SlideShare a Scribd company logo
1 of 33
Application of Australian Standards
to HV Switchgear Routine Testing
Gabriel Ojeah
Director, Principal Engineer,
Gadian Electrical Engineering Services Pty Ltd
High Voltage Conference
Perth 2015
GADIAN
E L E C
ENG
Presentation Outline
 Purpose and Legal Status of Standards
 Basic Functions of Electrical Switchgear
 Main Components of Typical Switchgear Assembly
 Applicable Standards for HV Switchgear Routine Tests
 HV Switchgear Routine Tests Under AS 62271.200
 Switchgear components not specifically covered by AS
62271.200
 Summary
 Quiz
GADIAN
E L E C
ENG
Purpose and Legal Status of Standards
 Standards exist for various reasons including;
• Specifying minimum design requirements
• Specifying legislative requirements
• Providing purchasing specifications
• Providing technical conditions for contracts
• Providing guidance
 Legal Status of Standards
• Own their own, no legal status and no requirement for
compliance
• When called up in government legislation, they become
mandatory and can be subject to the scrutiny of the courts
GADIAN
E L E C
ENG
Basic Functions of Electrical Switchgear
 Basic functions of a switchgear assembly include;
• Control: Functional switching and emergency
switching
• Protection: Fast isolation of faulted circuits
• Isolation: Secure physical isolation of downstream
circuits for maintenance or other purposes
GADIAN
E L E C
ENG
Main Components of Typical Switchgear Assembly
GADIAN
E L E C
ENG
Main Components of Typical Switchgear Assembly
GADIAN
E L E C
ENG
Applicable Standards for HV Switchgear Routine
Tests
 Australian Standard 2067-2014 - Substations and High
Voltage Installations Exceeding 1 kV ac
• Still in Draft as at August 2015
• “factory-built, type-tested high voltage switchgear shall be
manufactured and tested in accordance with relevant
standards such as AS 62271.1, AS 62271.200, AS 62271.201
and AS 62271.203”
 AS 62271.200 - High-voltage switchgear and
controlgear Part 200: A.C. metal-enclosed switchgear
and controlgear for rated voltages above 1 kV and up
to and including 52 kV
• Calls up AS 62271.1 frequently
GADIAN
E L E C
ENG
Applicable Standards for HV Switchgear Routine
Tests
 Standards for the main components of the switchgear
to be considered as well;
• Circuit breakers
• Voltage transformers
• Current transformers
• Disconnectors and earth switches
• Contactors
GADIAN
E L E C
ENG
HV Switchgear Routine Tests Under AS 62271.200
 Dielectric test on the main circuit (AS 62271.200 subclause 7.1)
 Test on auxiliary and control circuits (AS 62271.200 subclause
7.2)
 Measurement of the resistance of the main circuit (AS 62271.200
subclause 7.3)
 Tightness Check (AS 62271.200 subclause 7.4)
 Design and Visual Checks (AS 62271.200 subclause 7.5)
 Partial Discharge Measurement (AS 62271.200 subclause 7.101)
GADIAN
E L E C
ENG
HV Switchgear Routine Tests Under AS 62271.200
 Mechanical operation tests (AS 62271.200 subclause 7.102)
 Pressure tests of gas-filled compartments (AS 62271.200
subclause 7.103)
 Tests of auxiliary electrical, pneumatic and hydraulic devices (AS
62271.200 subclause 7.104)
 Tests after erection on site (AS 62271.200 subclause 7.105)
 Measurement of fluid condition after filling on site (AS 62271.200
subclause 7.106)
GADIAN
E L E C
ENG
Dielectric test on the main circuit (AS 62271.200
subclause 7.1)
 Dry short-duration power-frequency withstand voltage test
 With the circuit breakers (and disconnectors) closed, test voltage
is applied to one phase at a time with the other two phases
earthed
 Test duration is 1 minute
 Test is deemed successful if no disruptive discharge occurs
 Rate of increase of test voltage, test duration and acceptance
criterion are specified in subclause 6.3.1 of IEC 60060-1 (High-
voltage test techniques – Part 1: General definitions and test
requirements
 Requirements of the measurement system are specified in IEC
60060-2 (High-voltage test techniques – Part 2: Measuring
systems)
GADIAN
E L E C
ENG
Dielectric test on the main circuit (AS 62271.200
subclause 7.1)
Power-Frequency Withstand Test Voltages Extracted from Table 1a of AS 62271.1
