C. Scope
 To review the existing study reports, standards and
specifications.
 Detailed engineering survey of alignment.
 Preparation of topographical map.
 Study for cross-drainage works and propose suitable drainage
structure.
 Preparation of working drawings.
 Preparation of quantity and cost estimate.
 Preparation of survey and design report
D. Project location
 The proposed road is located in the Lalitpur District,
Bagmati Zone, Central Region. The road starts from
Badikhel and ends at Badegaun.
 The road runs along Karmanasha River corridor.
 The latitude and the longitude of the starting point are
27057’07’’ and 85035’27’’ respectively.
F. Hydrology And Meteorology
 Small temporary streams running only during monsoon crosses
the alignment with small discharge.
 The project area experiences marked seasonal and specific
climate variation with moderately hot summer and relatively
cool winters. Average temperature is 25oC in summer and 10oC
in winter.
 Almost 80% of the rainfall occurs during monsoon which starts
at the middle of the June and continues until the end of August.
METHODOLOGY
 DESK STUDY
 SOCIAL IMPACT ASSESMENT
 FIELD WORK
 EQUIPMENT USED FOR SURVEYING
 OFFICE WORK
DESK STUDY
 The geographical and the topographical maps
were studied and the relevant information
regarding the alignment selection, cross drainage
structures, gradient of the road were discussed.
 The strategy for the field study was made
accordingly.
 The study team member discussed the related
matters of the project.
SOCIAL IMPACT ASSESMENT
The study identified the following key social issues
for investigation:
 Loss of private property and other assets (land,
houses and trees) and compensation modalities
for these losses.
 Population displacement.
 EQUIPMENT USED FOR
SURVEYING
 Total station
 GPS device
 Staff
 Compass
 Measuring tape
 Hammer
 Communicating Device
DESIGN
Road Classification
 As per the NRS 2045, the road project falls on the
category of District Roads.
 A Design speed of 30 km/hr is taken for the
design of geometric parameters of the
road.
Design Speed
 The Design values are taken as recommended by
NRS 2045 as far as practicable
 The shoulder width is taken as 1 m considering
the site condition and the utility of the road
 Minimum Gradient recommended by NRS (1% for
better drainage) cannot be incorporated
considering the site condition
Horizontal Alignment
 The most suitable horizontal alignment was
selected considering the following factors:
 Short (S)
 Easy (E)
 Safe (S)
 Economical (E)
 Minimum radius for the horizontal curve as
recommended by NRS is 12 m. The minimum
radius of 12m is provided at the intersection of
existing road and proposed road.
 The extrawidening and transition curves are not
provided owing to low design speed and
simplicity in construction
 A maximum of 5 % super elevation is provided at
each horizontal curve.
 Superelevation is provided by rotation of
pavement about the center line.
 Transition length for super elevation is provided
as 5 m
 Summit curves are designed considering stopping
sight distance.
 Valley curves are designed on the basis of night
visibility
 The radius of vertical curve is adopted as large as
possible so that all the factors are satisfied
 The least vertical radius taken in design is 1000 m
Cross Section Design
 Cross section is designed providing camber of 4%
on carriageway and 5 % on shoulder
 For embankment the side slope of 1.5H: 1V and
for cut the side slope of 1H: 1V is adopted
 Total pavement thickness of 28 cm is adopted as
per CBR method of design
 Gravel is used as the sub-base course
 Otta Seal is used as the surface course
Drainage
 Longitudinal drain is provided on the cut slope side of
the road
 The side slope is 1:1 and longitudinal slope is parallel
to the alignment
 Earthen drain is provided from chainage 0+000 to the
chainage of 1+251.35
 Stoned masonry drain of thickness 20 cm is provided
from the chainage of 1+309.82 to chainage 2+027.24
 Pipe culverts of 60 cm in diameter and total
length of 7.5m are provided at 12 sections of the
road
 They are provided at the lowest point of the
vertical alignment
 A minimum depth of 60 cm is provided between
the surface of the pavement and the crown of
the pipe
Plan and Profile
 Ch. 0+000-0+200
 Ch. 0+200-0+480
 Ch. 0+480-0+760
 Ch. 0+760-1+040
 Ch. 1+040-1+360
 Ch. 1+360-1+700
 Ch. 1+700-2+027.24
Cross Section
 Ch. 0+000-0+271.50
 Ch. 0+280-0+500
 Ch. 0+511.92-0+680
 Ch. 0+683.87-0+760
 Ch. 0+780-0+920
 Ch. 0+936.71-1+125.89
 Ch. 1+130.75-1+213.66
 Ch.1+220-1+319.59
 Ch.1+320-1+380
 Ch.1+397.04-1+465.09
 Ch.1+480-1+545.77
 Ch.1+560-1+800
 Ch.1+800.91-1+980
 Ch.1+984.58-2+027.24
Typical Pavement
Cross Drainage Structure
ESTIMATE
Quantity Estimate
Calculation of Earthwork
Necessary Calculations
Rate Analysis
BoQ /Cost Estimate
QUANTITY ESTIMATE
 Earthwork Calculations:
 Calculated at each cross-section
 Separate calculation according to soil type
 Total cut volume = 10283.57 m3
 Total fill volume = 16052.44 m3
 Balance (fill) = 5768.869 m3
 Earthwork for drain = 768.129 m3
All the detailed calculation is shown in the
tabular form in the following slides:
Contd………
 Necessary calculations:
i. For side drain:
Calculations were made taking the following
design considerations:
 Section = trapezoidal
 Depth: 0.3m
 Base width: 0.3m
 Side slope: 1:1
 Unlined earthen canal(Ch. 0+000 to 1251.35)
 Lined canal: (ch.1+309.82 to Ch. 2+027.24)
ii. Sub-grade calculations:
RATE ANALYSIS
 Rate analysis was performed under the
following criteria:
 The quantity of the materials, required labor
force and plants, machinery, tools and
equipments were taken from the work norms
provided by the DoR.
 The rate for the materials, labors, plants and
machinery, tools and equipments was taken
from the district rates provided by the Lalitpur
DDC.
COST ESTIMATE
 The BoQ was prepared on the basis of
the quantity of work calculated and
rate analysis done previously:
 The cost estimate is as below:

