1. Schedule
2014 2015
Jan Feb Mar Apl May June July Aug Sept Oct Nov Dec Jan Feb Mar Apl May June July Aug Sept Oct Nov Dec
ORIGINAL CONTRACT DURATION ( 514 DAYS)
As- Planned
Schedule
As- Built
Schedule
As- Built but
for Schedule
ACTUAL DURATION AT COMPLETION( 698 DAYS)
ACTUAL DURATION AT COMPLETION( 698 DAYS)
TOTAL 184 DAYS ACTUAL DELAYS
EXCUSABLE + NON EXECUSABLE DELAY
ACTUAL DURATION AT COMPLETION( 698 DAYS)
As- Built but
for Schedule
Excusable
Delay
Non- Excusable
Delay
61 DAYS 123 DAYS
Liquidated
Damages
Non-Compensable
Delay
Compensable
Delay
Claim Analysis
SCHEMATIC DIAGRAM OF SCHEDULE AND DELAYANALYSIS
DELAYS