•Common values; phase-to-earth, and phase-to-phase
•Across the isolating distance; where the clearance between
open contacts is designed to meet the functional requirements for
disconnectors (i.e. minimum clearance in air requirement)
GADIAN
E L E C
ENG
Test on auxiliary and control circuits (AS 62271.200
subclause 7.2)
 Based on AS 62271.1 subclause 7.2 and consists of;
• Inspection of auxiliary and control circuits for
verification of conformity with circuit diagrams and
wiring diagrams
• Functional tests
• Verification of protection against electric shock
• Dielectric tests
GADIAN
E L E C
ENG
Test on auxiliary and control circuits (AS 62271.200
subclause 7.2)
 Inspection of auxiliary and control circuits;
• Physical damage
• Quality of the individual components
• Quality of the assembly
• Mounting
• Wiring termination
• Adequacy of terminal strips
• Adequacy of cable ducts
GADIAN
E L E C
ENG
Test on auxiliary and control circuits (AS 62271.200
subclause 7.2)
 Inspection of auxiliary and control circuits;
• Protection of wiring from heat & sharp objects, etc.
• Verification of General Arrangement drawings
against the physical installation (device location,
device details, etc.)
• Verification of Schematic drawings against the
physical installation (continuity of the physical
wiring, cable numbers, wire numbers, device details,
types of contacts, functional correctness, etc.)
GADIAN
E L E C
ENG
Test on auxiliary and control circuits (AS 62271.200
subclause 7.2)
 Functional tests
• Verify that the auxiliary and control circuits function
properly in conjunction with the other parts of the
switchgear
• Would include verification of voltage switching
through individual MCBs, mechanical/electrical
operation of switching devices, status of switching
device auxiliary contacts, anti-pumping device
operation, under-voltage relay operation, reduced
voltage operation of circuit breaker open & close
coils, etc.
GADIAN
E L E C
ENG
Test on auxiliary and control circuits (AS 62271.200
subclause 7.2)
 Verification of protection against electric shock;
• Done by visual inspection to ensure that metallic
partitions and shutters provide protection against
direct contact with the main circuit
• Also includes visual inspection to verify safe access
to auxiliary and control equipment that can be
touched during normal operation
• Where satisfactorily verification cannot be done
through visual inspection, earthed metallic parts are
checked for continuity to the earthing point (test at
30 A dc, result must be less than 0.1 Ω)
GADIAN
E L E C
ENG
Test on auxiliary and control circuits (AS 62271.200
subclause 7.2)
 Dielectric tests;
• Power-frequency voltage withstand tests at 1 kV for
1 second
• Test between the auxiliary & control circuits
connected together as a whole and the frame of the
switchgear
• For parts that are normally insulated from each
other, if practicable, also test between each part and
the other parts connected together and connected to
the switchgear frame
• Successful if no disruptive discharge occurs
GADIAN
E L E C
ENG
Measurement of the resistance of the main circuit
(AS 62271.200 subclause 7.3)
 Unlike the tests we have considered so far, AS 62271.1
is not applicable
 This test is subject to agreement between the
manufacturer and the user
 If the agreement is to use AS 62271.1 (subclause 7.3);
• Test current is between 50 A dc and rated current
• Acceptance Criterion: < 120% of the resistance
measured before the temperature-rise test during
Type testing
• High resistance at lower current must be verified at
a higher current as close as possible to the rated
current
GADIAN
E L E C
ENG
Tightness Check (AS 62271.200 subclause 7.4)
 Tightness check is based on leakage rate of the fluid
(gas or liquid)
 This test is based on AS 62271.1 subclause 7.4.
• Methods for measuring or calculating the leakage
are provided
GADIAN
E L E C
ENG
Design and Visual Checks (AS 62271.200 subclause
7.5)
 Checked to verify compliance with the purchase/design
specifications
 A comprehensive checklist can be built from the
information in subclause 5 (Design and construction) of