More Related Content

Similar to Detailed.pptx

1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
Er. Bam Bhandari
 

Similar to Detailed.pptx (20)

Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.pptHill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
 
Road-design-standards-for-LGED.pptx
Road-design-standards-for-LGED.pptxRoad-design-standards-for-LGED.pptx
Road-design-standards-for-LGED.pptx
 
Presentation sayed
Presentation sayedPresentation sayed
Presentation sayed
 
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
 
Case Study on Geometry of Four Lane Highway
Case Study on Geometry of Four Lane HighwayCase Study on Geometry of Four Lane Highway
Case Study on Geometry of Four Lane Highway
 
Site Plan for Rathmalana Railway Station - Amali Pathiraja
Site Plan for Rathmalana Railway Station - Amali PathirajaSite Plan for Rathmalana Railway Station - Amali Pathiraja
Site Plan for Rathmalana Railway Station - Amali Pathiraja
 
Module 1 Highway Engg (1).pdf
Module 1 Highway Engg (1).pdfModule 1 Highway Engg (1).pdf
Module 1 Highway Engg (1).pdf
 
Road construction in Civil engineering
Road construction in Civil engineeringRoad construction in Civil engineering
Road construction in Civil engineering
 
Vertical alignment of highways
Vertical alignment of highwaysVertical alignment of highways
Vertical alignment of highways
 
transportation Engineering.Highway planning,alignment and geometry.
transportation Engineering.Highway planning,alignment and geometry.transportation Engineering.Highway planning,alignment and geometry.
transportation Engineering.Highway planning,alignment and geometry.
 
Sewer Design
Sewer Design Sewer Design
Sewer Design
 
geometric design ppt unit 3 (1).ppt
geometric design ppt unit 3 (1).pptgeometric design ppt unit 3 (1).ppt
geometric design ppt unit 3 (1).ppt
 
Highway Alignment
Highway AlignmentHighway Alignment
Highway Alignment
 
Highway presentation
Highway presentationHighway presentation
Highway presentation
 
Design Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway AlignmentDesign Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway Alignment
 
hillroads-200131051526.pptx
hillroads-200131051526.pptxhillroads-200131051526.pptx
hillroads-200131051526.pptx
 
Site grading.pptx
Site grading.pptxSite grading.pptx
Site grading.pptx
 
Highway Project
Highway ProjectHighway Project
Highway Project
 
Canal Surveying.pdf
Canal Surveying.pdfCanal Surveying.pdf
Canal Surveying.pdf
 
Sight Distance for horizontal curves
Sight Distance for horizontal curvesSight Distance for horizontal curves
Sight Distance for horizontal curves
 

Recently uploaded

obat aborsi Bontang wa 081336238223 jual obat aborsi cytotec asli di Bontang6...
obat aborsi Bontang wa 081336238223 jual obat aborsi cytotec asli di Bontang6...obat aborsi Bontang wa 081336238223 jual obat aborsi cytotec asli di Bontang6...
obat aborsi Bontang wa 081336238223 jual obat aborsi cytotec asli di Bontang6...
yulianti213969
 
