Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015
1. Application of Australian Standards
to HV Switchgear Routine Testing
Gabriel Ojeah
Director, Principal Engineer,
Gadian Electrical Engineering Services Pty Ltd
High Voltage Conference
Perth 2015
GADIAN
E L E C
ENG
2. Presentation Outline
Purpose and Legal Status of Standards
Basic Functions of Electrical Switchgear
Main Components of Typical Switchgear Assembly
Applicable Standards for HV Switchgear Routine Tests
HV Switchgear Routine Tests Under AS 62271.200
Switchgear components not specifically covered by AS
62271.200
Summary
Quiz
GADIAN
E L E C
ENG
3. Purpose and Legal Status of Standards
Standards exist for various reasons including;
• Specifying minimum design requirements
• Specifying legislative requirements
• Providing purchasing specifications
• Providing technical conditions for contracts
• Providing guidance
Legal Status of Standards
• Own their own, no legal status and no requirement for
compliance
• When called up in government legislation, they become
mandatory and can be subject to the scrutiny of the courts
GADIAN
E L E C
ENG
4. Basic Functions of Electrical Switchgear
Basic functions of a switchgear assembly include;
• Control: Functional switching and emergency
switching
• Protection: Fast isolation of faulted circuits
• Isolation: Secure physical isolation of downstream
circuits for maintenance or other purposes
GADIAN
E L E C
ENG
7. Applicable Standards for HV Switchgear Routine
Tests
Australian Standard 2067-2014 - Substations and High
Voltage Installations Exceeding 1 kV ac
• Still in Draft as at August 2015
• “factory-built, type-tested high voltage switchgear shall be
manufactured and tested in accordance with relevant
standards such as AS 62271.1, AS 62271.200, AS 62271.201
and AS 62271.203”
AS 62271.200 - High-voltage switchgear and
controlgear Part 200: A.C. metal-enclosed switchgear
and controlgear for rated voltages above 1 kV and up
to and including 52 kV
• Calls up AS 62271.1 frequently
GADIAN
E L E C
ENG
8. Applicable Standards for HV Switchgear Routine
Tests
Standards for the main components of the switchgear
to be considered as well;
• Circuit breakers
• Voltage transformers
• Current transformers
• Disconnectors and earth switches
• Contactors
GADIAN
E L E C
ENG
9. HV Switchgear Routine Tests Under AS 62271.200
Dielectric test on the main circuit (AS 62271.200 subclause 7.1)
Test on auxiliary and control circuits (AS 62271.200 subclause
7.2)
Measurement of the resistance of the main circuit (AS 62271.200
subclause 7.3)
Tightness Check (AS 62271.200 subclause 7.4)
Design and Visual Checks (AS 62271.200 subclause 7.5)
Partial Discharge Measurement (AS 62271.200 subclause 7.101)
GADIAN
E L E C
ENG
10. HV Switchgear Routine Tests Under AS 62271.200
Mechanical operation tests (AS 62271.200 subclause 7.102)
Pressure tests of gas-filled compartments (AS 62271.200
subclause 7.103)
Tests of auxiliary electrical, pneumatic and hydraulic devices (AS
62271.200 subclause 7.104)
Tests after erection on site (AS 62271.200 subclause 7.105)
Measurement of fluid condition after filling on site (AS 62271.200
subclause 7.106)
GADIAN
E L E C
ENG
11. Dielectric test on the main circuit (AS 62271.200
subclause 7.1)
Dry short-duration power-frequency withstand voltage test
With the circuit breakers (and disconnectors) closed, test voltage
is applied to one phase at a time with the other two phases
earthed
Test duration is 1 minute
Test is deemed successful if no disruptive discharge occurs
Rate of increase of test voltage, test duration and acceptance
criterion are specified in subclause 6.3.1 of IEC 60060-1 (High-
voltage test techniques – Part 1: General definitions and test
requirements
Requirements of the measurement system are specified in IEC
60060-2 (High-voltage test techniques – Part 2: Measuring
systems)
GADIAN
E L E C
ENG
12. Dielectric test on the main circuit (AS 62271.200