this Standard
GADIAN
E L E C
ENG
Partial Discharge Measurement (AS 62271.200
subclause 7.101)
 This test is subject to agreement between the
manufacturer and the user
 A test procedure is provided in Annex B of this
Standard
GADIAN
E L E C
ENG
Mechanical operation tests (AS 62271.200
subclause 7.102)
 Switching devices are operated several times to;
• ensure that they open and close correctly within the
specified limits of the supply voltage and pressure
• ensure that the mechanical interlocks work properly
 Withdrawable parts are inserted and removed several
times to verify satisfactory operation
 The specified number of operations for mechanical
operations tests is 5
GADIAN
E L E C
ENG
Pressure tests of gas-filled compartments (AS
62271.200 subclause 7.103)
 Applicable only to gas-filled compartment rated above
50 kPa (relative pressure)
 Test for 1 min at 130% of the design pressure
GADIAN
E L E C
ENG
Tests of auxiliary electrical, pneumatic and
hydraulic devices (AS 62271.200 subclause 7.104)
 Electrical, pneumatic and other interlocks together with
control devices that have a predetermined sequence of
operation are tested;
• five times in succession
• at the most unfavourable limit (upper or lower) of the
auxiliary supply
 An example would be attempting to close a circuit
breaker with the close release coil disabled and making
another attempt with the close release coil energised at
a voltage just above the lower limit
GADIAN
E L E C
ENG
Tests of auxiliary electrical, pneumatic and
hydraulic devices (AS 62271.200 subclause 7.104)
 This test differs from functional test because it is
conducted repeatedly under adverse conditions
 The test is considered to be satisfactory if the auxiliary
device;
• Operates properly without adjustments between
repeated operations
• Remains in good operating condition after the tests
• The ease of operation is practically the same before
and after the tests
GADIAN
E L E C
ENG
Tests after erection on site (AS 62271.200
subclause 7.105)
 Test to check correct operation
 The following tests are required;
• Main circuit short-duration power-frequency
withstand voltage test at 80 % of the values
indicated in subclause 7.1
• Tightness tests as specified in subclause 7. 4
• For gas-filled compartments which are filled onsite,
measurement of fluid condition as specified in
subclause 7.106 is conducted after filling
 The same operational tests conducted during the
factory routine test would be beneficial
GADIAN
E L E C
ENG
Measurement of fluid condition after filling on site
(AS 62271.200 subclause 7.106)
 Applicable to all fluid-filled compartments
 Condition (pressure, volume, etc.) of the fluid is
determined in order to verify compliance with the
manufacturer's specification.
GADIAN
E L E C
ENG
Switchgear components not specifically covered by
AS 62271.200
 Circuit Breakers: AS 62271.100 (High-voltage
switchgear and controlgear Part 100: High-voltage
alternating current circuit-breakers)
 Disconnectors and Earth Switches: AS 62271.102
(High-voltage switchgear and controlgear Part 102:
Alternating current disconnectors and earthing switches)
 AS 60470 (High-voltage alternating current contactors
and contactor-based motor starters)
 Current Transformers: AS 60044.1 (Instrument
transformers Part 1: Current transformers)
 Voltage Transformers: AS 60044.2 (Instrument
transformers Part 1: Inductive voltage transformers)
 Protection Relays: Refer to system functional design
specification and IEC 60255 series Standards
GADIAN
E L E C
ENG
Summary
GADIAN
E L E C
ENG
Quiz
 How do we know whether a Standard is legally binding,
i.e. called up by legislation?
GADIAN
E L E C
ENG
Quiz
 Here in Australia, we often here the term “Medium
Voltage” used when referring to switchgear and other
electrical equipment. Which technically correct voltage
range does this refer to?
GADIAN
E L E C
ENG
Quiz
 For power-frequency voltage withstand tests after
erection on site, AS 62271.200 calls for de-rating the
test voltage to 80%. For subsequent routine tests
throughout the life of the switchgear, is it always safe to
continue testing at 80%?
GADIAN
E L E C
ENG

