SlideShare a Scribd company logo
1 of 6
VENKATARAMANA KINTALI
Plot no:8, Bankers Colony, Deepamahal behind, Front of Visakha school, Distt.-Srikakulam, State: Andhra
Pradesh, Pin code-532001
Email: venkataeee@gmail.com, venkataeee1@gmail.com ~ Ph: 09440838711
6 YEARS EXPERIENCED DEPUTY MANAGER, QUALIFIED B.TECH GRADUATE ELETRICAL AND
ELECTRONICS. ENGG. EXPOSURE TO O&M IN ENGINEERING CONSTRUCTION SECTOR WITH MAJOR
ORGANIZATION IN INDIA SERVING WITH MAJOR WIND POWER ORGANISATION AS DEPUTY MANAGER
AND SERVED IN PAST WITH MAJOR PRIVATE HYDRO POWER CORPORATION AT UTTATKHAND, AS SR.
ELECRTICAL ENGINEER
Competencies:
 In depth knowledge of electrical panels installation; electrical equipment management
 Erection and rectification of 11/33 kV overhead lines.
 Team leadership, manpower administration.
 Independent target execution. inter-dept. coordination
 Maintenance of records and preparation of contractor’s bills, debit notes by verifying at site.
 Keen on new technology adaptation.
 Fair communication skills and hardworking with dedication.
Objective: Seeking career opportunity as Deputy Manager in dynamic, growth oriented organizations in
the construction/real estate/ roads/ thermal, wind, hydro plants/ metro sectors where experience and
competencies can add value to organizational capabilities for achieving corporate objectives.
PROFESSIONAL EXPERIENCE
Range of experience:
 Operation and maintenance of 220/33kV 100MVA Switchyard and 33kV feeders.
 Control room shift engineer and looked after O&M works.
 Execution of wide ranges of electrical work at sites.
 Estimation & planning of building wiring i.e. commercial, residential, etc.
 Providing power at construction sites.
 Erection, maintenance of H.T. (11KV,33KV) & L.T. Lines, Transformers, Diesel Generators (up to
1010 KVA.), ACB’s, VCB’s, Distribution Boards, Panels, Compact secondary substations (CSS) .
 Planning, estimating of all installation work i.e. HT & LT lines. Substations, Compact Secondary
Substations etc. at site.
 Designing of panels and cables as per the load requirement at site.
 Indenting processes for electrical materials for projects.
 Installation of various vibrating wire type instruments at dam site.
 Execution of permanent lightning works as per drawings received from HO and coordinating
with site people.
 Operation and maintenance of 400kV switchyard, 400kV transmission line and coordinating with
SLDC Lucknow people and grid people during line and unit shutdown.
GRRENKO GROUP Greenko Rayala Wind Power Private Limited Atmakur Anantapur Andhra
Corporate Profile: Greenko is a mainstream participant in the growing Indian energy industry and a
market leading owner and operator of clean energy projects in India. The Group is building a
de-risked portfolio of wind, hydropower and natural gas and biomass assets within India and
intends to increase the installed capacity it operates by developing new Greenfield assets.
Greenko currently has 1.0 GW operating capacity and is aggressively working towards
reaching the capacity of 3.0 GW by 2018.
Deputy Manager (September 28th
2016 to till date)
Reporting to: State Head
Deliverables:
 Planning & implementing the preventive & predictive maintenance schedules for improving the
overall reliability and safety of plant equipments & machinery.
 Preparing system based documentation and conducting analysis of different maintenance data
to reduce the cost of maintenance.
 Monitoring & recording of incoming / outgoing & transformer loads and controlling of load as
per the instructions of Load Dispatch Centre.
 Handling issue of Line Clear for carrying of maintenance & repair works in Substations & EHV/HT
Lines.
 Assuring minor maintenance works of switchgear equipments in 220/110/11kV power
substation.
 Overseeing conditions of Air compressors, Switchgear equipments, Power transformers, Battery
cells & charger, Diesel generator set, Fire protection systems, etc.
 Monitoring oil & winding temperatures of power transformers, air & gas pressures of circuit
breakers, load, voltage, frequency, etc.
 Preparing daily and monthly energy audit & correspondences.
 Ensuring hot-line maintenance staff & MRT (meter, relay, testing) division of APTRANSCO during
testing & repair of relays, transformers & other substation equipments.
 Reviewing history records of key machines for repeated breakdowns to analysis and carrying out
necessary corrective actions.