一比一原版(ucla文凭证书)加州大学洛杉矶分校毕业证学历认证官方成绩单
一比一原版(ucla文凭证书)加州大学洛杉矶分校毕业证学历认证官方成绩单一比一原版(ucla文凭证书)加州大学洛杉矶分校毕业证学历认证官方成绩单
一比一原版(ucla文凭证书)加州大学洛杉矶分校毕业证学历认证官方成绩单
aqpto5bt
 
原件一样伦敦国王学院毕业证成绩单留信学历认证
原件一样伦敦国王学院毕业证成绩单留信学历认证原件一样伦敦国王学院毕业证成绩单留信学历认证
原件一样伦敦国王学院毕业证成绩单留信学历认证
pwgnohujw
 
1:1原版定制利物浦大学毕业证(Liverpool毕业证)成绩单学位证书留信学历认证
1:1原版定制利物浦大学毕业证(Liverpool毕业证)成绩单学位证书留信学历认证1:1原版定制利物浦大学毕业证(Liverpool毕业证)成绩单学位证书留信学历认证
1:1原版定制利物浦大学毕业证(Liverpool毕业证)成绩单学位证书留信学历认证
ppy8zfkfm
 
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
zifhagzkk
 
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
jk0tkvfv
 
Audience Researchndfhcvnfgvgbhujhgfv.pptx
Audience Researchndfhcvnfgvgbhujhgfv.pptxAudience Researchndfhcvnfgvgbhujhgfv.pptx
Audience Researchndfhcvnfgvgbhujhgfv.pptx
Stephen266013
 
1:1原版定制伦敦政治经济学院毕业证(LSE毕业证)成绩单学位证书留信学历认证
1:1原版定制伦敦政治经济学院毕业证(LSE毕业证)成绩单学位证书留信学历认证1:1原版定制伦敦政治经济学院毕业证(LSE毕业证)成绩单学位证书留信学历认证
1:1原版定制伦敦政治经济学院毕业证(LSE毕业证)成绩单学位证书留信学历认证
dq9vz1isj
 
如何办理(UPenn毕业证书)宾夕法尼亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UPenn毕业证书)宾夕法尼亚大学毕业证成绩单本科硕士学位证留信学历认证如何办理(UPenn毕业证书)宾夕法尼亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UPenn毕业证书)宾夕法尼亚大学毕业证成绩单本科硕士学位证留信学历认证
acoha1
 
NO1 Best Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialist I...
NO1 Best Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialist I...NO1 Best Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialist I...
NO1 Best Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialist I...
Amil baba
 
obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...
obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...
obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...
yulianti213969
 

Recently uploaded (20)

MATERI MANAJEMEN OF PENYAKIT TETANUS.ppt
MATERI  MANAJEMEN OF PENYAKIT TETANUS.pptMATERI  MANAJEMEN OF PENYAKIT TETANUS.ppt
MATERI MANAJEMEN OF PENYAKIT TETANUS.ppt
 
obat aborsi Bontang wa 081336238223 jual obat aborsi cytotec asli di Bontang6...
obat aborsi Bontang wa 081336238223 jual obat aborsi cytotec asli di Bontang6...obat aborsi Bontang wa 081336238223 jual obat aborsi cytotec asli di Bontang6...
obat aborsi Bontang wa 081336238223 jual obat aborsi cytotec asli di Bontang6...
 
一比一原版(ucla文凭证书)加州大学洛杉矶分校毕业证学历认证官方成绩单
一比一原版(ucla文凭证书)加州大学洛杉矶分校毕业证学历认证官方成绩单一比一原版(ucla文凭证书)加州大学洛杉矶分校毕业证学历认证官方成绩单
一比一原版(ucla文凭证书)加州大学洛杉矶分校毕业证学历认证官方成绩单
 
What is Insertion Sort. Its basic information
What is Insertion Sort. Its basic informationWhat is Insertion Sort. Its basic information
What is Insertion Sort. Its basic information
 
Formulas dax para power bI de microsoft.pdf
Formulas dax para power bI de microsoft.pdfFormulas dax para power bI de microsoft.pdf
Formulas dax para power bI de microsoft.pdf
 
Statistics Informed Decisions Using Data 5th edition by Michael Sullivan solu...
Statistics Informed Decisions Using Data 5th edition by Michael Sullivan solu...Statistics Informed Decisions Using Data 5th edition by Michael Sullivan solu...
Statistics Informed Decisions Using Data 5th edition by Michael Sullivan solu...
 