More Related Content

What's hot

Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protectionBinit Das
 
Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)Rohini Haridas
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1anuphowlader1
 
Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Low
 
2.components in a substation breaker
2.components in a substation   breaker2.components in a substation   breaker
2.components in a substation breakerayyadurai SHANMUGAM
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalNihal Shiroya
 
Hybrid HVDC Circuit Breaker Definitions
Hybrid HVDC Circuit Breaker  DefinitionsHybrid HVDC Circuit Breaker  Definitions
Hybrid HVDC Circuit Breaker DefinitionsAli Sepehri
 
Switchgear Installation Precomissioning Inspection.PPT
Switchgear Installation  Precomissioning Inspection.PPTSwitchgear Installation  Precomissioning Inspection.PPT
Switchgear Installation Precomissioning Inspection.PPTAbdullah Al Dushaishi
 
500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPT500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPTMahadev Kovalli
 
Out of phase current switching in High Voltage Circuit Breakers
Out of phase current switching in High Voltage Circuit BreakersOut of phase current switching in High Voltage Circuit Breakers
Out of phase current switching in High Voltage Circuit BreakersAli Sepehri
 
Circuits breakers for industrial automation and process controling
Circuits breakers for industrial automation and process controlingCircuits breakers for industrial automation and process controling
Circuits breakers for industrial automation and process controlingfairautomation
 
Electrical Protection Schemes in detail
Electrical Protection Schemes in detailElectrical Protection Schemes in detail
Electrical Protection Schemes in detailSlides Hub
 
transformer protection from over heating
transformer protection from over heatingtransformer protection from over heating
transformer protection from over heatingbishow kandel
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentationNikhil Kachare
 
Switchgear and protection - lab
Switchgear and protection - labSwitchgear and protection - lab
Switchgear and protection - labPremanandDesai
 
Richard Blakeley - Options for managing safety with elderly switchgear
Richard Blakeley - Options for managing safety with elderly switchgearRichard Blakeley - Options for managing safety with elderly switchgear
Richard Blakeley - Options for managing safety with elderly switchgearNSW Environment and Planning
 

What's hot (20)

Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protection
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
 
Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
 
Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
2.components in a substation breaker
2.components in a substation   breaker2.components in a substation   breaker
2.components in a substation breaker
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
 
Hybrid HVDC Circuit Breaker Definitions
Hybrid HVDC Circuit Breaker  DefinitionsHybrid HVDC Circuit Breaker  Definitions
Hybrid HVDC Circuit Breaker Definitions
 
1+1 venky
1+1 venky1+1 venky
1+1 venky
 
Switchgear Installation Precomissioning Inspection.PPT
Switchgear Installation  Precomissioning Inspection.PPTSwitchgear Installation  Precomissioning Inspection.PPT
Switchgear Installation Precomissioning Inspection.PPT
 
500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPT500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPT
 
Out of phase current switching in High Voltage Circuit Breakers
Out of phase current switching in High Voltage Circuit BreakersOut of phase current switching in High Voltage Circuit Breakers
Out of phase current switching in High Voltage Circuit Breakers
 
Circuits breakers for industrial automation and process controling
Circuits breakers for industrial automation and process controlingCircuits breakers for industrial automation and process controling
Circuits breakers for industrial automation and process controling
 
Electrical Protection Schemes in detail
Electrical Protection Schemes in detailElectrical Protection Schemes in detail
Electrical Protection Schemes in detail
 
transformer protection from over heating
transformer protection from over heatingtransformer protection from over heating
transformer protection from over heating
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Switchgear and protection - lab
Switchgear and protection - labSwitchgear and protection - lab
Switchgear and protection - lab
 
