SlideShare a Scribd company logo
1 of 6
Download to read offline
RM RM
1.0 81,200,000.00
2.0 Less : 9,600,000.00
71,600,000.00
3.0 Add : Variation works (V.O. Nos. 1-4)
33,000.00
50,500.00
(17,500.00) (17,500.00)
71,582,500.00
4.0 Add back: NSC's final account
4.1 1,600,000.00
4.2 Air Conditioning Services 2,200,000.00
4.3 Electrical Services 2,600,000.00
4.4 1,250,000.00
7,650,000.00 7,650,000.00
4.5 Profit and Attendance:
a. Profit @ 2% of RM7,650,000.00 153,000.00
b. Attendance @ lump sum 135,000.00
288,000.00 288,000.00
5.0
5.1 Additional Expenses 30,000.00
5.2 0.00
30,000.00 30,000.00
FINAL CONTRACT VALUE 79,550,500.00
Loss and Expense
Project: Construction and Completion of Clinton Residence, Kuala Lumpur
Nett Additions
Lift Services
Guard House
Contractual Claims:
Contractor: Sunshine Builder Construction
FINAL ACCOUNT
Total Omissions
P.C. & Provisional Sums
Original Contract Sum
Total Additions
Total Builder's works
Employer: Hilton Homes Sdn Bhd
Item Description Nett Amount (RM)
1 Preliminaries 4,250,000.00
2 Building Works 62,850,000.00
3 Local Infrastructure Works 4,500,000.00
4 P.C. and Provisional Sums 9,600,000.00
81,200,000.00TOTAL CARRIED TO STATEMENT OF FINAL ACCOUNT
SUMMARY OF ORIGINAL CONTRACT SUM
NSC/1 Lift Services 1,300,000.00 1,600,000.00 306,000.00
Profit @ 2% 26,000.00 32,000.00
Attendance as item 20,000.00 20,000.00
NSC/2 Air Conditoning Services 2,300,000.00 2,200,000.00 (102,000.00)
Profit @ 2% 46,000.00 44,000.00
Attendance as item 40,000.00 40,000.00
NSC/3 Electrical Services 2,700,000.00 2,600,000.00 (102,000.00)
Profit @ 2% 54,000.00 52,000.00
Attendance as item 50,000.00 50,000.00
NSC/4 Provisional Sums : Guard House 1,000,000.00 1,250,000.00 260,000.00
Profit@2% 20,000.00 25,000.00
Attendance as item 20,000.00 25,000.00
7,576,000.00 7,938,000.00 362,000.00
Total NSC Final Account 7,300,000.00 7,650,000.00 362,000.00
Total Profit 146,000.00 153,000.00
Total Attendance 130,000.00 135,000.00
Net addition/
omission (RM)
SUMMARY OF NSC FINAL ACCOUNT
TOTAL CARRIED TO STATEMENT OF FINAL
ACCOUNT
Variation Item Description Omission (RM) Addition (RM)
VO/1
Architect instructed the Contractor
to provide a colour photocopied
machine instead of the black and
white photocopier machine
0.00 8,000.00 8,000.00
VO/2
Architect insructed the Contractor to
use granite tiles and remove marble
tiles
50,000.00 20,000.00 (30,000.00)
VO/3 Revised rates for rock excavation 500.00 5,000.00 4,500.00
(17,500.00)33,000.00
Omission
(RM)
Addition
(RM)
Net addition/
omission
(RM)
Description
SUMMARY OF VARIATION WORK
Variation Item
50,500.00
TOTAL CARRIED TO STATEMENT OF FINAL
ACCOUNT
Item Description
Omission
(RM)
Addition
(RM)
Nett Addition/Omission
(RM)
1 Additional expenses for insurance premium 0.00 30,000.00 30,000.00
0.00 30,000.00 30,000.00
SUMMARY OF LOSS & EXPENSES
TOTAL CARRIED TO STATEMENT OF
FINAL ACCOUNT
SUMMARY OF EXTENSION OF TIME
Item Cause of Delay Clause Ref. Remarks
1 Late decision on toilet design 23.8 (e)
Confirmed by architect and
approved by employer
2 Exceptionally inclement weather 23.8 (b) Approved by architect
3
Change of marble floor tiles to granite
floor
23.8 (g)
Confirmed by architect and
approved by employer