 Organizing activities for continual improvement & working towards cost reduction activities.
 Responsible for Operation & maintenance activities of Transformers up to 100MVA,Switchgears
from 220KV, 110KV & 11KV,EHV Overhead lines -220KV, 110KV, 33kV & 11KV, Protection &
Control Equipment, MTTR & MTBF.
WIND WORLD INDIA LIMITED Narmada Wind Power Project Andhra
Corporate Profile: Wind World (India) Limited (WWIL) formerly Enercon (India) Limited since its
inception in 1994, has been making giant strides in the wind energy segment. It has already installed
more than 6204 wind energy converters in India with a total installed capacity exceeding 4561 MW.
Assistant Manager (June 09th
2016 to September 27th
2016 )
Reporting to: HOD / Zonal Head/ State Head assisted by 20 subordinates.
Deliverables:
 Planning & implementing the preventive & predictive maintenance schedules for improving the
overall reliability and safety of plant equipments & machinery.
 Preparing system based documentation and conducting analysis of different maintenance data
to reduce the cost of maintenance.
 Monitoring & recording of incoming / outgoing & transformer loads and controlling of load as
per the instructions of Load Dispatch Centre.
 Handling issue of Line Clear for carrying of maintenance & repair works in Substations & EHV/HT
Lines.
 Assuring minor maintenance works of switchgear equipments in 220/110/11kV power
substation.
 Overseeing conditions of Air compressors, Switchgear equipments, Power transformers, Battery
cells & charger, Diesel generator set, Fire protection systems, etc.
 Monitoring oil & winding temperatures of power transformers, air & gas pressures of circuit
breakers, load, voltage, frequency, etc.
 Preparing daily and monthly energy audit & correspondences.
 Ensuring hot-line maintenance staff & MRT (meter, relay, testing) division of APTRANSCO during
testing & repair of relays, transformers & other substation equipments.
 Reviewing history records of key machines for repeated breakdowns to analysis and carrying out
necessary corrective actions.
 Organizing activities for continual improvement & working towards cost reduction activities.
 Responsible for Operation & maintenance activities of Transformers up to 100MVA,Switchgears
from 220KV, 110KV & 11KV,EHV Overhead lines -220KV, 110KV, 33kV & 11KV, Protection &
Control Equipment, MTTR & MTBF, Liasoning & solving ROW issues.
GVK GROUP 330MW Hydro Electric Project. Srinagar, Uttarakhand
Corporate Profile: GVK is a leading Indian conglomerate with diversified interests across various sectors
including energy, resources, airports, transportation, hospitality and life sciences.
Electrical Engineer (November 08th
2010 to June 08th
2016)
Reporting to: GM / Manager assisted by 40 subordinates.
Deliverables:
 Supervising O&M works for 11/.433KV sub-stations at sites (Total length of lines are 10Km
approximately).
 Supervision of erection works of 11kV transmission lines of single/ double circuit. (Totally length
of lines erected are 15Km approximately).
 Erection commissioning and testing of CSS (compact secondary substations) of range 0.315 to
1MVA. ABB make (Totally erected 15 Substations)
 Erection commissioning and testing of silent diesel generator sets of Jacksons make. Range
varied from 0.05 to 1.010 MVA. (Totally erected 12 DG sets)
 Arrangement of proper earthing for installed substations of both temporary and permanent
types. Chemical earthing is also used at rocky areas.
 Erection of LT switchgear panels for LT power distribution to various loads from substations
along with backup power schemes.
 Laying of HT/LT cables of sizes ranging from 10 to 400sqmm of both armoured and unarmoured
type multicore power cables in cable trays, cable trenches and underground cabling. Also laid 40
core control cables jelly filled and armoured for instrumentation purposes. (Total 25Km of cable
was laid approximately under my supervision).
 Erection of 11kV SF6 Circuit breakers RMU of ABB make for protection of 11kV circuits and for
breaking point in the circuits. (Totally Installed 5 VCB panels).
 Installation of LT breaker panels of 1600 Amp, LT changeover switches of range up to 1600 Amp
and LT distribution panels at sub-stations for backup power arrangements of over all project
sites. (Totally installed up to 80 panels)
 Planning the work schedule for the successive day and deployment of man power at various
