SlideShare a Scribd company logo
1 of 13
Labour Productivity Measurement for
Construction Projects
By Kapuganti Jagannadha Gupta
BE, MBA, PMP, CCE
Building C Super
Sructure
Productivity
What is Labour Productivity?
Productivity = Output / Input
(Earned hours / Worked hours)
Examples:
• Kilograms of rebar fixed per manday
• Cu.m Concrete poured per manday
• Sq.m of formwork placed per manday
• Sq.m of block laid per manday
• Sq.m of tiles laid per manday
Building C Super
Sructure
Why Measure Productivity?
• You Can’t Correct a problem if you don’t know it exists
• By the time the job is over, you have lost the more
• You will have current information to manage and control
your project
• You should correct losses arising from internal problems
• You may be able to recover losses arising from external
causes.
•Extremely vital performance measurement tool within the
construction industry
•Productivity growth is important to an individual
enterprise, an industry or an economy
Building C Super
Sructure
Common causes of labour overruns
External:
• Overtime
• Changes
• Crowding
• Trade stacking
• Weather
• Site Access
Internal:
• Poor Planning & Management of
work
• Rework & Errors
• Bad Estimate
• Lack of Training
• Morale Problems
• Staff turnover
• Material and equipment availability
Building C Super
Sructure
Themes for Productivity Improvement
• Consistent Practices
• Process versus Results Management
• Consistent Procedures and Practices
• Proactive versus Reactive Management
• Measurement and Analysis of a defect
• Risk or Variation Analysis
• Vital Few versus Useful Many
• Planning Versus Reacting
• Focus on Quality first
• Pride and a Positive Attitude
Building C Super
Sructure
Methodology and Data Collection
• Daily activity form sheet will be distributed to concerned site engineer
•Site engineer will assign works to foreman, each foreman will fill the data in form.
•The contents in the form majorly covering:
•The quantity of activity completed for the activity being carried out
•The quantity of skilled & unskilled used to complete the activity
•End of each shift these forms are collected by Productivity Engineer and compiles
the information and generates reports e.g. building wise trade wise, etc.
• Generally monitoring major works like Steel, Formwork, Concrete, Block, Tiles etc.
•From the above reports are very useful to site management to take necessary
corrective action to improve productivity wherever necessary
Building C Super
Sructure
Methodology and Data Collection
Validating the progress at site on daily basis in micro level monitoring
DAY WORK SHEET
DAILY ACTIVITY REPORT
SECTION ENGINEER FORM
Sl.No WORK TASK DESCRIPTION BUILDING LEVEL
SUB-
ZONE
TRADE
WORKDONE NO OF MEN
QTY. UNITS DAY NIGHT
1
2
3
4
5
6
7
8
9
10
TOTAL: 0 0
REASON
FOR
WORK:
SCOPE OF
WORKS
REWORKS VARIATIONS IDLE TIME
FOREMAN NAME & SIGNATURE: DATE SUPERVISOR / ENGINEER NAME & Signature DATE:
Building C Super
Sructure
Productivity Rates
1. Productivity Rates for Structure works
Description
Planned Productivity
Rebar
(Kg/Manday)
Shutter
(m2/Manday)
Concrete
(m3/Manday)
Retaining Wall 300 4.00 5.00
Watertank Wall 300 5.00 5.00
Core Wall 300 7.00 8.00
Raft 380 7.00 15.00
Slab (Conventional) 150 7.00 10.00
Slab (PT) 100 10.00 10.00
Beam 250 7.00 8.00
Column 250 7.00 5.00
Ramp 250 8.00 8.00
Staircase 100 3.00 5.00
2. Productivity Rates for Finishing works
Description of work
Planned
Productivity