原件一样伦敦国王学院毕业证成绩单留信学历认证
原件一样伦敦国王学院毕业证成绩单留信学历认证原件一样伦敦国王学院毕业证成绩单留信学历认证
原件一样伦敦国王学院毕业证成绩单留信学历认证
 
Jual Obat Aborsi Bandung (Asli No.1) Wa 082134680322 Klinik Obat Penggugur Ka...
Jual Obat Aborsi Bandung (Asli No.1) Wa 082134680322 Klinik Obat Penggugur Ka...Jual Obat Aborsi Bandung (Asli No.1) Wa 082134680322 Klinik Obat Penggugur Ka...
Jual Obat Aborsi Bandung (Asli No.1) Wa 082134680322 Klinik Obat Penggugur Ka...
 
1:1原版定制利物浦大学毕业证(Liverpool毕业证)成绩单学位证书留信学历认证
1:1原版定制利物浦大学毕业证(Liverpool毕业证)成绩单学位证书留信学历认证1:1原版定制利物浦大学毕业证(Liverpool毕业证)成绩单学位证书留信学历认证
1:1原版定制利物浦大学毕业证(Liverpool毕业证)成绩单学位证书留信学历认证
 
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
 
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
 
Audience Researchndfhcvnfgvgbhujhgfv.pptx
Audience Researchndfhcvnfgvgbhujhgfv.pptxAudience Researchndfhcvnfgvgbhujhgfv.pptx
Audience Researchndfhcvnfgvgbhujhgfv.pptx
 
1:1原版定制伦敦政治经济学院毕业证(LSE毕业证)成绩单学位证书留信学历认证
1:1原版定制伦敦政治经济学院毕业证(LSE毕业证)成绩单学位证书留信学历认证1:1原版定制伦敦政治经济学院毕业证(LSE毕业证)成绩单学位证书留信学历认证
1:1原版定制伦敦政治经济学院毕业证(LSE毕业证)成绩单学位证书留信学历认证
 
Seven tools of quality control.slideshare
Seven tools of quality control.slideshareSeven tools of quality control.slideshare
Seven tools of quality control.slideshare
 
Predictive Precipitation: Advanced Rain Forecasting Techniques
Predictive Precipitation: Advanced Rain Forecasting TechniquesPredictive Precipitation: Advanced Rain Forecasting Techniques
Predictive Precipitation: Advanced Rain Forecasting Techniques
 
The Significance of Transliteration Enhancing
The Significance of Transliteration EnhancingThe Significance of Transliteration Enhancing
The Significance of Transliteration Enhancing
 
如何办理(UPenn毕业证书)宾夕法尼亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UPenn毕业证书)宾夕法尼亚大学毕业证成绩单本科硕士学位证留信学历认证如何办理(UPenn毕业证书)宾夕法尼亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UPenn毕业证书)宾夕法尼亚大学毕业证成绩单本科硕士学位证留信学历认证
 
NO1 Best Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialist I...
NO1 Best Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialist I...NO1 Best Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialist I...
NO1 Best Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialist I...
 
Bios of leading Astrologers & Researchers
Bios of leading Astrologers & ResearchersBios of leading Astrologers & Researchers
Bios of leading Astrologers & Researchers
 
obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...
obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...
obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...
 