sites regularly. (Handled 40 electricians and 15 Engineers).
 Coordinating and executing all the E&M works going on at all sites which were under the radius
of 6Kms from dam to power house.
 Planning and preparation of estimate for the work and executing them at site after getting
necessary approvals from GM/Director. Preparation of bills for works executed at sites. (Totally
prepared 300 bills approximately).
 Preparation of UPCL bills and UPCL liaison works. Coordination with UPCL line man and JE/AE
during 11kV line faults for shutdowns. (Handled the job for 3 Years).
 Preparation of grid/DG debit notes of the power provided to different contractors engaged at
site. (Prepared 100 debit notes till date)
 Maintenance of records which includes all substations data, diesel filling records of DG sets,
maintenance etc.
 Procurement of all operation and maintenance materials, tools, safety equipments in time to
prevent work delay and coordinating with store people and inspection of the same after
received at site. (Totally raised 4000 purchase requisitions till date).
 Installation of vibrating wire type instruments at dam site and collection of the readings of the
same.
 Operation and maintenance of 400kV switchyard, 400kV transmission line which includes SF6
circuit breakers, isolators, CVT’s, CT’s, and collection of data like hourly generation, daily
generation report and total power transmitted. Coordination with SLDC Lucknow people and
grid people during line and unit shutdown and relays monitoring. (Since last six months looking
after switch yard as additional responsibility)
Contributions:
 Successfully executed all detailed planning of E&M work in coordination with GM / Manager
(projects).
 Successfully erected tested and operated eight sub stations of 1MVA and handled 8MVA
construction power.
 Successfully looked after O&M works of 400kV switchyard and coordinated with SLDC Lucknow
and NRLDC Delhi during line/Unit shutdown.
EDUCATION
 B.Tech Graduate, Electrical and Electronics. Engg. (67.29%) 2009 - JNTUH, Hyderabad
 Intermediate , MPC (90.4%) – Board of Intermediate Education.
 SSC (81.5%) – Board of Secondary Education.
EXTRA CURRICULAR ACTIVITIES/ACHEIVEMENTS
 Got first prize in Quest for Talent conducted by Sri Vidya Junior college
 A paper presentation on ‘Preparation of Bio-Diesel’ at Pragna’07 conducted by Gokaraju
Rangaraju institute of technology and science.
 A paper presentation on ‘SCADA’ at Prathibha’08 conducted by TKRCET.
 Secured 2055 AIR in GATE 2012.
INDUSTRIAL ORIENTED MINI PROJECTS
220kV SWITCHGEAR MAINTENANCE OF HYDEL POWERHOUSE. Nagarjuna Sagar, Andhra
 Operation of SF6 & Minimum Oil Circuit Breakers
 Testing of Current Transformers
 Protection of Bus bars.
INDUSTRIAL ORIENTED MINI PROJECTS
DRIVERLESS TRAIN SHUTTLING BETWEEN TWO BUSY STATIONS
To run the train between two busy stations without a human driver and to open and close the
doors automatically, to run and stop the train automatically at stations, ultimately which can be
used to carry the passengers from one station to another station when a real system is
constructed.
PERSONAL INFORMATION
 Date of Birth :18 May 1988
 Father’s Name : Shri K.Laxmana Rao
 Nationality : Indian
 Marital Status : Single
 Driving license No : DLFAP03090842010
 DL expiry date : 19/05/2028
 Passport No. : M8226883
 Passport expiry date : 26/04/2025
 Language Skills : Hindi, English,Telugu
 Preferred location : Any where
 Present CTC : 7 Lacs per annum
 Notice period : 15 - 30 Days
 References : Will be provided on demand
 Testing of Current Transformers
 Protection of Bus bars.
INDUSTRIAL ORIENTED MINI PROJECTS
DRIVERLESS TRAIN SHUTTLING BETWEEN TWO BUSY STATIONS
To run the train between two busy stations without a human driver and to open and close the
doors automatically, to run and stop the train automatically at stations, ultimately which can be
used to carry the passengers from one station to another station when a real system is
constructed.
PERSONAL INFORMATION
 Date of Birth :18 May 1988
 Father’s Name : Shri K.Laxmana Rao
 Nationality : Indian
 Marital Status : Single
 Driving license No : DLFAP03090842010
 DL expiry date : 19/05/2028
 Passport No. : M8226883
 Passport expiry date : 26/04/2025
 Language Skills : Hindi, English,Telugu
 Preferred location : Any where
 Present CTC : 7 Lacs per annum
 Notice period : 15 - 30 Days
 References : Will be provided on demand