Richard Blakeley - Options for managing safety with elderly switchgear
Richard Blakeley - Options for managing safety with elderly switchgearRichard Blakeley - Options for managing safety with elderly switchgear
Richard Blakeley - Options for managing safety with elderly switchgear
 

Similar to Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015

Gabriel Ojeah - HV CONFERENCE PAPER- PERTH 2015
Gabriel Ojeah - HV CONFERENCE PAPER- PERTH 2015Gabriel Ojeah - HV CONFERENCE PAPER- PERTH 2015
Gabriel Ojeah - HV CONFERENCE PAPER- PERTH 2015Gabriel Emeka Ojeah
 
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...Ali Sepehri
 
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...Ali Sepehri
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100Ali Sepehri
 
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...Ali Sepehri
 
06612 iec zerti_rz11_e
06612 iec zerti_rz11_e06612 iec zerti_rz11_e
06612 iec zerti_rz11_eCesar Chilet
 
17th Edition Part 6
17th Edition  Part 617th Edition  Part 6
17th Edition Part 6Paul Holden
 
Hv capacitors application-guide-en-32044a-ltr-2018-04-r001_lr
Hv capacitors application-guide-en-32044a-ltr-2018-04-r001_lrHv capacitors application-guide-en-32044a-ltr-2018-04-r001_lr
Hv capacitors application-guide-en-32044a-ltr-2018-04-r001_lrVu Tai
 
INSPECTION AND TEST PROCEDURES FOR SWITCHGEAR AND SWITCHBOARD
INSPECTION AND TEST PROCEDURES FOR SWITCHGEAR AND SWITCHBOARDINSPECTION AND TEST PROCEDURES FOR SWITCHGEAR AND SWITCHBOARD
INSPECTION AND TEST PROCEDURES FOR SWITCHGEAR AND SWITCHBOARDhussein ibrahim
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakersKabilesh K
 
Electrical testing javid iqbal sodagar
Electrical testing javid iqbal sodagarElectrical testing javid iqbal sodagar
Electrical testing javid iqbal sodagarjavid iqbal sodagar
 

Similar to Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015 (20)

Gabriel Ojeah - HV CONFERENCE PAPER- PERTH 2015
Gabriel Ojeah - HV CONFERENCE PAPER- PERTH 2015Gabriel Ojeah - HV CONFERENCE PAPER- PERTH 2015
Gabriel Ojeah - HV CONFERENCE PAPER- PERTH 2015
 
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
 
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
 
Relay testing procedure
Relay testing procedure Relay testing procedure
Relay testing procedure
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100
 
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
 
06612 iec zerti_rz11_e
06612 iec zerti_rz11_e06612 iec zerti_rz11_e
06612 iec zerti_rz11_e
 
16950
1695016950
16950
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
 
Dialectirc tests
Dialectirc testsDialectirc tests
Dialectirc tests
 
17th Edition Part 6
17th Edition  Part 617th Edition  Part 6
17th Edition Part 6
 
Hv capacitors application-guide-en-32044a-ltr-2018-04-r001_lr
Hv capacitors application-guide-en-32044a-ltr-2018-04-r001_lrHv capacitors application-guide-en-32044a-ltr-2018-04-r001_lr
Hv capacitors application-guide-en-32044a-ltr-2018-04-r001_lr
 
INSPECTION AND TEST PROCEDURES FOR SWITCHGEAR AND SWITCHBOARD
INSPECTION AND TEST PROCEDURES FOR SWITCHGEAR AND SWITCHBOARDINSPECTION AND TEST PROCEDURES FOR SWITCHGEAR AND SWITCHBOARD
INSPECTION AND TEST PROCEDURES FOR SWITCHGEAR AND SWITCHBOARD
 
City & guilds 2392
City & guilds 2392City & guilds 2392
City & guilds 2392
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
 
SEMA 2016 - Introduction to Transformer Rated Metering
SEMA 2016 -  Introduction to Transformer Rated MeteringSEMA 2016 -  Introduction to Transformer Rated Metering
SEMA 2016 - Introduction to Transformer Rated Metering
 
