SlideShare a Scribd company logo
1 of 8
Transient Recovery Voltage(TRV) in Interruption of
Small Inductive Currents by Circuit Breakers
Article 5(01.10.2018)
Transients caused by switching operations in linear systems can be
analyzed by using the superposition principle. The switching process
caused by an opening operation is obtained by adding the steady-state
solution, which exists prior to the opening operation, and the transient
response of the system that results from short circuiting voltage sources
and open-circuiting current sources to a current injected through the
switch contacts.
Since the current through the switch terminals after the operation will
be zero, the injected current must equal to the current that was flowing
between switch terminals prior to the opening operation. When the
contacts of a switch start to open a transient voltage is developed across
them. This voltage, known as TRV, is present immediately after the
A good understanding of the transient phenomena associated with circuit
breaker operations in power systems has led to improved testing practice and
resulted in more reliable switchgear. Recommended characteristic values for
simulation of the TRV are fixed in standards.
In Fig Below you see TRV circuit breaker terminals when interrupting the
current in very simple circuits. Observe the different wave shape that appear
in each case. The representation of each circuit is that depicted in the figure,
except for the interruption of the inductive current since in this case the
current zero occurs when the voltage across the inductor terminals is
maximum, and a capacitive element is needed to account for the trapped
charge. The latter oscillation is caused by the energy transfer between the
inductor and the capacitor. Although real systems are much more complex
than the circuits analyzed above, these cases show that switching under
normal operating conditions can be categorized as resistive, inductive, and
The interruption of small currents can lead to situations that are known as
current chopping and virtual chopping. If the current is interrupted at current
zero, the interruption is normal and the TRVs are usually within the specified
values. However, if premature interruption occurs, due to current chopping,
the interruption will be abnormal and it can cause high-frequency
resignations and overvoltage's.
When the breaker chops the peak current, the voltage increases almost
instantaneously, if this overvoltage exceeds the specified dielectric strength of the
circuit breaker, re ignition takes place. When this process is repeated several times,
due to high-frequency resignations, the voltage increase continues with rapid
escalation of voltages. The high-frequency oscillations are governed by the
electrical parameters of the concerned circuit, circuit configuration and interrupter
design, and result in a zero crossing before the actual power-frequency current
zero.
In the figure below compares the load side voltage and the TRVs that are
generated when arc interruption takes place at current zero and before current
zero (current chopping),respectively. It is obvious from this example that the
second case is more severe. The importance of current chopping can be easily
understood by neglecting the influence of losses at the load side. After current
interruption at current zero, the energy stored in the load side is the energy stored
at the capacitance, whose voltage is at the maximum.
a) Equivalent circuit. (b) Arc interruption at current zero. (c) Arc interruption
before current zero.
In the case of current chopping, the instability of the arc around current zero
causes a high-frequency transient current to flow in the neighboring network
elements. This High Frequency current superimposes on the power-frequency
current whose amplitude is small and which is actually chopped to zero. In the case
of virtual chopping, the arc is made unstable through a superimposed high-
frequency current caused by oscillations with the neighboring phases in which
current chopping took place. Virtual chopping has been observed for gaseous arcs
in air, SF6, and oil. Vacuum arcs are also very sensitive to current chopping.
The phenomena of chopping and resignation, with associated high-frequency
oscillatory overvoltage's, are attributed to the design of the circuit breaker. Circuit
breakers are designed to cope with high fault currents. If a design is concentrated
only on an efficient performance for high currents, it will be also efficient for small
current and will try to interrupt before the natural current zero. This may produce
current chopping and resignations with adverse consequences. The breaker design
should incorporate features to cope equally well with small and high currents.
References:
*Transient recovery voltage analysis for various current breaking
mathematical models: shunt reactor and capacitor bank de-
energization study article by :PIOTR ORAMUS, TOMASZ
CHMIELEWSKI, TOMASZ KUCZEK, WOJCIECH PIASECKI, MARCIN
SZEWCZYK,ABB Corporate Research Center.
*Power system transients parameter determination Book edited
by : Juan A. Martinez Velasco.
*Tech Topics No. 35 from SIEMENS .
*Effects of Transient Recovery Voltages on Circuit Breaker
Ratings Article Term Project: - EE5220 - Power System
Transients. by :Himanshu Bahirat Muhammad Ali Praveen KK .