Detailed.pptx

  • 1. C. Scope  To review the existing study reports, standards and specifications.  Detailed engineering survey of alignment.  Preparation of topographical map.  Study for cross-drainage works and propose suitable drainage structure.
  • 2.  Preparation of working drawings.  Preparation of quantity and cost estimate.  Preparation of survey and design report
  • 3. D. Project location  The proposed road is located in the Lalitpur District, Bagmati Zone, Central Region. The road starts from Badikhel and ends at Badegaun.  The road runs along Karmanasha River corridor.  The latitude and the longitude of the starting point are 27057’07’’ and 85035’27’’ respectively.
  • 4. F. Hydrology And Meteorology  Small temporary streams running only during monsoon crosses the alignment with small discharge.  The project area experiences marked seasonal and specific climate variation with moderately hot summer and relatively cool winters. Average temperature is 25oC in summer and 10oC in winter.  Almost 80% of the rainfall occurs during monsoon which starts at the middle of the June and continues until the end of August.
  • 5. METHODOLOGY  DESK STUDY  SOCIAL IMPACT ASSESMENT  FIELD WORK  EQUIPMENT USED FOR SURVEYING  OFFICE WORK
  • 6. DESK STUDY  The geographical and the topographical maps were studied and the relevant information regarding the alignment selection, cross drainage structures, gradient of the road were discussed.  The strategy for the field study was made accordingly.  The study team member discussed the related matters of the project.
  • 7. SOCIAL IMPACT ASSESMENT The study identified the following key social issues for investigation:  Loss of private property and other assets (land, houses and trees) and compensation modalities for these losses.  Population displacement.
  • 8.  EQUIPMENT USED FOR SURVEYING  Total station  GPS device  Staff  Compass  Measuring tape  Hammer  Communicating Device
  • 10. Road Classification  As per the NRS 2045, the road project falls on the category of District Roads.
  • 11.  A Design speed of 30 km/hr is taken for the design of geometric parameters of the road. Design Speed
  • 12.  The Design values are taken as recommended by NRS 2045 as far as practicable  The shoulder width is taken as 1 m considering the site condition and the utility of the road  Minimum Gradient recommended by NRS (1% for better drainage) cannot be incorporated considering the site condition
  • 13. Horizontal Alignment  The most suitable horizontal alignment was selected considering the following factors:  Short (S)  Easy (E)  Safe (S)  Economical (E)  Minimum radius for the horizontal curve as recommended by NRS is 12 m. The minimum radius of 12m is provided at the intersection of existing road and proposed road.
  • 14.  The extrawidening and transition curves are not provided owing to low design speed and simplicity in construction  A maximum of 5 % super elevation is provided at each horizontal curve.  Superelevation is provided by rotation of pavement about the center line.  Transition length for super elevation is provided as 5 m
  • 15.  Summit curves are designed considering stopping sight distance.  Valley curves are designed on the basis of night visibility  The radius of vertical curve is adopted as large as possible so that all the factors are satisfied  The least vertical radius taken in design is 1000 m
  • 16. Cross Section Design  Cross section is designed providing camber of 4% on carriageway and 5 % on shoulder  For embankment the side slope of 1.5H: 1V and for cut the side slope of 1H: 1V is adopted  Total pavement thickness of 28 cm is adopted as per CBR method of design
  • 17.  Gravel is used as the sub-base course  Otta Seal is used as the surface course
  • 18. Drainage  Longitudinal drain is provided on the cut slope side of the road  The side slope is 1:1 and longitudinal slope is parallel to the alignment  Earthen drain is provided from chainage 0+000 to the chainage of 1+251.35  Stoned masonry drain of thickness 20 cm is provided from the chainage of 1+309.82 to chainage 2+027.24
  • 19.  Pipe culverts of 60 cm in diameter and total length of 7.5m are provided at 12 sections of the road  They are provided at the lowest point of the vertical alignment  A minimum depth of 60 cm is provided between the surface of the pavement and the crown of the pipe
  • 20. Plan and Profile  Ch. 0+000-0+200  Ch. 0+200-0+480  Ch. 0+480-0+760  Ch. 0+760-1+040  Ch. 1+040-1+360  Ch. 1+360-1+700  Ch. 1+700-2+027.24
  • 21. Cross Section  Ch. 0+000-0+271.50  Ch. 0+280-0+500  Ch. 0+511.92-0+680  Ch. 0+683.87-0+760  Ch. 0+780-0+920  Ch. 0+936.71-1+125.89  Ch. 1+130.75-1+213.66  Ch.1+220-1+319.59  Ch.1+320-1+380  Ch.1+397.04-1+465.09  Ch.1+480-1+545.77  Ch.1+560-1+800  Ch.1+800.91-1+980  Ch.1+984.58-2+027.24
  • 23. ESTIMATE Quantity Estimate Calculation of Earthwork Necessary Calculations Rate Analysis BoQ /Cost Estimate
  • 24. QUANTITY ESTIMATE  Earthwork Calculations:  Calculated at each cross-section  Separate calculation according to soil type  Total cut volume = 10283.57 m3  Total fill volume = 16052.44 m3  Balance (fill) = 5768.869 m3  Earthwork for drain = 768.129 m3 All the detailed calculation is shown in the tabular form in the following slides:
  • 25. Contd………  Necessary calculations: i. For side drain: Calculations were made taking the following design considerations:  Section = trapezoidal  Depth: 0.3m  Base width: 0.3m  Side slope: 1:1  Unlined earthen canal(Ch. 0+000 to 1251.35)  Lined canal: (ch.1+309.82 to Ch. 2+027.24) ii. Sub-grade calculations:
  • 26. RATE ANALYSIS  Rate analysis was performed under the following criteria:  The quantity of the materials, required labor force and plants, machinery, tools and equipments were taken from the work norms provided by the DoR.  The rate for the materials, labors, plants and machinery, tools and equipments was taken from the district rates provided by the Lalitpur DDC.
  • 27. COST ESTIMATE  The BoQ was prepared on the basis of the quantity of work calculated and rate analysis done previously:  The cost estimate is as below: