SlideShare a Scribd company logo
1 of 40
Presentation
on
Hydropower Engineering Field Visit
Presented By :
Arjun Sigdel (1305)
Lochan Shrestha (1313)
Nirmal Dangi (1317)
Suman Gautam (1327)
Tek B. Nepali (1329)
Group No:- 1
BE (Civil )
Asian Institute of Technology & Management (AITM)
(Khumaltar, Lalitpur, Nepal)
Department of Civil Engineering
October 29, 2017
Introduction
ā€¢ Hydropower is the power derived from the energy of
falling water.
ā€¢ In the late 19th century, hydropower became a source for
generating electricity.
ā€¢ World's first hydroelectric project was developed
at Northumberland in 1878.
ā€¢ And the first commercial hydroelectric power plant was
built at Niagara Falls in 1879.
ā€¢ First hydropower plant in Nepal is Pharping Hydroelectric
Plant ( 500 KW) constructed in 1911.
Background
ā€¢ The hydropower field visit was organized by the
Department of Civil Engineering , WhiteHouse
Institute of Science and Technology.
ā€¢ The hydropower field visit was held on 20th July to
22th July, 2017.
Objectives
ā€¢ Study about the head work component
ā€¢ Study about the components like Gravel trap,
Approach canal, Desander/ settling basin, Head race
Tunnel/ canal/ pipe, Adit, Inlet & Outlet portal etc..
ā€¢ Study about forebay and surge tank/Vertical Shaft
ā€¢ Study about penstock pipe, Anchor Blocks, Support
Piers.
ā€¢ Study about the Power house.
Status of Hydropower in Nepal
ā€¢ Nepalā€™s theoretical hydropower potential has been
estimated to be around 84,000 MW.
ā€¢ But only 42,000 MW has been identified as economically
viable.
ā€¢ Currently, Nepalā€™s installed hydropower capacity is 753
MW.
ā€¢ The first large-capacity interconnection between India and
Nepal (1,000 MW) was completed in February 2016.
ā€¢ 2015 saw Nepal connect over 45 MW of hydropower to the
national grid.
ā€¢A further seven projects in Nepal were scheduled to
be completed in the first half of 2015 but delayed due
to April-may earthquake.
Components of Hydropower Project
ā€¢ Weir/Dam/Barrage
ā€¢ Intake
ā€¢ Under Sluice
ā€¢ Gravel Trap
ā€¢ Settling Basin/ Desander
ā€¢ Headrace canal/ Tunnel
ā€¢ Forebay / Surge tank
ā€¢ Spillways
ā€¢ Anchor Block
ā€¢ Support pier
ā€¢ Penstocks
ā€¢ Power House
ā€¢ Tail Race
ā€¢ Transmission and
Distribution line
Lower Marsyangdi Hydropower Station
ā€¢ Marsyangdi hydropower is a peaking run of river type
hydropower.
ā€¢ Marsyangdi hydropower station is located at 114 km west
of Kathmandu on Prithivi highway, right bank of
Marsyangdi River , Aanbukhaireni, Tanahu.
ā€¢ It is owned by Nepal Electricity Authority.
Salient Features
Type Peak- run- of- the- river
Rated Net Head 90.5 meter
Rated Turbine Discharge 30.5 m3/s
Head Race Tunnel 7199m, 6.4m dia., concrete lined
Pressure Shaft 75m long, 5m dia., steel lined
Surge Tank 20.5m dia., 56m high concrete throttle shaft
Installed Capacity 69 MW
Turbine Generator Set 3 sets
Turbine Type Francis
Rated Output 23 MW x 3
Rated Speed 300 rpm
Generator Type Vertical shaft synchronous
Designed Annual Average Capacity 30 MVA
Voltage Ratio 11/132 KV
Power Transformer
11/132 KV single phase, 3x
10 KVA, 9 Nos.
Generation 462.5 GWh
Catchment Area 3850 Km2
Average Annual Discharge 210 m3/s
Construction Started February, 1886
Commercial Operation Started 5 November, 1989
Construction Cost 21.57 million USD
Different Component of Marsyangdi HPS
(i). Weir:
ā€¢ 5 Steel Radial Gate of about 102 m length has been
constructed to divert Marsyangdi River.
ā€¢ It controls the design discharge upto 9100 m3/sec.
(ii). Headrace Tunnel
ā€¢ Headrace tunnel is of length 7199m and diameter of
6.4m.
Figure 1 : Bird eye View of Headwork site
(iii). Power House
ā€¢ The Power House is Semi-underground type with three shafts to
power Generating Equipment.
ā€¢ Three Francis Turbines are installed in Powerhouse each
with capacity of 26 MW.
(iv). Transformer Line
ā€¢ Marsyangdi Power Plant is connected to the Central Grid
system with two transmission lines.
ā€¢ These transmission lines links the power plant with Kathmandu
and Chitwan(Suichatar and Bharatpur substations).
Figure 2: View of Power House
Upper Modikhola Hydropower Station
ā€¢ Upper Modikhola Hydropower is the Run-of-River type
hydropower.
ā€¢ It is located at Dimuwa, Parbat.
ā€¢ It was commissioned in 2000 AD and in the assistance from
EDCF (Korea), Government of Nepal and NEA at a cost of
USD 30 million.
Figure 3 : Layout of Upper Modikhola hydropower details
Figure 4: View of inside Powerhouse
Figure 5: View of inside Powerhouse
Figure 6 Modi Power Station
Type Run of river
Location Dimuwa, Parbat
Installed Capacity 14.8 MW
Annual average energy 92.5 GWh
Maximum Net Head 66.96 m
Catchment area 510 km2
Average annual flow 25 m3/s
Total length of the waterways 61 m (canal), 2,071 m (tunnel)
Turbine Number and Type 2, Francis
Salient Features
Rated Discharge 12.5 m3/s
Rated Output 7.6 MW
Rated Speed 428.6 rpm
Generator Rated Output 8260 kVA
Rated Voltage 6.6 kV
Rated Frequency 50 Hz
Power Factor 0.9
Power Transformer 7.8/8.3 MVA, 6.6/132 kV, 3 phase
Transmission line Single circuit 132 kV, upto Lekhnath s/s
Lower Modi Khola Hydro Power
ā€¢ Lower Modi Hydroelectric Project is located in Parbat
district is an under construction project.
ā€¢ It is the Run-of-River type hydropower project.
ā€¢ Installed capacity of Lower Modikhola Hydropower project
is 20 MW
Different Component of Lower Modikhola HEP
(i). Surface Structure
ā€¢ The weir is ogee shaped, located at about 120 m
downstream from the confluence of Pati and Modi khola.
ā€¢ The weir diverts stream flow through side intake to the
gravel trap and then to settling basins through approach
canal.
ā€¢ There are 3 undersluices and 6 orifice type side intakes.
ā€¢ Two deep hopper shaped gravel traps are provided
immediately after the intake.
ā€¢ Two approach canals of about 153 m each are provided
after the gravel traps to carry water to the settling basin.
ā€¢ Two hopper type surface settling basins are provided to
trap at least 90% of sediment above 0.2 mm.
ā€¢ The outlet transition zone of Settling basin functions as a
headpond of dimension 7 m x 32.4 m x 10.20 m..
Figure 7: Headworks
Figure 8: Gravel Trap
Figure 9: Desander
Figure 10: Desander
Figure 11: Forebay ( Underconstruction ) with Inlet Portal
(ii). Adit Tunnels
ā€¢ There are two adit tunnels namely Adit-1 and Adit-2
being excavated.
ā€¢ The excavation of two Adits each of length 181 meter
and 122 meter.
Figure 12: Adit-1
(iii). Headrace Tunnel
ā€¢ Excavation of 4,021 meter of headrace tunnel was in
progress.
ā€¢ All the primary support including shotcrete, rockbolting
and forepoling has been done along these excavated
length of the Tunnel Figure.
Figure 13: Inner View of HRT tunnel
(iv). Surge shaft and Penstock pipe
ā€¢ a vertical nonā€spilling type surge shaft is provided at the
end of headrace tunnel.
ā€¢ Surge shaft is 57.50 m high with internal diameter of 10
m.
ā€¢ From the surge shaft, a 454 m long steel penstock pipe
with 3.5 m internal diameter runs to the powerhouse.
(v). Power House
ā€¢ It is located at the right bank of Modi Khola of Chuwa VDC.
ā€¢ Two Vertica axis Francis turbines are installed in the
powerhouse to generate 10 MW each.
Salient Features
Location Deopur, Bajung, Tilahar and Chuwa VDC
Catchment area 560 km2
Net head 83.37 m
Designed discharge 28.8 m3/sec.
Annual average energy 117.53 GWh
Average annual flow 54.62 m3/s
Speed 750 rpm
Generator Rated output 12.5 MVA
Rated voltage 6.3 kV
Rated frequency 50Hz
Power transformer 12.5 MVA, 6.3/132 kV, 3 phase
Conclusion and Discussion
ā€¢ We gain the practical knowledge about the different component
of the hydropower plant
ā€¢ We also get the knowledge of the current situation of the
hydropower plant and the current problem in the plant.
ā€¢ We also got the chance to make the comparison between the
different hydropower plant
ā€¢ The performance of the upper modikhola plant is largely
unsatisfactory during rainy season due to abrasive sediment
so we recommended to construct a good settling unit
Reference
ā€¢ (2016). Retrieved from http://www.modihydro.com/index.php.
ā€¢ Dandekar, M. (2010). Water Power Engineering. Vikas publicating
house pvt ltd.
ā€¢ Garg, S. K. (2011). Irrigation Engineering And Hydraulis Structures.
khanna publications. (n.d.). http://nea.org.np/generation/index.php.
ā€¢ marsyngdi power station. (2017).
ā€¢ Retrieved from
http://www.nea.org.np/generation/index.php?page=powerhouse&pi
d=7#
ā€¢ Nea. (2017). Modikhola Hydropower Station
THANK YOU