More Related Content

What's hot

Draft final present for study market (last and burn)
Draft final present for study market (last and burn)Draft final present for study market (last and burn)
Draft final present for study market (last and burn)FARID YUNOS
Β 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - AssignmentQuo Ming
Β 
BVBA van Wim Lybaert keert alle winst uit
BVBA van Wim Lybaert keert alle winst uitBVBA van Wim Lybaert keert alle winst uit
BVBA van Wim Lybaert keert alle winst uitThierry Debels
Β 
Pengenalan prinsip pengurusan strata
Pengenalan prinsip pengurusan strataPengenalan prinsip pengurusan strata
Pengenalan prinsip pengurusan strataSr Ezwan Bustamin
Β 
ECA Workshop - Presentation
ECA Workshop - PresentationECA Workshop - Presentation
ECA Workshop - PresentationKai Yun Pang
Β 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 μ΄ν™˜
Β 
Analisa harga satuan pekerjaan (1)
Analisa harga satuan pekerjaan (1)Analisa harga satuan pekerjaan (1)
Analisa harga satuan pekerjaan (1)Ferdinand Nanubmat
Β 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerTrace96
Β 
PEDOMAN SERTIFIKAT LAIK FUNGSI BANGUNAN GEDUNG
PEDOMAN SERTIFIKAT LAIK FUNGSI BANGUNAN GEDUNGPEDOMAN SERTIFIKAT LAIK FUNGSI BANGUNAN GEDUNG
PEDOMAN SERTIFIKAT LAIK FUNGSI BANGUNAN GEDUNGinideedee
Β 
PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation Jaey Chai
Β 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
Β 
CL Final Report
CL Final ReportCL Final Report
CL Final ReportMelvin Lim
Β 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: GroupFarah Sham
Β 
Chapter 4 pengurusan strata
Chapter 4 pengurusan strataChapter 4 pengurusan strata
Chapter 4 pengurusan stratajantanhero
Β 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
Β 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
Β 
Manual Perolehan Perunding 2006
Manual Perolehan Perunding 2006Manual Perolehan Perunding 2006
Manual Perolehan Perunding 2006hadypower
Β 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost AnalysisPang Khai Shuen
Β 

What's hot (20)

Draft final present for study market (last and burn)
Draft final present for study market (last and burn)Draft final present for study market (last and burn)
Draft final present for study market (last and burn)
Β 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - Assignment
Β 
BVBA van Wim Lybaert keert alle winst uit
BVBA van Wim Lybaert keert alle winst uitBVBA van Wim Lybaert keert alle winst uit
BVBA van Wim Lybaert keert alle winst uit
Β 
TATA NASKAH DINAS 2014
TATA NASKAH DINAS 2014TATA NASKAH DINAS 2014
TATA NASKAH DINAS 2014
Β 
Pengenalan prinsip pengurusan strata
Pengenalan prinsip pengurusan strataPengenalan prinsip pengurusan strata
Pengenalan prinsip pengurusan strata
Β 
ECA Workshop - Presentation
ECA Workshop - PresentationECA Workshop - Presentation
ECA Workshop - Presentation
Β 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
Β 
Analisa harga satuan pekerjaan (1)
Analisa harga satuan pekerjaan (1)Analisa harga satuan pekerjaan (1)
Analisa harga satuan pekerjaan (1)
Β 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
Β 
PEDOMAN SERTIFIKAT LAIK FUNGSI BANGUNAN GEDUNG
PEDOMAN SERTIFIKAT LAIK FUNGSI BANGUNAN GEDUNGPEDOMAN SERTIFIKAT LAIK FUNGSI BANGUNAN GEDUNG
PEDOMAN SERTIFIKAT LAIK FUNGSI BANGUNAN GEDUNG
Β 
PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation
Β 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
Β 
CL Final Report
CL Final ReportCL Final Report
CL Final Report
Β 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: Group
Β 
Chapter 4 pengurusan strata
Chapter 4 pengurusan strataChapter 4 pengurusan strata
Chapter 4 pengurusan strata
Β 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
Β 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
Β 
Manual Perolehan Perunding 2006
Manual Perolehan Perunding 2006Manual Perolehan Perunding 2006
Manual Perolehan Perunding 2006
Β 
ECA form
ECA formECA form
ECA form
Β 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
Β 

