SlideShare a Scribd company logo
1 of 2
TIM A. FUGATE
15656 Bernardo Center Dr. 808 Email:ipdc4u@yahoo.com
Rancho Bernardo Ca. 92127 Cell Number 817-505-9117
Completed projects
Centre Builders Inc.
I am currently a commercial project superintendent, my first project was the core and shell structural retrofits for
a 31,000 sq. ft. building completed in 90 days with a budget of $ 850,000.00.
American Technologies Inc.
During my time at American Technologies Inc. my position was more of a traditional project manager position,
than as a Superintendent. My duties included handling all aspects of the job from meeting with the clients all the
way through to plans, design and schedules. I would buy out all of the materials as well hire and manage all of the
vendors through to the jobs completion. Jobs varied in value from $ 1,500.00 to $ 750,000.00. On average I would
handle 12 to 18 projects at any given time, with an average of finishing 3 per week. With a gross profit margin of
30 % and an annual volume of $ 2 million in business per year.
Some of the projects completed during my time at ATI:
Palermo Condos in Downtown San Diego 12 units $ 250,000.00 job and completed in 45 days.
City Walk Condos in Downtown San Diego 6 units $ 125,000.00 job and completed in 30 days
Westpark Apartment in Downtown San Diego 8 units $ 150,000.00 job and completed in 30 days
FL. Malik in Dallas Texas 50 sq. ft. commercial building $ 750,000.00 job and completed in 180days
Solar Installations and Design
I have worked with various solar companies over the last 18 months designing and installing PV systems. I ran all
aspects of the installation, permitting, design, coordinating the meeting with the Utility companies and upgrading
the existing electrical main meter panels and transformers for the new PV load’s. Jobs vary in value from $
25,000.00 to as Large as $ 1,250,000.00
Regis Development: Operations Manager
I was in charge of the property inspections, Vendors, and repairs for the REO and property preservation division
in all of Southern Ca. for the $ 5,000.00 value and under projects. Over the last 2.5 years I have set up and staffed 4
new Office Locations. I have traveled up to Northern Cal. Hiring over 100 new Vendors to work for Regis. Over all I
have hired on and qualified 250 new vendors. Jobs vary in value from $ 1,500.00 to as Large as $ 250,000.00
AT&T Site Development: Construction Manager
From: 1999 to 2004 we built and developed over 50 AT&T locations throughout Southern Calif. for CCB
construction. We helped with finding the site locations, assed all of the utilities coming into the unit and did the
preliminary site drawings for the architect. In the drawings I put together a plan to upgrade the infrastructure to
make the existing utilities work and or meet with the local utility to upgrade the utilities to meet AT &T‘s
needs. Then I handled pulling all of the permits and logistics with the malls and their development teams. Then
my other company Fugate Electrical came in and handled all aspects of the Electrical installations. Jobs vary in
value from $ 15,500.00 to as Large as $ 450,000.00
T i m A . F u g a t e P a g e | 2
Oak Hills Project: Supervised and installed UG Utilities, Roads and Erosion Control for slopes and landscape for a
Commercial Development in Oak Hills, CA. Coordinated with Utility designers to overcome all of the on-site
challenges. Also, ran electrical for two 79 unit Assisted Living Developments. Job value was $250,000.00
Riverside Project: Worked as a building consultant for a $ 25 million commercial project in Riverside, CA. This
was a 20-acre project with 19 tilt up buildings. I was involved with this project from the ground up to finishes. Our
electrical contract with extras was $ 895,000.00
Home Depot Project: I developed a service and installation program for Home Depot’s 65 southern California
locations. My installers covered 150-mile radius, where I supervised the phone center with over 500 calls a week,
15 field installers and handled all customer service coordination. Average $ 275,000 in business annually.
Residential Projects: includes ground up multi-million dollar homes. Purchased properties, brought in all of the
utilities and built each project from ground up including the permits, plans, negotiating all of the contracts.
American Honda Distribution Hub Project: Electrical contractor
American Honda Distribution Hub, which covers over 33 acres of land and over 1,000,000 square feet of
warehouse/office area. I ran a 38-man electrical crew, worked with the architect to design the electrical systems
on a design build contract, value engineered all aspects of the job and completed it by running two shifts in 45
days with over $ 450,000.00 in additional change orders. Total job value with change orders $ 795,000.00
California State University at Sacramento: Electrical contractor
Recently completed an $800,000.00 classroom improvement project. New lighting and new Telecom; ran new 4-
inch conduit for all new cabling to Telecom Rooms.
RESTAURANT WORK:
Chic Fila Restaurants: Electrical contractor
Completed all aspects from ground up electrical construction including all site utilities. This included setting the
main service panels and transformers to all EM Systems on 4 locations.
Apple Bees Restaurants: Electrical contractor
Completed all aspects from ground up electrical construction including all site utilities. This included setting the
main service panels and transformers to all EM Systems on 3 locations.
Jack in the Box: Electrical contractor
Completed all aspects from ground up electrical construction including all site utilities. This included setting the
main service panels and transformers to all EM Systems on 6 locations.
MEDICAL and MRI work:
Completed all aspects from ground up electrical construction including all site utilities. This included setting the
main service panels and transformers to all EM Systems on 9 locations. We had to work direct with the Engineers
from GE on the specialty ground systems need for the MRI equipment. Some of the locations where existing and
we had retro fit the old service panels to the new 277/480 requirements and still keep the existing tenants on line.