subclause 7.1)
Power-Frequency Withstand Test Voltages Extracted from Table 1a of AS 62271.1
•Common values; phase-to-earth, and phase-to-phase
•Across the isolating distance; where the clearance between
open contacts is designed to meet the functional requirements for
disconnectors (i.e. minimum clearance in air requirement)
GADIAN
E L E C
ENG
13. Test on auxiliary and control circuits (AS 62271.200
subclause 7.2)
Based on AS 62271.1 subclause 7.2 and consists of;
• Inspection of auxiliary and control circuits for
verification of conformity with circuit diagrams and
wiring diagrams
• Functional tests
• Verification of protection against electric shock
• Dielectric tests
GADIAN
E L E C
ENG
14. Test on auxiliary and control circuits (AS 62271.200
subclause 7.2)
Inspection of auxiliary and control circuits;
• Physical damage
• Quality of the individual components
• Quality of the assembly
• Mounting
• Wiring termination
• Adequacy of terminal strips
• Adequacy of cable ducts
GADIAN
E L E C
ENG
15. Test on auxiliary and control circuits (AS 62271.200
subclause 7.2)
Inspection of auxiliary and control circuits;
• Protection of wiring from heat & sharp objects, etc.
• Verification of General Arrangement drawings
against the physical installation (device location,
device details, etc.)
• Verification of Schematic drawings against the
physical installation (continuity of the physical
wiring, cable numbers, wire numbers, device details,
types of contacts, functional correctness, etc.)
GADIAN
E L E C
ENG
16. Test on auxiliary and control circuits (AS 62271.200
subclause 7.2)
Functional tests
• Verify that the auxiliary and control circuits function
properly in conjunction with the other parts of the
switchgear
• Would include verification of voltage switching
through individual MCBs, mechanical/electrical
operation of switching devices, status of switching
device auxiliary contacts, anti-pumping device
operation, under-voltage relay operation, reduced
voltage operation of circuit breaker open & close
coils, etc.
GADIAN
E L E C
ENG
17. Test on auxiliary and control circuits (AS 62271.200
subclause 7.2)
Verification of protection against electric shock;
• Done by visual inspection to ensure that metallic
partitions and shutters provide protection against
direct contact with the main circuit
• Also includes visual inspection to verify safe access
to auxiliary and control equipment that can be
touched during normal operation
• Where satisfactorily verification cannot be done
through visual inspection, earthed metallic parts are
checked for continuity to the earthing point (test at
30 A dc, result must be less than 0.1 Ω)
GADIAN
E L E C
ENG
18. Test on auxiliary and control circuits (AS 62271.200
subclause 7.2)
Dielectric tests;
• Power-frequency voltage withstand tests at 1 kV for
1 second
• Test between the auxiliary & control circuits
connected together as a whole and the frame of the
switchgear
• For parts that are normally insulated from each
other, if practicable, also test between each part and
the other parts connected together and connected to
the switchgear frame
• Successful if no disruptive discharge occurs
GADIAN
E L E C
ENG
19. Measurement of the resistance of the main circuit
(AS 62271.200 subclause 7.3)
Unlike the tests we have considered so far, AS 62271.1
is not applicable
This test is subject to agreement between the
manufacturer and the user
If the agreement is to use AS 62271.1 (subclause 7.3);
• Test current is between 50 A dc and rated current
• Acceptance Criterion: < 120% of the resistance
measured before the temperature-rise test during
Type testing
• High resistance at lower current must be verified at
a higher current as close as possible to the rated
current
GADIAN
E L E C
ENG
20. Tightness Check (AS 62271.200 subclause 7.4)
Tightness check is based on leakage rate of the fluid
(gas or liquid)
This test is based on AS 62271.1 subclause 7.4.
