Civilverse Admin 10 July 2021
All About Construction Labour Planning- Excel
Template
civilverse.org/construction-labour-planning
Table of Contents for Construction Labour Planning- Excel
1. Introduction
2. Need of Construction Labour Planning
3. Steps for Construction Labour Planning
4. Measurement of Construction Labour Productivity
5. Download Construction Labour Planning Excel
6. Attrition Rate Consideration
7. Cost Consideration
8. Conclusion
Labour Calculator Excel Template- Download the excel file below on this page
1. Introduction
The construction activities are getting lean day by day. The construction manpower needs
to be planned for each type of activity to ensure maximum utilization. This will save time
and cost. The quality is also controlled by deploying skilled manpower to the job.
The construction sector is one of the biggest employers in the world. As per a 2014 report,
the construction sector employs 8.6% of the total employees across the world. Another
report indicates, India had 40 million construction sector jobs in 2013 & expected to grow
2/5
to 67 Million by 2022. With the increasing construction activities, the need for skilled
manpower will be more than ever.
In this article, I will guide you through the construction labour planning process. Starting
with the need for labour planning, moving ahead with steps for construction manpower
planning, measurement of productivity, the construction manpower planning template,
attrition rate and the cost consideration. The article will be concluded with the final
remarks on the various points explained.
2. Need of Construction Labour Planning
The construction projects operate under scope, time and cost constraints. Labour
productivity is one of the key factors governing time & cost. The time taken by an activity
is inversely proportional to the productivity of labour with a lower limit on minimum
time. The labour cost is 30-50% of the total project cost (for my current project it comes
around 35%).
The construction manpower planning has helped me ensuring the following aspects for
my projects-
a. Reduction in labour cost hence the overall project cost.
b. Better quality of work.
c. Timely completion of job, thus lesser delays, EOTs and delay claims etc.
d. Better supervision of labour.
e. Development of phase wise labour mobilization/demobilization plan.
f. Labour accommodation facility development.
3/5
g. Cash flow requirement generation for wages, incentives, food, etc.
The advantages of construction manpower planning are project-specific and depend upon
the contract type. However, the multiple benefits can’t be ignored. The advantages also
depend upon the efficiency of planning and its’ implementation.
3. Steps of Construction Labour Planning
The construction labour planning is done in conjugation with the project schedule
development. The duration for an activity is estimated based on either of these methods.
Considering the work to be done, the complexity of the job and the labour productivity the
duration can also be estimated.
The below-stated points summarize the complete process of construction labour planning.
Collection of Inputs- The input for construction manpower planning are the
types of activities, work quantities, required skills and experience of labours,
productivity standards, tentative project timeline, deadlines for the project and
organizational template, if any.
Assessment of Manpower Requirement- The manpower requirement is
assessed from the historical data of previous projects of similar nature. If such data
is unavailable, the calculations are to be made. The formula for the per day
manpower calculation is-
Sorting & Grouping- The manpower required for each of the activity is sorted as
per their category i.e., carpenter, mason, fitter, welder, helper etc. Each category
man-days are summed up.
Plotting of Man-days on Project Timeline- Category wise man-days are
plotted against the project timeline. The daily category wise requirement of
manpower is be ascertained in this step.
Manpower Levelling- The requirement of manpower for some days can be higher
than other days. Hence, it is not possible to mobilize/demobilize the manpower so
quickly. Thus, problem is tackled by preponing or postponing the non-critical
activities as such that the daily demand becomes more or less same.