More Related Content

What's hot (20)

Home Interior Renovation
Home Interior RenovationHome Interior Renovation
Home Interior Renovation
 
Home Renovation by Creative Geometry
Home Renovation by Creative GeometryHome Renovation by Creative Geometry
Home Renovation by Creative Geometry
 
AKVES ENGINEERING SOLUTIONS_PROFILE
AKVES ENGINEERING SOLUTIONS_PROFILEAKVES ENGINEERING SOLUTIONS_PROFILE
AKVES ENGINEERING SOLUTIONS_PROFILE
 
Cone, Robert_Resume_8-13-2015
Cone, Robert_Resume_8-13-2015Cone, Robert_Resume_8-13-2015
Cone, Robert_Resume_8-13-2015
 
CP_AMEZZ
CP_AMEZZCP_AMEZZ
CP_AMEZZ
 
CV -Yusuf
CV  -YusufCV  -Yusuf
CV -Yusuf
 
Mechanical & electrical engineering
Mechanical & electrical engineeringMechanical & electrical engineering
Mechanical & electrical engineering
 
Fady samir cv
Fady samir cvFady samir cv
Fady samir cv
 
Kitchen Presentation
Kitchen PresentationKitchen Presentation
Kitchen Presentation
 
CV OF MVV
CV OF MVVCV OF MVV
CV OF MVV
 
Binder2
Binder2Binder2
Binder2
 
hazem mohamed cv - Copy
hazem mohamed cv - Copyhazem mohamed cv - Copy
hazem mohamed cv - Copy
 
cofieldresume
cofieldresumecofieldresume
cofieldresume
 
Stadium Project
Stadium ProjectStadium Project
Stadium Project
 
Item # 9 - Award ADA Swimming Pool Renovations
Item # 9 - Award ADA Swimming Pool RenovationsItem # 9 - Award ADA Swimming Pool Renovations
Item # 9 - Award ADA Swimming Pool Renovations
 
Greg Sandler Resume
Greg Sandler ResumeGreg Sandler Resume
Greg Sandler Resume
 
Eng.Ahmed-CV
Eng.Ahmed-CVEng.Ahmed-CV
Eng.Ahmed-CV
 
VINCI RESUME' waterfield
VINCI  RESUME' waterfieldVINCI  RESUME' waterfield
VINCI RESUME' waterfield
 
North Uhle Street
North Uhle StreetNorth Uhle Street
North Uhle Street
 
At Alex
At AlexAt Alex
At Alex
 

Viewers also liked

Diaporamawordpress
DiaporamawordpressDiaporamawordpress
DiaporamawordpressMPORTE
 
Carpeta de Presentacion SMR
Carpeta de Presentacion SMRCarpeta de Presentacion SMR
Carpeta de Presentacion SMRIvana Volkis
 
EBS To Fusion HCM Data Conversion Data Flow Diagram
EBS To Fusion HCM Data Conversion Data Flow DiagramEBS To Fusion HCM Data Conversion Data Flow Diagram
EBS To Fusion HCM Data Conversion Data Flow DiagramAshish Harbhajanka
 
Mapa conceptual pasado simple
Mapa conceptual pasado simpleMapa conceptual pasado simple
Mapa conceptual pasado simpleRobby Alvaro
 
Outbreak of avian influenza A(H5N8) in Hungary
Outbreak of avian influenza A(H5N8) in HungaryOutbreak of avian influenza A(H5N8) in Hungary
Outbreak of avian influenza A(H5N8) in HungaryCornelia Adlhoch
 
AssayQuant Technologies, Inc.
 AssayQuant Technologies, Inc. AssayQuant Technologies, Inc.
AssayQuant Technologies, Inc.Ramon Hernandez
 
Information technology and its impact on society
Information technology and its impact on societyInformation technology and its impact on society
Information technology and its impact on societyArijeet Dutta
 

Viewers also liked (12)

MAX Retrans
MAX RetransMAX Retrans
MAX Retrans
 
Diaporamawordpress
DiaporamawordpressDiaporamawordpress
Diaporamawordpress
 
Carpeta de Presentacion SMR
Carpeta de Presentacion SMRCarpeta de Presentacion SMR
Carpeta de Presentacion SMR
 
EBS To Fusion HCM Data Conversion Data Flow Diagram
EBS To Fusion HCM Data Conversion Data Flow DiagramEBS To Fusion HCM Data Conversion Data Flow Diagram
EBS To Fusion HCM Data Conversion Data Flow Diagram
 
Medication Adherence TECHNOLOGY Brief update 2016
Medication Adherence TECHNOLOGY Brief update 2016Medication Adherence TECHNOLOGY Brief update 2016
Medication Adherence TECHNOLOGY Brief update 2016
 
Mapa conceptual pasado simple
Mapa conceptual pasado simpleMapa conceptual pasado simple
Mapa conceptual pasado simple
 
Gary R Johsnon
Gary R JohsnonGary R Johsnon
Gary R Johsnon
 
Tarea 1
Tarea 1Tarea 1
Tarea 1
 
Outbreak of avian influenza A(H5N8) in Hungary
Outbreak of avian influenza A(H5N8) in HungaryOutbreak of avian influenza A(H5N8) in Hungary
Outbreak of avian influenza A(H5N8) in Hungary
 
AssayQuant Technologies, Inc.
 AssayQuant Technologies, Inc. AssayQuant Technologies, Inc.
AssayQuant Technologies, Inc.
 
Formato de registro foro móvil
Formato de registro foro móvilFormato de registro foro móvil
Formato de registro foro móvil
 
Information technology and its impact on society
Information technology and its impact on societyInformation technology and its impact on society
Information technology and its impact on society
 

Similar to Tim projects completed

Resume Oct 2015 Revision 2
Resume Oct 2015 Revision 2Resume Oct 2015 Revision 2
Resume Oct 2015 Revision 2David Seaward
 
Erik D resume for Project Manager position
Erik D resume for Project Manager positionErik D resume for Project Manager position
Erik D resume for Project Manager positionErik Slaughter
 
Tom's Resume 9-1-16
Tom's Resume 9-1-16Tom's Resume 9-1-16
Tom's Resume 9-1-16Tom Coughlin
 
RussRudolph Resume_Project List
RussRudolph Resume_Project ListRussRudolph Resume_Project List
RussRudolph Resume_Project ListRuss Rudolph
 
Power point resume music 1 15-2018
Power point resume music  1 15-2018Power point resume music  1 15-2018
Power point resume music 1 15-2018james bailey
 
James Baileys PowerPoint Resume
James Baileys PowerPoint ResumeJames Baileys PowerPoint Resume
James Baileys PowerPoint ResumeJames Bailey
 
Carl doucette res 2015
Carl doucette res 2015Carl doucette res 2015
Carl doucette res 2015carl doucette
 
KBE Building Futures - Higher Ed
KBE Building Futures - Higher EdKBE Building Futures - Higher Ed
KBE Building Futures - Higher Edcharkins
 
Edward E calder CV 2014
Edward E calder CV 2014Edward E calder CV 2014
Edward E calder CV 2014Edward Calder
 
J. Pena Resume 12.2015
J. Pena Resume 12.2015J. Pena Resume 12.2015
J. Pena Resume 12.2015Jesse Pena
 
Roger Carrillo Resume 2016 w pic PROOF FNL _0005 fnl III.
Roger Carrillo Resume 2016  w  pic PROOF FNL _0005 fnl III.Roger Carrillo Resume 2016  w  pic PROOF FNL _0005 fnl III.
Roger Carrillo Resume 2016 w pic PROOF FNL _0005 fnl III.Roger T. Carrillo, AIA
 
Roger Carrillo Resume 2015 - PROOF (2)
Roger Carrillo Resume 2015 - PROOF (2)Roger Carrillo Resume 2015 - PROOF (2)
Roger Carrillo Resume 2015 - PROOF (2)Roger T. Carrillo, AIA
 
RRozek Project List 9 20 15
RRozek Project List 9 20 15RRozek Project List 9 20 15
RRozek Project List 9 20 15Roman Rozek
 