Similar to Construction Completion Final Account

Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial AppraisalKai Yun Pang
Β 
531296468-2-4-Problems-Revaluation.pptxs
531296468-2-4-Problems-Revaluation.pptxs531296468-2-4-Problems-Revaluation.pptxs
531296468-2-4-Problems-Revaluation.pptxsjbonit
Β 
Bisnis plan-warnet-broadband
Bisnis plan-warnet-broadbandBisnis plan-warnet-broadband
Bisnis plan-warnet-broadbandRobby Ariebullah
Β 
Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Mourad Iskandar
Β 
De assignment
De assignmentDe assignment
De assignmentLwj Welson
Β 
Copy of Financial report
Copy of Financial reportCopy of Financial report
Copy of Financial reportCA Ramanuj Kumar
Β 
Calendario valorizado sistema de recreacion amotape
Calendario valorizado  sistema de recreacion amotapeCalendario valorizado  sistema de recreacion amotape
Calendario valorizado sistema de recreacion amotapeEdikson Soto
Β 
A157071 Modul 7 Tugasan Agihan Perjalanan
A157071 Modul 7 Tugasan Agihan PerjalananA157071 Modul 7 Tugasan Agihan Perjalanan
A157071 Modul 7 Tugasan Agihan PerjalananLoh Siew Ling
Β 
Costing assignment.docx
Costing assignment.docxCosting assignment.docx
Costing assignment.docxssuserdcbf4e
Β 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708Pang Khai Shuen
Β 
Solution chemalite
Solution chemaliteSolution chemalite
Solution chemalitealdo
Β 
Final slideshow presentation (1)
Final slideshow presentation (1)Final slideshow presentation (1)
Final slideshow presentation (1)Aura Investments
Β 
De assignment-finalized-28112017 2
De assignment-finalized-28112017 2De assignment-finalized-28112017 2
De assignment-finalized-28112017 2Arthur Wilson
Β 
The watergate confidential
The watergate confidentialThe watergate confidential
The watergate confidentialHaris Memon
Β 
cost appraisal
cost appraisalcost appraisal
cost appraisalahmong4
Β 
Hadi CAF6 March 2021 Q6
Hadi CAF6 March 2021 Q6Hadi CAF6 March 2021 Q6
Hadi CAF6 March 2021 Q6Fawad Hassan
Β 
Final presentation with excel 2
Final presentation with excel 2Final presentation with excel 2
Final presentation with excel 2Aura Investments
Β 
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary ReportSchedule of Works Cost Summary Report
Schedule of Works Cost Summary ReportNatalie Reid
Β 

Similar to Construction Completion Final Account (20)

Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial Appraisal
Β 
531296468-2-4-Problems-Revaluation.pptxs
531296468-2-4-Problems-Revaluation.pptxs531296468-2-4-Problems-Revaluation.pptxs
531296468-2-4-Problems-Revaluation.pptxs
Β 
Bisnis plan-warnet-broadband
Bisnis plan-warnet-broadbandBisnis plan-warnet-broadband
Bisnis plan-warnet-broadband
Β 
Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.
Β 
CA Unit-4 (Overhead) Problems and Solutions
CA Unit-4 (Overhead) Problems and SolutionsCA Unit-4 (Overhead) Problems and Solutions
CA Unit-4 (Overhead) Problems and Solutions
Β 
De assignment
De assignmentDe assignment
De assignment
Β 
Copy of Financial report
Copy of Financial reportCopy of Financial report
Copy of Financial report
Β 
Calendario valorizado sistema de recreacion amotape
Calendario valorizado  sistema de recreacion amotapeCalendario valorizado  sistema de recreacion amotape
Calendario valorizado sistema de recreacion amotape
Β 
A157071 Modul 7 Tugasan Agihan Perjalanan
A157071 Modul 7 Tugasan Agihan PerjalananA157071 Modul 7 Tugasan Agihan Perjalanan
A157071 Modul 7 Tugasan Agihan Perjalanan
Β 
Costing assignment.docx
Costing assignment.docxCosting assignment.docx
Costing assignment.docx
Β 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708
Β 
Solution chemalite
Solution chemaliteSolution chemalite
Solution chemalite
Β 
Final slideshow presentation (1)
Final slideshow presentation (1)Final slideshow presentation (1)
Final slideshow presentation (1)
Β 
De assignment-finalized-28112017 2
De assignment-finalized-28112017 2De assignment-finalized-28112017 2
De assignment-finalized-28112017 2
Β 
The watergate confidential
The watergate confidentialThe watergate confidential
The watergate confidential
Β 
cost appraisal
cost appraisalcost appraisal
cost appraisal
Β 
Hadi CAF6 March 2021 Q6
Hadi CAF6 March 2021 Q6Hadi CAF6 March 2021 Q6
Hadi CAF6 March 2021 Q6
Β 
Final presentation with excel 2
Final presentation with excel 2Final presentation with excel 2
Final presentation with excel 2
Β 
Modul 7 a157841
Modul 7  a157841Modul 7  a157841
Modul 7 a157841
Β 
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary ReportSchedule of Works Cost Summary Report
Schedule of Works Cost Summary Report
Β 

More from ashleyyeap

CSI JOURNAL cover page
CSI JOURNAL cover pageCSI JOURNAL cover page
CSI JOURNAL cover pageashleyyeap
Β 
CSI JOURNAL
CSI JOURNALCSI JOURNAL
CSI JOURNALashleyyeap
Β 
Fm group assignment
Fm group assignment Fm group assignment
Fm group assignment ashleyyeap
Β 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
Β 
Fm august 2018 group assignment brief
Fm august 2018 group assignment briefFm august 2018 group assignment brief
Fm august 2018 group assignment briefashleyyeap
Β 
Building Economics Assignment Report
Building Economics Assignment ReportBuilding Economics Assignment Report
Building Economics Assignment Reportashleyyeap
Β 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal ashleyyeap
Β 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentationashleyyeap
Β 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808ashleyyeap
Β 
Measurement Assignment
Measurement AssignmentMeasurement Assignment
Measurement Assignmentashleyyeap
Β 
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3ashleyyeap
Β 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7ashleyyeap
Β 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slidesashleyyeap
Β 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignmentashleyyeap
Β 
Estimating Assignment
Estimating Assignment Estimating Assignment
Estimating Assignment ashleyyeap
Β 
Software Assignment
Software AssignmentSoftware Assignment
Software Assignmentashleyyeap
Β 
Management Science Assignment
Management Science Assignment Management Science Assignment
Management Science Assignment ashleyyeap
Β 
People Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case StudyPeople Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case Studyashleyyeap
Β 
Building Services II Presentation Slides
Building Services II Presentation SlidesBuilding Services II Presentation Slides
Building Services II Presentation Slidesashleyyeap
Β 
Building Services II Assginment Report
Building Services II Assginment ReportBuilding Services II Assginment Report
Building Services II Assginment Reportashleyyeap
Β 

More from ashleyyeap (20)