More Related Content

What's hot

Hydro Power Plants
Hydro Power PlantsHydro Power Plants
Hydro Power PlantsVignesh Sekar
Ā 
indian railway training report
indian railway training reportindian railway training report
indian railway training reportravi kant
Ā 
Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India pptNikita James
Ā 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plantPradeep Yadav
Ā 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant Prasad Vejendla
Ā 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)sharda university
Ā 
Bandra worli sea link jay
Bandra worli sea link jayBandra worli sea link jay
Bandra worli sea link jayDhruv Seth
Ā 
Railway Electrification - Traction
Railway Electrification - TractionRailway Electrification - Traction
Railway Electrification - TractionSUDIN BISWAS
Ā 
MASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEMMASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEMChandanPadhi3
Ā 
internship report on NJHPP
internship report on NJHPPinternship report on NJHPP
internship report on NJHPPSaad Raja
Ā 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Akhilesh Shukla
Ā 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plantShaik Afzal
Ā 
Nepal east west rail project-feasibility study draft report presentation
Nepal east west rail project-feasibility study draft report presentationNepal east west rail project-feasibility study draft report presentation
Nepal east west rail project-feasibility study draft report presentationBhim Upadhyaya
Ā 
Project Report Hydraulic Power Plant
Project Report Hydraulic Power PlantProject Report Hydraulic Power Plant
Project Report Hydraulic Power PlantSanjay Duttamukhya
Ā 
training report
training reporttraining report
training reportLilonheart
Ā 
Railway track design ppt 2018
Railway track design ppt 2018Railway track design ppt 2018
Railway track design ppt 2018ishwar dhakad
Ā 
Railway project
Railway projectRailway project
Railway projectKiran Hadiya
Ā 

What's hot (20)

Hydro Power Plants
Hydro Power PlantsHydro Power Plants
Hydro Power Plants
Ā 
Different types of bridges or innovative bridges in india
Different types of bridges or innovative bridges in indiaDifferent types of bridges or innovative bridges in india
Different types of bridges or innovative bridges in india
Ā 
indian railway training report
indian railway training reportindian railway training report
indian railway training report
Ā 
Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India ppt
Ā 
Hydro-Electric Power
Hydro-Electric PowerHydro-Electric Power
Hydro-Electric Power
Ā 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
Ā 
Energy project report on hydropower
Energy project report on hydropowerEnergy project report on hydropower
Energy project report on hydropower
Ā 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant
Ā 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)
Ā 
Bandra worli sea link jay
Bandra worli sea link jayBandra worli sea link jay
Bandra worli sea link jay
Ā 
Railway Electrification - Traction
Railway Electrification - TractionRailway Electrification - Traction
Railway Electrification - Traction
Ā 
MASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEMMASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEM
Ā 
internship report on NJHPP
internship report on NJHPPinternship report on NJHPP
internship report on NJHPP
Ā 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
Ā 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
Ā 
Nepal east west rail project-feasibility study draft report presentation
Nepal east west rail project-feasibility study draft report presentationNepal east west rail project-feasibility study draft report presentation
Nepal east west rail project-feasibility study draft report presentation
Ā 
Project Report Hydraulic Power Plant
Project Report Hydraulic Power PlantProject Report Hydraulic Power Plant
Project Report Hydraulic Power Plant
Ā 
training report
training reporttraining report
training report
Ā 
Railway track design ppt 2018
Railway track design ppt 2018Railway track design ppt 2018
Railway track design ppt 2018
Ā 
Railway project
Railway projectRailway project
Railway project
Ā 