Electrical testing javid iqbal sodagar
Electrical testing javid iqbal sodagarElectrical testing javid iqbal sodagar
Electrical testing javid iqbal sodagar
 
High potential test
High potential testHigh potential test
High potential test
 
Testing of cb
Testing of cbTesting of cb
Testing of cb
 

Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015

  • 1. Application of Australian Standards to HV Switchgear Routine Testing Gabriel Ojeah Director, Principal Engineer, Gadian Electrical Engineering Services Pty Ltd High Voltage Conference Perth 2015 GADIAN E L E C ENG
  • 2. Presentation Outline  Purpose and Legal Status of Standards  Basic Functions of Electrical Switchgear  Main Components of Typical Switchgear Assembly  Applicable Standards for HV Switchgear Routine Tests  HV Switchgear Routine Tests Under AS 62271.200  Switchgear components not specifically covered by AS 62271.200  Summary  Quiz GADIAN E L E C ENG
  • 3. Purpose and Legal Status of Standards  Standards exist for various reasons including; • Specifying minimum design requirements • Specifying legislative requirements • Providing purchasing specifications • Providing technical conditions for contracts • Providing guidance  Legal Status of Standards • Own their own, no legal status and no requirement for compliance • When called up in government legislation, they become mandatory and can be subject to the scrutiny of the courts GADIAN E L E C ENG
  • 4. Basic Functions of Electrical Switchgear  Basic functions of a switchgear assembly include; • Control: Functional switching and emergency switching • Protection: Fast isolation of faulted circuits • Isolation: Secure physical isolation of downstream circuits for maintenance or other purposes GADIAN E L E C ENG
  • 5. Main Components of Typical Switchgear Assembly GADIAN E L E C ENG
  • 6. Main Components of Typical Switchgear Assembly GADIAN E L E C ENG
  • 7. Applicable Standards for HV Switchgear Routine Tests  Australian Standard 2067-2014 - Substations and High Voltage Installations Exceeding 1 kV ac • Still in Draft as at August 2015 • “factory-built, type-tested high voltage switchgear shall be manufactured and tested in accordance with relevant standards such as AS 62271.1, AS 62271.200, AS 62271.201 and AS 62271.203”  AS 62271.200 - High-voltage switchgear and controlgear Part 200: A.C. metal-enclosed switchgear and controlgear for rated voltages above 1 kV and up to and including 52 kV • Calls up AS 62271.1 frequently GADIAN E L E C ENG
  • 8. Applicable Standards for HV Switchgear Routine Tests  Standards for the main components of the switchgear to be considered as well; • Circuit breakers • Voltage transformers • Current transformers • Disconnectors and earth switches • Contactors GADIAN E L E C ENG
  • 9. HV Switchgear Routine Tests Under AS 62271.200  Dielectric test on the main circuit (AS 62271.200 subclause 7.1)  Test on auxiliary and control circuits (AS 62271.200 subclause 7.2)  Measurement of the resistance of the main circuit (AS 62271.200 subclause 7.3)  Tightness Check (AS 62271.200 subclause 7.4)  Design and Visual Checks (AS 62271.200 subclause 7.5)  Partial Discharge Measurement (AS 62271.200 subclause 7.101) GADIAN E L E C ENG
  • 10. HV Switchgear Routine Tests Under AS 62271.200  Mechanical operation tests (AS 62271.200 subclause 7.102)  Pressure tests of gas-filled compartments (AS 62271.200 subclause 7.103)  Tests of auxiliary electrical, pneumatic and hydraulic devices (AS 62271.200 subclause 7.104)  Tests after erection on site (AS 62271.200 subclause 7.105)  Measurement of fluid condition after filling on site (AS 62271.200 subclause 7.106) GADIAN E L E C ENG
  • 11. Dielectric test on the main circuit (AS 62271.200 subclause 7.1)  Dry short-duration power-frequency withstand voltage test  With the circuit breakers (and disconnectors) closed, test voltage is applied to one phase at a time with the other two phases earthed  Test duration is 1 minute  Test is deemed successful if no disruptive discharge occurs  Rate of increase of test voltage, test duration and acceptance criterion are specified in subclause 6.3.1 of IEC 60060-1 (High- voltage test techniques – Part 1: General definitions and test requirements  Requirements of the measurement system are specified in IEC 60060-2 (High-voltage test techniques – Part 2: Measuring systems) GADIAN E L E C ENG