CSI JOURNAL cover page
CSI JOURNAL cover pageCSI JOURNAL cover page
CSI JOURNAL cover page
Β 
CSI JOURNAL
CSI JOURNALCSI JOURNAL
CSI JOURNAL
Β 
Fm group assignment
Fm group assignment Fm group assignment
Fm group assignment
Β 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
Β 
Fm august 2018 group assignment brief
Fm august 2018 group assignment briefFm august 2018 group assignment brief
Fm august 2018 group assignment brief
Β 
Building Economics Assignment Report
Building Economics Assignment ReportBuilding Economics Assignment Report
Building Economics Assignment Report
Β 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
Β 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentation
Β 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
Β 
Measurement Assignment
Measurement AssignmentMeasurement Assignment
Measurement Assignment
Β 
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3
Β 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
Β 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slides
Β 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
Β 
Estimating Assignment
Estimating Assignment Estimating Assignment
Estimating Assignment
Β 
Software Assignment
Software AssignmentSoftware Assignment
Software Assignment
Β 
Management Science Assignment
Management Science Assignment Management Science Assignment
Management Science Assignment
Β 
People Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case StudyPeople Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case Study
Β 
Building Services II Presentation Slides
Building Services II Presentation SlidesBuilding Services II Presentation Slides
Building Services II Presentation Slides
Β 
Building Services II Assginment Report
Building Services II Assginment ReportBuilding Services II Assginment Report
Building Services II Assginment Report
Β 

Recently uploaded

The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
Β 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
Β 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
Β 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
Β 
call girls in Kamla Market (DELHI) πŸ” >ΰΌ’9953330565πŸ” genuine Escort Service πŸ”βœ”οΈβœ”οΈ
call girls in Kamla Market (DELHI) πŸ” >ΰΌ’9953330565πŸ” genuine Escort Service πŸ”βœ”οΈβœ”οΈcall girls in Kamla Market (DELHI) πŸ” >ΰΌ’9953330565πŸ” genuine Escort Service πŸ”βœ”οΈβœ”οΈ
call girls in Kamla Market (DELHI) πŸ” >ΰΌ’9953330565πŸ” genuine Escort Service πŸ”βœ”οΈβœ”οΈ9953056974 Low Rate Call Girls In Saket, Delhi NCR
Β 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
Β 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
Β 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
Β 
β€œOh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
β€œOh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...β€œOh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
β€œOh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
Β 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
Β 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
Β 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
Β 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
Β 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
Β 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
Β 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
Β 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
Β 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
Β 

Recently uploaded (20)

Model Call Girl in Bikash Puri Delhi reach out to us at πŸ”9953056974πŸ”
Model Call Girl in Bikash Puri  Delhi reach out to us at πŸ”9953056974πŸ”Model Call Girl in Bikash Puri  Delhi reach out to us at πŸ”9953056974πŸ”
Model Call Girl in Bikash Puri Delhi reach out to us at πŸ”9953056974πŸ”
Β 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
Β 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
Β 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
Β 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
Β 
call girls in Kamla Market (DELHI) πŸ” >ΰΌ’9953330565πŸ” genuine Escort Service πŸ”βœ”οΈβœ”οΈ
call girls in Kamla Market (DELHI) πŸ” >ΰΌ’9953330565πŸ” genuine Escort Service πŸ”βœ”οΈβœ”οΈcall girls in Kamla Market (DELHI) πŸ” >ΰΌ’9953330565πŸ” genuine Escort Service πŸ”βœ”οΈβœ”οΈ
call girls in Kamla Market (DELHI) πŸ” >ΰΌ’9953330565πŸ” genuine Escort Service πŸ”βœ”οΈβœ”οΈ
Β 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
Β 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
Β 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
Β 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
Β 
β€œOh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
β€œOh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...β€œOh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
β€œOh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
Β 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
Β 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
Β 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
Β 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
Β 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
Β 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
Β 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
Β 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
Β 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Β 