More Related Content

What's hot

Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protectionBinit Das
 
Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Low
 
Technical information for high voltage disconnector & earthing switch in enqu...
Technical information for high voltage disconnector & earthing switch in enqu...Technical information for high voltage disconnector & earthing switch in enqu...
Technical information for high voltage disconnector & earthing switch in enqu...Ali Sepehri
 
Measurement of the resistance of switchgear main circuit
Measurement of the resistance of switchgear main circuitMeasurement of the resistance of switchgear main circuit
Measurement of the resistance of switchgear main circuitRaveendranath Macherla
 
Transformer asset management
Transformer asset managementTransformer asset management
Transformer asset managementMuthar Hussain
 
Circuit breaker
Circuit breakerCircuit breaker
Circuit breakersarunkutti
 
Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015
Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015
Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015Gabriel Emeka Ojeah
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentationNadir Baloch
 
Transformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisTransformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisHamedPasha1
 
Frequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformerFrequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformerRaveendranath Macherla
 
Transformer testing
Transformer testingTransformer testing
Transformer testingajayknows
 
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...Jobin Abraham
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protectionRakesh Joshi
 
Power Transformer Differential protection
Power Transformer Differential protectionPower Transformer Differential protection
Power Transformer Differential protectionRishi Tandon
 
High voltage testing of electrical transformer
High voltage testing of electrical transformerHigh voltage testing of electrical transformer
High voltage testing of electrical transformerPraveenKumar5880
 
Unit 06 - Substation and maintenance
Unit 06 - Substation and maintenanceUnit 06 - Substation and maintenance
Unit 06 - Substation and maintenancePremanandDesai
 
Power transformer protection
Power transformer protectionPower transformer protection
Power transformer protectionmichaeljmack
 

What's hot (20)

Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protection
 
Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015
 
Technical information for high voltage disconnector & earthing switch in enqu...
Technical information for high voltage disconnector & earthing switch in enqu...Technical information for high voltage disconnector & earthing switch in enqu...
Technical information for high voltage disconnector & earthing switch in enqu...
 
Measurement of the resistance of switchgear main circuit
Measurement of the resistance of switchgear main circuitMeasurement of the resistance of switchgear main circuit
Measurement of the resistance of switchgear main circuit
 
Transformer asset management
Transformer asset managementTransformer asset management
Transformer asset management
 
Circuit breaker
Circuit breakerCircuit breaker
Circuit breaker
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015
Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015
Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015
 
SSSC and GCSC
SSSC and GCSCSSSC and GCSC
SSSC and GCSC
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Transformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisTransformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response Analysis
 
Frequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformerFrequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformer
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
 
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
 
Power Transformer Differential protection
Power Transformer Differential protectionPower Transformer Differential protection
Power Transformer Differential protection
 
High voltage testing of electrical transformer
High voltage testing of electrical transformerHigh voltage testing of electrical transformer
High voltage testing of electrical transformer
 
Transformer
TransformerTransformer
Transformer
 
Unit 06 - Substation and maintenance
Unit 06 - Substation and maintenanceUnit 06 - Substation and maintenance
Unit 06 - Substation and maintenance
 
Power transformer protection
Power transformer protectionPower transformer protection
Power transformer protection
 

Similar to Transient Recovery Voltage(TRV) in Interruption of Small Inductive Currents by Circuit Breakers

Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in briefMuthar Hussain
 
Circuit Breaker : Types
Circuit Breaker : TypesCircuit Breaker : Types
Circuit Breaker : TypesRidwanul Hoque
 
pptonprotectionofpowertransformers-161020085118 (1).pdf
pptonprotectionofpowertransformers-161020085118 (1).pdfpptonprotectionofpowertransformers-161020085118 (1).pdf
pptonprotectionofpowertransformers-161020085118 (1).pdfSunny268892
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformerssiddharam kantoli
 