  • 12. Dielectric test on the main circuit (AS 62271.200 subclause 7.1) Power-Frequency Withstand Test Voltages Extracted from Table 1a of AS 62271.1 •Common values; phase-to-earth, and phase-to-phase •Across the isolating distance; where the clearance between open contacts is designed to meet the functional requirements for disconnectors (i.e. minimum clearance in air requirement) GADIAN E L E C ENG
  • 13. Test on auxiliary and control circuits (AS 62271.200 subclause 7.2)  Based on AS 62271.1 subclause 7.2 and consists of; • Inspection of auxiliary and control circuits for verification of conformity with circuit diagrams and wiring diagrams • Functional tests • Verification of protection against electric shock • Dielectric tests GADIAN E L E C ENG
  • 14. Test on auxiliary and control circuits (AS 62271.200 subclause 7.2)  Inspection of auxiliary and control circuits; • Physical damage • Quality of the individual components • Quality of the assembly • Mounting • Wiring termination • Adequacy of terminal strips • Adequacy of cable ducts GADIAN E L E C ENG
  • 15. Test on auxiliary and control circuits (AS 62271.200 subclause 7.2)  Inspection of auxiliary and control circuits; • Protection of wiring from heat & sharp objects, etc. • Verification of General Arrangement drawings against the physical installation (device location, device details, etc.) • Verification of Schematic drawings against the physical installation (continuity of the physical wiring, cable numbers, wire numbers, device details, types of contacts, functional correctness, etc.) GADIAN E L E C ENG
  • 16. Test on auxiliary and control circuits (AS 62271.200 subclause 7.2)  Functional tests • Verify that the auxiliary and control circuits function properly in conjunction with the other parts of the switchgear • Would include verification of voltage switching through individual MCBs, mechanical/electrical operation of switching devices, status of switching device auxiliary contacts, anti-pumping device operation, under-voltage relay operation, reduced voltage operation of circuit breaker open & close coils, etc. GADIAN E L E C ENG
  • 17. Test on auxiliary and control circuits (AS 62271.200 subclause 7.2)  Verification of protection against electric shock; • Done by visual inspection to ensure that metallic partitions and shutters provide protection against direct contact with the main circuit • Also includes visual inspection to verify safe access to auxiliary and control equipment that can be touched during normal operation • Where satisfactorily verification cannot be done through visual inspection, earthed metallic parts are checked for continuity to the earthing point (test at 30 A dc, result must be less than 0.1 Ω) GADIAN E L E C ENG
  • 18. Test on auxiliary and control circuits (AS 62271.200 subclause 7.2)  Dielectric tests; • Power-frequency voltage withstand tests at 1 kV for 1 second • Test between the auxiliary & control circuits connected together as a whole and the frame of the switchgear • For parts that are normally insulated from each other, if practicable, also test between each part and the other parts connected together and connected to the switchgear frame • Successful if no disruptive discharge occurs GADIAN E L E C ENG
  • 19. Measurement of the resistance of the main circuit (AS 62271.200 subclause 7.3)  Unlike the tests we have considered so far, AS 62271.1 is not applicable  This test is subject to agreement between the manufacturer and the user  If the agreement is to use AS 62271.1 (subclause 7.3); • Test current is between 50 A dc and rated current • Acceptance Criterion: < 120% of the resistance measured before the temperature-rise test during Type testing • High resistance at lower current must be verified at a higher current as close as possible to the rated current GADIAN E L E C ENG
  • 20. Tightness Check (AS 62271.200 subclause 7.4)  Tightness check is based on leakage rate of the fluid (gas or liquid)  This test is based on AS 62271.1 subclause 7.4. • Methods for measuring or calculating the leakage are provided GADIAN E L E C ENG