Energy Savings for Hotel & Lodging Industry
Energy Savings for Hotel & Lodging IndustryEnergy Savings for Hotel & Lodging Industry
Energy Savings for Hotel & Lodging IndustryRayco Energy
 
Seattle Remodeling Contractors - Presentation
Seattle Remodeling Contractors - Presentation Seattle Remodeling Contractors - Presentation
Seattle Remodeling Contractors - Presentation keeverassociates
 
Future-Proof Commerial Buildings
Future-Proof Commerial BuildingsFuture-Proof Commerial Buildings
Future-Proof Commerial BuildingsJoe Dowling
 

Similar to Tim projects completed (20)

Martin L Reetz Resume 092215
Martin L Reetz Resume 092215Martin L Reetz Resume 092215
Martin L Reetz Resume 092215
 
Resume Oct 2015 Revision 2
Resume Oct 2015 Revision 2Resume Oct 2015 Revision 2
Resume Oct 2015 Revision 2
 
Erik D resume for Project Manager position
Erik D resume for Project Manager positionErik D resume for Project Manager position
Erik D resume for Project Manager position
 
Tom's Resume 9-1-16
Tom's Resume 9-1-16Tom's Resume 9-1-16
Tom's Resume 9-1-16
 
RussRudolph Resume_Project List
RussRudolph Resume_Project ListRussRudolph Resume_Project List
RussRudolph Resume_Project List
 
Power point resume music 1 15-2018
Power point resume music  1 15-2018Power point resume music  1 15-2018
Power point resume music 1 15-2018
 
James Baileys PowerPoint Resume
James Baileys PowerPoint ResumeJames Baileys PowerPoint Resume
James Baileys PowerPoint Resume
 
fpbcurrent1
fpbcurrent1fpbcurrent1
fpbcurrent1
 
Charles Riha
Charles RihaCharles Riha
Charles Riha
 
Carl doucette res 2015
Carl doucette res 2015Carl doucette res 2015
Carl doucette res 2015
 
Resume Format FINAL
Resume Format FINALResume Format FINAL
Resume Format FINAL
 
KBE Building Futures - Higher Ed
KBE Building Futures - Higher EdKBE Building Futures - Higher Ed
KBE Building Futures - Higher Ed
 
Edward E calder CV 2014
Edward E calder CV 2014Edward E calder CV 2014
Edward E calder CV 2014
 
J. Pena Resume 12.2015
J. Pena Resume 12.2015J. Pena Resume 12.2015
J. Pena Resume 12.2015
 
Roger Carrillo Resume 2016 w pic PROOF FNL _0005 fnl III.
Roger Carrillo Resume 2016  w  pic PROOF FNL _0005 fnl III.Roger Carrillo Resume 2016  w  pic PROOF FNL _0005 fnl III.
Roger Carrillo Resume 2016 w pic PROOF FNL _0005 fnl III.
 
Roger Carrillo Resume 2015 - PROOF (2)
Roger Carrillo Resume 2015 - PROOF (2)Roger Carrillo Resume 2015 - PROOF (2)
Roger Carrillo Resume 2015 - PROOF (2)
 
RRozek Project List 9 20 15
RRozek Project List 9 20 15RRozek Project List 9 20 15
RRozek Project List 9 20 15
 
Energy Savings for Hotel & Lodging Industry
Energy Savings for Hotel & Lodging IndustryEnergy Savings for Hotel & Lodging Industry
Energy Savings for Hotel & Lodging Industry
 
Seattle Remodeling Contractors - Presentation
Seattle Remodeling Contractors - Presentation Seattle Remodeling Contractors - Presentation
Seattle Remodeling Contractors - Presentation
 
Future-Proof Commerial Buildings
Future-Proof Commerial BuildingsFuture-Proof Commerial Buildings
Future-Proof Commerial Buildings
 

Recently uploaded

Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 

Recently uploaded (13)

sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 

Tim projects completed

  • 1. TIM A. FUGATE 15656 Bernardo Center Dr. 808 Email:ipdc4u@yahoo.com Rancho Bernardo Ca. 92127 Cell Number 817-505-9117 Completed projects Centre Builders Inc. I am currently a commercial project superintendent, my first project was the core and shell structural retrofits for a 31,000 sq. ft. building completed in 90 days with a budget of $ 850,000.00. American Technologies Inc. During my time at American Technologies Inc. my position was more of a traditional project manager position, than as a Superintendent. My duties included handling all aspects of the job from meeting with the clients all the way through to plans, design and schedules. I would buy out all of the materials as well hire and manage all of the vendors through to the jobs completion. Jobs varied in value from $ 1,500.00 to $ 750,000.00. On average I would handle 12 to 18 projects at any given time, with an average of finishing 3 per week. With a gross profit margin of 30 % and an annual volume of $ 2 million in business per year. Some of the projects completed during my time at ATI: Palermo Condos in Downtown San Diego 12 units $ 250,000.00 job and completed in 45 days. City Walk Condos in Downtown San Diego 6 units $ 125,000.00 job and completed in 30 days Westpark Apartment in Downtown San Diego 8 units $ 150,000.00 job and completed in 30 days FL. Malik in Dallas Texas 50 sq. ft. commercial building $ 750,000.00 job and completed in 180days Solar Installations and Design I have worked with various solar companies over the last 18 months designing and installing PV systems. I ran all aspects of the installation, permitting, design, coordinating the meeting with the Utility companies and upgrading the existing electrical main meter panels and transformers for the new PV load’s. Jobs vary in value from $ 25,000.00 to as Large as $ 1,250,000.00 Regis Development: Operations Manager I was in charge of the property inspections, Vendors, and repairs for the REO and property preservation division in all of Southern Ca. for the $ 5,000.00 value and under projects. Over the last 2.5 years I have set up and staffed 4 new Office Locations. I have traveled up to Northern Cal. Hiring over 100 new Vendors to work for Regis. Over all I have hired on and qualified 250 new vendors. Jobs vary in value from $ 1,500.00 to as Large as $ 250,000.00 AT&T Site Development: Construction Manager From: 1999 to 2004 we built and developed over 50 AT&T locations throughout Southern Calif. for CCB construction. We helped with finding the site locations, assed all of the utilities coming into the unit and did the preliminary site drawings for the architect. In the drawings I put together a plan to upgrade the infrastructure to make the existing utilities work and or meet with the local utility to upgrade the utilities to meet AT &T‘s needs. Then I handled pulling all of the permits and logistics with the malls and their development teams. Then my other company Fugate Electrical came in and handled all aspects of the Electrical installations. Jobs vary in value from $ 15,500.00 to as Large as $ 450,000.00
  • 2. T i m A . F u g a t e P a g e | 2 Oak Hills Project: Supervised and installed UG Utilities, Roads and Erosion Control for slopes and landscape for a Commercial Development in Oak Hills, CA. Coordinated with Utility designers to overcome all of the on-site challenges. Also, ran electrical for two 79 unit Assisted Living Developments. Job value was $250,000.00 Riverside Project: Worked as a building consultant for a $ 25 million commercial project in Riverside, CA. This was a 20-acre project with 19 tilt up buildings. I was involved with this project from the ground up to finishes. Our electrical contract with extras was $ 895,000.00 Home Depot Project: I developed a service and installation program for Home Depot’s 65 southern California locations. My installers covered 150-mile radius, where I supervised the phone center with over 500 calls a week, 15 field installers and handled all customer service coordination. Average $ 275,000 in business annually. Residential Projects: includes ground up multi-million dollar homes. Purchased properties, brought in all of the utilities and built each project from ground up including the permits, plans, negotiating all of the contracts. American Honda Distribution Hub Project: Electrical contractor American Honda Distribution Hub, which covers over 33 acres of land and over 1,000,000 square feet of warehouse/office area. I ran a 38-man electrical crew, worked with the architect to design the electrical systems on a design build contract, value engineered all aspects of the job and completed it by running two shifts in 45 days with over $ 450,000.00 in additional change orders. Total job value with change orders $ 795,000.00 California State University at Sacramento: Electrical contractor Recently completed an $800,000.00 classroom improvement project. New lighting and new Telecom; ran new 4- inch conduit for all new cabling to Telecom Rooms. RESTAURANT WORK: Chic Fila Restaurants: Electrical contractor Completed all aspects from ground up electrical construction including all site utilities. This included setting the main service panels and transformers to all EM Systems on 4 locations. Apple Bees Restaurants: Electrical contractor Completed all aspects from ground up electrical construction including all site utilities. This included setting the main service panels and transformers to all EM Systems on 3 locations. Jack in the Box: Electrical contractor Completed all aspects from ground up electrical construction including all site utilities. This included setting the main service panels and transformers to all EM Systems on 6 locations. MEDICAL and MRI work: Completed all aspects from ground up electrical construction including all site utilities. This included setting the main service panels and transformers to all EM Systems on 9 locations. We had to work direct with the Engineers from GE on the specialty ground systems need for the MRI equipment. Some of the locations where existing and we had retro fit the old service panels to the new 277/480 requirements and still keep the existing tenants on line.