Construction Completion Final Account

  • 1. RM RM 1.0 81,200,000.00 2.0 Less : 9,600,000.00 71,600,000.00 3.0 Add : Variation works (V.O. Nos. 1-4) 33,000.00 50,500.00 (17,500.00) (17,500.00) 71,582,500.00 4.0 Add back: NSC's final account 4.1 1,600,000.00 4.2 Air Conditioning Services 2,200,000.00 4.3 Electrical Services 2,600,000.00 4.4 1,250,000.00 7,650,000.00 7,650,000.00 4.5 Profit and Attendance: a. Profit @ 2% of RM7,650,000.00 153,000.00 b. Attendance @ lump sum 135,000.00 288,000.00 288,000.00 5.0 5.1 Additional Expenses 30,000.00 5.2 0.00 30,000.00 30,000.00 FINAL CONTRACT VALUE 79,550,500.00 Loss and Expense Project: Construction and Completion of Clinton Residence, Kuala Lumpur Nett Additions Lift Services Guard House Contractual Claims: Contractor: Sunshine Builder Construction FINAL ACCOUNT Total Omissions P.C. & Provisional Sums Original Contract Sum Total Additions Total Builder's works Employer: Hilton Homes Sdn Bhd
  • 2. Item Description Nett Amount (RM) 1 Preliminaries 4,250,000.00 2 Building Works 62,850,000.00 3 Local Infrastructure Works 4,500,000.00 4 P.C. and Provisional Sums 9,600,000.00 81,200,000.00TOTAL CARRIED TO STATEMENT OF FINAL ACCOUNT SUMMARY OF ORIGINAL CONTRACT SUM
  • 3. NSC/1 Lift Services 1,300,000.00 1,600,000.00 306,000.00 Profit @ 2% 26,000.00 32,000.00 Attendance as item 20,000.00 20,000.00 NSC/2 Air Conditoning Services 2,300,000.00 2,200,000.00 (102,000.00) Profit @ 2% 46,000.00 44,000.00 Attendance as item 40,000.00 40,000.00 NSC/3 Electrical Services 2,700,000.00 2,600,000.00 (102,000.00) Profit @ 2% 54,000.00 52,000.00 Attendance as item 50,000.00 50,000.00 NSC/4 Provisional Sums : Guard House 1,000,000.00 1,250,000.00 260,000.00 Profit@2% 20,000.00 25,000.00 Attendance as item 20,000.00 25,000.00 7,576,000.00 7,938,000.00 362,000.00 Total NSC Final Account 7,300,000.00 7,650,000.00 362,000.00 Total Profit 146,000.00 153,000.00 Total Attendance 130,000.00 135,000.00 Net addition/ omission (RM) SUMMARY OF NSC FINAL ACCOUNT TOTAL CARRIED TO STATEMENT OF FINAL ACCOUNT Variation Item Description Omission (RM) Addition (RM)
  • 4. VO/1 Architect instructed the Contractor to provide a colour photocopied machine instead of the black and white photocopier machine 0.00 8,000.00 8,000.00 VO/2 Architect insructed the Contractor to use granite tiles and remove marble tiles 50,000.00 20,000.00 (30,000.00) VO/3 Revised rates for rock excavation 500.00 5,000.00 4,500.00 (17,500.00)33,000.00 Omission (RM) Addition (RM) Net addition/ omission (RM) Description SUMMARY OF VARIATION WORK Variation Item 50,500.00 TOTAL CARRIED TO STATEMENT OF FINAL ACCOUNT
  • 5. Item Description Omission (RM) Addition (RM) Nett Addition/Omission (RM) 1 Additional expenses for insurance premium 0.00 30,000.00 30,000.00 0.00 30,000.00 30,000.00 SUMMARY OF LOSS & EXPENSES TOTAL CARRIED TO STATEMENT OF FINAL ACCOUNT
  • 6. SUMMARY OF EXTENSION OF TIME Item Cause of Delay Clause Ref. Remarks 1 Late decision on toilet design 23.8 (e) Confirmed by architect and approved by employer 2 Exceptionally inclement weather 23.8 (b) Approved by architect 3 Change of marble floor tiles to granite floor 23.8 (g) Confirmed by architect and approved by employer