Preparation of Mobilization Plan- The mobilization plan is prepared for the
week / month. The levelled manpower is arranged to be mobilized to the site in
batches as per the calculated requirement.
5. Measurement of Construction Labour Productivity
The construction labour productivity measurement is essential to monitor and control the
progress. The productivity measurement ensures if the desired output is being achieved.
If not, the corrective actions need to be implemented.
4/5
The productivity measurement is a ratio of output to input.
The output is the work done per day and the input is the number of man-days consumed
to complete the work.
The unit of productivity is the work unit per day. The work units for different types of
works are different. The concrete poured is measured in cubic-meter, shuttering in
square-meter, excavation in cubic-meter, reinforcement bars tying in kg or MT, 9” thick
brickwork in cubic-meter, 4.5” thick brickwork in square-meter etc.
6. Construction Labour Planning Excel
The construction labour planning Excel sheet attached herewith helps calculate the labour
required for the day. The various types of works like shuttering, concrete pouring,
reinforcement cutting-bending & tying, blockwork, plaster and tiling are covered. Each
type of work has been detailed into various forms like foundation, columns, beams,
soffits, slabs etc.
The input required for the construction labour calculation by the sheet is work quantity
for the day and the working hours per day. The sheet calculates the labours and divides
them into the category.
Download Labour Calculator Excel
7. Attrition Rate Consideration
The attrition rate is the turnover rate. Out of all the labourers mobilized at the site, some
do not stay back and work. There might be several reasons for them returning. Thus, the
turnover can lead to a shortfall of manpower at work and hence delay in work as they
cannot be replaced immediately (especially skilled labour).
A suitable attrition rate should be considered while mobilizing the manpower. The
labours should be mobilized in excess as per the attrition rate. For example, if 100 Nos.
manpower is required for the work and the attrition rate is 10%, the mobilization plan
should be for 110 Nos. (100 + 100 x 10%) manpower.
The formula to calculate the attrition rate is as follows-
5/5
The attrition rate depends upon various factors. For my current project, the attrition rate
is as high as 10% for the week and 25% for the month. This means 10% of the mobilized
labour return within a week and 25% labourers return within a month. The high attrition
is due to extreme weather, remote location, the higher price of commodities in the local
market, connectivity, etc.
8. Cost Consideration
The cost involved in the labour aspect depends upon the contractual terms. For unit rate
contract & lump sum contract, the client doesn’t have to worry about the labour wage, he
only has to pay for as per the work executed. The contractor pays the wage or he can
further sub-contract the work. For time & material contract, cost-plus contract and target
cost contract, the client pays for the labour as per the usage.
The additional costs that are incurred other than the wages are the labour
accommodation, transportation charges, insurances, workers’ license, food, incentives,
additional allowances, bonus etc. The scope for these costs is also mentioned in the
contract.
9. Conclusion
Construction labour planning has proved to be an essential and critical step in project
planning. The over-estimates lead to additional cost and the lower estimates cause delay
to the project. It is a key challenge for the estimator to maintain a perfect balance for
manpower estimation.
The attrition rate for the manpower should be suitably adopted. Historical data for the
similar nature of projects in the nearby locations of the project can be referred to for
better estimates. Too high or too low assumptions shows the inability of the team to find
the balance.
The direct and indirect costs for manpower are to be considered in the contract. For
lump-sum and unit price contracts, the indirect costs should be covered in prices.
Liked the article? Share your thoughts in the comments. Also, let me know your insights.
Happy Engineering!

More Related Content

What's hot

3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity SSudhaVelan
 
Construction account management_Construction Management (2180611) (Semester-8...
Construction account management_Construction Management (2180611) (Semester-8...Construction account management_Construction Management (2180611) (Semester-8...
Construction account management_Construction Management (2180611) (Semester-8...A Makwana
 
Project organization_Construction Management (2180611) (Semester-8), Civil En...
Project organization_Construction Management (2180611) (Semester-8), Civil En...Project organization_Construction Management (2180611) (Semester-8), Civil En...
Project organization_Construction Management (2180611) (Semester-8), Civil En...A Makwana
 
Manpower planning for a construction company
Manpower planning for a construction companyManpower planning for a construction company
Manpower planning for a construction companyRevati Bargale
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineeringKailash Chander
 
What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...SANJEEV Wazir
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line methodmalang1214
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPSagar Kaptan
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
Construction Productivity
Construction ProductivityConstruction Productivity
Construction ProductivitySunil Manjeri
 
Construction site supervision aalecture one.
Construction site supervision aalecture one.Construction site supervision aalecture one.
Construction site supervision aalecture one.Gebeyehu Worku
 
Construction labor
Construction laborConstruction labor
Construction laborArun Kumar
 
Site organization and networking techniques
Site organization and networking techniquesSite organization and networking techniques
Site organization and networking techniquestivar rose
 
Introduction to Lean Construction
Introduction to Lean ConstructionIntroduction to Lean Construction
Introduction to Lean ConstructionVedzen Consultants
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2ArunRavi43
 

What's hot (20)

3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Schedule-Delay Analysis
Schedule-Delay AnalysisSchedule-Delay Analysis
Schedule-Delay Analysis
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
 
Construction account management_Construction Management (2180611) (Semester-8...
Construction account management_Construction Management (2180611) (Semester-8...Construction account management_Construction Management (2180611) (Semester-8...
Construction account management_Construction Management (2180611) (Semester-8...
 
Project organization_Construction Management (2180611) (Semester-8), Civil En...
Project organization_Construction Management (2180611) (Semester-8), Civil En...Project organization_Construction Management (2180611) (Semester-8), Civil En...
Project organization_Construction Management (2180611) (Semester-8), Civil En...
 
Manpower planning for a construction company
Manpower planning for a construction companyManpower planning for a construction company
Manpower planning for a construction company
 
Labor management at construction site
Labor management at construction siteLabor management at construction site
Labor management at construction site
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Construction Productivity
Construction ProductivityConstruction Productivity
Construction Productivity
 
Estimatingandcosting
EstimatingandcostingEstimatingandcosting
Estimatingandcosting
 
Construction site supervision aalecture one.
Construction site supervision aalecture one.Construction site supervision aalecture one.
Construction site supervision aalecture one.
 
Construction labor
Construction laborConstruction labor
Construction labor
 
Site organization and networking techniques
Site organization and networking techniquesSite organization and networking techniques
Site organization and networking techniques
 
Introduction to Lean Construction
Introduction to Lean ConstructionIntroduction to Lean Construction
Introduction to Lean Construction
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
 

Similar to All About Construction Labour Planning- Excel Template

Evaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysisEvaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysiseSAT Publishing House
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementIRJET Journal
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
Introduction of civil engineering.pdf
Introduction of civil engineering.pdfIntroduction of civil engineering.pdf
Introduction of civil engineering.pdfbkbk37
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET Journal
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to EstimationMuthanna Abbu
 
Industrial Engineering & Operation Research Lecture Notes
Industrial Engineering & Operation Research Lecture NotesIndustrial Engineering & Operation Research Lecture Notes
Industrial Engineering & Operation Research Lecture NotesFellowBuddy.com
 
Resource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction ProjectResource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction ProjectIRJET Journal
 
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECTEARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECTIAEME Publication
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction projectIAEME Publication
 
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...IRJET Journal
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IRJET Journal
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIRJET Journal
 
ACHAL_JOSHI_Academic_Profile
ACHAL_JOSHI_Academic_ProfileACHAL_JOSHI_Academic_Profile
ACHAL_JOSHI_Academic_ProfileACHAL JOSHI
 

Similar to All About Construction Labour Planning- Excel Template (20)

Evaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysisEvaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysis
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
H1303055462
H1303055462H1303055462
H1303055462
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Introduction of civil engineering.pdf
Introduction of civil engineering.pdfIntroduction of civil engineering.pdf
Introduction of civil engineering.pdf
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Workforce planning model
Workforce planning modelWorkforce planning model
Workforce planning model
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
H1303024956
H1303024956H1303024956
H1303024956
 
Industrial Engineering & Operation Research Lecture Notes
Industrial Engineering & Operation Research Lecture NotesIndustrial Engineering & Operation Research Lecture Notes
Industrial Engineering & Operation Research Lecture Notes
 
Resource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction ProjectResource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction Project
 
