by its success in
manufacturing (Womack and Jones 1996).
Weekly work plans can be developed as valuable
tools for production planning and control.
This is possible through the application of lean
construction techniques.
In the application weekly work plans are generated
using a database (Choo, Tommelein