More Related Content

What's hot

What's hot (20)

Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017
 
CV_Ashok Jain
CV_Ashok JainCV_Ashok Jain
CV_Ashok Jain
 
Tahir Mahmood Butt
Tahir Mahmood ButtTahir Mahmood Butt
Tahir Mahmood Butt
 
SRao_cv
SRao_cvSRao_cv
SRao_cv
 
PDV narasimha Rao 6+ (2)
PDV narasimha Rao 6+ (2)PDV narasimha Rao 6+ (2)
PDV narasimha Rao 6+ (2)
 
Vipin Resume
Vipin ResumeVipin Resume
Vipin Resume
 
bala.1
bala.1bala.1
bala.1
 
Resume
ResumeResume
Resume
 
Rex Scott 2016-11-03 resume
Rex Scott 2016-11-03 resumeRex Scott 2016-11-03 resume
Rex Scott 2016-11-03 resume
 
Nazh cv rev.2
Nazh cv  rev.2Nazh cv  rev.2
Nazh cv rev.2
 
Sam res (houston) oil and gas
Sam res (houston) oil and gasSam res (houston) oil and gas
Sam res (houston) oil and gas
 
Sharma Resume
Sharma ResumeSharma Resume
Sharma Resume
 
Resume' 2015
Resume' 2015Resume' 2015
Resume' 2015
 
Sam res (houston) O &G
Sam res (houston) O &GSam res (houston) O &G
Sam res (houston) O &G
 
Resume_for_Kendall_Holland1
Resume_for_Kendall_Holland1Resume_for_Kendall_Holland1
Resume_for_Kendall_Holland1
 
Interview Preparation
Interview PreparationInterview Preparation
Interview Preparation
 
Resume-Murugan
Resume-MuruganResume-Murugan
Resume-Murugan
 
Doug Caley1
Doug Caley1Doug Caley1
Doug Caley1
 
RESUME_ ARULMANI-ELECTRICAL COMMISSIONING ENGINEER (1)
RESUME_ ARULMANI-ELECTRICAL COMMISSIONING ENGINEER (1)RESUME_ ARULMANI-ELECTRICAL COMMISSIONING ENGINEER (1)
RESUME_ ARULMANI-ELECTRICAL COMMISSIONING ENGINEER (1)
 

Viewers also liked

Barry Moran ROV - Plough Log Book.
Barry Moran ROV - Plough Log Book.Barry Moran ROV - Plough Log Book.
Barry Moran ROV - Plough Log Book.bazza323
 
Rescued document
Rescued documentRescued document
Rescued documentabdubalol
 
manish resume Nov 2014
manish resume Nov 2014manish resume Nov 2014
manish resume Nov 2014Manish Soni
 
Ranjan Roy- 25.10.16
Ranjan Roy- 25.10.16Ranjan Roy- 25.10.16
Ranjan Roy- 25.10.16Ranjan Roy
 
RESUME RAJBIR SINGH (1)
RESUME RAJBIR SINGH (1)RESUME RAJBIR SINGH (1)
RESUME RAJBIR SINGH (1)Rajbir Singh
 
shivender resume
shivender resumeshivender resume
shivender resumeshivender
 
Cv atul kale_b.e(instrumentation and control)_dcs engineer
Cv atul kale_b.e(instrumentation and control)_dcs engineerCv atul kale_b.e(instrumentation and control)_dcs engineer
Cv atul kale_b.e(instrumentation and control)_dcs engineerATUL KALE
 
Avtar_singh CV 2016
Avtar_singh  CV 2016Avtar_singh  CV 2016
Avtar_singh CV 2016Avtar Singh
 
CV- SHASHI KANT THAKUR
CV- SHASHI KANT THAKURCV- SHASHI KANT THAKUR
CV- SHASHI KANT THAKURshashi thakur
 
2016-11-01 CV - Peter Lundgren
2016-11-01 CV - Peter Lundgren2016-11-01 CV - Peter Lundgren
2016-11-01 CV - Peter LundgrenPeter lundgren
 
Director Power Projects Resume
Director Power Projects ResumeDirector Power Projects Resume
Director Power Projects Resumeprasunkishoreroy
 

Viewers also liked (20)

Barry Moran ROV - Plough Log Book.
Barry Moran ROV - Plough Log Book.Barry Moran ROV - Plough Log Book.
Barry Moran ROV - Plough Log Book.
 