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECTEARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 
3 estimate considerations
3 estimate considerations3 estimate considerations
3 estimate considerations
 
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
ACHAL_JOSHI_Academic_Profile
ACHAL_JOSHI_Academic_ProfileACHAL_JOSHI_Academic_Profile
ACHAL_JOSHI_Academic_Profile
 

More from SHAZEBALIKHAN1

Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them TooSHAZEBALIKHAN1
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowSHAZEBALIKHAN1
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateSHAZEBALIKHAN1
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction WorksSHAZEBALIKHAN1
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil EngineersSHAZEBALIKHAN1
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingSHAZEBALIKHAN1
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileSHAZEBALIKHAN1
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims EffectivelySHAZEBALIKHAN1
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsSHAZEBALIKHAN1
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteSHAZEBALIKHAN1
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksSHAZEBALIKHAN1
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepSHAZEBALIKHAN1
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckSHAZEBALIKHAN1
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract ManagementSHAZEBALIKHAN1
 

More from SHAZEBALIKHAN1 (20)

Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should Know
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel Template
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel file
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling Factors
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at Site
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and Deep
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract Management
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 

All About Construction Labour Planning- Excel Template

  • 1. 1/5 Civilverse Admin 10 July 2021 All About Construction Labour Planning- Excel Template civilverse.org/construction-labour-planning Table of Contents for Construction Labour Planning- Excel 1. Introduction 2. Need of Construction Labour Planning 3. Steps for Construction Labour Planning 4. Measurement of Construction Labour Productivity 5. Download Construction Labour Planning Excel 6. Attrition Rate Consideration 7. Cost Consideration 8. Conclusion Labour Calculator Excel Template- Download the excel file below on this page 1. Introduction The construction activities are getting lean day by day. The construction manpower needs to be planned for each type of activity to ensure maximum utilization. This will save time and cost. The quality is also controlled by deploying skilled manpower to the job. The construction sector is one of the biggest employers in the world. As per a 2014 report, the construction sector employs 8.6% of the total employees across the world. Another report indicates, India had 40 million construction sector jobs in 2013 & expected to grow
  • 2. 2/5 to 67 Million by 2022. With the increasing construction activities, the need for skilled manpower will be more than ever. In this article, I will guide you through the construction labour planning process. Starting with the need for labour planning, moving ahead with steps for construction manpower planning, measurement of productivity, the construction manpower planning template, attrition rate and the cost consideration. The article will be concluded with the final remarks on the various points explained. 2. Need of Construction Labour Planning The construction projects operate under scope, time and cost constraints. Labour productivity is one of the key factors governing time & cost. The time taken by an activity is inversely proportional to the productivity of labour with a lower limit on minimum time. The labour cost is 30-50% of the total project cost (for my current project it comes around 35%). The construction manpower planning has helped me ensuring the following aspects for my projects- a. Reduction in labour cost hence the overall project cost. b. Better quality of work. c. Timely completion of job, thus lesser delays, EOTs and delay claims etc. d. Better supervision of labour. e. Development of phase wise labour mobilization/demobilization plan. f. Labour accommodation facility development.
  • 3. 3/5 g. Cash flow requirement generation for wages, incentives, food, etc. The advantages of construction manpower planning are project-specific and depend upon the contract type. However, the multiple benefits can’t be ignored. The advantages also depend upon the efficiency of planning and its’ implementation. 