Similar to Hydropower field visi report, pokhara (Presentation slide)

Presentation on two major hydro electric power plants in india
Presentation on two major hydro electric power plants in indiaPresentation on two major hydro electric power plants in india
Presentation on two major hydro electric power plants in indiaSaikat Ghosh
Ā 
Hydropower projects in Jammu and Kashmir
Hydropower projects in Jammu and KashmirHydropower projects in Jammu and Kashmir
Hydropower projects in Jammu and KashmirAaquib Firdous
Ā 
Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report muhammad khurram
Ā 
55661002-Hydro-Electric-Power-Plant.pptx
55661002-Hydro-Electric-Power-Plant.pptx55661002-Hydro-Electric-Power-Plant.pptx
55661002-Hydro-Electric-Power-Plant.pptxDovalin
Ā 
Neelum jehlum hydropower project
Neelum jehlum hydropower projectNeelum jehlum hydropower project
Neelum jehlum hydropower projectMuhammad Aqeel
Ā 
Koyna Hydro-electric Project
Koyna Hydro-electric Project Koyna Hydro-electric Project
Koyna Hydro-electric Project Agrodwip Das
Ā 
Chichoki power plant
Chichoki power plantChichoki power plant
Chichoki power plantIbadullah Sahito
Ā 
Gulpur Hydropower Plant Project Full Report 2019
Gulpur Hydropower Plant Project Full Report 2019Gulpur Hydropower Plant Project Full Report 2019
Gulpur Hydropower Plant Project Full Report 2019HasnatAmin1
Ā 
Prospect of Small Hydro Power in Uttarakhand
Prospect of Small Hydro Power in UttarakhandProspect of Small Hydro Power in Uttarakhand
Prospect of Small Hydro Power in Uttarakhandijsrd.com
Ā 
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Aniket Raj
Ā 
idukki Hydro power project
idukki Hydro power projectidukki Hydro power project
idukki Hydro power projectVodepalliManaswini
Ā 
Lecture Note 2_2023A Power Systems II (PWRS 201).pdf
Lecture Note 2_2023A Power Systems II (PWRS 201).pdfLecture Note 2_2023A Power Systems II (PWRS 201).pdf
Lecture Note 2_2023A Power Systems II (PWRS 201).pdfNandi77
Ā 
Punasa report on indra sagar Dam, 9608684800
Punasa  report on indra sagar Dam, 9608684800Punasa  report on indra sagar Dam, 9608684800
Punasa report on indra sagar Dam, 9608684800PRIYANSHU KUMAR
Ā 
Rani awanti bai hydel power plant by vijayendra singh rajput - Bargi Dam Jaba...
Rani awanti bai hydel power plant by vijayendra singh rajput - Bargi Dam Jaba...Rani awanti bai hydel power plant by vijayendra singh rajput - Bargi Dam Jaba...
Rani awanti bai hydel power plant by vijayendra singh rajput - Bargi Dam Jaba...Vijayendra Singh Rajput
Ā 
Hydro Energy or Hydro power conversion Technology
Hydro Energy or Hydro power conversion TechnologyHydro Energy or Hydro power conversion Technology
Hydro Energy or Hydro power conversion TechnologyTesfaye Birara
Ā 

Similar to Hydropower field visi report, pokhara (Presentation slide) (20)

Presentation on two major hydro electric power plants in india
Presentation on two major hydro electric power plants in indiaPresentation on two major hydro electric power plants in india
Presentation on two major hydro electric power plants in india
Ā 
Hydropower projects in Jammu and Kashmir
Hydropower projects in Jammu and KashmirHydropower projects in Jammu and Kashmir
Hydropower projects in Jammu and Kashmir
Ā 
Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report
Ā 
Hydropower
HydropowerHydropower
Hydropower
Ā 
55661002-Hydro-Electric-Power-Plant.pptx
55661002-Hydro-Electric-Power-Plant.pptx55661002-Hydro-Electric-Power-Plant.pptx
55661002-Hydro-Electric-Power-Plant.pptx
Ā 
Neelum jehlum hydropower project
Neelum jehlum hydropower projectNeelum jehlum hydropower project
Neelum jehlum hydropower project
Ā 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
Ā 
Project report
Project reportProject report
Project report
Ā 
Koyna Hydro-electric Project
Koyna Hydro-electric Project Koyna Hydro-electric Project
Koyna Hydro-electric Project
Ā 
Chichoki power plant
Chichoki power plantChichoki power plant
Chichoki power plant
Ā 
Hydropower palnts
Hydropower palntsHydropower palnts
Hydropower palnts
Ā 
Gulpur Hydropower Plant Project Full Report 2019
Gulpur Hydropower Plant Project Full Report 2019Gulpur Hydropower Plant Project Full Report 2019
Gulpur Hydropower Plant Project Full Report 2019
Ā 
Prospect of Small Hydro Power in Uttarakhand
Prospect of Small Hydro Power in UttarakhandProspect of Small Hydro Power in Uttarakhand
Prospect of Small Hydro Power in Uttarakhand
Ā 
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Ā 
idukki Hydro power project
idukki Hydro power projectidukki Hydro power project
idukki Hydro power project
Ā 
Lecture Note 2_2023A Power Systems II (PWRS 201).pdf
Lecture Note 2_2023A Power Systems II (PWRS 201).pdfLecture Note 2_2023A Power Systems II (PWRS 201).pdf
Lecture Note 2_2023A Power Systems II (PWRS 201).pdf
Ā 
Presention ppt
Presention pptPresention ppt
Presention ppt
Ā 
Punasa report on indra sagar Dam, 9608684800
Punasa  report on indra sagar Dam, 9608684800Punasa  report on indra sagar Dam, 9608684800
Punasa report on indra sagar Dam, 9608684800
Ā 
Rani awanti bai hydel power plant by vijayendra singh rajput - Bargi Dam Jaba...
Rani awanti bai hydel power plant by vijayendra singh rajput - Bargi Dam Jaba...Rani awanti bai hydel power plant by vijayendra singh rajput - Bargi Dam Jaba...
Rani awanti bai hydel power plant by vijayendra singh rajput - Bargi Dam Jaba...
Ā 
Hydro Energy or Hydro power conversion Technology
Hydro Energy or Hydro power conversion TechnologyHydro Energy or Hydro power conversion Technology
Hydro Energy or Hydro power conversion Technology
Ā 

Recently uploaded

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
Ā 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
Ā 
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
Ā 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
Ā 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
Ā 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
Ā 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
Ā 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
Ā 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
Ā 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
Ā 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
Ā 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
Ā 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
Ā 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
Ā 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
Ā 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
Ā 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
Ā 

Recently uploaded (20)

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
Ā 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Ā 
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
Ā 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
Ā 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
Ā 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Ā 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
Ā 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
Ā 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
Ā 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
Ā 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
Ā 
young call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Service
young call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Serviceyoung call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Service
young call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Service
Ā 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
Ā 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
Ā 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
Ā 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
Ā 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Ā 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
Ā 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
Ā 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
Ā 

Hydropower field visi report, pokhara (Presentation slide)