Rescued document
Rescued documentRescued document
Rescued document
 
CV BISWAJIT New
CV BISWAJIT NewCV BISWAJIT New
CV BISWAJIT New
 
Resume_Mithilesh
Resume_MithileshResume_Mithilesh
Resume_Mithilesh
 
Ravi Ranjan
Ravi RanjanRavi Ranjan
Ravi Ranjan
 
manish resume Nov 2014
manish resume Nov 2014manish resume Nov 2014
manish resume Nov 2014
 
Ranjan Roy- 25.10.16
Ranjan Roy- 25.10.16Ranjan Roy- 25.10.16
Ranjan Roy- 25.10.16
 
Ashish Resume
Ashish ResumeAshish Resume
Ashish Resume
 
RESUME RAJBIR SINGH (1)
RESUME RAJBIR SINGH (1)RESUME RAJBIR SINGH (1)
RESUME RAJBIR SINGH (1)
 
Gyanendra Kumar Verma_2 (1)
Gyanendra Kumar Verma_2 (1)Gyanendra Kumar Verma_2 (1)
Gyanendra Kumar Verma_2 (1)
 
shivender resume
shivender resumeshivender resume
shivender resume
 
Ishan Srivastava_CV
Ishan Srivastava_CVIshan Srivastava_CV
Ishan Srivastava_CV
 
Pdv narasimha rao 7+
Pdv narasimha rao 7+Pdv narasimha rao 7+
Pdv narasimha rao 7+
 
Cv atul kale_b.e(instrumentation and control)_dcs engineer
Cv atul kale_b.e(instrumentation and control)_dcs engineerCv atul kale_b.e(instrumentation and control)_dcs engineer
Cv atul kale_b.e(instrumentation and control)_dcs engineer
 
Avtar_singh CV 2016
Avtar_singh  CV 2016Avtar_singh  CV 2016
Avtar_singh CV 2016
 
CV- SHASHI KANT THAKUR
CV- SHASHI KANT THAKURCV- SHASHI KANT THAKUR
CV- SHASHI KANT THAKUR
 
CV.2016
CV.2016CV.2016
CV.2016
 
2016-11-01 CV - Peter Lundgren
2016-11-01 CV - Peter Lundgren2016-11-01 CV - Peter Lundgren
2016-11-01 CV - Peter Lundgren
 
Director Power Projects Resume
Director Power Projects ResumeDirector Power Projects Resume
Director Power Projects Resume
 
Ashish Resume
Ashish ResumeAshish Resume
Ashish Resume
 

Similar to Resume (20)

Engr. Asim Mahmood CV
Engr. Asim Mahmood CVEngr. Asim Mahmood CV
Engr. Asim Mahmood CV
 
NEW CV
NEW CVNEW CV
NEW CV
 
Resume mohan
Resume mohanResume mohan
Resume mohan
 
Loganathan Resume
Loganathan ResumeLoganathan Resume
Loganathan Resume
 
CV_Susovan
CV_SusovanCV_Susovan
CV_Susovan
 
CV_ susovan
CV_ susovanCV_ susovan
CV_ susovan
 
Resume
ResumeResume
Resume
 
Cv
CvCv
Cv
 
venkatCV
venkatCVvenkatCV
venkatCV
 
Solar Power Engineering & Operation Maintenances
Solar Power Engineering & Operation Maintenances Solar Power Engineering & Operation Maintenances
Solar Power Engineering & Operation Maintenances
 
Sharma Resume
Sharma ResumeSharma Resume
Sharma Resume
 
CURRICULUM VITAE - Asif
CURRICULUM VITAE - AsifCURRICULUM VITAE - Asif
CURRICULUM VITAE - Asif
 
Electrical engineer 5 Years Exp
Electrical engineer 5 Years ExpElectrical engineer 5 Years Exp
Electrical engineer 5 Years Exp
 
Resume_Ravindra
Resume_RavindraResume_Ravindra
Resume_Ravindra
 
Resume ravindra
Resume ravindraResume ravindra
Resume ravindra
 
Resume_Latif Khan
Resume_Latif KhanResume_Latif Khan
Resume_Latif Khan
 
Electrical technician
Electrical technicianElectrical technician
Electrical technician
 