3. Steps of Construction Labour Planning The construction labour planning is done in conjugation with the project schedule development. The duration for an activity is estimated based on either of these methods. Considering the work to be done, the complexity of the job and the labour productivity the duration can also be estimated. The below-stated points summarize the complete process of construction labour planning. Collection of Inputs- The input for construction manpower planning are the types of activities, work quantities, required skills and experience of labours, productivity standards, tentative project timeline, deadlines for the project and organizational template, if any. Assessment of Manpower Requirement- The manpower requirement is assessed from the historical data of previous projects of similar nature. If such data is unavailable, the calculations are to be made. The formula for the per day manpower calculation is- Sorting & Grouping- The manpower required for each of the activity is sorted as per their category i.e., carpenter, mason, fitter, welder, helper etc. Each category man-days are summed up. Plotting of Man-days on Project Timeline- Category wise man-days are plotted against the project timeline. The daily category wise requirement of manpower is be ascertained in this step. Manpower Levelling- The requirement of manpower for some days can be higher than other days. Hence, it is not possible to mobilize/demobilize the manpower so quickly. Thus, problem is tackled by preponing or postponing the non-critical activities as such that the daily demand becomes more or less same. Preparation of Mobilization Plan- The mobilization plan is prepared for the week / month. The levelled manpower is arranged to be mobilized to the site in batches as per the calculated requirement. 5. Measurement of Construction Labour Productivity The construction labour productivity measurement is essential to monitor and control the progress. The productivity measurement ensures if the desired output is being achieved. If not, the corrective actions need to be implemented.
  • 4. 4/5 The productivity measurement is a ratio of output to input. The output is the work done per day and the input is the number of man-days consumed to complete the work. The unit of productivity is the work unit per day. The work units for different types of works are different. The concrete poured is measured in cubic-meter, shuttering in square-meter, excavation in cubic-meter, reinforcement bars tying in kg or MT, 9” thick brickwork in cubic-meter, 4.5” thick brickwork in square-meter etc. 6. Construction Labour Planning Excel The construction labour planning Excel sheet attached herewith helps calculate the labour required for the day. The various types of works like shuttering, concrete pouring, reinforcement cutting-bending & tying, blockwork, plaster and tiling are covered. Each type of work has been detailed into various forms like foundation, columns, beams, soffits, slabs etc. The input required for the construction labour calculation by the sheet is work quantity for the day and the working hours per day. The sheet calculates the labours and divides them into the category. Download Labour Calculator Excel 7. Attrition Rate Consideration The attrition rate is the turnover rate. Out of all the labourers mobilized at the site, some do not stay back and work. There might be several reasons for them returning. Thus, the turnover can lead to a shortfall of manpower at work and hence delay in work as they cannot be replaced immediately (especially skilled labour). A suitable attrition rate should be considered while mobilizing the manpower. The labours should be mobilized in excess as per the attrition rate. For example, if 100 Nos. manpower is required for the work and the attrition rate is 10%, the mobilization plan should be for 110 Nos. (100 + 100 x 10%) manpower. The formula to calculate the attrition rate is as follows-
  • 5. 5/5 The attrition rate depends upon various factors. For my current project, the attrition rate is as high as 10% for the week and 25% for the month. This means 10% of the mobilized labour return within a week and 25% labourers return within a month. The high attrition is due to extreme weather, remote location, the higher price of commodities in the local market, connectivity, etc. 8. Cost Consideration The cost involved in the labour aspect depends upon the contractual terms. For unit rate contract & lump sum contract, the client doesn’t have to worry about the labour wage, he only has to pay for as per the work executed. The contractor pays the wage or he can further sub-contract the work. For time & material contract, cost-plus contract and target cost contract, the client pays for the labour as per the usage. The additional costs that are incurred other than the wages are the labour accommodation, transportation charges, insurances, workers’ license, food, incentives, additional allowances, bonus etc. The scope for these costs is also mentioned in the contract. 9. Conclusion Construction labour planning has proved to be an essential and critical step in project planning. The over-estimates lead to additional cost and the lower estimates cause delay to the project. It is a key challenge for the estimator to maintain a perfect balance for manpower estimation. The attrition rate for the manpower should be suitably adopted. Historical data for the similar nature of projects in the nearby locations of the project can be referred to for better estimates. Too high or too low assumptions shows the inability of the team to find the balance. The direct and indirect costs for manpower are to be considered in the contract. For lump-sum and unit price contracts, the indirect costs should be covered in prices. Liked the article? Share your thoughts in the comments. Also, let me know your insights. Happy Engineering!