Catastrophic failure of system equipment during switching of 115kV shunt reac...
Catastrophic failure of system equipment during switching of 115kV shunt reac...Catastrophic failure of system equipment during switching of 115kV shunt reac...
Catastrophic failure of system equipment during switching of 115kV shunt reac...rannaluru
 
electrical transients in power system
electrical transients in power systemelectrical transients in power system
electrical transients in power systemVinayaka Shetty
 
SGPD(MOD-4).pdf...................................................
SGPD(MOD-4).pdf...................................................SGPD(MOD-4).pdf...................................................
SGPD(MOD-4).pdf...................................................MANOJ KHARADE
 
SGPD(MOD-4).pdfsgp .....................
SGPD(MOD-4).pdfsgp .....................SGPD(MOD-4).pdfsgp .....................
SGPD(MOD-4).pdfsgp .....................MANOJ KHARADE
 
Transcat and Megger: Power Quality 101 Webinar
Transcat and Megger: Power Quality 101 WebinarTranscat and Megger: Power Quality 101 Webinar
Transcat and Megger: Power Quality 101 WebinarTranscat
 
Over current protection
Over current protectionOver current protection
Over current protectionSHUBHAM KUMAR
 
Ppt on introduction to power quality
Ppt on introduction to power qualityPpt on introduction to power quality
Ppt on introduction to power qualityShivani Mishra
 
Protection of transformer
Protection of transformerProtection of transformer
Protection of transformerSumeet Ratnawat
 
High voltage grounding methods
High voltage grounding methods High voltage grounding methods
High voltage grounding methods Adnan Khan
 

Similar to Transient Recovery Voltage(TRV) in Interruption of Small Inductive Currents by Circuit Breakers (20)

Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in brief
 
unit_2.ppt
unit_2.pptunit_2.ppt
unit_2.ppt
 
unit_2.ppt
unit_2.pptunit_2.ppt
unit_2.ppt
 
EE-524 Project report
EE-524 Project reportEE-524 Project report
EE-524 Project report
 
Circuit Breaker : Types
Circuit Breaker : TypesCircuit Breaker : Types
Circuit Breaker : Types
 
Reduction of transients in switches using embedded machine learning
Reduction of transients in switches using embedded machine learningReduction of transients in switches using embedded machine learning
Reduction of transients in switches using embedded machine learning
 
pptonprotectionofpowertransformers-161020085118 (1).pdf
pptonprotectionofpowertransformers-161020085118 (1).pdfpptonprotectionofpowertransformers-161020085118 (1).pdf
pptonprotectionofpowertransformers-161020085118 (1).pdf
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
 
Super
SuperSuper
Super
 
Catastrophic failure of system equipment during switching of 115kV shunt reac...
Catastrophic failure of system equipment during switching of 115kV shunt reac...Catastrophic failure of system equipment during switching of 115kV shunt reac...
Catastrophic failure of system equipment during switching of 115kV shunt reac...
 
electrical transients in power system
electrical transients in power systemelectrical transients in power system
electrical transients in power system
 
SGPD(MOD-4).pdf...................................................
SGPD(MOD-4).pdf...................................................SGPD(MOD-4).pdf...................................................
SGPD(MOD-4).pdf...................................................
 
SGPD(MOD-4).pdfsgp .....................
SGPD(MOD-4).pdfsgp .....................SGPD(MOD-4).pdfsgp .....................
SGPD(MOD-4).pdfsgp .....................
 
Transcat and Megger: Power Quality 101 Webinar
Transcat and Megger: Power Quality 101 WebinarTranscat and Megger: Power Quality 101 Webinar
Transcat and Megger: Power Quality 101 Webinar
 
Over current protection
Over current protectionOver current protection
Over current protection
 
Transformers Protection
Transformers ProtectionTransformers Protection
Transformers Protection
 
Series circuits
Series circuitsSeries circuits
Series circuits
 
Ppt on introduction to power quality
Ppt on introduction to power qualityPpt on introduction to power quality
Ppt on introduction to power quality
 
Protection of transformer
Protection of transformerProtection of transformer
Protection of transformer
 
High voltage grounding methods
High voltage grounding methods High voltage grounding methods
High voltage grounding methods
 

Recently uploaded

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 

Transient Recovery Voltage(TRV) in Interruption of Small Inductive Currents by Circuit Breakers