Raghu Resume
Raghu Resume Raghu Resume
Raghu Resume
 
Graduate Electrical Engineer having 6.6 Years exprience in renewable energy &...
Graduate Electrical Engineer having 6.6 Years exprience in renewable energy &...Graduate Electrical Engineer having 6.6 Years exprience in renewable energy &...
Graduate Electrical Engineer having 6.6 Years exprience in renewable energy &...
 
krishnaraj CV1
krishnaraj CV1krishnaraj CV1
krishnaraj CV1
 

Resume

  • 1. VENKATARAMANA KINTALI Plot no:8, Bankers Colony, Deepamahal behind, Front of Visakha school, Distt.-Srikakulam, State: Andhra Pradesh, Pin code-532001 Email: venkataeee@gmail.com, venkataeee1@gmail.com ~ Ph: 09440838711 6 YEARS EXPERIENCED DEPUTY MANAGER, QUALIFIED B.TECH GRADUATE ELETRICAL AND ELECTRONICS. ENGG. EXPOSURE TO O&M IN ENGINEERING CONSTRUCTION SECTOR WITH MAJOR ORGANIZATION IN INDIA SERVING WITH MAJOR WIND POWER ORGANISATION AS DEPUTY MANAGER AND SERVED IN PAST WITH MAJOR PRIVATE HYDRO POWER CORPORATION AT UTTATKHAND, AS SR. ELECRTICAL ENGINEER Competencies:  In depth knowledge of electrical panels installation; electrical equipment management  Erection and rectification of 11/33 kV overhead lines.  Team leadership, manpower administration.  Independent target execution. inter-dept. coordination  Maintenance of records and preparation of contractor’s bills, debit notes by verifying at site.  Keen on new technology adaptation.  Fair communication skills and hardworking with dedication. Objective: Seeking career opportunity as Deputy Manager in dynamic, growth oriented organizations in the construction/real estate/ roads/ thermal, wind, hydro plants/ metro sectors where experience and competencies can add value to organizational capabilities for achieving corporate objectives. PROFESSIONAL EXPERIENCE Range of experience:  Operation and maintenance of 220/33kV 100MVA Switchyard and 33kV feeders.  Control room shift engineer and looked after O&M works.  Execution of wide ranges of electrical work at sites.  Estimation & planning of building wiring i.e. commercial, residential, etc.  Providing power at construction sites.  Erection, maintenance of H.T. (11KV,33KV) & L.T. Lines, Transformers, Diesel Generators (up to 1010 KVA.), ACB’s, VCB’s, Distribution Boards, Panels, Compact secondary substations (CSS) .  Planning, estimating of all installation work i.e. HT & LT lines. Substations, Compact Secondary Substations etc. at site.  Designing of panels and cables as per the load requirement at site.  Indenting processes for electrical materials for projects.  Installation of various vibrating wire type instruments at dam site.  Execution of permanent lightning works as per drawings received from HO and coordinating with site people.  Operation and maintenance of 400kV switchyard, 400kV transmission line and coordinating with SLDC Lucknow people and grid people during line and unit shutdown.
  • 2. GRRENKO GROUP Greenko Rayala Wind Power Private Limited Atmakur Anantapur Andhra Corporate Profile: Greenko is a mainstream participant in the growing Indian energy industry and a market leading owner and operator of clean energy projects in India. The Group is building a de-risked portfolio of wind, hydropower and natural gas and biomass assets within India and intends to increase the installed capacity it operates by developing new Greenfield assets. Greenko currently has 1.0 GW operating capacity and is aggressively working towards reaching the capacity of 3.0 GW by 2018. Deputy Manager (September 28th 2016 to till date) Reporting to: State Head Deliverables:  Planning & implementing the preventive & predictive maintenance schedules for improving the overall reliability and safety of plant equipments & machinery.  Preparing system based documentation and conducting analysis of different maintenance data to reduce the cost of maintenance.  Monitoring & recording of incoming / outgoing & transformer loads and controlling of load as per the instructions of Load Dispatch Centre.  Handling issue of Line Clear for carrying of maintenance & repair works in Substations & EHV/HT Lines.  Assuring minor maintenance works of switchgear equipments in 220/110/11kV power substation.  Overseeing conditions of Air compressors, Switchgear equipments, Power transformers, Battery cells & charger, Diesel generator set, Fire protection systems, etc.  Monitoring oil & winding temperatures of power transformers, air & gas pressures of circuit breakers, load, voltage, frequency, etc.  Preparing daily and monthly energy audit & correspondences.  