(m2/Manday)
Water Proofing - Horizontal 25.00
Water Proofing - Vertical 15.00
Protection Screed 10.00
Blockwork 7.00
Wall tiles 5.00
Floor tiles 8.00
Plaster(Wall) 10.00
Staircase tiles 5.00
Staircase Plaster 8.00
Ceiling Plaster 5.00
Building C Super
Sructure
Total Quantities – Concrete Works
Structural Works
Level Rebar (KG) Shutter (m2)
Concrete
(m3)
Planned
Productivity
(MD/Cu.m)
Mandays to
Complete
Basement - 3 7,553,230 27,245 28,251 2.5 70,628
Basement - 2 1,821,000 26,747 7,202 2.5 18,005
Basement - 1 2,615,000 30,285 9,093 2.5 22,733
Building - A 2,506,000 60,539 16,135 2.5 40,338
Building - B 2,408,000 51,804 13,610 2.5 34,025
Building - C 945,000 25,472 5,412 2.5 13,530
Building - D 2,257,000 54,546 13,121 2.5 32,803
Total 20,105,230 276,638 92,824 2.5 232,060
Structural Works for a Single Level
Level
Sub-
Zones
Rebar
(KG)
Shutter
(m2)
Concrete
(m3)
Planned
Productivity
(MD/Cu.m)
Mandays to
Complete
Level - 1
A-1 140,643 2,782 665 2.5 1,663
A-2 133,652 2,225 599 3.5 2,097
B-1 132,000 2,521 605 4.5 2,723
B-2 128,000 2,264 529 5.5 2,910
C 120,000 2,625 538 6.5 3,497
D-1 159,000 2,887 557 7.5 4,178
D-2 81,000 1,512 341 8.5 2,899
Building C Super
Sructure
Total Quantities - Finishes
Finishing Works
Description
of work
Unit
Quantities
Basement Building A
Building
B
Building C Building D
Total
Quantity
Planned Avg
Productivity
(Unit/Md)
Planned
Man Days
Blockwork m2 9,468 53,276 46,859 7,496 36,597 153,696 7 21,957
Plastering m2 72,797 64,448 6,205 50,006 193,456 9 21,495
Ceiling m2 537 7,918 13,736 2,416 13,736 38,343 5 7,669
Tile m2 622 48,380 42,960 5,281 42,960 140,203 7 20,029
Stone m2 350 3,756 3,663 2,338 4,534 14,641 7 2,092
Doors Nos 125 1,955 1,695 318 431 4,524 2 2,262
Building C Super
Sructure
Current Status – Concrete Works
Level/
Building
Planned Actual (As of Date)
Rebar (KG) Shutter (m2)
Concrete
(m3)
Planned
Productivity
Mandays to
Complete
Rebar (KG)
Shutter
(m2)
Concrete
(m3)
Mandays Productivity
Basement - 3 7,553,230 27,245 28,251 2.5 70,628 7,553,230 26,245 27,853 69,472 2.49
Basement - 2 1,821,000 26,747 7,202 2.5 18,005 1,343,000 21,117 7,202 31,096 4.32
Basement - 1 2,615,000 30,285 9,093 2.5 22,733 1,923,000 18,466 6,821 34,285 5.03
Building - A 2,506,000 60,539 16,135 2.5 40,338 781,000 25,630 3,653 19,249 5.27
Building - B 2,408,000 51,804 13,610 2.5 34,025 524,000 15,078 2,218 10,897 4.91
Building - C 945,000 25,472 5,412 2.5 13,530
Building - D 2,257,000 54,546 13,121 2.5 32,803 225,000 4,200 856 4,051 4.73
Total 20,105,230 276,638 92,824 2.5 232,060
12,349,23
0
110,736 48,603 169,050 3.48
% of Work Completed 52.36%
Actual Man Days 169,050
Earned Mandays 121,508
Loss / Gain -47,543
Required Man Days to complete remaining @ Current Rate of Productivity 153,809
Total Mandays for Completion (Expected) 322,859
Total Planned Mandays 232,060
Loss of Man days after Completion of Structure work -90,799
Building C Super
Sructure
Productivity History – Planned vs Actual
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
0.00
1.00
2.00
3.00
4.00
5.00
6.00
Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17
Planned Productivity (Avg/Month) Actual Productivity (Avg/Month)
Planned Productivity Cumulative Actual Productivity Cumulative
Building C Super
Sructure
Conclusion
•Various ways of improving productivity
•For an organisation to survive and prosper improving
productivity is a must
By Kapuganti Jagannadha Gupta
BE, MBA, PMP, CCE