  • 1. Transient Recovery Voltage(TRV) in Interruption of Small Inductive Currents by Circuit Breakers
  • 2. Article 5(01.10.2018) Transients caused by switching operations in linear systems can be analyzed by using the superposition principle. The switching process caused by an opening operation is obtained by adding the steady-state solution, which exists prior to the opening operation, and the transient response of the system that results from short circuiting voltage sources and open-circuiting current sources to a current injected through the switch contacts. Since the current through the switch terminals after the operation will be zero, the injected current must equal to the current that was flowing between switch terminals prior to the opening operation. When the contacts of a switch start to open a transient voltage is developed across them. This voltage, known as TRV, is present immediately after the
  • 3. A good understanding of the transient phenomena associated with circuit breaker operations in power systems has led to improved testing practice and resulted in more reliable switchgear. Recommended characteristic values for simulation of the TRV are fixed in standards. In Fig Below you see TRV circuit breaker terminals when interrupting the current in very simple circuits. Observe the different wave shape that appear in each case. The representation of each circuit is that depicted in the figure, except for the interruption of the inductive current since in this case the current zero occurs when the voltage across the inductor terminals is maximum, and a capacitive element is needed to account for the trapped charge. The latter oscillation is caused by the energy transfer between the inductor and the capacitor. Although real systems are much more complex than the circuits analyzed above, these cases show that switching under normal operating conditions can be categorized as resistive, inductive, and
  • 4. The interruption of small currents can lead to situations that are known as current chopping and virtual chopping. If the current is interrupted at current zero, the interruption is normal and the TRVs are usually within the specified values. However, if premature interruption occurs, due to current chopping, the interruption will be abnormal and it can cause high-frequency resignations and overvoltage's.
  • 5. When the breaker chops the peak current, the voltage increases almost instantaneously, if this overvoltage exceeds the specified dielectric strength of the circuit breaker, re ignition takes place. When this process is repeated several times, due to high-frequency resignations, the voltage increase continues with rapid escalation of voltages. The high-frequency oscillations are governed by the electrical parameters of the concerned circuit, circuit configuration and interrupter design, and result in a zero crossing before the actual power-frequency current zero. In the figure below compares the load side voltage and the TRVs that are generated when arc interruption takes place at current zero and before current zero (current chopping),respectively. It is obvious from this example that the second case is more severe. The importance of current chopping can be easily understood by neglecting the influence of losses at the load side. After current interruption at current zero, the energy stored in the load side is the energy stored at the capacitance, whose voltage is at the maximum.
  • 6. a) Equivalent circuit. (b) Arc interruption at current zero. (c) Arc interruption before current zero.
  • 7. In the case of current chopping, the instability of the arc around current zero causes a high-frequency transient current to flow in the neighboring network elements. This High Frequency current superimposes on the power-frequency current whose amplitude is small and which is actually chopped to zero. In the case of virtual chopping, the arc is made unstable through a superimposed high- frequency current caused by oscillations with the neighboring phases in which current chopping took place. Virtual chopping has been observed for gaseous arcs in air, SF6, and oil. Vacuum arcs are also very sensitive to current chopping. The phenomena of chopping and resignation, with associated high-frequency oscillatory overvoltage's, are attributed to the design of the circuit breaker. Circuit breakers are designed to cope with high fault currents. If a design is concentrated only on an efficient performance for high currents, it will be also efficient for small current and will try to interrupt before the natural current zero. This may produce current chopping and resignations with adverse consequences. The breaker design should incorporate features to cope equally well with small and high currents.
  • 8. References: *Transient recovery voltage analysis for various current breaking mathematical models: shunt reactor and capacitor bank de- energization study article by :PIOTR ORAMUS, TOMASZ CHMIELEWSKI, TOMASZ KUCZEK, WOJCIECH PIASECKI, MARCIN SZEWCZYK,ABB Corporate Research Center. *Power system transients parameter determination Book edited by : Juan A. Martinez Velasco. *Tech Topics No. 35 from SIEMENS . *Effects of Transient Recovery Voltages on Circuit Breaker Ratings Article Term Project: - EE5220 - Power System Transients. by :Himanshu Bahirat Muhammad Ali Praveen KK .