Ensuring hot-line maintenance staff & MRT (meter, relay, testing) division of APTRANSCO during testing & repair of relays, transformers & other substation equipments.  Reviewing history records of key machines for repeated breakdowns to analysis and carrying out necessary corrective actions.  Organizing activities for continual improvement & working towards cost reduction activities.  Responsible for Operation & maintenance activities of Transformers up to 100MVA,Switchgears from 220KV, 110KV & 11KV,EHV Overhead lines -220KV, 110KV, 33kV & 11KV, Protection & Control Equipment, MTTR & MTBF. WIND WORLD INDIA LIMITED Narmada Wind Power Project Andhra Corporate Profile: Wind World (India) Limited (WWIL) formerly Enercon (India) Limited since its inception in 1994, has been making giant strides in the wind energy segment. It has already installed more than 6204 wind energy converters in India with a total installed capacity exceeding 4561 MW. Assistant Manager (June 09th 2016 to September 27th 2016 ) Reporting to: HOD / Zonal Head/ State Head assisted by 20 subordinates. Deliverables:  Planning & implementing the preventive & predictive maintenance schedules for improving the overall reliability and safety of plant equipments & machinery.  Preparing system based documentation and conducting analysis of different maintenance data to reduce the cost of maintenance.  Monitoring & recording of incoming / outgoing & transformer loads and controlling of load as
  • 3. per the instructions of Load Dispatch Centre.  Handling issue of Line Clear for carrying of maintenance & repair works in Substations & EHV/HT Lines.  Assuring minor maintenance works of switchgear equipments in 220/110/11kV power substation.  Overseeing conditions of Air compressors, Switchgear equipments, Power transformers, Battery cells & charger, Diesel generator set, Fire protection systems, etc.  Monitoring oil & winding temperatures of power transformers, air & gas pressures of circuit breakers, load, voltage, frequency, etc.  Preparing daily and monthly energy audit & correspondences.  Ensuring hot-line maintenance staff & MRT (meter, relay, testing) division of APTRANSCO during testing & repair of relays, transformers & other substation equipments.  Reviewing history records of key machines for repeated breakdowns to analysis and carrying out necessary corrective actions.  Organizing activities for continual improvement & working towards cost reduction activities.  Responsible for Operation & maintenance activities of Transformers up to 100MVA,Switchgears from 220KV, 110KV & 11KV,EHV Overhead lines -220KV, 110KV, 33kV & 11KV, Protection & Control Equipment, MTTR & MTBF, Liasoning & solving ROW issues. GVK GROUP 330MW Hydro Electric Project. Srinagar, Uttarakhand Corporate Profile: GVK is a leading Indian conglomerate with diversified interests across various sectors including energy, resources, airports, transportation, hospitality and life sciences. Electrical Engineer (November 08th 2010 to June 08th 2016) Reporting to: GM / Manager assisted by 40 subordinates. Deliverables:  Supervising O&M works for 11/.433KV sub-stations at sites (Total length of lines are 10Km approximately).  Supervision of erection works of 11kV transmission lines of single/ double circuit. (Totally length of lines erected are 15Km approximately).  Erection commissioning and testing of CSS (compact secondary substations) of range 0.315 to 1MVA. ABB make (Totally erected 15 Substations)  Erection commissioning and testing of silent diesel generator sets of Jacksons make. Range varied from 0.05 to 1.010 MVA. (Totally erected 12 DG sets)  Arrangement of proper earthing for installed substations of both temporary and permanent types. Chemical earthing is also used at rocky areas.  Erection of LT switchgear panels for LT power distribution to various loads from substations along with backup power schemes.  Laying of HT/LT cables of sizes ranging from 10 to 400sqmm of both armoured and unarmoured type multicore power cables in cable trays, cable trenches and underground cabling. Also laid 40 core control cables jelly filled and armoured for instrumentation purposes. (Total 25Km of cable was laid approximately under my supervision).  Erection of 11kV SF6 Circuit breakers RMU of ABB make for protection of 11kV circuits and for breaking point in the circuits. (Totally Installed 5 VCB panels).  Installation of LT breaker panels of 1600 Amp, LT changeover switches of range up to 1600 Amp and LT distribution panels at sub-stations for backup power arrangements of over all project sites. (Totally installed up to 80 panels)  Planning the work schedule for the successive day and deployment of man power at various sites regularly. (Handled 40 electricians and 15 Engineers).  Coordinating and executing all the E&M works going on at all sites which were under the radius