More Related Content

What's hot

Rate Analysis Site Meeting
Rate Analysis   Site MeetingRate Analysis   Site Meeting
Rate Analysis Site MeetingSanjay Patnaik
 
Construction Productivity
Construction ProductivityConstruction Productivity
Construction ProductivitySunil Manjeri
 
Batcoda technical specification
Batcoda technical specificationBatcoda technical specification
Batcoda technical specificationDejene Tsegaye
 
Construction Material Management
Construction Material ManagementConstruction Material Management
Construction Material ManagementPriya Ramaraj
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateSHAZEBALIKHAN1
 
Construction productivity
Construction productivityConstruction productivity
Construction productivitySunil Manjeri
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering MeasurmentSultan M Muzahir
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management pptRajeshPV12
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
Construction phases
Construction phasesConstruction phases
Construction phasesMeesum Zaidi
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineeringKailash Chander
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONSANJEEV Wazir
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projectsakashpadole
 

What's hot (20)

Rate Analysis Site Meeting
Rate Analysis   Site MeetingRate Analysis   Site Meeting
Rate Analysis Site Meeting
 
Construction Productivity
Construction ProductivityConstruction Productivity
Construction Productivity
 
Batcoda technical specification
Batcoda technical specificationBatcoda technical specification
Batcoda technical specification
 
Construction Material Management
Construction Material ManagementConstruction Material Management
Construction Material Management
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel Template
 
Construction productivity
Construction productivityConstruction productivity
Construction productivity
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering Measurment
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management ppt
 
Construction process
Construction processConstruction process
Construction process
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
Construction phases
Construction phasesConstruction phases
Construction phases
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTION
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
 

Similar to Labour Productivity for construction projects

internship review .pdf
internship review .pdfinternship review .pdf
internship review .pdfPAYALINAMDAR
 
6.0 CURT CII - Digital Transformation of Construction Industry
6.0 CURT CII  - Digital Transformation of Construction Industry6.0 CURT CII  - Digital Transformation of Construction Industry
6.0 CURT CII - Digital Transformation of Construction IndustryCCT International
 
Architect Sample
Architect SampleArchitect Sample
Architect SampleHai Nguyen
 
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)Shubham Arora
 
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...CCT International
 
BIMCampus presentation - Northumbria University Graduates - Josh, Angus and Rob
BIMCampus presentation - Northumbria University Graduates - Josh, Angus and RobBIMCampus presentation - Northumbria University Graduates - Josh, Angus and Rob
BIMCampus presentation - Northumbria University Graduates - Josh, Angus and RobCampus
 
EarthQuake Reistant Building
EarthQuake Reistant BuildingEarthQuake Reistant Building
EarthQuake Reistant BuildingHemant Srivastava
 
The Remote Build V2 Ark Conduit Assimilation
The Remote Build V2 Ark Conduit AssimilationThe Remote Build V2 Ark Conduit Assimilation
The Remote Build V2 Ark Conduit AssimilationBrij Consulting, LLC
 
MIVAN CONSTRUCTION TECHNOLOGY for const
MIVAN CONSTRUCTION TECHNOLOGY  for constMIVAN CONSTRUCTION TECHNOLOGY  for const
MIVAN CONSTRUCTION TECHNOLOGY for constPradeepPandya1
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Hamza Waheed
 
Trusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationTrusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationClearEdge3D Inc
 
Presentation. jkr lawatan IBS kilang HC Precast System
Presentation.   jkr lawatan IBS kilang HC Precast SystemPresentation.   jkr lawatan IBS kilang HC Precast System
Presentation. jkr lawatan IBS kilang HC Precast SystemTeow Beng Hur
 
Presentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSPresentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSTeow Beng Hur
 
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Morgan
 
Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryCCT International
 

Similar to Labour Productivity for construction projects (20)

internship review .pdf
internship review .pdfinternship review .pdf
internship review .pdf
 
6.0 CURT CII - Digital Transformation of Construction Industry
6.0 CURT CII  - Digital Transformation of Construction Industry6.0 CURT CII  - Digital Transformation of Construction Industry
6.0 CURT CII - Digital Transformation of Construction Industry
 
BIM Based Project Controls
BIM Based Project ControlsBIM Based Project Controls
BIM Based Project Controls
 
Architect Sample
Architect SampleArchitect Sample
Architect Sample
 
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
AH15019
AH15019AH15019
AH15019
 
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
 
BIMCampus presentation - Northumbria University Graduates - Josh, Angus and Rob
BIMCampus presentation - Northumbria University Graduates - Josh, Angus and RobBIMCampus presentation - Northumbria University Graduates - Josh, Angus and Rob
BIMCampus presentation - Northumbria University Graduates - Josh, Angus and Rob
 
EarthQuake Reistant Building
EarthQuake Reistant BuildingEarthQuake Reistant Building
EarthQuake Reistant Building
 