• Methods for measuring or calculating the leakage
are provided
GADIAN
E L E C
ENG
21. Design and Visual Checks (AS 62271.200 subclause
7.5)
Checked to verify compliance with the purchase/design
specifications
A comprehensive checklist can be built from the
information in subclause 5 (Design and construction) of
this Standard
GADIAN
E L E C
ENG
22. Partial Discharge Measurement (AS 62271.200
subclause 7.101)
This test is subject to agreement between the
manufacturer and the user
A test procedure is provided in Annex B of this
Standard
GADIAN
E L E C
ENG
23. Mechanical operation tests (AS 62271.200
subclause 7.102)
Switching devices are operated several times to;
• ensure that they open and close correctly within the
specified limits of the supply voltage and pressure
• ensure that the mechanical interlocks work properly
Withdrawable parts are inserted and removed several
times to verify satisfactory operation
The specified number of operations for mechanical
operations tests is 5
GADIAN
E L E C
ENG
24. Pressure tests of gas-filled compartments (AS
62271.200 subclause 7.103)
Applicable only to gas-filled compartment rated above
50 kPa (relative pressure)
Test for 1 min at 130% of the design pressure
GADIAN
E L E C
ENG
25. Tests of auxiliary electrical, pneumatic and
hydraulic devices (AS 62271.200 subclause 7.104)
Electrical, pneumatic and other interlocks together with
control devices that have a predetermined sequence of
operation are tested;
• five times in succession
• at the most unfavourable limit (upper or lower) of the
auxiliary supply
An example would be attempting to close a circuit
breaker with the close release coil disabled and making
another attempt with the close release coil energised at
a voltage just above the lower limit
GADIAN
E L E C
ENG
26. Tests of auxiliary electrical, pneumatic and
hydraulic devices (AS 62271.200 subclause 7.104)
This test differs from functional test because it is
conducted repeatedly under adverse conditions
The test is considered to be satisfactory if the auxiliary
device;
• Operates properly without adjustments between
repeated operations
• Remains in good operating condition after the tests
• The ease of operation is practically the same before
and after the tests
GADIAN
E L E C
ENG
27. Tests after erection on site (AS 62271.200
subclause 7.105)
Test to check correct operation
The following tests are required;
• Main circuit short-duration power-frequency
withstand voltage test at 80 % of the values
indicated in subclause 7.1
• Tightness tests as specified in subclause 7. 4
• For gas-filled compartments which are filled onsite,
measurement of fluid condition as specified in
subclause 7.106 is conducted after filling
The same operational tests conducted during the
factory routine test would be beneficial
GADIAN
E L E C
ENG
28. Measurement of fluid condition after filling on site
(AS 62271.200 subclause 7.106)
Applicable to all fluid-filled compartments
Condition (pressure, volume, etc.) of the fluid is
determined in order to verify compliance with the
manufacturer's specification.
GADIAN
E L E C
ENG
29. Switchgear components not specifically covered by
AS 62271.200
Circuit Breakers: AS 62271.100 (High-voltage
switchgear and controlgear Part 100: High-voltage
alternating current circuit-breakers)
Disconnectors and Earth Switches: AS 62271.102
(High-voltage switchgear and controlgear Part 102:
Alternating current disconnectors and earthing switches)
AS 60470 (High-voltage alternating current contactors
and contactor-based motor starters)
Current Transformers: AS 60044.1 (Instrument
transformers Part 1: Current transformers)
Voltage Transformers: AS 60044.2 (Instrument
transformers Part 1: Inductive voltage transformers)
Protection Relays: Refer to system functional design
specification and IEC 60255 series Standards
GADIAN
E L E C
ENG
31. Quiz
How do we know whether a Standard is legally binding,
i.e. called up by legislation?
GADIAN
E L E C
ENG
32. Quiz
Here in Australia, we often here the term “Medium
Voltage” used when referring to switchgear and other
electrical equipment. Which technically correct voltage
range does this refer to?
GADIAN
E L E C
ENG
33. Quiz
For power-frequency voltage withstand tests after
erection on site, AS 62271.200 calls for de-rating the
test voltage to 80%. For subsequent routine tests
throughout the life of the switchgear, is it always safe to
continue testing at 80%?
GADIAN
E L E C
ENG