  • 4. of 6Kms from dam to power house.  Planning and preparation of estimate for the work and executing them at site after getting necessary approvals from GM/Director. Preparation of bills for works executed at sites. (Totally prepared 300 bills approximately).  Preparation of UPCL bills and UPCL liaison works. Coordination with UPCL line man and JE/AE during 11kV line faults for shutdowns. (Handled the job for 3 Years).  Preparation of grid/DG debit notes of the power provided to different contractors engaged at site. (Prepared 100 debit notes till date)  Maintenance of records which includes all substations data, diesel filling records of DG sets, maintenance etc.  Procurement of all operation and maintenance materials, tools, safety equipments in time to prevent work delay and coordinating with store people and inspection of the same after received at site. (Totally raised 4000 purchase requisitions till date).  Installation of vibrating wire type instruments at dam site and collection of the readings of the same.  Operation and maintenance of 400kV switchyard, 400kV transmission line which includes SF6 circuit breakers, isolators, CVT’s, CT’s, and collection of data like hourly generation, daily generation report and total power transmitted. Coordination with SLDC Lucknow people and grid people during line and unit shutdown and relays monitoring. (Since last six months looking after switch yard as additional responsibility) Contributions:  Successfully executed all detailed planning of E&M work in coordination with GM / Manager (projects).  Successfully erected tested and operated eight sub stations of 1MVA and handled 8MVA construction power.  Successfully looked after O&M works of 400kV switchyard and coordinated with SLDC Lucknow and NRLDC Delhi during line/Unit shutdown. EDUCATION  B.Tech Graduate, Electrical and Electronics. Engg. (67.29%) 2009 - JNTUH, Hyderabad  Intermediate , MPC (90.4%) – Board of Intermediate Education.  SSC (81.5%) – Board of Secondary Education. EXTRA CURRICULAR ACTIVITIES/ACHEIVEMENTS  Got first prize in Quest for Talent conducted by Sri Vidya Junior college  A paper presentation on ‘Preparation of Bio-Diesel’ at Pragna’07 conducted by Gokaraju Rangaraju institute of technology and science.  A paper presentation on ‘SCADA’ at Prathibha’08 conducted by TKRCET.  Secured 2055 AIR in GATE 2012. INDUSTRIAL ORIENTED MINI PROJECTS 220kV SWITCHGEAR MAINTENANCE OF HYDEL POWERHOUSE. Nagarjuna Sagar, Andhra  Operation of SF6 & Minimum Oil Circuit Breakers
  • 5.  Testing of Current Transformers  Protection of Bus bars. INDUSTRIAL ORIENTED MINI PROJECTS DRIVERLESS TRAIN SHUTTLING BETWEEN TWO BUSY STATIONS To run the train between two busy stations without a human driver and to open and close the doors automatically, to run and stop the train automatically at stations, ultimately which can be used to carry the passengers from one station to another station when a real system is constructed. PERSONAL INFORMATION  Date of Birth :18 May 1988  Father’s Name : Shri K.Laxmana Rao  Nationality : Indian  Marital Status : Single  Driving license No : DLFAP03090842010  DL expiry date : 19/05/2028  Passport No. : M8226883  Passport expiry date : 26/04/2025  Language Skills : Hindi, English,Telugu  Preferred location : Any where  Present CTC : 7 Lacs per annum  Notice period : 15 - 30 Days  References : Will be provided on demand
  • 6.  Testing of Current Transformers  Protection of Bus bars. INDUSTRIAL ORIENTED MINI PROJECTS DRIVERLESS TRAIN SHUTTLING BETWEEN TWO BUSY STATIONS To run the train between two busy stations without a human driver and to open and close the doors automatically, to run and stop the train automatically at stations, ultimately which can be used to carry the passengers from one station to another station when a real system is constructed. PERSONAL INFORMATION  Date of Birth :18 May 1988  Father’s Name : Shri K.Laxmana Rao  Nationality : Indian  Marital Status : Single  Driving license No : DLFAP03090842010  DL expiry date : 19/05/2028  Passport No. : M8226883  Passport expiry date : 26/04/2025  Language Skills : Hindi, English,Telugu  Preferred location : Any where  Present CTC : 7 Lacs per annum  Notice period : 15 - 30 Days  References : Will be provided on demand