  • 1. Presentation on Hydropower Engineering Field Visit Presented By : Arjun Sigdel (1305) Lochan Shrestha (1313) Nirmal Dangi (1317) Suman Gautam (1327) Tek B. Nepali (1329) Group No:- 1 BE (Civil ) Asian Institute of Technology & Management (AITM) (Khumaltar, Lalitpur, Nepal) Department of Civil Engineering October 29, 2017
  • 2. Introduction ā€¢ Hydropower is the power derived from the energy of falling water. ā€¢ In the late 19th century, hydropower became a source for generating electricity. ā€¢ World's first hydroelectric project was developed at Northumberland in 1878. ā€¢ And the first commercial hydroelectric power plant was built at Niagara Falls in 1879. ā€¢ First hydropower plant in Nepal is Pharping Hydroelectric Plant ( 500 KW) constructed in 1911.
  • 3.
  • 4. Background ā€¢ The hydropower field visit was organized by the Department of Civil Engineering , WhiteHouse Institute of Science and Technology. ā€¢ The hydropower field visit was held on 20th July to 22th July, 2017.
  • 5. Objectives ā€¢ Study about the head work component ā€¢ Study about the components like Gravel trap, Approach canal, Desander/ settling basin, Head race Tunnel/ canal/ pipe, Adit, Inlet & Outlet portal etc.. ā€¢ Study about forebay and surge tank/Vertical Shaft ā€¢ Study about penstock pipe, Anchor Blocks, Support Piers. ā€¢ Study about the Power house.
  • 6. Status of Hydropower in Nepal ā€¢ Nepalā€™s theoretical hydropower potential has been estimated to be around 84,000 MW. ā€¢ But only 42,000 MW has been identified as economically viable. ā€¢ Currently, Nepalā€™s installed hydropower capacity is 753 MW. ā€¢ The first large-capacity interconnection between India and Nepal (1,000 MW) was completed in February 2016.
  • 7. ā€¢ 2015 saw Nepal connect over 45 MW of hydropower to the national grid. ā€¢A further seven projects in Nepal were scheduled to be completed in the first half of 2015 but delayed due to April-may earthquake.
  • 8. Components of Hydropower Project ā€¢ Weir/Dam/Barrage ā€¢ Intake ā€¢ Under Sluice ā€¢ Gravel Trap ā€¢ Settling Basin/ Desander ā€¢ Headrace canal/ Tunnel ā€¢ Forebay / Surge tank ā€¢ Spillways ā€¢ Anchor Block ā€¢ Support pier ā€¢ Penstocks ā€¢ Power House ā€¢ Tail Race ā€¢ Transmission and Distribution line
  • 9.
  • 10. Lower Marsyangdi Hydropower Station ā€¢ Marsyangdi hydropower is a peaking run of river type hydropower. ā€¢ Marsyangdi hydropower station is located at 114 km west of Kathmandu on Prithivi highway, right bank of Marsyangdi River , Aanbukhaireni, Tanahu. ā€¢ It is owned by Nepal Electricity Authority.
  • 11. Salient Features Type Peak- run- of- the- river Rated Net Head 90.5 meter Rated Turbine Discharge 30.5 m3/s Head Race Tunnel 7199m, 6.4m dia., concrete lined Pressure Shaft 75m long, 5m dia., steel lined Surge Tank 20.5m dia., 56m high concrete throttle shaft Installed Capacity 69 MW Turbine Generator Set 3 sets Turbine Type Francis Rated Output 23 MW x 3 Rated Speed 300 rpm
  • 12. Generator Type Vertical shaft synchronous Designed Annual Average Capacity 30 MVA Voltage Ratio 11/132 KV Power Transformer 11/132 KV single phase, 3x 10 KVA, 9 Nos. Generation 462.5 GWh Catchment Area 3850 Km2 Average Annual Discharge 210 m3/s Construction Started February, 1886 Commercial Operation Started 5 November, 1989 Construction Cost 21.57 million USD
  • 13. Different Component of Marsyangdi HPS (i). Weir: ā€¢ 5 Steel Radial Gate of about 102 m length has been constructed to divert Marsyangdi River. ā€¢ It controls the design discharge upto 9100 m3/sec. (ii). Headrace Tunnel ā€¢ Headrace tunnel is of length 7199m and diameter of 6.4m.
  • 14. Figure 1 : Bird eye View of Headwork site
  • 15. (iii). Power House ā€¢ The Power House is Semi-underground type with three shafts to power Generating Equipment. ā€¢ Three Francis Turbines are installed in Powerhouse each with capacity of 26 MW. (iv). Transformer Line ā€¢ Marsyangdi Power Plant is connected to the Central Grid system with two transmission lines. ā€¢ These transmission lines links the power plant with Kathmandu and Chitwan(Suichatar and Bharatpur substations).
  • 16. Figure 2: View of Power House
  • 17. Upper Modikhola Hydropower Station ā€¢ Upper Modikhola Hydropower is the Run-of-River type hydropower. ā€¢ It is located at Dimuwa, Parbat. ā€¢ It was commissioned in 2000 AD and in the assistance from EDCF (Korea), Government of Nepal and NEA at a cost of USD 30 million.