  • 21. Design and Visual Checks (AS 62271.200 subclause 7.5)  Checked to verify compliance with the purchase/design specifications  A comprehensive checklist can be built from the information in subclause 5 (Design and construction) of this Standard GADIAN E L E C ENG
  • 22. Partial Discharge Measurement (AS 62271.200 subclause 7.101)  This test is subject to agreement between the manufacturer and the user  A test procedure is provided in Annex B of this Standard GADIAN E L E C ENG
  • 23. Mechanical operation tests (AS 62271.200 subclause 7.102)  Switching devices are operated several times to; • ensure that they open and close correctly within the specified limits of the supply voltage and pressure • ensure that the mechanical interlocks work properly  Withdrawable parts are inserted and removed several times to verify satisfactory operation  The specified number of operations for mechanical operations tests is 5 GADIAN E L E C ENG
  • 24. Pressure tests of gas-filled compartments (AS 62271.200 subclause 7.103)  Applicable only to gas-filled compartment rated above 50 kPa (relative pressure)  Test for 1 min at 130% of the design pressure GADIAN E L E C ENG
  • 25. Tests of auxiliary electrical, pneumatic and hydraulic devices (AS 62271.200 subclause 7.104)  Electrical, pneumatic and other interlocks together with control devices that have a predetermined sequence of operation are tested; • five times in succession • at the most unfavourable limit (upper or lower) of the auxiliary supply  An example would be attempting to close a circuit breaker with the close release coil disabled and making another attempt with the close release coil energised at a voltage just above the lower limit GADIAN E L E C ENG
  • 26. Tests of auxiliary electrical, pneumatic and hydraulic devices (AS 62271.200 subclause 7.104)  This test differs from functional test because it is conducted repeatedly under adverse conditions  The test is considered to be satisfactory if the auxiliary device; • Operates properly without adjustments between repeated operations • Remains in good operating condition after the tests • The ease of operation is practically the same before and after the tests GADIAN E L E C ENG
  • 27. Tests after erection on site (AS 62271.200 subclause 7.105)  Test to check correct operation  The following tests are required; • Main circuit short-duration power-frequency withstand voltage test at 80 % of the values indicated in subclause 7.1 • Tightness tests as specified in subclause 7. 4 • For gas-filled compartments which are filled onsite, measurement of fluid condition as specified in subclause 7.106 is conducted after filling  The same operational tests conducted during the factory routine test would be beneficial GADIAN E L E C ENG
  • 28. Measurement of fluid condition after filling on site (AS 62271.200 subclause 7.106)  Applicable to all fluid-filled compartments  Condition (pressure, volume, etc.) of the fluid is determined in order to verify compliance with the manufacturer's specification. GADIAN E L E C ENG
  • 29. Switchgear components not specifically covered by AS 62271.200  Circuit Breakers: AS 62271.100 (High-voltage switchgear and controlgear Part 100: High-voltage alternating current circuit-breakers)  Disconnectors and Earth Switches: AS 62271.102 (High-voltage switchgear and controlgear Part 102: Alternating current disconnectors and earthing switches)  AS 60470 (High-voltage alternating current contactors and contactor-based motor starters)  Current Transformers: AS 60044.1 (Instrument transformers Part 1: Current transformers)  Voltage Transformers: AS 60044.2 (Instrument transformers Part 1: Inductive voltage transformers)  Protection Relays: Refer to system functional design specification and IEC 60255 series Standards GADIAN E L E C ENG
  • 31. Quiz  How do we know whether a Standard is legally binding, i.e. called up by legislation? GADIAN E L E C ENG
  • 32. Quiz  Here in Australia, we often here the term “Medium Voltage” used when referring to switchgear and other electrical equipment. Which technically correct voltage range does this refer to? GADIAN E L E C ENG
  • 33. Quiz  For power-frequency voltage withstand tests after erection on site, AS 62271.200 calls for de-rating the test voltage to 80%. For subsequent routine tests throughout the life of the switchgear, is it always safe to continue testing at 80%? GADIAN E L E C ENG