Training PPT
Training PPTTraining PPT
Training PPT
 
The Remote Build V2 Ark Conduit Assimilation
The Remote Build V2 Ark Conduit AssimilationThe Remote Build V2 Ark Conduit Assimilation
The Remote Build V2 Ark Conduit Assimilation
 
MIVAN CONSTRUCTION TECHNOLOGY for const
MIVAN CONSTRUCTION TECHNOLOGY  for constMIVAN CONSTRUCTION TECHNOLOGY  for const
MIVAN CONSTRUCTION TECHNOLOGY for const
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)
 
Trusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationTrusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project Coordination
 
Presentation. jkr lawatan IBS kilang HC Precast System
Presentation.   jkr lawatan IBS kilang HC Precast SystemPresentation.   jkr lawatan IBS kilang HC Precast System
Presentation. jkr lawatan IBS kilang HC Precast System
 
Presentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSPresentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPS
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
 
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
 
Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction Industry
 

Recently uploaded

Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 

Recently uploaded (20)

Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 

Labour Productivity for construction projects

  • 1. Labour Productivity Measurement for Construction Projects By Kapuganti Jagannadha Gupta BE, MBA, PMP, CCE
  • 2. Building C Super Sructure Productivity What is Labour Productivity? Productivity = Output / Input (Earned hours / Worked hours) Examples: • Kilograms of rebar fixed per manday • Cu.m Concrete poured per manday • Sq.m of formwork placed per manday • Sq.m of block laid per manday • Sq.m of tiles laid per manday
  • 3. Building C Super Sructure Why Measure Productivity? • You Can’t Correct a problem if you don’t know it exists • By the time the job is over, you have lost the more • You will have current information to manage and control your project • You should correct losses arising from internal problems • You may be able to recover losses arising from external causes. •Extremely vital performance measurement tool within the construction industry •Productivity growth is important to an individual enterprise, an industry or an economy
  • 4. Building C Super Sructure Common causes of labour overruns External: • Overtime • Changes • Crowding • Trade stacking • Weather • Site Access Internal: • Poor Planning & Management of work • Rework & Errors • Bad Estimate • Lack of Training • Morale Problems • Staff turnover • Material and equipment availability
  • 5. Building C Super Sructure Themes for Productivity Improvement • Consistent Practices • Process versus Results Management • Consistent Procedures and Practices • Proactive versus Reactive Management • Measurement and Analysis of a defect • Risk or Variation Analysis • Vital Few versus Useful Many • Planning Versus Reacting • Focus on Quality first • Pride and a Positive Attitude
  • 6. Building C Super Sructure Methodology and Data Collection • Daily activity form sheet will be distributed to concerned site engineer •Site engineer will assign works to foreman, each foreman will fill the data in form. •The contents in the form majorly covering: •The quantity of activity completed for the activity being carried out •The quantity of skilled & unskilled used to complete the activity •End of each shift these forms are collected by Productivity Engineer and compiles the information and generates reports e.g. building wise trade wise, etc. • Generally monitoring major works like Steel, Formwork, Concrete, Block, Tiles etc. •From the above reports are very useful to site management to take necessary corrective action to improve productivity wherever necessary
  • 7. Building C Super Sructure Methodology and Data Collection Validating the progress at site on daily basis in micro level monitoring DAY WORK SHEET DAILY ACTIVITY REPORT SECTION ENGINEER FORM Sl.No WORK TASK DESCRIPTION BUILDING LEVEL SUB- ZONE TRADE WORKDONE NO OF MEN QTY. UNITS DAY NIGHT 1 2 3 4 5 6 7 8 9 10 TOTAL: 0 0 REASON FOR WORK: SCOPE OF WORKS REWORKS VARIATIONS IDLE TIME FOREMAN NAME & SIGNATURE: DATE SUPERVISOR / ENGINEER NAME & Signature DATE:
  • 8. Building C Super Sructure Productivity Rates 1. Productivity Rates for Structure works Description Planned Productivity Rebar (Kg/Manday) Shutter (m2/Manday) Concrete (m3/Manday) Retaining Wall 300 4.00 5.00 Watertank Wall 300 5.00 5.00 Core Wall 300 7.00 8.00 Raft 380 7.00 15.00 Slab (Conventional) 150 7.00 10.00 Slab (PT) 100 10.00 10.00 Beam 250 7.00 8.00 Column 250 7.00 5.00 Ramp 250 8.00 8.00 Staircase 100 3.00 5.00 2. Productivity Rates for Finishing works Description of work Planned Productivity (m2/Manday) Water Proofing - Horizontal 25.00 Water Proofing - Vertical 15.00 Protection Screed 10.00 Blockwork 7.00 Wall tiles 5.00 Floor tiles 8.00 Plaster(Wall) 10.00 Staircase tiles 5.00 Staircase Plaster 8.00 Ceiling Plaster 5.00
  • 9. Building C Super Sructure Total Quantities – Concrete Works Structural Works Level Rebar (KG) Shutter (m2) Concrete (m3) Planned Productivity (MD/Cu.m) Mandays to Complete Basement - 3 7,553,230 27,245 28,251 2.5 70,628 Basement - 2 1,821,000 26,747 7,202 2.5 18,005 Basement - 1 2,615,000 30,285 9,093 2.5 22,733 Building - A 2,506,000 60,539 16,135 2.5 40,338 Building - B 2,408,000 51,804 13,610 2.5 34,025 Building - C 945,000 25,472 5,412 2.5 13,530 Building - D 2,257,000 54,546 13,121 2.5 32,803 Total 20,105,230 276,638 92,824 2.5 232,060 Structural Works for a Single Level Level Sub- Zones Rebar (KG) Shutter (m2) Concrete (m3) Planned Productivity (MD/Cu.m) Mandays to Complete Level - 1 A-1 140,643 2,782 665 2.5 1,663 A-2 133,652 2,225 599 3.5 2,097 B-1 132,000 2,521 605 4.5 2,723 B-2 128,000 2,264 529 5.5 2,910 C 120,000 2,625 538 6.5 3,497 D-1 159,000 2,887 557 7.5 4,178 D-2 81,000 1,512 341 8.5 2,899
  • 10. Building C Super Sructure Total Quantities - Finishes Finishing Works Description of work Unit Quantities Basement Building A Building B Building C Building D Total Quantity Planned Avg Productivity (Unit/Md) Planned Man Days Blockwork m2 9,468 53,276 46,859 7,496 36,597 153,696 7 21,957 Plastering m2 72,797 64,448 6,205 50,006 193,456 9 21,495 Ceiling m2 537 7,918 13,736 2,416 13,736 38,343 5 7,669 Tile m2 622 48,380 42,960 5,281 42,960 140,203 7 20,029 Stone m2 350 3,756 3,663 2,338 4,534 14,641 7 2,092 Doors Nos 125 1,955 1,695 318 431 4,524 2 2,262
  • 11. Building C Super Sructure Current Status – Concrete Works Level/ Building Planned Actual (As of Date) Rebar (KG) Shutter (m2) Concrete (m3) Planned Productivity Mandays to Complete Rebar (KG) Shutter (m2) Concrete (m3) Mandays Productivity Basement - 3 7,553,230 27,245 28,251 2.5 70,628 7,553,230 26,245 27,853 69,472 2.49 Basement - 2 1,821,000 26,747 7,202 2.5 18,005 1,343,000 21,117 7,202 31,096 4.32 Basement - 1 2,615,000 30,285 9,093 2.5 22,733 1,923,000 18,466 6,821 34,285 5.03 Building - A 2,506,000 60,539 16,135 2.5 40,338 781,000 25,630 3,653 19,249 5.27 Building - B 2,408,000 51,804 13,610 2.5 34,025 524,000 15,078 2,218 10,897 4.91 Building - C 945,000 25,472 5,412 2.5 13,530 Building - D 2,257,000 54,546 13,121 2.5 32,803 225,000 4,200 856 4,051 4.73 Total 20,105,230 276,638 92,824 2.5 232,060 12,349,23 0 110,736 48,603 169,050 3.48 % of Work Completed 52.36% Actual Man Days 169,050 Earned Mandays 121,508 Loss / Gain -47,543 Required Man Days to complete remaining @ Current Rate of Productivity 153,809 Total Mandays for Completion (Expected) 322,859 Total Planned Mandays 232,060 Loss of Man days after Completion of Structure work -90,799
  • 12. Building C Super Sructure Productivity History – Planned vs Actual 0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Planned Productivity (Avg/Month) Actual Productivity (Avg/Month) Planned Productivity Cumulative Actual Productivity Cumulative
  • 13. Building C Super Sructure Conclusion •Various ways of improving productivity •For an organisation to survive and prosper improving productivity is a must By Kapuganti Jagannadha Gupta BE, MBA, PMP, CCE