  • 18. Figure 3 : Layout of Upper Modikhola hydropower details
  • 19. Figure 4: View of inside Powerhouse
  • 20. Figure 5: View of inside Powerhouse
  • 21. Figure 6 Modi Power Station
  • 22. Type Run of river Location Dimuwa, Parbat Installed Capacity 14.8 MW Annual average energy 92.5 GWh Maximum Net Head 66.96 m Catchment area 510 km2 Average annual flow 25 m3/s Total length of the waterways 61 m (canal), 2,071 m (tunnel) Turbine Number and Type 2, Francis Salient Features
  • 23. Rated Discharge 12.5 m3/s Rated Output 7.6 MW Rated Speed 428.6 rpm Generator Rated Output 8260 kVA Rated Voltage 6.6 kV Rated Frequency 50 Hz Power Factor 0.9 Power Transformer 7.8/8.3 MVA, 6.6/132 kV, 3 phase Transmission line Single circuit 132 kV, upto Lekhnath s/s
  • 24. Lower Modi Khola Hydro Power ā€¢ Lower Modi Hydroelectric Project is located in Parbat district is an under construction project. ā€¢ It is the Run-of-River type hydropower project. ā€¢ Installed capacity of Lower Modikhola Hydropower project is 20 MW
  • 25. Different Component of Lower Modikhola HEP (i). Surface Structure ā€¢ The weir is ogee shaped, located at about 120 m downstream from the confluence of Pati and Modi khola. ā€¢ The weir diverts stream flow through side intake to the gravel trap and then to settling basins through approach canal. ā€¢ There are 3 undersluices and 6 orifice type side intakes. ā€¢ Two deep hopper shaped gravel traps are provided immediately after the intake.
  • 26. ā€¢ Two approach canals of about 153 m each are provided after the gravel traps to carry water to the settling basin. ā€¢ Two hopper type surface settling basins are provided to trap at least 90% of sediment above 0.2 mm. ā€¢ The outlet transition zone of Settling basin functions as a headpond of dimension 7 m x 32.4 m x 10.20 m..
  • 31. Figure 11: Forebay ( Underconstruction ) with Inlet Portal
  • 32. (ii). Adit Tunnels ā€¢ There are two adit tunnels namely Adit-1 and Adit-2 being excavated. ā€¢ The excavation of two Adits each of length 181 meter and 122 meter.
  • 34. (iii). Headrace Tunnel ā€¢ Excavation of 4,021 meter of headrace tunnel was in progress. ā€¢ All the primary support including shotcrete, rockbolting and forepoling has been done along these excavated length of the Tunnel Figure.
  • 35. Figure 13: Inner View of HRT tunnel
  • 36. (iv). Surge shaft and Penstock pipe ā€¢ a vertical nonā€spilling type surge shaft is provided at the end of headrace tunnel. ā€¢ Surge shaft is 57.50 m high with internal diameter of 10 m. ā€¢ From the surge shaft, a 454 m long steel penstock pipe with 3.5 m internal diameter runs to the powerhouse. (v). Power House ā€¢ It is located at the right bank of Modi Khola of Chuwa VDC. ā€¢ Two Vertica axis Francis turbines are installed in the powerhouse to generate 10 MW each.
  • 37. Salient Features Location Deopur, Bajung, Tilahar and Chuwa VDC Catchment area 560 km2 Net head 83.37 m Designed discharge 28.8 m3/sec. Annual average energy 117.53 GWh Average annual flow 54.62 m3/s Speed 750 rpm Generator Rated output 12.5 MVA Rated voltage 6.3 kV Rated frequency 50Hz Power transformer 12.5 MVA, 6.3/132 kV, 3 phase
  • 38. Conclusion and Discussion ā€¢ We gain the practical knowledge about the different component of the hydropower plant ā€¢ We also get the knowledge of the current situation of the hydropower plant and the current problem in the plant. ā€¢ We also got the chance to make the comparison between the different hydropower plant ā€¢ The performance of the upper modikhola plant is largely unsatisfactory during rainy season due to abrasive sediment so we recommended to construct a good settling unit
  • 39. Reference ā€¢ (2016). Retrieved from http://www.modihydro.com/index.php. ā€¢ Dandekar, M. (2010). Water Power Engineering. Vikas publicating house pvt ltd. ā€¢ Garg, S. K. (2011). Irrigation Engineering And Hydraulis Structures. khanna publications. (n.d.). http://nea.org.np/generation/index.php. ā€¢ marsyngdi power station. (2017). ā€¢ Retrieved from http://www.nea.org.np/generation/index.php?page=powerhouse&pi d=7# ā€¢ Nea. (2017). Modikhola Hydropower Station

Editor's Notes

  1. Single Circuit 132 KV Transmission Lines 83 and 25 KM in length